#REDIRECT [[ND-18-0986, Tenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)]]
| number = ML18242A066
| issue date = 08/29/2018
| title = Vogtle, Units 3 and 4, Tenth Six-Month Status Report of the Implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049)
| author name = Yox M J
| author affiliation = Southern Nuclear Operating Co, Inc
| addressee name =
| addressee affiliation = NRC/Document Control Desk, NRC/NRO
| docket = 05200025, 05200026
| license number =
| contact person =
| case reference number = EA-12-049, ND-18-0986
| document type = Letter, Status Report
| page count = 8
| project =
| stage = Other
}}
 
=Text=
{{#Wiki_filter:Southern Nuclear AUG 2 9 2018 Docket Nos.: 52-025 52-026U.S.Nuclear Regulatory Commission ATTN;Document Control Desk Washington,D.C.20555-0001 Michael J.Yox Regulatory Affairs Director Vogtle 3&4 7825 River Road Waynesboro, GA 30830 706 848 6459 tel myox@southemco.com ND-18-0986 Vogtle Electric Generating Plant-Units3 and 4 Tenth Six-Month StatusReportoftheImplementationoftheRequirementsoftheCommissionOrder withRegardto Mitigation Strategies for Bevond-Desian-Basis External Events (EA-12-0491
 
==References:==
 
1.NRC Order Number EA-12-049, Order Modifying Licenses withRegardto Requirements for MitigationStrategiesfor Beyond-Design-BasisExternalEvents,dated March 12, 2012.2.NRC InterimStaffGuidance JLD-ISG-2012-01, Compliance with Order EA-12-049, Order Modifying Licenses withRegardto Requirements for MitigationStrategiesfor Beyond-Design-BasisExternalEvents, Revision0,datedAugust29,2012.
3.NEI 12-06, Diverse and Flexible Coping Strategies (FLEX)Implementation Guide, Revision 0, dated August 2012.4.SNC Letter ND-13-1702, Vogtle Electric Generating Plant Units3and4 Overall IntegratedPlaninResponseto March 12, 2012 Commission Order Modifying Licenses withRegardtoRequirementsfor MitigationStrategiesfor Beyond-Design-Basis ExternalEvents(Order Number EA-12-049), dated August 22, 2013.Ladies and Gentlemen:
On March 12, 2012, the Nuclear Regulatory Commission (NRC)issuedanorder (Reference 1)toSouthernNuclearOperating Company.Reference1was immediately effectiveanddirected the Vogtle Electric GeneratingPlant-Units3and4 (VEGP 3&4)to develop, implement, and maintainguidanceandstrategiesto maintainorrestorecore cooling, containment,andspent fuel pool cooling capabilities intheeventofa beyond-design-basis external event.Specific requirements are outlined in Attachment3of Reference 1.Reference1 required submissionofan Overall Integrated Plan withinoneyearafterissuanceof the final NRC InterimStaffGuidance(Reference2).Reference2endorses industry guidance document NEI 12-06, Revision0(Reference3) with clarificationsandexceptions identified inReference2.Reference4providedtheVEGP 3&4 OverallIntegratedPlan.
U.S.NuclearRegulatoryCommission ND-18-0986 Page 2 Reference 1 requires submission of a status report at six-month intervals following submittal of the Overall Integrated Plan.Reference 3 provides direction regarding the contentofthestatus reportsandwas followed in developingtheenclosed report.Thepurposeofthisletteristo provide the tenth six-month status report pursuant to Section IV, Condition C.2, of Reference 1,thatdelineatesprogressmade in implementing the requirementsofReference 1.Theenclosed status report provides an update of milestone accomplishmentssincethelast six-month update, includinganychangestothe compliance method, schedule,orneed for reliefandthebasis, if any.Thisletter containsnonew regulatory commitments.Thisletter has been reviewed and determinednottocontain security-related information.Ifyou have any questions, please contact Mr.Dave Midlik at 706-848-6737.
I declare under penalty of perjurythatthe foregoingistrueand correct.Executedonthe davof^(^usj 2018.Respectfully submitted.
