APPENDIX A NOTICE OF VIOLATION R.J.M. Manufacturing                               Docket No. 99990001 Bensalem, Pennsylvania 19020                       License No. General License As a result of the inspection conducted ;n June 17, 1985, and in accordance
APPENDIX A NOTICE OF VIOLATION R.J.M. Manufacturing Docket No. 99990001 Bensalem, Pennsylvania 19020 License No. General License As a result of the inspection conducted ;n June 17, 1985, and in accordance with the NRC Enforcement Policy (10 CFR 2, Appendix C), the following violations were identified:
..                            with the NRC Enforcement Policy (10 CFR 2, Appendix C), the following violations were identified:
10 CFR 31.5(c)(2) requires that the device be tested for leakage of radio-active material at no longer than six-month intervals.
10 CFR 31.5(c)(2) requires that the device be tested for leakage of radio-active material at no longer than six-month intervals.
Contrary to the above, as of June 17, 1985, sealed sources containing 25 millicuries of Americium-241 had not been testem for leakage of radio-active material since December 1983.
Contrary to the above, as of June 17, 1985, sealed sources containing 25 millicuries of Americium-241 had not been testem for leakage of radio-active material since December 1983.
This is a Severity Level IV violation (Supplement VI).
This is a Severity Level IV violation (Supplement VI).
Pursuant to the provisions of 10 CFR 2.201, R.J.M Manufacturing is hereby re-quired to submit to this office within thirty days of the date of the letter which transmitted this Notice, a written statement or explanation in reply, including: (1) the corrective steps which have been taken and the results achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the date when full compliance will be achieved. Where good cause is shown, considaration will be given to extending this response time.
Pursuant to the provisions of 10 CFR 2.201, R.J.M Manufacturing is hereby re-quired to submit to this office within thirty days of the date of the letter which transmitted this Notice, a written statement or explanation in reply, including: (1) the corrective steps which have been taken and the results achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the date when full compliance will be achieved. Where good cause is shown, considaration will be given to extending this response time.
hh g,,b
hhg,,b
      -________-_-____-___                                                                          ___        _}}
-}}

Latest revision as of 18:49, 11 December 2024

Notice of Violation from Insp on 850617.Violation Noted: Sealed Sources,Containing 25 Mci Am-241,not Leak Tested Since Dec 1983
ML20138L688
Person / Time
Issue date: 10/25/1985
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20138L679 List:
References
99990001-85-13, NUDOCS 8510310382
Download: ML20138L688 (1)


Text

.

APPENDIX A NOTICE OF VIOLATION R.J.M. Manufacturing Docket No. 99990001 Bensalem, Pennsylvania 19020 License No. General License As a result of the inspection conducted ;n June 17, 1985, and in accordance with the NRC Enforcement Policy (10 CFR 2, Appendix C), the following violations were identified:

10 CFR 31.5(c)(2) requires that the device be tested for leakage of radio-active material at no longer than six-month intervals.

Contrary to the above, as of June 17, 1985, sealed sources containing 25 millicuries of Americium-241 had not been testem for leakage of radio-active material since December 1983.

This is a Severity Level IV violation (Supplement VI).

Pursuant to the provisions of 10 CFR 2.201, R.J.M Manufacturing is hereby re-quired to submit to this office within thirty days of the date of the letter which transmitted this Notice, a written statement or explanation in reply, including: (1) the corrective steps which have been taken and the results achieved; (2) corrective steps which will be taken to avoid further violations; and (3) the date when full compliance will be achieved. Where good cause is shown, considaration will be given to extending this response time.

hhg,,b

-