=Text=
=Text=
{{#Wiki_filter:January 19, 2005 LICENSEE:       Nuclear Management Company, LLC FACILITY:       Point Beach Nuclear Plant, Units 1 and 2
{{#Wiki_filter:January 19, 2005 LICENSEE:
Nuclear Management Company, LLC FACILITY:
Point Beach Nuclear Plant, Units 1 and 2


==SUBJECT:==
==SUBJECT:==
==SUMMARY==
==SUMMARY==
OF TELEPHONE CONFERENCE HELD ON JANUARY 14, 2005, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference on January 14, 2005, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Point Beach Nuclear Plant, Units 1 and 2, license renewal application. The conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the meeting participants. Enclosure 2 contains a listing of the RAIs discussed with the applicant, including a brief description on the status of the items. contains draft responses provided by the applicant.
OF TELEPHONE CONFERENCE HELD ON JANUARY 14, 2005, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference on January 14, 2005, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Point Beach Nuclear Plant, Units 1 and 2, license renewal application. The conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the meeting participants. Enclosure 2 contains a listing of the RAIs discussed with the applicant, including a brief description on the status of the items. contains draft responses provided by the applicant.
The applicant had an opportunity to comment on this summary.
The applicant had an opportunity to comment on this summary.
                                                              /RA/
/RA/
Verónica M. Rodríguez, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Verónica M. Rodríguez, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301


Line 30: Line 31:
As stated cc w/encls: See next page
As stated cc w/encls: See next page


DOCUMENT NAME: E:\Filenet\ML050270037.wpd OFFICE       PM:RLEP                 SC:RLEP NAME         VRodríguez             SLee DATE           01 / 14 / 05           01 / 19 / 05 Point Beach Nuclear Plant, Units 1 and 2 cc:
DOCUMENT NAME: E:\\Filenet\\ML050270037.wpd OFFICE PM:RLEP SC:RLEP NAME VRodríguez SLee DATE 01 / 14 / 05 01 / 19 / 05
Jonathan Rogoff, Esq.                   Mr. Jeffrey Kitsembel Vice President, Counsel & Secretary     Electric Division Nuclear Management Company, LLC         Public Service Commission of Wisconsin 700 First Street                        P.O. Box 7854 Hudson, WI 54016                        Madison, WI 53707-7854 Mr. Frederick D. Kuester                David Weaver President and Chief Executive Officer    Nuclear Asset Manager We Generation                            Wisconsin Electric Power Company 231 West Michigan Street                 231 West Michigan Street Milwaukee, WI 53201                      Milwaukee, WI 53201 James Connolly                          John Paul Cowan Manager, Regulatory Affairs              Executive Vice President & Chief Nuclear Point Beach Nuclear Plant                  Officer Nuclear Management Company, LLC         Nuclear Management Company, LLC 6610 Nuclear Road                        700 First Street Two Rivers, WI 54241                    Hudson, WI 54016 Mr. Ken Duveneck                        Douglas E. Cooper Town Chairman                            Senior Vice President - Group Operations Town of Two Creeks                      Palisades Nuclear Plant 13017 State Highway 42                  Nuclear Management Company, LLC Mishicot, WI 54228                      27780 Blue Star Memorial Highway Covert, MI 49043 Chairman Public Service Commission                Fred Emerson of Wisconsin                            Nuclear Energy Institute P.O. Box 7854                            1776 I Street, NW., Suite 400 Madison, WI 53707-7854                  Washington, DC 20006-3708 Regional Administrator, Region III      Roger A. Newton U.S. Nuclear Regulatory Commission      3623 Nagawicka Shores Drive 801 Warrenville Road                    Hartland, WI 53029 Lisle, IL 60532-4351 James E. Knorr Resident Inspector's Office              License Renewal Project U.S. Nuclear Regulatory Commission      Nuclear Management Company, LLC 6612 Nuclear Road                        6610 Nuclear Road Two Rivers, WI 54241                    Point Beach Nuclear Plant Two Rivers, WI 54241
 
Point Beach Nuclear Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esq.
Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. Frederick D. Kuester President and Chief Executive Officer We Generation 231 West Michigan Street Milwaukee, WI 53201 James Connolly Manager, Regulatory Affairs Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffrey Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 David Weaver Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Fred Emerson Nuclear Energy Institute 1776 I Street, NW., Suite 400 Washington, DC 20006-3708 Roger A. Newton 3623 Nagawicka Shores Drive Hartland, WI 53029 James E. Knorr License Renewal Project Nuclear Management Company, LLC 6610 Nuclear Road Point Beach Nuclear Plant Two Rivers, WI 54241


DISTRIBUTION: Note to Licensee: Nuclear Management Company, LLC, Re:Summary of telephone conference held on January 14, 2005, Dated: January 19, 2005 Adams Accession No.: ML050270037 HARD COPY RLEP RF E-MAIL:
DISTRIBUTION: Note to Licensee: Nuclear Management Company, LLC, Re:Summary of telephone conference held on January 14, 2005, Dated: January 19, 2005 Adams Accession No.: ML050270037 HARD COPY RLEP RF E-MAIL:
RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis G. Galletti C. Li M. Itzkowitz (RidsOgcMailCenter)
RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis G. Galletti C. Li M. Itzkowitz (RidsOgcMailCenter)
R. Weisman M. Mayfield A. Murphy S. Smith (srs3)
R. Weisman M. Mayfield A. Murphy S. Smith (srs3)
S. Duraiswamy Y. L. (Renee) Li RLEP Staff P. Lougheed, RIII J. Strasma, RIII A. Stone, RIII H. Chernoff W. Ruland C. Marco L. Raghavan T. Mensah OPA
S. Duraiswamy Y. L. (Renee) Li RLEP Staff P. Lougheed, RIII J. Strasma, RIII A. Stone, RIII H. Chernoff W. Ruland C. Marco L. Raghavan T. Mensah OPA LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE TO DISCUSS THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION JANUARY 10, 2005 Participants Affiliations J. Knorr Nuclear Management Company, LLC M. Morgan Nuclear Regulatory Commission G. Suber Nuclear Regulatory Commission V. Rodriguez Nuclear Regulatory Commission DRAFT REQUESTS FOR ADDITIONAL INFORMATION (RAI)
 
LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE TO DISCUSS THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION JANUARY 10, 2005 Participants                     Affiliations J. Knorr                         Nuclear Management Company, LLC M. Morgan                       Nuclear Regulatory Commission G. Suber                         Nuclear Regulatory Commission V. Rodriguez                     Nuclear Regulatory Commission Enclosure 1
 
DRAFT REQUESTS FOR ADDITIONAL INFORMATION (RAI)
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION January 14, 2005 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on January 14, 2005, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Point Beach Nuclear Plant, Units 1 and 2, license renewal application (LRA). The following RAIs were discussed during the telephone conference call.
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION January 14, 2005 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on January 14, 2005, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Point Beach Nuclear Plant, Units 1 and 2, license renewal application (LRA). The following RAIs were discussed during the telephone conference call.
2.3.3.10 Essential Ventilation System RAI 2.3.3.10-1 (previously D-RAI 2.3.3.10-2)
2.3.3.10 Essential Ventilation System RAI 2.3.3.10-1 (previously D-RAI 2.3.3.10-2)
Line 47: Line 47:
If these components are excluded from the scope of license renewal and not subject to an AMR, provide justification for the exclusion.
If these components are excluded from the scope of license renewal and not subject to an AMR, provide justification for the exclusion.
Discussion: The applicant clarified their draft response. The applicant will provide their formal response in writing.
Discussion: The applicant clarified their draft response. The applicant will provide their formal response in writing.
Enclosure 2
ENCLOSURE RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION The following information is provided in response to the Nuclear Regulatory Commission (NRC) staff's request for additional information (RAI) regarding the Point Beach Nuclear Plant (PBNP)
ENCLOSURE RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION The following information is provided in response to the Nuclear Regulatory Commission (NRC) staff's request for additional information (RAI) regarding the Point Beach Nuclear Plant (PBNP)
License Renewal Application (LRA).
License Renewal Application (LRA).
Line 58: Line 56:
NMC Response:
NMC Response:
The chiller and associated subcomponents for the control room ventilation system are within the scope of license renewal in accordance with 10 CFR 54.4(a) and subject to aging management review in accordance with 10 CFR 54.21(a)(1).
The chiller and associated subcomponents for the control room ventilation system are within the scope of license renewal in accordance with 10 CFR 54.4(a) and subject to aging management review in accordance with 10 CFR 54.21(a)(1).
The chiller and associated subcomponents at PBNP that is being referenced above is referred to as a heat exchanger in the plant equipment database. As part of NMCs license renewal review of this component, sub-components were created to represent the chiller (and condenser) portions of this air conditioning unit. However, this did not result in the creation of a specific Chiller Component type but rather incorporated these sub-components in the Heat Exchanger Component Type. Therefore, a Chiller Component Type does not appear in LRA Enclosure 3
The chiller and associated subcomponents at PBNP that is being referenced above is referred to as a heat exchanger in the plant equipment database. As part of NMCs license renewal review of this component, sub-components were created to represent the chiller (and condenser) portions of this air conditioning unit. However, this did not result in the creation of a specific Chiller Component type but rather incorporated these sub-components in the Heat Exchanger Component Type. Therefore, a Chiller Component Type does not appear in LRA Tables 2.3.3-10 or 3.3.2-9. The Heat Exchanger line items in LRA Table 3.3.2-9 that have a "Treated Water" Environment represent those sub-components that are on the chilled water side of the unit. The Heat Exchanger line items with an "Air/Gas" Environment represent the sub-components that are on the refrigerant side of the unit. The Heat Exchanger line items with a "Raw Water" Environment represent the sub-components that are on the service water side of the unit.}}
 
Tables 2.3.3-10 or 3.3.2-9. The Heat Exchanger line items in LRA Table 3.3.2-9 that have a "Treated Water" Environment represent those sub-components that are on the chilled water side of the unit. The Heat Exchanger line items with an "Air/Gas" Environment represent the sub-components that are on the refrigerant side of the unit. The Heat Exchanger line items with a "Raw Water" Environment represent the sub-components that are on the service water side of the unit.
Enclosure 3}}

Latest revision as of 22:52, 15 January 2025

Summary of Telephone Conference Held on January 14, 2005, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Draft Requests for Additional Information Pertaining to the Point Beach Nuclear Plant,
ML050270037
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 01/19/2005
From: Veronica Rodriguez
NRC/NRR/DRIP/RLEP
To:
Nuclear Management Co
Rodriguez VM, RLEP/DRIP/NRR, 415-3703
References
Download: ML050270037 (8)


Text

January 19, 2005 LICENSEE:

Nuclear Management Company, LLC FACILITY:

Point Beach Nuclear Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE HELD ON JANUARY 14, 2005, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference on January 14, 2005, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Point Beach Nuclear Plant, Units 1 and 2, license renewal application. The conference call was useful in clarifying the intent of the staffs RAIs. provides a listing of the meeting participants. Enclosure 2 contains a listing of the RAIs discussed with the applicant, including a brief description on the status of the items. contains draft responses provided by the applicant.

The applicant had an opportunity to comment on this summary.

/RA/

Verónica M. Rodríguez, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301

Enclosures:

As stated cc w/encls: See next page

DOCUMENT NAME: E:\\Filenet\\ML050270037.wpd OFFICE PM:RLEP SC:RLEP NAME VRodríguez SLee DATE 01 / 14 / 05 01 / 19 / 05

Point Beach Nuclear Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esq.

Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. Frederick D. Kuester President and Chief Executive Officer We Generation 231 West Michigan Street Milwaukee, WI 53201 James Connolly Manager, Regulatory Affairs Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffrey Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 David Weaver Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Fred Emerson Nuclear Energy Institute 1776 I Street, NW., Suite 400 Washington, DC 20006-3708 Roger A. Newton 3623 Nagawicka Shores Drive Hartland, WI 53029 James E. Knorr License Renewal Project Nuclear Management Company, LLC 6610 Nuclear Road Point Beach Nuclear Plant Two Rivers, WI 54241

DISTRIBUTION: Note to Licensee: Nuclear Management Company, LLC, Re:Summary of telephone conference held on January 14, 2005, Dated: January 19, 2005 Adams Accession No.: ML050270037 HARD COPY RLEP RF E-MAIL:

RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis G. Galletti C. Li M. Itzkowitz (RidsOgcMailCenter)

R. Weisman M. Mayfield A. Murphy S. Smith (srs3)

S. Duraiswamy Y. L. (Renee) Li RLEP Staff P. Lougheed, RIII J. Strasma, RIII A. Stone, RIII H. Chernoff W. Ruland C. Marco L. Raghavan T. Mensah OPA LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE TO DISCUSS THE POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION JANUARY 10, 2005 Participants Affiliations J. Knorr Nuclear Management Company, LLC M. Morgan Nuclear Regulatory Commission G. Suber Nuclear Regulatory Commission V. Rodriguez Nuclear Regulatory Commission DRAFT REQUESTS FOR ADDITIONAL INFORMATION (RAI)

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION January 14, 2005 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on January 14, 2005, to discuss and clarify the staffs requests for additional information (RAIs) concerning the Point Beach Nuclear Plant, Units 1 and 2, license renewal application (LRA). The following RAIs were discussed during the telephone conference call.

