Agency Response Dated May 21, 2018:        In the Agencys response dated March 8, 2018, the staff communicated that the Commission paper was expected to be submitted no later than March 8, 2018. On April 24, 2018, staff submitted SECY-18-0050, Analysis and Options for Export Inspection Program, in response to OIG-17-A-08.
Agency Response Dated May 21, 2018:        In the Agencys response dated March 8, 2018, the staff communicated that the Commission paper was expected to be submitted no later than March 8, 2018. On April 24, 2018, staff submitted SECY-18-0050, Analysis and Options for Export Inspection Program, in response to OIG-17-A-08.
To date, the Commission has not issued a Staff Requirements Memorandum related to the Commission Paper.
To date, the Commission has not issued a Staff Requirements Memorandum related to the Commission Paper.
Target Completion Date: Completed Agency Point of Contact:
Target Completion Date: Completed Agency Point of
 
==Contact:==
Peter Habighorst, OIP/ECNP (301) 287-9241 OIG Analysis:        OIG has reviewed SECY-18-0050 and acknowledges that NRC has proposed random pre-licensing site visits as one of three options for the Commission to consider. However, the agency recommended the Commission to not change the current pre-licensing inspection policy (or lack thereof).
Peter Habighorst, OIP/ECNP (301) 287-9241 OIG Analysis:        OIG has reviewed SECY-18-0050 and acknowledges that NRC has proposed random pre-licensing site visits as one of three options for the Commission to consider. However, the agency recommended the Commission to not change the current pre-licensing inspection policy (or lack thereof).
Thus the proposed actions may not meet the intent of the recommendation.
Thus the proposed actions may not meet the intent of the recommendation.
Status:              Resolved.}}
Status:              Resolved.}}

Latest revision as of 12:09, 30 November 2019

OIG-17-A-08-Audit of the U.S Nuclear Regulatory Commission'S Oversight of Source Material Exports to Foreign Countries, Dated June 26, 2018
ML18177A407
Person / Time
Issue date: 06/26/2018
From: Baker B
NRC/OIG/AIGA
To: Mccree V
NRC/EDO
References
OIG-17-A-08
Download: ML18177A407 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 OFFICE OF THE INSPECTOR GENERAL June 26, 2018 MEMORANDUM TO: Victor M. McCree Executive Director for Operations FROM: Dr. Brett M. Baker /RA/

Assistant Inspector General for Audits

SUBJECT:

AUDIT OF THE U.S. NUCLEAR REGULATORY COMMISSIONS OVERSIGHT OF SOURCE MATERIAL EXPORTS TO FOREIGN COUNTRIES (OIG-17-A-08)

REFERENCE:

DIRECTOR, OFFICE OF INTERNATIONAL PROGRAMS, MEMORANDUM DATED MAY 21, 2018 Attached is the Office of the Inspector Generals (OIG) analysis and status of recommendation 1 as discussed in the agencys response dated May 21, 2018. Based on this response, recommendation 1 remains resolved. Recommendations 2, 3, 4, and 5 were previously closed. Please provide an updated status of the resolved recommendation by December 31, 2018.

If you have any questions or concerns, please call me at (301) 415-5915, or Sherri Miotla, Team Leader at (301) 415-5914.

Attachment:

As stated cc: R. Lewis, OEDO H. Rasouli, OEDO J. Jolicoeur, OEDO J. Bowen, OEDO EDO_ACS Distribution

Audit Report AUDIT OF THE U.S. NUCLEAR REGULATORY COMMISSIONS OVERSIGHT OF SOURCE MATERIAL EXPORTS TO FOREIGN COUNTRIES OIG-17-A-08 Status of Recommendations Recommendation 1: Coordinate among the Office of International Programs (OIP), Office of Nuclear Materials Safety and Safeguards (NMSS), and regional offices, as appropriate, in developing and implementing an export inspection program to include pre-licensing site visits and periodic post-licensing inspections at Part 110 applicant and licensee locations.

The pre-licensing visits may only apply to export applicants who do not already possess another NRC license.

Agency Response Dated May 21, 2018: In the Agencys response dated March 8, 2018, the staff communicated that the Commission paper was expected to be submitted no later than March 8, 2018. On April 24, 2018, staff submitted SECY-18-0050, Analysis and Options for Export Inspection Program, in response to OIG-17-A-08.

To date, the Commission has not issued a Staff Requirements Memorandum related to the Commission Paper.

Target Completion Date: Completed Agency Point of

Contact:

Peter Habighorst, OIP/ECNP (301) 287-9241 OIG Analysis: OIG has reviewed SECY-18-0050 and acknowledges that NRC has proposed random pre-licensing site visits as one of three options for the Commission to consider. However, the agency recommended the Commission to not change the current pre-licensing inspection policy (or lack thereof).

Thus the proposed actions may not meet the intent of the recommendation.

Status: Resolved.