| {{#Wiki_filter:/RA/ | | {{#Wiki_filter:December 27, 2018 |
| | EA-18-173 |
| | Mr. Brad Sawatzke |
| | Chief Executive Officer |
| | Energy Northwest |
| | MD 1023 |
| | P.O. Box 968 |
| | Richland, WA 99352 |
| | SUBJECT: COLUMBIA GENERATING STATION - ACKNOWLEDGMENT OF RESPONSE |
| | TO NRC BASELINE INSPECTION REPORT 05000397/2018003 AND |
| | DISPUTED NON-CITED VIOLATION |
| | Dear Mr. Sawatzke: |
| | This letter acknowledges your November 29, 2018, correspondence (ML18333A389) |
| | in response to the U.S. Nuclear Regulatory Commission (NRC) Inspection |
| | Report 05000397/2018003 (ML18304A362), dated October 31, 2018. In the inspection report, |
| | the NRC documented a Green non-cited violation (NCV) that was the subject of your response: |
| | NCV 05000397/2018003-02, Green NCV of Technical Specification 5.7.2 for failure to control |
| | workers in a high radiation area exceeding 1.0 rem/hr. The cover letter to the inspection report |
| | requested you to respond in writing within 30 days if you contested any of the violations. |
| | On November 29, 2018, the NRC received a letter from you contesting this NCV. The NRC is |
| | currently reviewing your basis for contesting the violation in accordance with Section 2.2.7 of the |
| | Enforcement Manual. Accordingly, we will provide the results of our evaluations by written |
| | response within 90 days of the receipt of your letter. |
| | This letter, its enclosure, and your response (if any) will be made available for public inspection |
| | and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document |
| | Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for |
| | Withholding. |
| | Sincerely, |
| | /RA/ |
| | Heather J. Gepford, Chief |
| | Plant Support Branch 2 |
| | Division of Reactor Safety |
| | Docket No. 50-397 |
| | License No. NPF-21 |
| | cc: Electronic Distribution |
|
| |
|
|
| |
|
| | | ML18361A865 |
| | | SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: |
| | | By: HJG Yes No Publicly Available Sensitive NRC-002 |
| | | OFFICE C:PSB2 C:DRP/A C:PSB2 D:DRS C:PSB2 |
| | | NAME HGepford MHaire HGepford MShaffer HGepford |
| | | SIGNATURE /RA/ /RA/ /RA/ /RA REL for/ /RA/ |
| | | DATE 12/21/2018 12/21/2018 12/21/2018 12/27/2018 12/27/2018 |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| /RA/ /RA/ /RA/ /RA REL for/ /RA/ 12/21/2018 12/21/2018 12/21/2018 12/27/2018 12/27/2018 | |
| }} | | }} |
Latest revision as of 07:37, 20 October 2019
|
---|
Category:Inspection Report
MONTHYEARML24290A1142024-10-17017 October 2024 CGS FPTI 2024011 IR 05000397/20244032024-10-0101 October 2024 Cybersecurity Inspection Report 05000397/2024403 Public IR 05000397/20240052024-08-22022 August 2024 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2024005) IR 07200035/20244012024-08-19019 August 2024 Security Baseline Inspection Report 07200035/2024401 IR 05000397/20244022024-08-13013 August 2024 Security Baseline Inspection Report 05000397/2024402 IR 05000397/20240022024-08-0909 August 2024 Integrated Inspection Report 05000397/2024002 IR 05000397/20240122024-07-10010 July 2024 – Safety Conscious Work Environment Issue of Concern Follow-up Inspection 05000397/2024012 IR 05000397/20244202024-06-27027 June 2024 – Security Baseline Inspection Report 05000397 2024420 Cover Letter IR 05000397/20240012024-04-24024 April 2024 Integrated Inspection Report 05000397/2024001 IR 05000397/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000397/2024401 (Cover Letter Only) IR 05000397/20230062024-02-28028 February 2024 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2023006) IR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 IR 05000397/20220062023-03-0101 March 2023 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2022006) IR 05000397/20234022023-02-23023 February 2023 NRC Security Baseline Inspection Report 050003972023402 (Full Report) IR 05000397/20220042023-01-23023 January 2023 Integrated Inspection Report 05000397/2022004- 4th Quarter IR 05000397/20224062023-01-18018 January 2023 NRC Security Baseline Inspection Report 05000397/2022406 (Cover Letter) IR 05000397/20224042023-01-17017 January 2023 Amended - Columbia Generating Station - Security Baseline Inspection Report 05000397/2022404 (Public) IR 05000397/20224012022-11-12012 November 2022 Cyber Security Inspection Report 05000397/2022401 (Cover Letter Only) IR 05000397/20220032022-10-31031 October 2022 Integrated Inspection Report 05000397/2022003 IR 05000397/20224052022-09-15015 September 2022 Material Control and Accounting Program Inspection Report 05000397 2022405 Cover Ltr Only IR 05000397/20224032022-09-0101 September 2022 NRC Security Inspection