| Line 1: |
Line 1: |
| {{Adams
| | #REDIRECT [[IR 05000282/1992022]] |
| | number = ML20056H096
| |
| | issue date = 08/31/1993
| |
| | title = Ack RO Anderson Revising Commitments Associated W/Requalification Exam Rept 50-282/OL-92-02 & Insp Repts 50-282/92-22 & 50-306/92-22
| |
| | author name = Forney W
| |
| | author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
| |
| | addressee name = Anthony D
| |
| | addressee affiliation = NORTHERN STATES POWER CO.
| |
| | docket = 05000282, 05000306
| |
| | license number =
| |
| | contact person =
| |
| | document report number = NUDOCS 9309080219
| |
| | title reference date = 08-24-1993
| |
| | document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE
| |
| | page count = 2
| |
| }}
| |
| See also: [[see also::IR 05000282/1992022]]
| |
| | |
| =Text=
| |
| {{#Wiki_filter:_ _ - . . . . , -. . . ._. . . . - - . - . ... . - - - . _ - - _ - _ _
| |
| [
| |
| p stou UNIT ED STATES
| |
| {
| |
| '
| |
| [j k NUCLEAR REGULATORY COMMISSION !
| |
| (
| |
| r 'j
| |
| % REGION lil f
| |
| 7ss noosEvELT nono
| |
| ! GLE N ELLY N. ILUNOIS 60137 [
| |
| ""*
| |
| AUG' 31 1993 l
| |
| i
| |
| l
| |
| !
| |
| Docket No. 50-282
| |
| Docket No. 50-306 :
| |
| l
| |
| Northern States Power Company ;
| |
| ATTN: Mr. D. D. Antony ,
| |
| '
| |
| Vice President
| |
| Nuclear Generation ,
| |
| 414 Nicollet Mall i
| |
| Minneapolis, MN 55401 !
| |
| Dear Mr. Antony: l
| |
| SUBJECT: FAILURE TO COMPLETE NRC COMMITMENTS WITHIN THE COMMITTED SCHEDULE
| |
| f
| |
| This letter acknowledges Mr. Roger 0. Anderson, Director, Licensing and j
| |
| i
| |
| Management Issues, August 24, 1993 letter, revising commitments associated i
| |
| ;
| |
| ;
| |
| with NRC Requalification Examination Report No. 50-282/0L-92-02-and Inspection
| |
| l Reports No. 50-282/92022(DRP) and No. 50-306/92022(DRP). Th'ese reports l
| |
| summarized the results of a requalification examination and an announced team '
| |
| l
| |
| inspection at your Prairie Island Nuclear Generating Station, Units 1 and 2.
| |
| While we are concerned that your commitment tracking system was not completely
| |
| effective in these areas, your identification of the issue and efforts to
| |
| .
| |
| improve your system appear appropriate. l
| |
| l
| |
| !
| |
| i
| |
| ; Sincerely,
| |
| !
| |
| i
| |
| "~ ' ~
| |
| ._O n . _ -
| |
| .c
| |
| W. L. Forney, Acting Director
| |
| .
| |
| y
| |
| ,.
| |
| Division of Reactor Safety ,
| |
| i
| |
| See Attached Distribution *
| |
| j
| |
| i
| |
| 4
| |
| ,
| |
| ..
| |
| !
| |
| !
| |
| 9309000219 930831 )
| |
| PDR ADOCK0500g22
| |
| 0 -
| |
| )
| |
| fubl./E SSYrL
| |
| | |
| .
| |
| O
| |
| Northern States Power Company 2 AUG 311993
| |
| ;
| |
| l
| |
| Distribution ;
| |
| cc: E. L. Watzl, Site Manager, l
| |
| Peairie Island Site '
| |
| M. WLdley, Plant Manager l
| |
| R. C. Anderson, Director,
| |
| Licensing and Management
| |
| Issues
| |
| cc w/ltr dtd 08/24/93:
| |
| OC/LFDCB j
| |
| Resident Inspector, RIII 4
| |
| Prairie Island
| |
| Resident Inspector, RIII l
| |
| Monticello
| |
| John W. Ferman, Ph.D.,
| |
| Nuclear Engineer, MPCA
| |
| !
| |
| Kris Sanda, Commissioner
| |
| Minnesota Dept. of Public
| |
| Service
| |
| Prairie Island LPM, NRR i
| |
| Robert M. Thompson, Administrator
| |
| Wisconsin Division of Emergency i
| |
| Government l
| |
| l
| |
| if
| |
| | |
| p .X.. .
| |
| ,
| |
| .
| |
| [ Northem States Power Company
| |
| .
| |
| 414 Nicollet Mall
| |
| Minneapolis, Minnesota $5401-1927
| |
| Telephone (612) 3315500
| |
| August 24, 1993
| |
| US Nuclear Regulatory Commission
| |
| Attn: Document Control Desk
| |
| Vashington, DC 20555
| |
| PPAIRIE ISIAND NUCLEAR GENERATING PLANT
| |
| Docket Nos. 50-282 License Nos. DPR-42
| |
| 50-306 DPR-60
| |
| Failure To Complete NRC Commitments
| |
| Within The Committed Schedule
| |
| The purpose of this letter is to notify the NRC of two commitments which were
| |
| not ccepleted within the schedule committed to in previous NRC correspondence .
