ML18086B617: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
Line 27: Line 27:
* Liden, Manager
* Liden, Manager
                                                                 ,,:Nuclear Licensing and
                                                                 ,,:Nuclear Licensing and
                                                                 /Regulation
                                                                 /Regulation CC    Mr. Leif' Norrholm NRC Senior Resident Inspector - Salem Mr. William J. Ross NRC Licensing Project Manager
                                                          ;*
CC    Mr. Leif' Norrholm NRC Senior Resident Inspector - Salem Mr. William J. Ross NRC Licensing Project Manager
_ The Energy People 8208250198 820813                                                                                        95-2001 (400MI 10-81 PDR ADOCK 05000272 P                  PDR}}
_ The Energy People 8208250198 820813                                                                                        95-2001 (400MI 10-81 PDR ADOCK 05000272 P                  PDR}}

Revision as of 11:55, 23 February 2020

Responds to NRC 820712 Ltr Re post-accident sampling/post- Implementation review.Post-accident Sampling Sys for Each Unit Expected to Be Installed & Operational Prior to Startup Following Upcoming Refueling Outage
ML18086B617
Person / Time
Site: Salem  
Issue date: 08/13/1982
From: Liden E
Public Service Enterprise Group
To: Varga S
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-2.B.3, TASK-TM NUDOCS 8208250198
Download: ML18086B617 (1)


Text

Public Service PS~G Electric and Gas Company 80 Park Plaza, Newark, NJ 07101 / 201 430-7000 MAILING ADDRESS/ PO. Box 570, Newark, NJ 07101 August 13, 1982 Mr. Steven A. Varga, Chief Operating Reactors Branch #1 Division of Licensing

u. s. Nuclear Regulatory Commission 7920 Norfolk Avenue Bethesda, MD 20014 Gentlemen:

NUREG-0737 ITEM II.B.3, POST-ACCIDENT SAMPLING POST IMPLEMENTATION REVIEW SALEM UNITS NO. 1 AND 2 This response is in answer to your letter dated July 12, 1982.

The Post-Accident Sampling System for each Salem Unit is expected to be installed and operational prior to startup following each unit's upcoming refueling outage.

We will document how we have satisfied each of the criteria of NUREG-0737, ITEM II.B.3 within one month after completion of the Unit No. 1 refueling outage. Our submittal will cover both Sale~ Units. *

  • Very truly yours,

/

,~*/"/.j E,./

  • Liden, Manager

,,:Nuclear Licensing and

/Regulation CC Mr. Leif' Norrholm NRC Senior Resident Inspector - Salem Mr. William J. Ross NRC Licensing Project Manager

_ The Energy People 8208250198 820813 95-2001 (400MI 10-81 PDR ADOCK 05000272 P PDR