{{#Wiki_filter:VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 March 22, 2010 Attention:
Document Control Desk Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards United States Nuclear Regulatory Commission Washington, D. C. 20555-0001 Serial No.NAPS/JHL Docket Nos.License No.10-176 72-16 72-56 SNM-2507 Gentlemen:
VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
NORTH ANNA POWER STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)
 
==SUMMARY==
OF FACILITY CHANGES, TESTS AND EXPERIMENTS Pursuant to 10 CFR 72.48(d)(2), a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each, must be submitted to the NRC -Office of Nuclear Material Safety and Safeguards, at intervals not to exceed 24 months. This letter is to notify you that there were no evaluations affecting the North Anna Power Station ISFSI facility during 2009.If you have any questions, please contact Page Kemp at (540) 894-2295.Very trul yours, N. Larry*:D Site Vice Presider cc: U. S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, DC 20555-0001 U. S. Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 NRC Senior Resident Inspector North Anna Power Station 0 ý ý'-) D I}}

Revision as of 13:59, 19 September 2018

North Anna, Independent Spent Fuel Storage Installation, Summary of Evaluation Affecting the Facility Changes, Tests and Experiments
ML100890378
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 03/22/2010
From: Lane N L
Virginia Electric & Power Co (VEPCO)
To:
NRC/NMSS/SFPO
References
10-176
Download: ML100890378 (1)


Text

VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 March 22, 2010 Attention:

Document Control Desk Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards United States Nuclear Regulatory Commission Washington, D. C. 20555-0001 Serial No.NAPS/JHL Docket Nos.License No.10-176 72-16 72-56 SNM-2507 Gentlemen:

VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)

NORTH ANNA POWER STATION INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)

SUMMARY

OF FACILITY CHANGES, TESTS AND EXPERIMENTS Pursuant to 10 CFR 72.48(d)(2), a report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each, must be submitted to the NRC -Office of Nuclear Material Safety and Safeguards, at intervals not to exceed 24 months. This letter is to notify you that there were no evaluations affecting the North Anna Power Station ISFSI facility during 2009.If you have any questions, please contact Page Kemp at (540) 894-2295.Very trul yours, N. Larry*:D Site Vice Presider cc: U. S. Nuclear Regulatory Commission Attention: