Accession No. ML17338A930), a Category 2 public meeting was held between the U. S.
Accession No. ML17338A930), a Category 2 public meeting was held between the U. S.
Nuclear Regulatory Commission (NRC) staff and representatives from the Nuclear Energy Institute (NEI) to discuss their draft document that requests the Use of Flexible Scheduling Provisions of Title 10 of the Code of Federal Regulations (10 CFR) Section 50.155(h)(2) to establish an alternative date for compliance with reevaluated seismic hazard mitigation requirements of 10 CFR 50.155(b)(2) (ADAMS Accession No. ML17321B023).
Nuclear Regulatory Commission (NRC) staff and representatives from the Nuclear Energy Institute (NEI) to discuss their draft document that requests the Use of Flexible Scheduling Provisions of Title 10 of the Code of Federal Regulations (10 CFR) Section 50.155(h)(2) to establish an alternative date for compliance with reevaluated seismic hazard mitigation requirements of 10 CFR 50.155(b)(2) (ADAMS Accession No. ML17321B023).
The NEI gave a presentation to discuss the details of its draft document (ADAMS Accession No.
The NEI gave a presentation to discuss the details of its draft document (ADAMS Accession No. ML17338A818) and addressed comments and questions from the NRC staff.
ML17338A818) and addressed comments and questions from the NRC staff.
Members of the public attended the meeting in person and through the bridge line. At designated points during the meeting, members of the public were invited to provide any comments on the presentations.
Members of the public attended the meeting in person and through the bridge line. At designated points during the meeting, members of the public were invited to provide any comments on the presentations.


Line 34: Line 33:


ML17362A074                                    *via e-mail OFFICE NRR/DLP/PBEB* NRR/DLP/LA          NRR/DLP/PBEB/BC (A)    NRR/DLP/PBEB*
ML17362A074                                    *via e-mail OFFICE NRR/DLP/PBEB* NRR/DLP/LA          NRR/DLP/PBEB/BC (A)    NRR/DLP/PBEB*
NAME    JQuinones        SLent          TBrown                  JQuinones DATE    12/28/2017      12/28/2017    1/2/2018                1/4/2018
NAME    JQuinones        SLent          TBrown                  JQuinones DATE    12/28/2017      12/28/2017    1/2/2018                1/4/2018 PUBLIC MEETING WITH NUCLEAR ENERGY INSTITUTE TO DISCUSS DRAFT DOCUMENT THAT REQUESTS THE USE OF FLEXIBLE SCHEDULING PROVISIONS OF 10 CFR50.155(h)(2)
 
PUBLIC MEETING WITH NUCLEAR ENERGY INSTITUTE TO DISCUSS DRAFT DOCUMENT THAT REQUESTS THE USE OF FLEXIBLE SCHEDULING PROVISIONS OF 10 CFR50.155(h)(2)
December 7, 2017 List of Attendees Name                                        Organization Brenda Kovarik                              American Electric Power John Edgorf                                Nuclear Energy Institute Paul Guill                                  Duke Energy Eric Bowman                                NRC (U.S. Nuclear Regulatory Commission)
December 7, 2017 List of Attendees Name                                        Organization Brenda Kovarik                              American Electric Power John Edgorf                                Nuclear Energy Institute Paul Guill                                  Duke Energy Eric Bowman                                NRC (U.S. Nuclear Regulatory Commission)
Tony Brown                                  NRC Joylynn Quinones                            NRC Brett Titus                                NRC Milton Valentin                            NRC Enclosure}}
Tony Brown                                  NRC Joylynn Quinones                            NRC Brett Titus                                NRC Milton Valentin                            NRC Enclosure}}

Revision as of 20:53, 3 February 2020

Summary of Meeting with the Nuclear Energy Institute to Discuss Draft Document That Requests the Use of Flexible Scheduling Provisions of 10 CFR 50.155(H)(2)
ML17362A074
Person / Time
Issue date: 01/04/2018
From: Joylynn Quinones-Navarro
Beyond-Design-Basis Engineering Branch
To: Tony Brown
Beyond-Design-Basis Engineering Branch
Quinones-Navarro J
References
Download: ML17362A074 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 4, 2018 MEMORANDUM TO: Tony Brown, Acting Chief Beyond Design Basis Project Engineering Branch Division of Licensing Projects Office of Nuclear Reactor Regulation FROM: Joylynn Quinones-Navarro, Reactor Engineer /RA/

Beyond Design Basis Project Engineering Branch Division of Licensing Projects Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF DECEMBER 7, 2017, PUBLIC MEETING WITH THE NUCLEAR ENERGY INSTITUTE (NEI) TO DISCUSS DRAFT DOCUMENT THAT REQUESTS THE USE OF FLEXIBLE SCHEDULING PROVISIONS OF 10 CFR 50.155(h)(2)

On December 7, 2017 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML17338A930), a Category 2 public meeting was held between the U. S.

Nuclear Regulatory Commission (NRC) staff and representatives from the Nuclear Energy Institute (NEI) to discuss their draft document that requests the Use of Flexible Scheduling Provisions of Title 10 of the Code of Federal Regulations (10 CFR) Section 50.155(h)(2) to establish an alternative date for compliance with reevaluated seismic hazard mitigation requirements of 10 CFR 50.155(b)(2) (ADAMS Accession No. ML17321B023).

The NEI gave a presentation to discuss the details of its draft document (ADAMS Accession No. ML17338A818) and addressed comments and questions from the NRC staff.

Members of the public attended the meeting in person and through the bridge line. At designated points during the meeting, members of the public were invited to provide any comments on the presentations.

Enclosure:

Lists of Attendees CONTACT: Joylynn Quinones-Navarro, NRR/DLP/PBEB 404-997-4469

ML17362A074 *via e-mail OFFICE NRR/DLP/PBEB* NRR/DLP/LA NRR/DLP/PBEB/BC (A) NRR/DLP/PBEB*

NAME JQuinones SLent TBrown JQuinones DATE 12/28/2017 12/28/2017 1/2/2018 1/4/2018 PUBLIC MEETING WITH NUCLEAR ENERGY INSTITUTE TO DISCUSS DRAFT DOCUMENT THAT REQUESTS THE USE OF FLEXIBLE SCHEDULING PROVISIONS OF 10 CFR50.155(h)(2)

December 7, 2017 List of Attendees Name Organization Brenda Kovarik American Electric Power John Edgorf Nuclear Energy Institute Paul Guill Duke Energy Eric Bowman NRC (U.S. Nuclear Regulatory Commission)

Tony Brown NRC Joylynn Quinones NRC Brett Titus NRC Milton Valentin NRC Enclosure