{{#Wiki_filter:U.S. Nuclear Regulatory Commission Public Meeting Summary May 10, 2021
{{#Wiki_filter:}}
 
==Title:==
Fitness for Duty Drug Testing Requirements Final Rule (Cumulative Effects of Regulation)
Meeting Identifier: 20210348 Date of Meeting: April 13, 2021 Location: Webinar Type of Meeting: Information Meeting with a Question and Answer Session.
Purpose of the Meeting:
To discuss the proposed effective date of the draft final rule for Fitness for Duty Drug Testing Requirements and to provide a summary of substantive public comments received on the proposed rule resulting in changes to the final rule.
This meeting also provided an opportunity for the NRC staff to obtain feedback from members of the public on the effective date of the final rule as it pertains to the cumulative effects of regulation.
General Details:
The NRC conducted a public meeting scheduled from 10:00 a.m. - 11:00 a.m. eastern standard time that ran approximately 1 hour. The meeting was attended by 93 individuals, including 19 NRC staff and 74 members of the public. All attendees participated via WebEx and teleconference. Meeting participants included nuclear power reactor licensees (e.g., Energy Harbor, Exelon, Duke Energy), representatives from the nuclear industry (e.g., Nuclear Energy Institute), other stakeholders (e.g., Curtiss-Wright, Morgan Lewis & Bockius LLP), and a private citizen. The meeting was transcribed, and the transcript is available in the NRCs Agencywide Document Access and Management System (ADAMS) under Accession No. ML21096A011, and at Regulations.gov under Docket No. NRC-2009-0225. A list of attendees is provided as an attachment to this meeting summary.
Summary of NRC Presentation:
The meeting began with an NRC presentation on the rulemaking background and final rule schedule. The NRC noted that 22 public comment submissions were received on the proposed rule. Next the NRC explained the concept of cumulative effects of regulation (CER) and its relationship to informing the implementation schedule for licensees to comply with the final rule requirements. The NRC proposed a 60-day compliance schedule based on CER and the substantive changes to the final rule.
 
The NRC summarized key proposed rule revisions on the drug testing panel, subversion attempt detection, and shy-bladder hydration process. The NRC discussed substantive public comments received in response to questions included in the proposed rule notice (84 FR 48750; September 16, 2019) on new test analytes (2017 HHS Guidelines) and directly observed specimen collections. The NRC explained final rule changes in response to the two questions. Specifically, expanding the drug testing panel to include hydrocodone, hydromorphone, oxycodone, and oxymorphone; and providing the option to collect an oral fluid specimen instead of a urine specimen under direct observation conditions.
The NRC discussed two public comments received on a question in the proposed rule notice on the 60-day effective date to comply with the final rule changes. One commenter requested a period of 120 days to comply with the revised requirements and the other requested 1 year.
The NRC explained that the 60-day implementation schedule was proposed because the rule changes were not expected to result in CER impacts on effected licensees and other entities.
The NRC provided three reasons for this decision: 1) no other pending 10 CFR Part 26 regulatory actions exist that would impact the site professionals responsible for implementing the rule requirements, 2) changes to the fitness for duty (FFD) policy, procedures, contracts, and training are minimal, and 3) implementation guidance will be issued with the rule. This completed the NRCs discussion on the rulemaking activity.
The NRC then opened the meeting for feedback and questions. The meeting concluded with a description of how to find information for this rulemaking at regulations.gov and use of the NRC public meeting feedback form.
The meeting transcript, which provides the complete meeting discussions, is available in ADAMS under Accession No. ML21096A011. Also, the NRCs presentation slides are available in ADAMS under Accession No. ML21096A010.
Public Participation Themes:
Feedback was received from one public participant, the Nuclear Energy Institute (NEI), during the discussion and question segment of the meeting. NEI was supportive of the proposed new rule changes and the resulting increased effectiveness of the FFD Program, but stated that a one-year implementation period was needed to comply with the final rule changes. The NEI representatives concern was that the 60-day implementation period did not provide sufficient time for management and staff to handle the significant operational challenges posed prior to, during, and after Spring and Fall outages, updates to the industrys training system (NANTeL),
licensee information technology system changes, and the ongoing impacts of COVID and remote work status of staff. This and the NRC response are captured in the public meeting transcript.
Action Items/Next Steps:
* There were no action items as a result of the public meeting.
* Final rule will be provided to the Commission by early fall 2021.
 
Additional Information:
* Meeting notice and agenda: ADAMS Accession No. ML21084A074
* NRC staff presentation: ADAMS Accession No. ML21096A010
* Transcript: ADAMS Accession No. ML21096A011
* Meeting Summary: ADAMS Accession No. ML21096A015
 
