{{#Wiki_filter:January 30, 2006LICENSEE:Nuclear Management Company, LLCFACILITY:Monticello Nuclear Generating Plant
{{#Wiki_filter:January 30, 2006 LICENSEE:     Nuclear Management Company, LLC FACILITY:     Monticello Nuclear Generating Plant


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF A TELEPHONE CONFERENCE CALL HELD ON JANUARY 9, 2006, BETWEEN THE U.S. NUCLEAR REGULATORYCOMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING INFORMATION PERTAINING TO THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATIONThe U.S. Nuclear Regulatory Commission staff (the staff) and representatives of NuclearManagement Company, LLC (NMC) held a telephone conference call on January 9, 2006, to discuss and clarify the applicant's responses to requests for additional information (RAIs) concerning the Monticello Nuclear Generating Plant license renewal application. Theconference call was useful in clarifying the staff's questions.Enclosure 1 provides a listing of the conference call participants. Enclosure 2 contains a listingof the issues discussed with the applicant, including a brief description on the status of the items.The applicant had an opportunity to comment on this summary./RA/Daniel J. Merzke, Project ManagerLicense Renewal Branch B Division of License Renewal Office of Nuclear Reactor RegulationDocket No. 50-263
OF A TELEPHONE CONFERENCE CALL HELD ON JANUARY 9, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING INFORMATION PERTAINING TO THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on January 9, 2006, to discuss and clarify the applicants responses to requests for additional information (RAIs) concerning the Monticello Nuclear Generating Plant license renewal application. The conference call was useful in clarifying the staffs questions. provides a listing of the conference call participants. Enclosure 2 contains a listing of the issues discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
                                      /RA/
Daniel J. Merzke, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-263


==Enclosures:==
==Enclosures:==
As statedcc w/encls:  See next page


ML060310635 DOCUMENT NAME:  E:\Filenet\ML060310635.wpdOFFICEPM:RLRBLA:RLRABC:RLRBNAMEDMerzke YEdmonds JZimmermanDATE01/30/0601/23/0601/30/06 Monticello Nuclear Generating Plant cc:
As stated cc w/encls: See next page
Jonathan Rogoff, EsquireVice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI  54016 U.S. Nuclear Regulatory CommissionResident Inspector's Office 2807 W. County Road 75 Monticello, MN  55362 Manager, Regulatory AffairsMonticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN  55362-9637Robert Nelson, PresidentMinnesota Environmental Control Citizens Association (MECCA) 1051 South McKnight Road St. Paul, MN  55119CommissionerMinnesota Pollution Control Agency 520 Lafayette Road St. Paul, MN  55155-4194Regional Administrator, Region IIIU.S. Nuclear Regulatory Commission 801 Warrenville RoadLisle, IL  60532-4351CommissionerMinnesota Department of Health 717 Delaware Street, S.E.
Minneapolis, MN  55440Douglas M. Gruber, Auditor/TreasurerWright County Government Center 10 NW Second Street Buffalo, MN  55313CommissionerMinnesota Department of Commerce


85 7 th Place East, Suite 500St. Paul, MN  55101-2198Manager - Environmental Protection            Division Minnesota Attorney General's Office 445 Minnesota St., Suite 900 St. Paul, MN  55101-2127John Paul CowanExecutive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI  54016Nuclear Asset ManagerXcel Energy, Inc.
ML060310635 DOCUMENT NAME: E:\Filenet\ML060310635.wpd OFFICE    PM:RLRB                LA:RLRA                  BC:RLRB NAME      DMerzke                YEdmonds                JZimmerman DATE      01/30/06              01/23/06                01/30/06
414 Nicollet Mall, R.S. 8 Minneapolis, MN  55401Mr. James RossNuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC  20006-3708Joseph PairitzLicense Renewal Project Manager Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN  55362-9637Mr. Douglas F. JohnsonDirector, Plant Life Cycle Issues Nuclear Management Company, LLC 700 First Street Hudson, WI  54016


