ML080920170: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:April 9, 2008  
{{#Wiki_filter:April 9, 2008 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
 
Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702
Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702  


==SUBJECT:==
==SUBJECT:==
CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 - REVISION TO REACTOR PRESSURE VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE (TAC NO. MD8235)  
CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 - REVISION TO REACTOR PRESSURE VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE (TAC NO. MD8235)


==Dear Mr. Spina:==
==Dear Mr. Spina:==


By letter dated March 5, 2008, Calvert Cliffs Nuclear Power Plant, Inc. submitted for Nuclear Regulatory Commission (NRC) staff review a request for revising the withdrawal schedule for the reactor pressure vessel (RPV) surveillance capsule at the 104° location for Calvert Cliffs Nuclear Power Plant (CCNPP), Unit No. 1. The purpose of the licensee's submittal was to provide a surveillance capsule withdrawal schedule for CCNPP, Unit No. 1 that is consistent with the most recent projected extended end-of-license fluence at one-quarter of the RPV wall thickness.  
By letter dated March 5, 2008, Calvert Cliffs Nuclear Power Plant, Inc. submitted for Nuclear Regulatory Commission (NRC) staff review a request for revising the withdrawal schedule for the reactor pressure vessel (RPV) surveillance capsule at the 104° location for Calvert Cliffs Nuclear Power Plant (CCNPP), Unit No. 1. The purpose of the licensees submittal was to provide a surveillance capsule withdrawal schedule for CCNPP, Unit No. 1 that is consistent with the most recent projected extended end-of-license fluence at one-quarter of the RPV wall thickness.
 
The NRC staff has completed its review and concludes that the proposed withdrawal schedule for the CCNPP, Unit No. 1 capsule mentioned above meets the requirements of the American Society for Testing and Materials Standard E185-82, Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels, and Appendix H to Title 10 of the Code of Federal Regulations Part 50, Reactor Vessel Material Surveillance Program Requirements. The staffs safety evaluation is enclosed.
The NRC staff has completed its review and concludes that the proposed withdrawal schedule for the CCNPP, Unit No. 1 capsule mentioned above meets the requirements of the American Society for Testing and Materials Standard E185-82, "Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels," and Appendix H to Title 10 of the Code of Federal Regulations Part 50, "Reactor Vessel Material Surveillance Program Requirements.The staff's safety evaluation is enclosed.  
Please contact me at 301-415-1364 if you have any questions.
 
Sincerely,
Please contact me at 301-415-1364 if you have any questions.  
                                              /RA/
 
Douglas V. Pickett, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-317
Sincerely,       /RA/
Douglas V. Pickett, S enior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation  
 
Docket No. 50-317  


==Enclosure:==
==Enclosure:==


Safety Evaluation  
Safety Evaluation cc w/encl: See next page


cc w/encl:  See next page 
ML080920170 OFFICE LPLI-1/PM                LPLI-1/LA              CVIB/BC              LPLI-1/BC NAME        DPickett            SLittle                MMitchell as signed MKowal on DATE        4 /4/ 08            4 / 8/ 08              3 / 20 / 08          4 /9/ 08


ML080920170 OFFICE  LPLI-1/PM LPLI-1/LA CVIB/BC  LPLI-1/BC
Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 cc:
 
Regional Administrator, Region I Mr. Michael J. Wallace, President                   U.S. Nuclear Regulatory Commission Constellation Energy Nuclear Group, LLC             475 Allendale Road 750 East Pratt Street, 18th Floor                   King of Prussia, PA 19406 Baltimore, MD 21202 Ms. Kristen A. Burger, Esquire Mr. John M. Heffley, Senior Vice President         Maryland People's Counsel and Chief Nuclear Officer                         6 St. Paul Centre Constellation Energy Nuclear Generation             Suite 2102 Group                                             Baltimore, MD 21202-1631 111 Market Place Baltimore, MD 21202                                 Ms. Patricia T. Birnie, Esquire Co-Director President                                           Maryland Safe Energy Coalition Calvert County Board of                             P.O. Box 33111 Commissioners                                     Baltimore, MD 21218 175 Main Street Prince Frederick, MD 20678                         Mr. Roy Hickok NRC Technical Training Center Mr. Carey Fleming, Esquire                         5700 Brainerd Road Sr. Counsel - Nuclear Generation                   Chattanooga, TN 37411-4017 Constellation Energy Nuclear Group, LLC 750 East Pratt Street, 17th floor                   Mr. Louis S. Larragoite Baltimore, MD 21202                                 Manager - Nuclear Licensing Constellation Energy Nuclear Generation Mr. Jay S. Gaines                                     Group Director, Licensing                                 111 Market Place, 2nd Floor Calvert Cliffs Nuclear Power Plant                 Baltimore, MD 21202 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Ms. Susan T. Gray, Program Manager Power Plant Assessment Program Maryland Department of Natural Resources Tawes State Office Building B-3 580 Taylor Avenue Annapolis, MD 21401
NAME  DPickett  SLittle  MMitchell as signed on  MKowal DATE  4 /4/ 08  4 / 8/ 08 3 / 20 / 08 4 /9/ 08 Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2  
 
cc:
 
Mr. Michael J. Wallace, President Constellation Energy Nuclear Group, LLC 750 East Pratt Street, 18 th Floor Baltimore, MD 21202  
 
Mr. John M. Heffley, Senior Vice President and Chief Nuclear Officer Constellation Energy Nuclear Generation Group 111 Market Place Baltimore, MD 21202  
 
President Calvert County Board of Commissioners 175 Main Street Prince Frederick, MD 20678  
 
Mr. Carey Fleming, Esquire Sr. Counsel - Nuclear Generation Constellation Energy Nuclear Group, LLC 750 East Pratt Street, 17 th floor Baltimore, MD 21202  
 
Mr. Jay S. Gaines Director, Licensing Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702  
 
Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685  
 
Ms. Susan T. Gray, Program Manager Power Plant Assessment Program Maryland Department of Natural Resources Tawes State Office Building B-3 580 Taylor Avenue Annapolis, MD 21401  
 
Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA  19406
 
Ms. Kristen A. Burger, Esquire Maryland People's Counsel 6 St. Paul Centre Suite 2102 Baltimore, MD  21202-1631
 
Ms. Patricia T. Birnie, Esquire Co-Director Maryland Safe Energy Coalition P.O. Box 33111 Baltimore, MD  21218
 
Mr. Roy Hickok NRC Technical Training Center 5700 Brainerd Road Chattanooga, TN  37411-4017
 
Mr. Louis S. Larragoite Manager - Nuclear Licensing Constellation Energy Nuclear Generation Group 111 Market Place, 2 nd Floor Baltimore, MD 21202
 
Enclosure 


SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION REACTOR VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE REVISION CALVERT CLIFFS NUCLEAR POWER PLANT, INC.
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION REACTOR VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE REVISION CALVERT CLIFFS NUCLEAR POWER PLANT, INC.
CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-317
CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-317


==1.0 INTRODUCTION==
==1.0     INTRODUCTION==
 
By letter dated March 5, 2008 (Agencywide Documents Access Management Systems Accession No. ML080660110), Calvert Cliffs Nuclear Power Plant, Inc. submitted for staff review a request for revising the withdrawal schedule for the reactor pressure vessel (RPV) surveillance capsule at the 104° location for Calvert Cliffs Nuclear Power Plant (CCNPP), Unit No. 1. The purpose of the licensee's submittal was to provide an RPV surveillance capsule withdrawal schedule for CCNPP, Unit  No. 1, that is consistent with the recently projected 60-year end-of-license (EOL) fluence at one-quarter of the RPV wall thickness (1/4T).
 
2.0 REGULATORY REQUIREMENTS
 
The surveillance program for CCNPP, Unit No. 1, was implemented to monitor the radiation-induced changes in the mechanical and impact properties of the RPV materials. The surveillance program was established in accordance with Appendix H to Title 10 of the Code of Federal Regulations Part 50 (10 CFR Part 50), "Reactor Vessel Material Surveillance Program Requirements."  Appendix H to 10 CFR Part 50 requires licensees to monitor changes in the fracture toughness properties of ferritic materials in the RPV beltline region of light water nuclear power reactors. Appendix H to 10 CFR Part 50 states that the design of the surveillance program and the withdrawal schedule must meet the requirements of the edition of the American Society for Testing and Materials (ASTM) Standard E185, "Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels," that is current on the issue date of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) to which the reactor vessel was purchased. Later editions of ASTM E185 may be used including those editions through 1982 (ASTM E 185-82). The RPV surveillance program for CCNPP, Unit No. 1, was initially established per ASTM E 185-70, which was the edition of the ASTM standard that was current on the issue date of the ASME Code to which the CCNPP, Unit No. 1 RPV was designed. However, its current surveillance capsule withdrawal schedule has been developed in accordance with ASTM E 185-
: 82. 
 
