{{#Wiki_filter:July 26, 2013 EN 13-026 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION
Licensee: Exelon Generation Company, LLC    EA-13-079  Dresden Nuclear Power Station, Units 2 and 3 Docket Nos.: 50-237; 50-249
==Subject:==
ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation will be issued on or about July 31, 2013, to Exelon Generation Company, LLC (Exelon) for a violation associated with a White Significance Determination Process finding identified during an inspection of the Dresden Nuclear Power Station (Dresden), Units 2 and 3. This White finding, an issue of low to moderate safety significance, will require additional U.S. Nuclear Regulatory Commission (NRC) inspections. The finding involves Exelon's failure to establish a procedure addressing all of the effects of an external flooding scenario at Dresden. Specifically, Dresden procedure DOA 0010-04, Floods, did not account for reactor vessel inventory make up during an external flooding scenario up to and including the probable maximum flood event which could result in reactor vessel water level lowering below the top of active fuel. Exelon's corrective actions were to incorporate methods to provide RPV inventory make up during an external flood into its procedures. 
A Notice of Violation (NOV) is included based on Exelon's failure to meet Technical Specification Section 5.4.1, which requires, in part, that written procedures be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33, Revision 2, Appendix A, Paragraph 6 addresses "Procedures for Combating Emergencies and Other Significant Events" and lists Item w, "Acts of Nature (e.g., tornado, flood, dam failure, earthquakes)", as an activity under Paragraph 6 to be covered by written procedures. In accordance with the NRC Enforcement Policy, the NOV is considered an escalated enforcement action because it is associated with a White finding.
The NRC issued a preliminary determination letter for this issue on May 7, 2013. On June 6, 2013 and June 21, 2013, Exelon provided a written response. After considering the additional information provided by Exelon, the staff concluded that the finding is appropriately characterized as White.
It should be noted that the licensee has not been specifically informed of the enforcement action. The schedule of issuance and notification is:  Mailing of Final Significance Determination  July 31, 2013  Telephone Notification of Licensee  July 31, 2013 The State of Illinois will be notified.
CONTACTS:  Lauren Casey, OE, (301) 415-1038  Nick Hilton, OE, (301) 415-2741 DISTRIBUTION
: EN-13-026, July 26, 2013 OWFN  Chair. MacFarlane Comm. Svinicki Comm. Apostolakis Comm. Magwood
Comm. Ostendorff SECY OCA OPA OIP OWFN EDO DEDR DEDMRS OE OGC NRR OI OIG TWFN  OCFO OP CENTER OIS FSME RES ACRS RES  3WFN NMSS NSIR  Regional Offices RI          RII
RIII        RIV MAIL Public OE staff
Electronic DISTRIBUTION:  R. Zimmerman, OE
N. Hilton, OE L. Casey, OE OE r/f EN binder
X  PUBLIC      X NON-SENSITIVE
ADAMS ML13207A040 OFFICE OE:ES  OE:BC  NAME LCasey BFretz
/RA/for NHilton DATE 7/25/2013 7/26/2013 OFFICIAL RECORD COPY}}

Revision as of 19:08, 4 July 2018

EN-13-026, Issuance of Final Significance Determination and Notice of Violation to Exelon Generation Company, LLC, Dresden Nuclear Power Station, Units 2 & 3
ML13207A040
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 07/26/2013
From: Hilton N D
NRC/OE
To:
Casey L
References
EA-13-079 EN-13-026
Download: ML13207A040 (2)


Text

July 26, 2013 EN 13-026 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION

Licensee: Exelon Generation Company, LLC EA-13-079 Dresden Nuclear Power Station, Units 2 and 3 Docket Nos.: 50-237; 50-249

Subject:

ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that a Notice of Violation will be issued on or about July 31, 2013, to Exelon Generation Company, LLC (Exelon) for a violation associated with a White Significance Determination Process finding identified during an inspection of the Dresden Nuclear Power Station (Dresden), Units 2 and 3. This White finding, an issue of low to moderate safety significance, will require additional U.S. Nuclear Regulatory Commission (NRC) inspections. The finding involves Exelon's failure to establish a procedure addressing all of the effects of an external flooding scenario at Dresden. Specifically, Dresden procedure DOA 0010-04, Floods, did not account for reactor vessel inventory make up during an external flooding scenario up to and including the probable maximum flood event which could result in reactor vessel water level lowering below the top of active fuel. Exelon's corrective actions were to incorporate methods to provide RPV inventory make up during an external flood into its procedures.

A Notice of Violation (NOV) is included based on Exelon's failure to meet Technical Specification Section 5.4.1, which requires, in part, that written procedures be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33, Revision 2, Appendix A, Paragraph 6 addresses "Procedures for Combating Emergencies and Other Significant Events" and lists Item w, "Acts of Nature (e.g., tornado, flood, dam failure, earthquakes)", as an activity under Paragraph 6 to be covered by written procedures. In accordance with the NRC Enforcement Policy, the NOV is considered an escalated enforcement action because it is associated with a White finding.

The NRC issued a preliminary determination letter for this issue on May 7, 2013. On June 6, 2013 and June 21, 2013, Exelon provided a written response. After considering the additional information provided by Exelon, the staff concluded that the finding is appropriately characterized as White.

It should be noted that the licensee has not been specifically informed of the enforcement action. The schedule of issuance and notification is: Mailing of Final Significance Determination July 31, 2013 Telephone Notification of Licensee July 31, 2013 The State of Illinois will be notified.

CONTACTS: Lauren Casey, OE, (301) 415-1038 Nick Hilton, OE, (301) 415-2741 DISTRIBUTION

EN-13-026, July 26, 2013 OWFN Chair. MacFarlane Comm. Svinicki Comm. Apostolakis Comm. Magwood

Comm. Ostendorff SECY OCA OPA OIP OWFN EDO DEDR DEDMRS OE OGC NRR OI OIG TWFN OCFO OP CENTER OIS FSME RES ACRS RES 3WFN NMSS NSIR Regional Offices RI RII

RIII RIV MAIL Public OE staff

Electronic DISTRIBUTION: R. Zimmerman, OE

N. Hilton, OE L. Casey, OE OE r/f EN binder

X PUBLIC X NON-SENSITIVE

ADAMS ML13207A040 OFFICE OE:ES OE:BC NAME LCasey BFretz