Monticello Nuclear Generating Plant             cc:
Monticello Nuclear Generating Plant cc:
David R. LewisPillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037-1122Mr. George CrockerNorth American Water Office
Jonathan Rogoff, Esquire            Commissioner Vice President, Counsel & Secretary  Minnesota Department of Commerce Nuclear Management Company, LLC      85 7th Place East, Suite 500 700 First Street                    St. Paul, MN 55101-2198 Hudson, WI 54016 Manager - Environmental Protection U.S. Nuclear Regulatory Commission    Division Resident Inspectors Office          Minnesota Attorney Generals Office 2807 W. County Road 75              445 Minnesota St., Suite 900 Monticello, MN 55362                St. Paul, MN 55101-2127 Manager, Regulatory Affairs          John Paul Cowan Monticello Nuclear Generating Plant  Executive Vice President & Chief Nuclear Nuclear Management Company, LLC        Officer 2807 West County Road 75            Nuclear Management Company, LLC Monticello, MN 55362-9637            700 First Street Hudson, WI 54016 Robert Nelson, President Minnesota Environmental Control      Nuclear Asset Manager Citizens Association (MECCA)      Xcel Energy, Inc.
1051 South McKnight Road            414 Nicollet Mall, R.S. 8 St. Paul, MN 55119                  Minneapolis, MN 55401 Commissioner                        Mr. James Ross Minnesota Pollution Control Agency  Nuclear Energy Institute 520 Lafayette Road                  1776 I Street, NW, Suite 400 St. Paul, MN 55155-4194              Washington, DC 20006-3708 Regional Administrator, Region III  Joseph Pairitz U.S. Nuclear Regulatory Commission  License Renewal Project Manager 801 Warrenville Road                Monticello Nuclear Generating Plant Lisle, IL 60532-4351                Nuclear Management Company, LLC 2807 West County Road 75 Commissioner                        Monticello, MN 55362-9637 Minnesota Department of Health 717 Delaware Street, S.E.            Mr. Douglas F. Johnson Minneapolis, MN 55440                Director, Plant Life Cycle Issues Nuclear Management Company, LLC Douglas M. Gruber, Auditor/Treasurer 700 First Street Wright County Government Center      Hudson, WI 54016 10 NW Second Street Buffalo, MN 55313


P.O. Box 174 Lake Elmo, MN 55042Mr. John T. ConwaySite Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637 Letter to Licensee Nuclear Management Co. from Daniel J. Merzke dated,January 30, 2006_______________ __________________________________________
Monticello Nuclear Generating Plant  cc:
David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037-1122 Mr. George Crocker North American Water Office P.O. Box 174 Lake Elmo, MN 55042 Mr. John T. Conway Site Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637
 
Letter to Licensee Nuclear Management Co. from Daniel J. Merzke dated, January 30, 2006_______________ __________________________________________


==SUBJECT:==
==SUBJECT:==


==SUMMARY==
==SUMMARY==
OF A TELEPHONE CONFERENCE CALL HELD ON JANUARY 9, 2006, BETWEEN THE U.S. NUCLEAR REGULATORYCOMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING INFORMATION PERTAINING TO THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATIONHARD COPYDMerzke E-MAILJFairRWeisman AMurphy RPettis GGalletti CLi GBagchi SSmith (srs3)
OF A TELEPHONE CONFERENCE CALL HELD ON JANUARY 9, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING INFORMATION PERTAINING TO THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION HARD COPY DMerzke E-MAIL JFair RWeisman AMurphy RPettis GGalletti CLi GBagchi SSmith (srs3)
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrDipm DLR Staff
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrDipm DLR Staff
-----------
-----------
LRaghavan PTam AStone, RIII BBurgess, RIII PLougheed, RIII SRay, RIII AHodgdon MWoods OPA LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALLTO DISCUSS THE MONTICELLO NUCLEAR GENERATING PLANTLICENSE RENEWAL APPLICATIONJanuary 9, 2006Participants                                      AffiliationsDaniel MerzkeU.S. Nuclear Regulatory Commission (NRC)Barry ElliotNRC Mark HartzmanNRC Joe PairitzNuclear Management Company, LLC (NMC)
LRaghavan PTam AStone, RIII BBurgess, RIII PLougheed, RIII SRay, RIII AHodgdon MWoods OPA
Mike AlekseyNMC Dave MusolfNMC  MONTICELLO NUCLEAR GENERATING PLANTLICENSE RENEWAL APPLICATIONJanuary 9, 2006The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of NuclearManagement Company, LLC (NMC) held a telephone conference call on January 9, 2006, to discuss and clarify the applicant's responses to requests for additional information (RAIs) concerning the Monticello Nuclear Generating Plant license renewal application. The followingissues were discussed during the telephone conference call:1.In a letter dated December 16, 2005, the applicant provided a supplemental response toRAI 4.8-2. The applicant provided a proprietary reportconcerning the investigation of the sliding behavior of a number of alloys under dry and water-lubricated conditions. NRC staff review identified some apparent discrepancies withthe data presented in the report. The staff reiterated its position that for the analysis of thestress relaxation of rim hold down bolts time-limited aging analysis (TLAA), a friction coefficient of 0.5 was unacceptably high. The NRC staff referenced Boiling Water Reactor Vessel and Internals Project-25 (BWRVIP-25) which did not include friction in an analysis acceptable to the NRC staff, and Code Case N-730, which used a friction coefficient of 0.2in an analysis of similar materials in a different geometry. The staff requested the applicant to provide additional information on the GE testing described in the proprietary report, or provide another analysis for the TLAA.Discussion: The applicant indicated that the question is clear. The applicant will perform ananalysis of the stress relaxation in accordance with the process described in BWRVIP-25, andprovide the analysis to the staff for its review.2. In its initial response to RAI 4.2-3, dated October 28, 2005, the applicant provided a tableprojecting Upper Shelf Energy (USE) data through the period of extended operation. The staff noted the table was missing the data for the nozzles. The applicant referencedBWRVIP-74, which provided USE data for plates. However, the staff noted that nozzles areforged components, not plates, and requested the applicant to provide a technical basis fortheir position that the plates are the limiting components.Discussion: The applicant indicated that the question is clear. The applicant will provide theUSE information for the nozzles.}}
 
LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION January 9, 2006 Participants                  Affiliations Daniel Merzke                  U.S. Nuclear Regulatory Commission (NRC)
Barry Elliot                  NRC Mark Hartzman                  NRC Joe Pairitz                    Nuclear Management Company, LLC (NMC)
Mike Aleksey                  NMC Dave Musolf                    NMC Enclosure 1
 
MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION January 9, 2006 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on January 9, 2006, to discuss and clarify the applicants responses to requests for additional information (RAIs) concerning the Monticello Nuclear Generating Plant license renewal application. The following issues were discussed during the telephone conference call:
: 1. In a letter dated December 16, 2005, the applicant provided a supplemental response to RAI 4.8-2. The applicant provided a                                     proprietary report concerning the investigation of the sliding behavior of a number of alloys under dry and water-lubricated conditions. NRC staff review identified some apparent discrepancies with the data presented in the report. The staff reiterated its position that for the analysis of the stress relaxation of rim hold down bolts time-limited aging analysis (TLAA), a friction coefficient of 0.5 was unacceptably high. The NRC staff referenced Boiling Water Reactor Vessel and Internals Project-25 (BWRVIP-25) which did not include friction in an analysis acceptable to the NRC staff, and Code Case N-730, which used a friction coefficient of 0.2 in an analysis of similar materials in a different geometry. The staff requested the applicant to provide additional information on the GE testing described in the proprietary report, or provide another analysis for the TLAA.
Discussion: The applicant indicated that the question is clear. The applicant will perform an analysis of the stress relaxation in accordance with the process described in BWRVIP-25, and provide the analysis to the staff for its review.
: 2. In its initial response to RAI 4.2-3, dated October 28, 2005, the applicant provided a table projecting Upper Shelf Energy (USE) data through the period of extended operation. The staff noted the table was missing the data for the nozzles. The applicant referenced BWRVIP-74, which provided USE data for plates. However, the staff noted that nozzles are forged components, not plates, and requested the applicant to provide a technical basis for their position that the plates are the limiting components.
Discussion: The applicant indicated that the question is clear. The applicant will provide the USE information for the nozzles.
Enclosure 2}}

Revision as of 22:46, 23 November 2019

01/30/2006 - Summary of Telephone Conference Call Held on 01/09/2006, Between the U.S. Nuclear Regulatory Commission and Nuclear Management Company, LLC, Concerning Information Pertaining to the Monticello Nuclear Generating Plant License R
ML060310635
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 01/30/2006
From: Daniel Merzke
NRC/NRR/ADRO/DLR
To:
Nuclear Management Co
Merzke, D., NRR/ADRO/DLR/RLRB, 415-3777
References
Download: ML060310635 (7)