==3.0  TECHNICAL EVALUATION==
 
The licensee's RPV surveillance program for CCNPP, Unit No. 1, is in accordance with the ASTM E185-82 standard and has a five-capsule withdrawal schedule (the sixth capsule is


considered standby). This surveillance program, which was approved on November 8, 2000, was revised to satisfy the commitments stated in the NRC "Safety Evaluation Report Related to the License Renewal of Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (NUREG-1705)" for properly monitoring changes in the fracture toughness properties of RPV beltline materials during the extended period of operation. Currently, the first two capsules have been withdrawn and analyzed. The third capsule, the capsule at the 104° location, was scheduled to be withdrawn during the CCNPP, Unit No. 1 spring 2008 refueling outage. This schedule was based on the projected 60-year EOL 1/4T fluence of 2.96 X 10 19 n/cm 2 (E > 1.0 MeV) and the same projected fluence in 2008 for the third capsule. As reported in the submittal, these projected values have been revised to 3.06 X 10 19 n/cm 2 (E > 1.0 MeV) for the 60-year EOL 1/4T fluence and 3.12 X 10 19 n/cm 2 (E > 1.0 MeV) for the 2010 capsule fluence. Based on this, the licensee proposed to withdraw the third capsule during the unit's spring 2010 refueling outage.  
By letter dated March 5, 2008 (Agencywide Documents Access Management Systems Accession No. ML080660110), Calvert Cliffs Nuclear Power Plant, Inc. submitted for staff review a request for revising the withdrawal schedule for the reactor pressure vessel (RPV) surveillance capsule at the 104° location for Calvert Cliffs Nuclear Power Plant (CCNPP), Unit No. 1. The purpose of the licensees submittal was to provide an RPV surveillance capsule withdrawal schedule for CCNPP, Unit No. 1, that is consistent with the recently projected 60-year end-of-license (EOL) fluence at one-quarter of the RPV wall thickness (1/4T).
2.0     REGULATORY REQUIREMENTS The surveillance program for CCNPP, Unit No. 1, was implemented to monitor the radiation-induced changes in the mechanical and impact properties of the RPV materials. The surveillance program was established in accordance with Appendix H to Title 10 of the Code of Federal Regulations Part 50 (10 CFR Part 50), Reactor Vessel Material Surveillance Program Requirements. Appendix H to 10 CFR Part 50 requires licensees to monitor changes in the fracture toughness properties of ferritic materials in the RPV beltline region of light water nuclear power reactors. Appendix H to 10 CFR Part 50 states that the design of the surveillance program and the withdrawal schedule must meet the requirements of the edition of the American Society for Testing and Materials (ASTM) Standard E185, Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels, that is current on the issue date of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) to which the reactor vessel was purchased. Later editions of ASTM E185 may be used including those editions through 1982 (ASTM E 185-82).
The RPV surveillance program for CCNPP, Unit No. 1, was initially established per ASTM E 185-70, which was the edition of the ASTM standard that was current on the issue date of the ASME Code to which the CCNPP, Unit No. 1 RPV was designed. However, its current surveillance capsule withdrawal schedule has been developed in accordance with ASTM E 185-82.
Enclosure


ASTM E185-82 recommends that in a five capsule surveillance program the third capsule be withdrawn and tested at the time when the accumulated neutron fluence of the capsule corresponds to approximately the EOL 1/4T fluence. As discussed above, it is evident that the newly projected 2010 fluence for the third capsule is closer to the EOL 1/4T fluence than the previously projected fluence for the third capsule in 2008. Therefore, the NRC staff determined that withdrawing the third capsule during the unit's spring 2010 refueling outage meets the ASTM E185-82 recommendation for the third capsule. Table 2 of the submittal showed that the withdrawal schedule for all other capsules (Capsules 4, 5, and standby) remained unchanged. This is reasonable considering the minor change in the projected 60-year EOL 1/4T fluence. Based on this, the staff determined that Capsules 4 and 5 still meet the ASTM E185-82 recommendation and the NUREG-1705 commitments. When better fluence predictions become available after the Capsule 3 data are analyzed, the licensee will perform additional evaluations to adjust, if necessary, the remaining capsule withdrawal schedules in accordance with 10 CFR Part 50, Appendix H, as stated in the submittal.  
==3.0      TECHNICAL EVALUATION==


==4.0  CONCLUSION==
The licensees RPV surveillance program for CCNPP, Unit No. 1, is in accordance with the ASTM E185-82 standard and has a five-capsule withdrawal schedule (the sixth capsule is considered standby). This surveillance program, which was approved on November 8, 2000, was revised to satisfy the commitments stated in the NRC Safety Evaluation Report Related to the License Renewal of Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (NUREG-1705) for properly monitoring changes in the fracture toughness properties of RPV beltline materials during the extended period of operation. Currently, the first two capsules have been withdrawn and analyzed. The third capsule, the capsule at the 104° location, was scheduled to be withdrawn during the CCNPP, Unit No. 1 spring 2008 refueling outage. This schedule was based on the projected 60-year EOL 1/4T fluence of 2.96 X 1019 n/cm2 (E > 1.0 MeV) and the same projected fluence in 2008 for the third capsule. As reported in the submittal, these projected values have been revised to 3.06 X 1019 n/cm2 (E > 1.0 MeV) for the 60-year EOL 1/4T fluence and 3.12 X 1019 n/cm2 (E > 1.0 MeV) for the 2010 capsule fluence. Based on this, the licensee proposed to withdraw the third capsule during the units spring 2010 refueling outage.
ASTM E185-82 recommends that in a five capsule surveillance program the third capsule be withdrawn and tested at the time when the accumulated neutron fluence of the capsule corresponds to approximately the EOL 1/4T fluence. As discussed above, it is evident that the newly projected 2010 fluence for the third capsule is closer to the EOL 1/4T fluence than the previously projected fluence for the third capsule in 2008. Therefore, the NRC staff determined that withdrawing the third capsule during the units spring 2010 refueling outage meets the ASTM E185-82 recommendation for the third capsule.
Table 2 of the submittal showed that the withdrawal schedule for all other capsules (Capsules 4, 5, and standby) remained unchanged. This is reasonable considering the minor change in the projected 60-year EOL 1/4T fluence. Based on this, the staff determined that Capsules 4 and 5 still meet the ASTM E185-82 recommendation and the NUREG-1705 commitments. When better fluence predictions become available after the Capsule 3 data are analyzed, the licensee will perform additional evaluations to adjust, if necessary, the remaining capsule withdrawal schedules in accordance with 10 CFR Part 50, Appendix H, as stated in the submittal.


Based on the NRC staff's review of the submittal, the staff found that the revised withdrawal schedule for CCNPP, Unit No. 1, RPV satisfy the requirements of ASTM E185-82 and Appendix H to 10 CFR Part 50. In addition, the staff found that the revised withdrawal schedules for CCNPP still fulfills the commitment associated with Item 69 in Appendix E of NUREG-1705 for the renewed license period of 60 years. Therefore, the staff concludes that the licensee's modified withdrawal schedule for CCNPP, Unit No. 1 is acceptable. Principal Contributor:  S. Sheng
==4.0      CONCLUSION==


Date: April 9, 2008}}
Based on the NRC staffs review of the submittal, the staff found that the revised withdrawal schedule for CCNPP, Unit No. 1, RPV satisfy the requirements of ASTM E185-82 and Appendix H to 10 CFR Part 50. In addition, the staff found that the revised withdrawal schedules for CCNPP still fulfills the commitment associated with Item 69 in Appendix E of NUREG-1705 for the renewed license period of 60 years. Therefore, the staff concludes that the licensees modified withdrawal schedule for CCNPP, Unit No. 1 is acceptable.
Principal Contributor: S. Sheng Date: April 9, 2008}}

Revision as of 19:17, 14 November 2019

Revision to Reactor Pressure Vessel Surveillance Capsule Withdrawal Schedule
ML080920170
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 04/09/2008
From: Pickett D
NRC/NRR/ADRO/DORL/LPLI-1
To: Spina J
Calvert Cliffs
Pickett D, NRR/DORL, 415-1364
References
TAC MD8235
Download: ML080920170 (5)


Text

April 9, 2008 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.

Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

SUBJECT:

CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 - REVISION TO REACTOR PRESSURE VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE (TAC NO. MD8235)

Dear Mr. Spina:

By letter dated March 5, 2008, Calvert Cliffs Nuclear Power Plant, Inc. submitted for Nuclear Regulatory Commission (NRC) staff review a request for revising the withdrawal schedule for the reactor pressure vessel (RPV) surveillance capsule at the 104° location for Calvert Cliffs Nuclear Power Plant (CCNPP), Unit No. 1. The purpose of the licensees submittal was to provide a surveillance capsule withdrawal schedule for CCNPP, Unit No. 1 that is consistent with the most recent projected extended end-of-license fluence at one-quarter of the RPV wall thickness.

The NRC staff has completed its review and concludes that the proposed withdrawal schedule for the CCNPP, Unit No. 1 capsule mentioned above meets the requirements of the American Society for Testing and Materials Standard E185-82, Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels, and Appendix H to Title 10 of the Code of Federal Regulations Part 50, Reactor Vessel Material Surveillance Program Requirements. The staffs safety evaluation is enclosed.

Please contact me at 301-415-1364 if you have any questions.

Sincerely,

/RA/

Douglas V. Pickett, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-317

Enclosure:

Safety Evaluation cc w/encl: See next page

ML080920170 OFFICE LPLI-1/PM LPLI-1/LA CVIB/BC LPLI-1/BC NAME DPickett SLittle MMitchell as signed MKowal on DATE 4 /4/ 08 4 / 8/ 08 3 / 20 / 08 4 /9/ 08

Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2 cc:

Regional Administrator, Region I Mr. Michael J. Wallace, President U.S. Nuclear Regulatory Commission Constellation Energy Nuclear Group, LLC 475 Allendale Road 750 East Pratt Street, 18th Floor King of Prussia, PA 19406 Baltimore, MD 21202 Ms. Kristen A. Burger, Esquire Mr. John M. Heffley, Senior Vice President Maryland People's Counsel and Chief Nuclear Officer 6 St. Paul Centre Constellation Energy Nuclear Generation Suite 2102 Group Baltimore, MD 21202-1631 111 Market Place Baltimore, MD 21202 Ms. Patricia T. Birnie, Esquire Co-Director President Maryland Safe Energy Coalition Calvert County Board of P.O. Box 33111 Commissioners Baltimore, MD 21218 175 Main Street Prince Frederick, MD 20678 Mr. Roy Hickok NRC Technical Training Center Mr. Carey Fleming, Esquire 5700 Brainerd Road Sr. Counsel - Nuclear Generation Chattanooga, TN 37411-4017 Constellation Energy Nuclear Group, LLC 750 East Pratt Street, 17th floor Mr. Louis S. Larragoite Baltimore, MD 21202 Manager - Nuclear Licensing Constellation Energy Nuclear Generation Mr. Jay S. Gaines Group Director, Licensing 111 Market Place, 2nd Floor Calvert Cliffs Nuclear Power Plant Baltimore, MD 21202 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 287 St. Leonard, MD 20685 Ms. Susan T. Gray, Program Manager Power Plant Assessment Program Maryland Department of Natural Resources Tawes State Office Building B-3 580 Taylor Avenue Annapolis, MD 21401

SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION REACTOR VESSEL SURVEILLANCE CAPSULE WITHDRAWAL SCHEDULE REVISION CALVERT CLIFFS NUCLEAR POWER PLANT, INC.

CALVERT CLIFFS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-317

1.0 INTRODUCTION

By letter dated March 5, 2008 (Agencywide Documents Access Management Systems Accession No. ML080660110), Calvert Cliffs Nuclear Power Plant, Inc. submitted for staff review a request for revising the withdrawal schedule for the reactor pressure vessel (RPV) surveillance capsule at the 104° location for Calvert Cliffs Nuclear Power Plant (CCNPP), Unit No. 1. The purpose of the licensees submittal was to provide an RPV surveillance capsule withdrawal schedule for CCNPP, Unit No. 1, that is consistent with the recently projected 60-year end-of-license (EOL) fluence at one-quarter of the RPV wall thickness (1/4T).

2.0 REGULATORY REQUIREMENTS The surveillance program for CCNPP, Unit No. 1, was implemented to monitor the radiation-induced changes in the mechanical and impact properties of the RPV materials. The surveillance program was established in accordance with Appendix H to Title 10 of the Code of Federal Regulations Part 50 (10 CFR Part 50), Reactor Vessel Material Surveillance Program Requirements. Appendix H to 10 CFR Part 50 requires licensees to monitor changes in the fracture toughness properties of ferritic materials in the RPV beltline region of light water nuclear power reactors. Appendix H to 10 CFR Part 50 states that the design of the surveillance program and the withdrawal schedule must meet the requirements of the edition of the American Society for Testing and Materials (ASTM) Standard E185, Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels, that is current on the issue date of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code) to which the reactor vessel was purchased. Later editions of ASTM E185 may be used including those editions through 1982 (ASTM E 185-82).

The RPV surveillance program for CCNPP, Unit No. 1, was initially established per ASTM E 185-70, which was the edition of the ASTM standard that was current on the issue date of the ASME Code to which the CCNPP, Unit No. 1 RPV was designed. However, its current surveillance capsule withdrawal schedule has been developed in accordance with ASTM E 185-82.

Enclosure

3.0 TECHNICAL EVALUATION

The licensees RPV surveillance program for CCNPP, Unit No. 1, is in accordance with the ASTM E185-82 standard and has a five-capsule withdrawal schedule (the sixth capsule is considered standby). This surveillance program, which was approved on November 8, 2000, was revised to satisfy the commitments stated in the NRC Safety Evaluation Report Related to the License Renewal of Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (NUREG-1705) for properly monitoring changes in the fracture toughness properties of RPV beltline materials during the extended period of operation. Currently, the first two capsules have been withdrawn and analyzed. The third capsule, the capsule at the 104° location, was scheduled to be withdrawn during the CCNPP, Unit No. 1 spring 2008 refueling outage. This schedule was based on the projected 60-year EOL 1/4T fluence of 2.96 X 1019 n/cm2 (E > 1.0 MeV) and the same projected fluence in 2008 for the third capsule. As reported in the submittal, these projected values have been revised to 3.06 X 1019 n/cm2 (E > 1.0 MeV) for the 60-year EOL 1/4T fluence and 3.12 X 1019 n/cm2 (E > 1.0 MeV) for the 2010 capsule fluence. Based on this, the licensee proposed to withdraw the third capsule during the units spring 2010 refueling outage.

ASTM E185-82 recommends that in a five capsule surveillance program the third capsule be withdrawn and tested at the time when the accumulated neutron fluence of the capsule corresponds to approximately the EOL 1/4T fluence. As discussed above, it is evident that the newly projected 2010 fluence for the third capsule is closer to the EOL 1/4T fluence than the previously projected fluence for the third capsule in 2008. Therefore, the NRC staff determined that withdrawing the third capsule during the units spring 2010 refueling outage meets the ASTM E185-82 recommendation for the third capsule.

Table 2 of the submittal showed that the withdrawal schedule for all other capsules (Capsules 4, 5, and standby) remained unchanged. This is reasonable considering the minor change in the projected 60-year EOL 1/4T fluence. Based on this, the staff determined that Capsules 4 and 5 still meet the ASTM E185-82 recommendation and the NUREG-1705 commitments. When better fluence predictions become available after the Capsule 3 data are analyzed, the licensee will perform additional evaluations to adjust, if necessary, the remaining capsule withdrawal schedules in accordance with 10 CFR Part 50, Appendix H, as stated in the submittal.

4.0 CONCLUSION

Based on the NRC staffs review of the submittal, the staff found that the revised withdrawal schedule for CCNPP, Unit No. 1, RPV satisfy the requirements of ASTM E185-82 and Appendix H to 10 CFR Part 50. In addition, the staff found that the revised withdrawal schedules for CCNPP still fulfills the commitment associated with Item 69 in Appendix E of NUREG-1705 for the renewed license period of 60 years. Therefore, the staff concludes that the licensees modified withdrawal schedule for CCNPP, Unit No. 1 is acceptable.

Principal Contributor: S. Sheng Date: April 9, 2008