{{#Wiki_filter:Apr 12Start ASLB HearingProcessApr-12CompleteFuel LoadProcedure(TVA)Apr-12TVA Certification of As-Built Plant(TVA)May-12Integrated Safeguards Test(TVA)Feb-12TVA Certify Tech SpecsFeb-12Primary Hydro(TVA)Feb-12Final As-Built Drawing(TVA)Sep-12NRC Senior Mgt Meeting at SiteOct-12ASLB HearingComplete& DecisionOct-12Certification of As-BuiltPlant (R-II)Feb-12Issue FinalFES-OL (NRR)Feb-12Cyber Security Inspection(NSIR)Oct-11Cyber Security Pilot (NSIR)Oct-11ACRS Subcommittee Mar-12INPO ReadinessAssessment(TVA)Dec-12Commission Briefings Mar-12Complete Hot Functional Testing(TVA)Nov-12Commission PaperJan-12Complete Fire Protection ProgramReview (NRR)Apr-12Final ACRS SubcommitteeOct-12Operational Readiness Assessment(R-II)Aug-11Issue Draft EIS for Public Comment(NRR)Jul-11ACRS SubcommitteeOct-11Emergency Preparedness DrillAug-11Proof andReviewTech SpecsJun-12Load IceBaskets(TVA)Dec-11ACRS SubcommitteeFeb-12Complete Pre-Operational Testing (TVA)Dec-12Issue Full Power License(NRR)WATTS BAR UNIT 2 REACTIVATION PROJECT PLANU.S. Nuclear Regulatory CommissionOffice of Nuclear Reactor Regulation PHASE II PHASE IIIOct-12VerifyReadiness to Load Fuel(R-II)May-12ACRS Full-CommitteeMar 12-Oct 12 Hearings and BriefingsCenter for Planning and Analysis Branch Control Number: 171273_DP_TMLN_Rev19.vsdJul 11Oct 11Jan 12 Apr 12Jul 12 Oct 1220112012Dec-12Fuel Load(TVA)Nov 12-Dec 12 Operating License PHASE IV As of July 21, 2011Jun 11-Feb 12Production Review Hearing Option}}
{{#Wiki_filter:Jul 11                          Oct 11                          Jan 12                              Apr 12                                Jul 12                          Oct 12 2011                                                                                                                                                                                                                    2012 Aug-11                                                      Feb-12                  Apr 12                                                              Oct-12 Issue Draft EIS                                              Issue Final                  Start                                                          ASLB Hearing for Public Comment                                                FES-OL              ASLB Hearing                                                          Complete (NRR)                                                      (NRR)                   Process                                                            & Decision Oct-11                  Jan-12              Feb-12                                                                                        Oct-12 Cyber Security        Complete Fire      Cyber Security                                                                                  Certification Pilot            Protection Program      Inspection                                                                                    of As-Built (NSIR)              Review (NRR)            (NSIR)                                                                                      Plant (R-II)
Jul-11                      Oct-11            Dec-11                                            Apr-12              May-12                        Sep-12                        Nov-12          Dec-12 ACRS                          ACRS              ACRS                                            Final ACRS              ACRS                        NRC Senior Mgt                 Commission        Commission Subcommittee                  Subcommittee      Subcommittee                                      Subcommittee        Full-Committee                  Meeting at Site                    Paper          Briefings Oct-12                Oct-12              Dec-12 Aug-11          Oct-11 Operational              Verify              Issue Proof and      Emergency                                                                                                                      Readiness            Readiness            Full Power Review      Preparedness                                                                                                                    Assessment            to Load Fuel          License Tech Specs          Drill                                                                                                                          (R-II)                 (R-II)            (NRR)
Jun 11 - Feb 12                                                                                    Mar 12 - Oct 12                                            Nov 12 - Dec 12 Production Review                                                                                Hearings and Briefings                                      Operating License Feb-12          Mar-12                    May-12                                                                              Dec-12 Complete        Complete Hot                Integrated                                                                          Fuel Load Pre-Operational    Functional             Safeguards Test                                                                            (TVA)
Testing         Testing                      (TVA)
(TVA)           (TVA)
Feb-12          Mar-12              Apr-12                Jun-12 Final As-Built  INPO Readiness     TVA Certification          Load Ice Drawing        Assessment       of As-Built Plant          Baskets (TVA)          (TVA)               (TVA)                 (TVA)
Feb-12                              Apr-12 Primary                          Complete Hydro                            Fuel Load (TVA)                           Procedure (TVA)
Feb-12 PHASE II                            TVA Certify Tech Specs PHASE III                                              PHASE IV As of July 21, 2011 WATTS BAR UNIT 2 REACTIVATION PROJECT PLAN                                        Center for Planning and Analysis Branch U.S. Nuclear Regulatory Commission                                                      Control Number:
Office of Nuclear Reactor Regulation                                         171273_DP_TMLN_Rev19.vsd Hearing Option Enclosure 1}}

Latest revision as of 18:09, 12 November 2019

SECY-11-0102 - Enclosure 2 - Chart of Future Activities - Fourth Report on Status of Reactivation of Construction and Licensing for Watts Bar Nuclear Plant Unit 2
ML11203A005
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 07/21/2011
From:
Watts Bar Special Projects Branch
To:
Milano Patrick, NRR/DORL 415-1457
Shared Package
ML111530391 List:
References
SECY-11-0102
Download: ML11203A005 (1)


Text

Jul 11 Oct 11 Jan 12 Apr 12 Jul 12 Oct 12 2011 2012 Aug-11 Feb-12 Apr 12 Oct-12 Issue Draft EIS Issue Final Start ASLB Hearing for Public Comment FES-OL ASLB Hearing Complete (NRR) (NRR) Process & Decision Oct-11 Jan-12 Feb-12 Oct-12 Cyber Security Complete Fire Cyber Security Certification Pilot Protection Program Inspection of As-Built (NSIR) Review (NRR) (NSIR) Plant (R-II)

Jul-11 Oct-11 Dec-11 Apr-12 May-12 Sep-12 Nov-12 Dec-12 ACRS ACRS ACRS Final ACRS ACRS NRC Senior Mgt Commission Commission Subcommittee Subcommittee Subcommittee Subcommittee Full-Committee Meeting at Site Paper Briefings Oct-12 Oct-12 Dec-12 Aug-11 Oct-11 Operational Verify Issue Proof and Emergency Readiness Readiness Full Power Review Preparedness Assessment to Load Fuel License Tech Specs Drill (R-II) (R-II) (NRR)

Jun 11 - Feb 12 Mar 12 - Oct 12 Nov 12 - Dec 12 Production Review Hearings and Briefings Operating License Feb-12 Mar-12 May-12 Dec-12 Complete Complete Hot Integrated Fuel Load Pre-Operational Functional Safeguards Test (TVA)

Testing Testing (TVA)

(TVA) (TVA)

Feb-12 Mar-12 Apr-12 Jun-12 Final As-Built INPO Readiness TVA Certification Load Ice Drawing Assessment of As-Built Plant Baskets (TVA) (TVA) (TVA) (TVA)

Feb-12 Apr-12 Primary Complete Hydro Fuel Load (TVA) Procedure (TVA)

Feb-12 PHASE II TVA Certify Tech Specs PHASE III PHASE IV As of July 21, 2011 WATTS BAR UNIT 2 REACTIVATION PROJECT PLAN Center for Planning and Analysis Branch U.S. Nuclear Regulatory Commission Control Number:

Office of Nuclear Reactor Regulation 171273_DP_TMLN_Rev19.vsd Hearing Option Enclosure 1