2.3.3.10 Essential Ventilation System RAI 2.3.3.10-1 (previously D-RAI 2.3.3.10-2)

The Essential Ventilation System as described in the Point Beach Final Safety Analysis Report (PBNP FSAR) Sections 9.8 and 9.8.3 include the control room ventilation system, which is designed to provide heating, ventilation, air conditioning, and radiological habitability for the control and computer rooms within the control room envelope. The Essential Ventilation System license renewal drawings LR-M-144 sheet 2 and LR-M-214 sheets 1 and 4 highlight chiller components as in scope that are not included in LRA table 2.3.3-10, Essential Ventilation System and LRA Table 3.3.2-9, Auxiliary Systems - Essential Ventilation System -

Summary of Aging Management Evaluation. For example, while the tables list piping and fittings, pump casing, heat exchangers and coolers etc., they do not list the chiller and associated components shown on LR-M-214 sheet 4 at location C-9 for the control room chill water system. Degradation of these components could adversely impact the ability of the control room ventilation system to carry out its intended functions. Clarify whether these components and all other applicable components of the chill water system are within the scope of license renewal in accordance with 10CFR 54.4(a), and subject to aging management review in accordance with 10CFR 54.21(a)(1). If these components are within the scope of license renewal, update the LRA by providing the applicable information in the appropriate LRA tables.

If these components are excluded from the scope of license renewal and not subject to an AMR, provide justification for the exclusion.

Discussion: The applicant clarified their draft response. The applicant will provide their formal response in writing.

ENCLOSURE RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION The following information is provided in response to the Nuclear Regulatory Commission (NRC) staff's request for additional information (RAI) regarding the Point Beach Nuclear Plant (PBNP)

License Renewal Application (LRA).

The NRC staff's question is restated below, with the Nuclear Management Company (NMC) response following.

2.3.3.10 Essential Ventilation System RAI 2.3.3.10-1 (previously D-RAI 2.3.3.10-2)

The Essential Ventilation System as described in the Point Beach Final Safety Analysis Report (PBNP FSAR) Sections 9.8 and 9.8.3 include the control room ventilation system, which is designed to provide heating, ventilation, air conditioning, and radiological habitability for the control and computer rooms within the control room envelope. The Essential Ventilation System license renewal drawings LR-M-144 sheet 2 and LR-M-214 sheets 1 and 4 highlight chiller components as in scope that are not included in LRA table 2.3.3-10, Essential Ventilation System and LRA Table 3.3.2-9, Auxiliary Systems - Essential Ventilation System -

Summary of Aging Management Evaluation. For example, while the tables list piping and fittings, pump casing, heat exchangers and coolers etc., they do not list the chiller and associated components shown on LR-M-214 sheet 4 at location C-9 for the control room chill water system. Degradation of these components could adversely impact the ability of the control room ventilation system to carry out its intended functions. Clarify whether these components and all other applicable components of the chill water system are within the scope of license renewal in accordance with 10CFR 54.4(a), and subject to aging management review in accordance with 10CFR 54.21(a)(1). If these components are within the scope of license renewal, update the LRA by providing the applicable information in the appropriate LRA tables.

If these components are excluded from the scope of license renewal and not subject to an AMR, provide justification for the exclusion.

NMC Response:

The chiller and associated subcomponents for the control room ventilation system are within the scope of license renewal in accordance with 10 CFR 54.4(a) and subject to aging management review in accordance with 10 CFR 54.21(a)(1).

The chiller and associated subcomponents at PBNP that is being referenced above is referred to as a heat exchanger in the plant equipment database. As part of NMCs license renewal review of this component, sub-components were created to represent the chiller (and condenser) portions of this air conditioning unit. However, this did not result in the creation of a specific Chiller Component type but rather incorporated these sub-components in the Heat Exchanger Component Type. Therefore, a Chiller Component Type does not appear in LRA Tables 2.3.3-10 or 3.3.2-9. The Heat Exchanger line items in LRA Table 3.3.2-9 that have a "Treated Water" Environment represent those sub-components that are on the chilled water side of the unit. The Heat Exchanger line items with an "Air/Gas" Environment represent the sub-components that are on the refrigerant side of the unit. The Heat Exchanger line items with a "Raw Water" Environment represent the sub-components that are on the service water side of the unit.