Report 05000397/2022403 (Full Report) IR 05000397/20220022022-07-28028 July 2022 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000397/2022002 and 07200035/2022001 IR 05000397/20220102022-06-30030 June 2022 Design Basis Assurance Inspection (Team) Inspection Report 05000397/2022010 IR 05000397/20224022022-06-23023 June 2022 Security Baseline Inspection Report 05000397/2022402 IR 05000397/20220012022-04-29029 April 2022 Integrated Inspection Report 05000397/2022001 IR 05000397/20210062022-03-0202 March 2022 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2021006) IR 05000397/20210042022-01-20020 January 2022 Integrated Inspection Report 05000397/2021004 IR 05000397/20214012022-01-19019 January 2022 Security Baseline Inspection Report 05000397/2021401 IR 05000397/20210902022-01-13013 January 2022 NRC Inspection Report 05000397/2021090 and Preliminary White Finding IR 05000397/20214202021-11-0404 November 2021 Security Baseline Inspection Report-Cover Letter - 05000397/2021420 IR 05000397/20210122021-11-0303 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000397/2021012 IR 05000397/20210032021-11-0202 November 2021 Integrated Inspection Report 05000397/2021003 IR 05000397/20210112021-09-21021 September 2021 Triennial Fire Protection Inspection Report 05000397/2021011 IR 05000397/20214022021-09-0909 September 2021 Security Baseline Inspection Report 05000397/2021402 IR 05000397/20210102021-08-29029 August 2021 Biennial Problem Identification and Resolution Inspection Report 05000397/2021010 IR 05000397/20210022021-08-0202 August 2021 Integrated Inspection Report 05000397/2021002 2024-08-09
[Table view] Category:Letter
MONTHYEARML24290A1142024-10-17017 October 2024 CGS FPTI 2024011 IR 05000397/20244032024-10-0101 October 2024 Cybersecurity Inspection Report 05000397/2024403 Public GO2-24-088, Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-24024 September 2024 Supplement to Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan GO2-24-051, Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements2024-09-23023 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24247A1572024-09-12012 September 2024 Withholding Determination Letter for Presentation Materials for Energy Northwest Pre-application Meeting 8-9-2024 ML24255A1012024-09-12012 September 2024 Request for Withholding Information from Public Disclosure Energy Northwest Regulatory Engagement Plan, Revision 0 GO2-24-082, Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan2024-09-10010 September 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Columbia Emergency Plan IR 05000397/20240052024-08-22022 August 2024 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2024005) IR 07200035/20244012024-08-19019 August 2024 Security Baseline Inspection Report 07200035/2024401 IR 05000397/20244022024-08-13013 August 2024 Security Baseline Inspection Report 05000397/2024402 IR 05000397/20240022024-08-0909 August 2024 Integrated Inspection Report 05000397/2024002 GO2-24-060, Reply to a Notice of Violation, EA-21-170 and EA-23-0542024-07-30030 July 2024 Reply to a Notice of Violation, EA-21-170 and EA-23-054 GO2-24-070, Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program2024-07-29029 July 2024 Response to Request for Additional Information Regarding Fifth Interval Inservice Testing Program GO2-24-063, Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan2024-07-15015 July 2024 Notification of Extension to Columbias Fourth 10-Year Interval Inservice Testing Program Plan IR 05000397/20240122024-07-10010 July 2024 – Safety Conscious Work Environment Issue of Concern Follow-up Inspection 05000397/2024012 ML24180A1482024-06-28028 June 2024 Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000397/2024011) and Request for Information IR 05000397/20244202024-06-27027 June 2024 – Security Baseline Inspection Report 05000397 2024420 Cover Letter GO2-24-057, Notice of Readiness for Supplemental Inspection2024-06-19019 June 2024 Notice of Readiness for Supplemental Inspection ML24099A2232024-06-12012 June 2024 Issuance of Amendment No. 275 to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling GO2-24-056, Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing2024-06-11011 June 2024 Relief Request for the Columbia Generating Station Fourth Ten-Year Interval Inservice Testing ML24128A2242024-05-31031 May 2024 Issuance of Amendment No. 274 to Revise Technical Specifications to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-13013 May 2024 2023 Annual Radiological Environmental Operating Report GO2-24-050, Annual Environmental Operating Report2024-04-30030 April 2024 Annual Environmental Operating Report IR 05000397/20240012024-04-24024 April 2024 Integrated Inspection Report 05000397/2024001 GO2-24-042, 2023 Annual Radioactive Effluent Release Report2024-04-22022 April 2024 2023 Annual Radioactive Effluent Release Report ML24089A2282024-04-15015 April 2024 – Acceptance of Requested Licensing Action License Amendment Request to Revise Columbia Generating Station Emergency Plan ML24074A4532024-04-11011 April 2024 Request for Withholding Information from Public Disclosure GO2-24-044, Voluntary Response to Regulatory Issue Summary 2024-012024-04-11011 April 2024 Voluntary Response to Regulatory Issue Summary 2024-01 IR 05000397/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000397/2024401 (Cover Letter Only) GO2-24-034, Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan2024-03-20020 March 2024 Supplement to License Amendment Request to Revise Columbia Generating Station Emergency Plan ML24058A0692024-03-14014 March 2024 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Emergency Plan ML24044A0492024-03-12012 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0064 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) GO2-24-041, Level of Financial Protection - Annual Reporting Requirement2024-03-12012 March 2024 Level of Financial Protection - Annual Reporting Requirement GO2-24-036, Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate2024-03-11011 March 2024 Presentation Information for Pre-Application Meeting Regarding Columbia’S Replacement Steam Dryer Evaluation Approach for Extended Power Uprate GO2-24-039, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462024-03-11011 March 2024 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 ML24047A0422024-03-0707 March 2024 Issuance of Amendment No. 273 Renewed Facility Operating License and Technical Specification Clean Up IR 05000397/20230062024-02-28028 February 2024 Annual Assessment Letter for Columbia Generating Station (Report 05000397/2023006) IR 05000397/20253012024-02-14014 February 2024 Notification of NRC Initial Operator Licensing Examination 05000397/2025301 GO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing GO2-24-014, Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation 2024-09-24
[Table view] Category:Non-Cited Violation
MONTHYEARML19108A4872019-04-16016 April 2019 NRC Inspection Report 05000397/2018003 NRC Response to Disputed Non-Cited Violation ML18361A8652018-12-27027 December 2018 Acknowledgement of Response to NRC Baseline Inspection Report 05000397/2018003 and Disputed Non-Cited Violation ML17142A2192017-05-22022 May 2017 Disputed Non-Cited Violations and Finding from NRC Inspection Report 05000397/2016009 ML17100A4992017-04-10010 April 2017 NRC Special Inspection Report 05000397/2016009; Preliminary White Finding 2019-04-16
[Table view] |
See also: IR 05000397/2018003
Text
December 27, 2018
EA-18-173
Mr. Brad Sawatzke
Chief Executive Officer
Energy Northwest
MD 1023
P.O. Box 968
Richland, WA 99352
SUBJECT: COLUMBIA GENERATING STATION - ACKNOWLEDGMENT OF RESPONSE
TO NRC BASELINE INSPECTION REPORT 05000397/2018003 AND
DISPUTED NON-CITED VIOLATION
Dear Mr. Sawatzke:
This letter acknowledges your November 29, 2018, correspondence (ML18333A389)
in response to the U.S. Nuclear Regulatory Commission (NRC) Inspection
Report 05000397/2018003 (ML18304A362), dated October 31, 2018. In the inspection report,
the NRC documented a Green non-cited violation (NCV) that was the subject of your response:
NCV 05000397/2018003-02, Green NCV of Technical Specification 5.7.2 for failure to control
workers in a high radiation area exceeding 1.0 rem/hr. The cover letter to the inspection report
requested you to respond in writing within 30 days if you contested any of the violations.
On November 29, 2018, the NRC received a letter from you contesting this NCV. The NRC is
currently reviewing your basis for contesting the violation in accordance with Section 2.2.7 of the
Enforcement Manual. Accordingly, we will provide the results of our evaluations by written
response within 90 days of the receipt of your letter.
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document
Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for
Withholding.
Sincerely,
/RA/
Heather J. Gepford, Chief
Plant Support Branch 2
Division of Reactor Safety
Docket No. 50-397
License No. NPF-21
cc: Electronic Distribution
ML18361A865
SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: HJG Yes No Publicly Available Sensitive NRC-002
OFFICE C:PSB2 C:DRP/A C:PSB2 D:DRS C:PSB2
NAME HGepford MHaire HGepford MShaffer HGepford
SIGNATURE /RA/ /RA/ /RA/ /RA REL for/ /RA/
DATE 12/21/2018 12/21/2018 12/21/2018 12/27/2018 12/27/2018