| |
| This deviation from commitments was discussed with the NRC resident inspectors
| |
| on August 12, 1993. Each of the commitments is discussed separately below.
| |
| Commitment 1
| |
| Pricr to the 1992 NRC-observed operator requalification examinations,
| |
| individuals designated to participate in the examination inadvertently
| |
| received training from an instructor who was under the Pre-examination
| |
| Security agreement. This is discussed .n the NRC Requalification Examinatict
| |
| Report No. 2S2/0L-92-02.
| |
| In our response to the Requalification Examination Report, dated November 15,
| |
| 1992, we identified two actions to be taken to preclude a further occurrence
| |
| of this type. One of the actions committed to was the review of this
| |
| violation during the first quarter of 1993 with all licensed operators and
| |
| operations instructors.
| |
| Following the submittal of the November 18, 1992 response, the subject
| |
| c omr:i t n:ent was entered into the plant commitment tracking system with a
| |
| required completion date of March 31, 1993 However, no Request for Training
| |
| Se rvices was initiated. This form is the normal mechanism for requesting
| |
| training to he performed by the Prairie Island Training Center. The form is t
| |
| '
| |
| used ::y the training center to identify, schedule and track training requests.
| |
| This lack of a Request for Training Services in comhination with mis-
| |
| communication within the training department resulted in the required trainir.g
| |
| not being completed in the first quarter of 1993.
| |
| A contributing cau e of the failure to meet the committed date was the
| |
| inadequacy of the current commitment tracking system monthly reporting process
| |
| for ensuring that commitments with firm completion. dates are completed per the
| |
| committed schedule.
| |
| r8 e eth! 2)('\
| |
| ) ') ; *
| |
| # { 'p
| |
| l ^
| |
| v.-
| |
| -
| |
| . ..
| |
| .
| |
| 4 4 ,n R
| |
| Lt _
| |
| ~ -
| |
| . j
| |
| | |
| .
| |
| 4
| |
| E. NORTHERN STATES POWER COMPANY
| |
| Act .t 24, 1993
| |
| Page 2
| |
| The committed review will be performed during the six-week training cycle
| |
| immediately preceding the 1993 operator requalification examinations and will
| |
| be completed by September 24, 1993. This schedule will meet the intent of the
| |
| original committed action by completing the review prior to the next
| |
| requalification examination.
| |
| Commitment 2
| |
| NRC Inspection Reports 50-282/92022 and 50-306/92022 included a Notice of
| |
| Violation concerning design and construction of a new building wall. In our
| |
| response letter dated January 19, 1993, we committed to training on the
| |
| subject to be completed during the first quarter of 1993.
| |
| Again, as in the situation described above, no Request for Training Services
| |
| was initiated following submittal of the commitment. In addition, this
| |
| commitment was not entered into the commitment tracking system in a timely
| |
| manner. The subject commitment was discussed with the Training Department
| |
| prior tc submittal; however, the lack of a Request for Training Services , the
| |
| failure to enter the commitment in the tracking system and miscommunication
| |
| within the training department resulted in the required training not being
| |
| completed in the first quarter of 1993.
| |
| This training has now been scheduled and will be completed by August 27, 1993.
| |
| Actions to Prevent Recurrence
| |
| Site personnel will be reminded of the proper use of the Request for Training
| |
| Services.
| |
| While miscommunication was a factor in these deviations, it was only a factor
| |
| because the formal Request for Training Services process was not used.
| |
| Therefore, no corrective actions are deemed necessary to address
| |
| miscommunication.
| |
| A process re-engineering effort has been initiated to strengthen the process
| |
| for development of outgoing correspondence to the NRC and commitments that may
| |
| be contained in that correspondence. It is anticipated that as part of the
| |
| new process, commitments to the NRC will receive increased management review
| |
| during development of the correspondence and that the responsibility for
| |
| completion of the commitment will be more clearly defined before the
| |
| correspondence is submitted.
| |
| The current process at Prairie Island for the tracking of NRC commitments is
| |
| being evaluated to identify any improvements that can be made to ensure that
| |
| NRC commitments are entered into the system in a timely manner and that
| |
| periodic reminders are sent to personnel assigned to complete commitments.
| |
| The review is being conducted concurrent with the conversion of the commitment
| |
| tracking system to the new plant information computer system. Necessary
| |
| revisions to the commitment tracking system will be incorporcted during the
| |
| conversion process.
| |
| L -
| |
| | |
| l,
| |
| *
| |
| t l
| |
| l
| |
| USNRC NORTHERN STATES POWER COMPANY l
| |
| -
| |
| August 24, 1993
| |
| -
| |
| Page 3
| |
| This letter contains the following new NRC commitment:
| |
| f
| |
| Site personnel will be reminded of the proper use of the Request for
| |
| Training Services.
| |
| Please contact Gene Ecliolt (612) 388-1121 ext 4663 if you have any questions
| |
| related to the information we have provided,
| |
| i
| |
| 0 I
| |
| , hf:She
| |
| /
| |
| V~
| |
| Roger O Anderson
| |
| Director
| |
| Licensing and Management Issues
| |
| c: Regional Administrator - III, NRC
| |
| Wayne Shafer, NRC Region III
| |
| NRR Project Manager, NRC
| |
| Sr Resident Inspector, NRC
| |
| State of Minnesota
| |
| Attn: Kris Sanda
| |
| J Silberg
| |
| k_ J
| |
| }}
| |