{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 22, 2016 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008 | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 22, 2016 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008 | ||
==SUBJECT:== | ==SUBJECT:== | ||
FORT CALHOUN STATION, UNIT NO. 1 -CLOSURE OF NRC GENERIC LETTER 2004-02 (CAC NO. MC4686) | FORT CALHOUN STATION, UNIT NO. 1 - CLOSURE OF NRC GENERIC LETTER 2004-02 (CAC NO. MC4686) | ||
==Dear Mr. Marik:== | ==Dear Mr. Marik:== | ||
By letter dated June 24, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16176A213), Omaha Public Power District (OPPD, the licensee) provided a certification of permanent cessation of power operations to the U.S. Nuclear Regulatory Commission (NRC) for Fort Calhoun Station, Unit No. 1 (FCS). OPPD certified to the NRC that it plans to permanently cease power operations at FCS by December 31, 2016. Based upon OPP D's letter, no additional action is requested for FCS for the following NRC generic communication: | |||
* NRC Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004. Therefore, the NRC staff has closed Cost Activity Code (CAC) No. MC4686 for GL 2004-02. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov. | By letter dated June 24, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16176A213), Omaha Public Power District (OPPD, the licensee) provided a certification of permanent cessation of power operations to the U.S. Nuclear Regulatory Commission (NRC) for Fort Calhoun Station, Unit No. 1 (FCS). OPPD certified to the NRC that it plans to permanently cease power operations at FCS by December 31, 2016. | ||
Based upon OPP D's letter, no additional action is requested for FCS for the following NRC generic communication: | |||
* NRC Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004. | |||
Therefore, the NRC staff has closed Cost Activity Code (CAC) No. MC4686 for GL 2004-02. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov. | |||
Sincerely, Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285 cc: Distribution via Listserv | |||
July 22, 2016 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008 | |||
==SUBJECT:== | ==SUBJECT:== | ||
FORT CALHOUN STATION, UNIT NO. 1 -CLOSURE OF NRC GENERIC LETTER 2004-02 (CAC NO. MC4686) | FORT CALHOUN STATION, UNIT NO. 1 - CLOSURE OF NRC GENERIC LETTER 2004-02 (CAC NO. MC4686) | ||
==Dear Mr. Marik:== | ==Dear Mr. Marik:== | ||
By letter dated June 24, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16176A213), Omaha Public Power District (OPPD, the licensee) provided a certification of permanent cessation of power operations to the U.S. Nuclear Regulatory Commission (NRC) for Fort Calhoun Station, Unit No. 1 (FCS). OPPD certified to the NRC that it plans to permanently cease power operations at FCS by December 31, 2016. Based upon OPPD's letter, no additional action is requested for FCS for the following NRC generic communication: | |||
* NRC Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004. Therefore, the NRC staff has closed Cost Activity Code (CAC) No. MC4686 for GL 2004-02. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov. | By letter dated June 24, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16176A213), Omaha Public Power District (OPPD, the licensee) provided a certification of permanent cessation of power operations to the U.S. Nuclear Regulatory Commission (NRC) for Fort Calhoun Station, Unit No. 1 (FCS). OPPD certified to the NRC that it plans to permanently cease power operations at FCS by December 31, 2016. | ||
Based upon OPPD's letter, no additional action is requested for FCS for the following NRC generic communication: | |||
* NRC Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004. | |||
Therefore, the NRC staff has closed Cost Activity Code (CAC) No. MC4686 for GL 2004-02. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov. | |||
/PM NRR/DORL/LPL4-1 | Sincerely, IRA/ | ||
/LA NRR/DPR/PGCB/BC NAME | Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285 cc: Distribution via Listserv DISTRIBUTION: | ||