Michael J.Vox Vogtle 3&4 Regula^ry Affairs Director SouthernNuclearOperatingCompany MJY/DWM/amw Enclosure; Tenth Six-Month Status Reportofthe Implementationofthe Requirements of the Commission Order withRegardto MitigationStrategiesfor Beyond-Design-Basis External Events (EA-12-049)
U.S.Nuclear Regulatory Commission ND-18-0986 Page 3 cc: Southern Nuclear Operating Company/Georgia Power Company Mr.8.Kuczynski(w/o enclosure)
Mr.D.A.Bost(w/o enclosure)
Mr.M.D.Meier Mr.D.H.Jones (w/o enclosure)Mr.D.L.McKinney Mr.J.8.Klecha Mr.T.W.YelvertonMr.B.H.Whitley Mr.C.R.PierceMs.A.G.AughtmanMr.W.A.Sparkman Ms.A.0.Chamberlain Mr.O.J.Miller Mr.J.D.Williams Mr.M.J.Vox Mr.T.G.PetrakMs.A.L.Pugh Mr.A.8.Parton Ms.K.A.Roberts Mr.C.T.Defnall Document 8ervices RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Regulatory Commission Mr.W.Jones (w/o enclosure)
Ms.J.M.Heisserer Mr.C.P.Patel Mr.M.E.Ernstes Mr.G.J.Khouri Ms.8.E.Temple Mr.F.D.Brown Mr.A.J.Lerch Mr.C.J.Even Ms.V.L.Ordaz Ms.L.A.KentMr.P.B.Donnelly Mr.N.D.KarlovichMs.C.D.Taylor Ms.A.E.Rivera-Varona Mr.B.J.Kemker Oalethorpe Power Corporation Mr.R.B.Brinkman U.S.Nuclear Regulatory Commission ND-18-0986 Page 4 Municipal Electric Authority of Georgia Mr.J.E.Fuller Mr.S.M.Jackson Dalton Utilities Mr.T.Bundros Westinahouse Electric Company.LLC Ms.K.B.CheskoMr.M.L.Clyde Mr.M.N.CorlettiMr.J.Hopkins Mr.D.Hawkins Ms.J.Monahan Other Mr.J.E.Hesler, Bechtel Power CorporationMs.L.A.Matis, Tetra TechNUS,Inc.Dr.W.R.Jacobs, Jr., Ph.D., GDS Associates, Inc.Mr.S.Roetger, Georgia Public Service CommissionMs.S.W.Kernizan, Georgia Public Service CommissionMr.K.C.Greene, Troutman SandersMr.S.Blanton, Balch BIngham Southern Nuclear Operating Company ND-18-0986 Enclosure Vogtle Electric Generating Plant Units 3 and 4 Tenth Six-Month Status Report of the Impiementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Bevond-Desiqn-Basis External Events IEA-12-0491 (This enclosure consistsof4 pagesincludingthis cover page)
ND-18-0986 Enclosure Tenth Six-Month Status Reportofthe implementationofthe Requirementsofthe Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049) 1 Introduction Vogtle Electric Generating Plant-Units3and4 developed an Overall Integrated Plan (Reference 1 in Section 8), documenting the diverse and flexible strategies (FLEX), in response to Nuclear Regulatory Commission Order EA-12-049 (Reference 2).This status report provides an update of milestone accomplishmentssincethelast six-month update, including anychangestothe compliance method, schedule,orneed for relief/relaxationandthe basis, if any.2 Milestone Accomplishments In additiontothe submittalofstatus reports, the following milestone(s) directly related to FLEX implementationhavebeen completedsincethelast six-month update (Reference 3),andare current as of June 30, 2018:*None 3 Milestone Schedule Status The followingprovidesamilestonescheduleupdate with the activity statusofeach item, andwhethertheexpected completiondatehaschanged.Thedatesare planningdatessubjectto changeasdesignand implementationdetailsaredeveloped.Thetablecontainsnewand revised milestone activities, designatedinItalics.Therevised milestone target completiondatesdonotimpacttheOrder implementation date.Page 2 of 4 ND-18-0986 Enclosure Tenth Six-Month Status Reportofthe Implementationofthe Requirementsofthe Commission Order with Regard to Mitigation Strategies for Beyond-Deslgn-Basis External Events (EA-12-049)
