ML20238B196: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 1: Line 1:
{{Adams
#REDIRECT [[U-601015, Ro:On 870816,protected Area Intrusion Detection Sys Deactivated Due to Severe Weather.Compensatory Measures in Place.Security Personnel Removed from Post booths.Closed- Circuit Television Observers Posted Until Weather Cleared]]
| number = ML20238B196
| issue date = 08/21/1987
| title = Ro:On 870816,protected Area Intrusion Detection Sys Deactivated Due to Severe Weather.Compensatory Measures in Place.Security Personnel Removed from Post booths.Closed- Circuit Television Observers Posted Until Weather Cleared
| author name = Spangenberg F
| author affiliation = ILLINOIS POWER CO.
| addressee name = Davis A
| addressee affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
| docket = 05000461
| license number =
| contact person =
| document report number = U-601015, NUDOCS 8709010110
| document type = INCOMING CORRESPONDENCE, REPORTABLE OCCURRENCE REPORT (SEE ALSO AO LER), TEXT-SAFETY REPORT
| page count = 2
}}
 
=Text=
{{#Wiki_filter:q J
  ~.    .
U-601015t 1A.120
()a0
          /LLINDIS POWER 00MPANY CLINTON POWER STATION, P,o. BOX 678. CLINTON. ILLINOIS 61727 August 21,.1987                                ..
f-c10R1H RQutING'
                                                                                                .ul    ysnDL
                                                                                            /~'      R$il[  _
Docket No. 50-461                              ,                    gW -]2                    -
Mr. A. B. Davis                                                                kIh~  I % #"
LC Regional Administrator Region III U.S. Nuclear Regulatory Commission 799 Roosevelt Road' Glen Ellyn, Illinois 60137
 
==Subject:==
Five-Day Report, Loss of Perimeter Detection                                                .;
August 16, 1987, Incident Number 011/87                                                        l
 
==Dear Mr. Davis:==
 
Please find attached, for your information, the Five-Day Report on the Loss of Perimeter Detection (Incident Number 011/87). August 16, 1987. This report is being submitted in accordance with 10CFR73.71(c).
If you'have any questions, please contact me.
Sincerely yours, F. A. Spangenberg, III Manager - Licensing.and Safety                              -
JAB /krm Attachment cc without attachments:
B. L. Siegel, NRC Clinton Licensing Project Manager NRC Resident Inspector Illinois Department of Nuclear Safety                                                                    j
                                                                                                                      ,l l
8709010110 870821                                                        AUG 2 51987                    {0E DR  ADOCK 0500g1 '
ir o
 
  ,                                                                                  v Attachment                                    j 1111ncis Power Company                              I Clinton Power Station Incident At approximately 2212 hours, on August 16, 1987, the protected area intrusion detection system was deactivated due to severe weather.
Compensatory measures that were in place -- posting of the perimeter --
were removed due to personnel safety concerns. The protected area              !
perimeter was fully compensated at 2245 hours after the severe weather          !
subsided.                                                                      !
Chronology of Events At approximately 2210 hours, the Shift Liaison directed the Captain to post compensatory security force members on the protected area perimeter because of imminent severe weather.
At approximately 2212 hours, compensatory measures were in place and the protected area alarm points were deactivated,                                    l l
l    At approximately 2214 hours, vehicles were dispatched to pick up security force members from all of the compensatory post booths due to severe winds.
At approximately.2215 hours, additional security force members were posted in the Central Alarm Station (CAS) and Secondary Alarm Station (SAS) as dedicated Closed Circuit Television (CCTV) observers.
At approximately 2235 hours, weather conditions began improving as wind subsided. Posting of compensatory security force members began.
At approximately 2245 hours, the protected area perimeter was properly compensated.
Corrective Actions shift supervision verified that winds had exceeded seventy-five (75) miles per hour. Protection of personnel safety and the posting of dedicated CCTV observers were the appropriate actions to be taken. No further corrective actions are necessary.
Conclusion Illinois Power considers this incident to be a moderate loss of physical security effectiveness.
_ . _ _ _}}