SStuchell* | PUBLIC LPL4-1 Reading RidsACRS_MailCTR Resource RidsNrrDeEsgb Resource RidsNrrDorllpl4-1 Resource RidsNrrDprPgcb Resource RidsNrrDraApla Resource RidsNrrDssSsib Resource RidsNrrLAJBurkhardt Resource RidsRgn4MailCenter Resource RidsNrrPMFortCalhoun Resource ADAMS A ccess1on N0. ML16180A030 *ema1*1 dae t d **P rev1ous1y concurre d OFFICE N RR/DORL/LPL4-1 /PM NRR/DORL/LPL4-1 /LA NRR/DPR/PGCB/BC NAME FLyon JBurkhardt** SStuchell* | ||
DATE 7/22/16 6/28/16 6/27/16 OFFICE NRR/DSS/SSIB/BC NRR/DORL/LPL4-1/BC NRR/DORL/LPL4-1 | DATE 7/22/16 6/28/16 6/27/16 OFFICE NRR/DSS/SSIB/BC NRR/DORL/LPL4-1/BC NRR/DORL/LPL4-1 /PM NAME VCusumano** RPascarelli FL yon DATE 7/14/16 7/22/16 7/22/16 OFFICIAL RECORD COPY}} | ||
/PM NAME VCusumano** | |||
RPascarelli FL yon DATE 7/14/16 7/22/16 7/22/16 OFFICIAL RECORD COPY}} | |||
Revision as of 17:24, 30 October 2019
| ML16180A030 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 07/22/2016 |
| From: | Lyon C Plant Licensing Branch IV |
| To: | Marik S Omaha Public Power District |
| Lyon C, NRR/DORL/LPLIV-1, 415-2296 | |
| References | |
| CAC MC4686, GL-04-002 | |
| Download: ML16180A030 (2) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 22, 2016 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008
SUBJECT:
FORT CALHOUN STATION, UNIT NO. 1 - CLOSURE OF NRC GENERIC LETTER 2004-02 (CAC NO. MC4686)
Dear Mr. Marik:
By letter dated June 24, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16176A213), Omaha Public Power District (OPPD, the licensee) provided a certification of permanent cessation of power operations to the U.S. Nuclear Regulatory Commission (NRC) for Fort Calhoun Station, Unit No. 1 (FCS). OPPD certified to the NRC that it plans to permanently cease power operations at FCS by December 31, 2016.
Based upon OPP D's letter, no additional action is requested for FCS for the following NRC generic communication:
- NRC Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004.
Therefore, the NRC staff has closed Cost Activity Code (CAC) No. MC4686 for GL 2004-02. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov.
Sincerely, Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285 cc: Distribution via Listserv
July 22, 2016 Mr. Shane M. Marik Site Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station 9610 Power Lane, Mail Stop FC-2-4 Blair, NE 68008
SUBJECT:
FORT CALHOUN STATION, UNIT NO. 1 - CLOSURE OF NRC GENERIC LETTER 2004-02 (CAC NO. MC4686)
Dear Mr. Marik:
By letter dated June 24, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16176A213), Omaha Public Power District (OPPD, the licensee) provided a certification of permanent cessation of power operations to the U.S. Nuclear Regulatory Commission (NRC) for Fort Calhoun Station, Unit No. 1 (FCS). OPPD certified to the NRC that it plans to permanently cease power operations at FCS by December 31, 2016.
Based upon OPPD's letter, no additional action is requested for FCS for the following NRC generic communication:
- NRC Generic Letter (GL) 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004.
Therefore, the NRC staff has closed Cost Activity Code (CAC) No. MC4686 for GL 2004-02. If you have any questions, please contact me at 301-415-2296 or via e-mail at Fred.Lyon@nrc.gov.
Sincerely, IRA/
Carl F. Lyon, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-285 cc: Distribution via Listserv DISTRIBUTION:
PUBLIC LPL4-1 Reading RidsACRS_MailCTR Resource RidsNrrDeEsgb Resource RidsNrrDorllpl4-1 Resource RidsNrrDprPgcb Resource RidsNrrDraApla Resource RidsNrrDssSsib Resource RidsNrrLAJBurkhardt Resource RidsRgn4MailCenter Resource RidsNrrPMFortCalhoun Resource ADAMS A ccess1on N0. ML16180A030 *ema1*1 dae t d **P rev1ous1y concurre d OFFICE N RR/DORL/LPL4-1 /PM NRR/DORL/LPL4-1 /LA NRR/DPR/PGCB/BC NAME FLyon JBurkhardt** SStuchell*
DATE 7/22/16 6/28/16 6/27/16 OFFICE NRR/DSS/SSIB/BC NRR/DORL/LPL4-1/BC NRR/DORL/LPL4-1 /PM NAME VCusumano** RPascarelli FL yon DATE 7/14/16 7/22/16 7/22/16 OFFICIAL RECORD COPY