Milestone Target Completion Date Activity Status Revised Target Completion Date Submit60Day Status Report Oct2012 Complete N/A Submit Overall Integrated Plan (OIP)Aug 2013 Complete N/A Submit 6 Month Status Report Feb 2014 Complete N/A Submit 6 Month Status Report Aug 2014 Complete N/A Submit 6 Month Status Report Feb 2015 Complete N/A Submit6Month Status Report Aug 2015 Complete N/A Submit 6 Month Status Report Feb 2016 Complete N/A Submit 6 Month Status Report Aug 2016 Complete N/A Submit 6 Month Status Report Feb 2017 Complete N/A Submit 6 Month Status Report Aug 2017 Complete N/A Submit 6 Month Status Report Feb 2018 Complete N/A Submit 6 Month Status Report Aug 2018 Complete N/A Submit 6 Month Status Report^Feb 2019 Not Started N/A Submit 6 Month Status Report Aug 2019 Not Started N/A Develop FLEX training Aug 2019 In progress N/A Staffing Analysis Completed Oct2019 Not Started N/A Ensure Operational Procedures Include necessary Information NOV2019 In progress N/A Complete Response Plan with NSRC (storage plan and procedural guidance for strategy/maintenance)
Nov2019 In progress N/A Initiate Phase 3 Equipment Procurement Dec 2019 Not Started Submit 6 Month Status Report Feb 2020 Not Started N/A Demonstration for Unit 3 Apr 2020 Not Started N/A Completion Report for Unit 3 Dec 2020 Not Started Jun 2020 NSRC Operational for Vogtle 3&4 Aug 2020 Not Started N/A Training Complete for Phase3to include connection and use of redundant off site equipment for Anciiiary Equipment.
Aug 2020 Not Started Feb 2020 Submit 6 Month Status Report Aug 2020 Not Started N/A Submit 6 Month Status Report Feb 2021 Not Started N/A Demonstration for Unit 4 Apr 2021 Not Started N/A Submit Completion Report for Unit 4 and Final Integrated Plan (FIR)Jun 2021 Not Started N/A Unit3-Full compliancepriorto Fuel Load for Unit 3 Unit4-Full compliancepriorto Fuel Load for Unit 4^Updated plant-specific GIF anticipatedtobe submitted with Feb 2019 6-month update.Page 3 of 4 ND-18-0986 Enclosure Tenth Six-MonthStatusReportofthe Implementationofthe Requirementsofthe Commission Order withRegardto MitigationStrategiesfor Beyond-Deslgn-Basis External Events (EA-12-049) 4 Changes to Compliance Method There are no changes to the compliance method as documented In Reference 1.5 Need for Relief/Relaxation and Basis for the Relief/Relaxation Vogtle ElectricGeneratingPlant-Units3and4expectsto comply withtheorder Implementation date andnorelief/relaxationIs required at this time.6 Open Items from Overall Integrated Plan and Draft Safety Evaluation The following tables provideasummaryoftheopenItemsdocumented In the Overall IntegratedPlanor the Draft Safety Evaluation (SE)and the status of each Item.Overall Integrated Plan Open Item Status N/A N/A Draft Safety Evaluation Open Item Status Draft Safety Evaluation not received N/A 7 Potential Draft Safety Evaluation ImpactsADraft Safety Evaluation has not been received.8 References The following references support the updates to the Overall Integrated Plan described In this enclosure.
1.SNCLetter ND-13-1702, Vogtle Electric Generating PlantUnits3 and4Overall IntegratedPlanin ResponsetoMarch 12,2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049), dated August 22, 2013.2.NRG Order Number EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, dated March 12, 2012.3.SNCletter ND-18-0154, Vogtle Electric Generating Plant-Units3 and4NinthSix-Month Status Reportofthe implementation of the Requirements of the Commission Order with Regard to Mitigation Strategies for Beyond-Design-Basis External Events (EA-12-049), dated February 26, 2018.Page 4 of 4}}