FITNESS FOR DUTY DRUG TESTING REQUIREMENTS FINAL RULE (CUMULATIVE EFFECTS OF REGULATION PUBLIC MEETING HELD ON 04/13/2021 CATEGORY: INFORMATION MEETING WITH A QUESTION AND ANSWER SESSION LIST OF ATTENDEES No. First Name          Last Name      Affiliation 1 Howard              Benowitz      NRC 2 Helen                Chang          NRC 3 Christian            Cowdrey        NRC 4 Kevin                Coyne          NRC 5 David                Desaulniers    NRC 6 Brian                Green          NRC 7 Paul                Harris        NRC 8 Glenna              Lappert        NRC 9 Tim                  Mossman        NRC 10 James                O'Driscoll    NRC 11 Kevin                Ramsey        NRC 12 Stewart              Schneider      NRC 13 Fred                Schofer        NRC 14 Soly                Soto Lugo      NRC 15 Gregory              Suber          NRC 16 Brian                Thomas        NRC 17 Justin              Vazquez        NRC 18 Ilka                Verrius        NRC 19 Brian                Zaleski        NRC 20 Amy                  Findley        Ameren Missouri 21 Mike                Haglund        Calloway Energy Center 22 Shane                Mecaskey      Comanche Peak Nuclear Power Plant 23 Latham              Meiers        Comanche Peak Nuclear Power Plant 24 Richard              Swanson        Comanche Peak Nuclear Power Plant 25 Jeff                Schwarting    Cooper Nuclear Station 26 Anna                Raleigh        Curtiss-Wright 27 Zack                Schwenk        Curtiss-Wright 28 Patrick              Anhalt        Dominion Energy 29 Richard              Hanson        Dominion Energy 30 Bobby                Hote          Dominion Energy 31 Adam                Murphy        Dominion Energy
 
FITNESS FOR DUTY DRUG TESTING REQUIREMENTS FINAL RULE (CUMULATIVE EFFECTS OF REGULATION PUBLIC MEETING HELD ON 04/13/2021 CATEGORY: INFORMATION MEETING WITH A QUESTION AND ANSWER SESSION LIST OF ATTENDEES No. First Name            Last Name        Affiliation 32 Cynthia              Bomyea          DTE Energy 33 Leah                  Paul            DTE Energy 34 Cara                  Davis            Duke Energy (Medical One Medical Group) 35 Terry                King            Duke Energy 36 Theodore (Teddy)      Reed            Duke Energy 37 Wendy                Wilder          Duke Energy 38 John                  Coleman          Endevor 39 Alexander            Ellis            Energy Harbor 40 Vincent              Forbus          Energy Harbor 41 Maureen              Gulliford        Energy Harbor 42 Bryan                Jackway          Energy Harbor 43 Norbert              Schutte          Energy Harbor 44 Brenda                Thorbahn        Energy Harbor (Davis Besse) 45 Vanessa              Perez            Energy Northwest 46 Steven                Chambliss        Entergy Nuclear (Grand Gulf) 47 Stephanie            Colburn          Entergy Nuclear 48 Matthew              Deignan          Entergy Nuclear (Riverbend Station) 49 Kelly                Pettus          Entergy Nuclear 50 Chris                Pond            Entergy Nuclear 51 Karen                Murphy          Entergy Nuclear (Grand Gulf) 52 Scott                Summers          Entergy Nuclear (Palisades) 53 Jerry                Woods            Entergy Nuclear 54 Delores              Adams            Exelon 55 Andy                  Anderson        Exelon 56 Stephen              Henry            Exelon 57 Mary                  Scarce          Exelon 58 Tim                  Chapin          INPO 59 Ben                  Schaffer        INPO 60 Latham                Meier            Luminant 61 Richard              Swanson          Luminant 62 Lewis                Csedrik          Morgan Lewis
 
FITNESS FOR DUTY DRUG TESTING REQUIREMENTS FINAL RULE (CUMULATIVE EFFECTS OF REGULATION PUBLIC MEETING HELD ON 04/13/2021 CATEGORY: INFORMATION MEETING WITH A QUESTION AND ANSWER SESSION LIST OF ATTENDEES No. First Name            Last Name      Affiliation 63 Ariel                Braunstein      Morgan Lewis & Bockius LLP 64 Misty                Thomas          n/a 65 David                Vandercamp      NE Public Power District 66 Joseph                Garry          Neal R Gross & Co., Inc. (Court Reporter) 67 William              Gross          NEI 68 Johnny                Rogers          NEI 69 Don                  Popp            NextEra Energy 70 Anonymous            Anonymous      NuScale Power 71 Kevin                Deyette        NuScale Power, LLC 72 Theresa              Jones          Palo Verde 73 Don                  Townsend        PG&E 74 Cajya                Darling        PSEG 75 Elizabeth            Fox            PSEG 76 Tina                  Gregory        PSEG 77 Trina                Washington      PSEG 78 John                  Coleman        Software Vendor 79 Leslie                Lathrop        Southern California Edison Co.
80 Cheree                Montgomery      Southern Nuclear 81 Sara                  Ledwig          STP Nuclear-South Texas Project 82 Clair                Manges          Susquehanna Steam Electric Plant 83 Michele              Hockenberry    Talen Energy 84 Mike                  Palmer          Talen Energy (Susquehanna Nuclear) 85 Paul                  Zaffuts        The Zaffuts Group 86 Bryan                Henderson      TVA 87 Patrick              Asendorf        TVA 88 Michael              Covert          Vistra 89 Sonya                Jones          Wolf Creek 90 Pam                  Black          Wolf Creek 91 Dana                  Hickey          Xcel Energy 92 David                Gerads          Xcel Energy}}

Revision as of 20:20, 8 September 2021

Summary of Public Meeting for Fitness for Duty Drug Testing Requirements Final Rule; Part 26, Cumulative Effects of Regulation Public Meeting
ML21096A015
Person / Time
Issue date: 05/10/2021
From: Stewart Schneider
NRC/NMSS/DREFS/RRPB
To:
Schneider, Stewart
References
10 CFR Part 26, 20210348, NRC-2009-0225, RIN 3150-AI67
Download: ML21096A015 (6)