Text

January 30, 2006 LICENSEE: Nuclear Management Company, LLC FACILITY: Monticello Nuclear Generating Plant

SUBJECT:

SUMMARY

OF A TELEPHONE CONFERENCE CALL HELD ON JANUARY 9, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING INFORMATION PERTAINING TO THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on January 9, 2006, to discuss and clarify the applicants responses to requests for additional information (RAIs) concerning the Monticello Nuclear Generating Plant license renewal application. The conference call was useful in clarifying the staffs questions. provides a listing of the conference call participants. Enclosure 2 contains a listing of the issues discussed with the applicant, including a brief description on the status of the items.

The applicant had an opportunity to comment on this summary.

/RA/

Daniel J. Merzke, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-263

Enclosures:

As stated cc w/encls: See next page

ML060310635 DOCUMENT NAME: E:\Filenet\ML060310635.wpd OFFICE PM:RLRB LA:RLRA BC:RLRB NAME DMerzke YEdmonds JZimmerman DATE 01/30/06 01/23/06 01/30/06

Monticello Nuclear Generating Plant cc:

Jonathan Rogoff, Esquire Commissioner Vice President, Counsel & Secretary Minnesota Department of Commerce Nuclear Management Company, LLC 85 7th Place East, Suite 500 700 First Street St. Paul, MN 55101-2198 Hudson, WI 54016 Manager - Environmental Protection U.S. Nuclear Regulatory Commission Division Resident Inspectors Office Minnesota Attorney Generals Office 2807 W. County Road 75 445 Minnesota St., Suite 900 Monticello, MN 55362 St. Paul, MN 55101-2127 Manager, Regulatory Affairs John Paul Cowan Monticello Nuclear Generating Plant Executive Vice President & Chief Nuclear Nuclear Management Company, LLC Officer 2807 West County Road 75 Nuclear Management Company, LLC Monticello, MN 55362-9637 700 First Street Hudson, WI 54016 Robert Nelson, President Minnesota Environmental Control Nuclear Asset Manager Citizens Association (MECCA) Xcel Energy, Inc.

1051 South McKnight Road 414 Nicollet Mall, R.S. 8 St. Paul, MN 55119 Minneapolis, MN 55401 Commissioner Mr. James Ross Minnesota Pollution Control Agency Nuclear Energy Institute 520 Lafayette Road 1776 I Street, NW, Suite 400 St. Paul, MN 55155-4194 Washington, DC 20006-3708 Regional Administrator, Region III Joseph Pairitz U.S. Nuclear Regulatory Commission License Renewal Project Manager 801 Warrenville Road Monticello Nuclear Generating Plant Lisle, IL 60532-4351 Nuclear Management Company, LLC 2807 West County Road 75 Commissioner Monticello, MN 55362-9637 Minnesota Department of Health 717 Delaware Street, S.E. Mr. Douglas F. Johnson Minneapolis, MN 55440 Director, Plant Life Cycle Issues Nuclear Management Company, LLC Douglas M. Gruber, Auditor/Treasurer 700 First Street Wright County Government Center Hudson, WI 54016 10 NW Second Street Buffalo, MN 55313

Monticello Nuclear Generating Plant cc:

David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, NW Washington, DC 20037-1122 Mr. George Crocker North American Water Office P.O. Box 174 Lake Elmo, MN 55042 Mr. John T. Conway Site Vice President Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637

Letter to Licensee Nuclear Management Co. from Daniel J. Merzke dated, January 30, 2006_______________ __________________________________________

SUBJECT:

SUMMARY

OF A TELEPHONE CONFERENCE CALL HELD ON JANUARY 9, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND NUCLEAR MANAGEMENT COMPANY, LLC, CONCERNING INFORMATION PERTAINING TO THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION HARD COPY DMerzke E-MAIL JFair RWeisman AMurphy RPettis GGalletti CLi GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrDipm DLR Staff


LRaghavan PTam AStone, RIII BBurgess, RIII PLougheed, RIII SRay, RIII AHodgdon MWoods OPA

LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION January 9, 2006 Participants Affiliations Daniel Merzke U.S. Nuclear Regulatory Commission (NRC)

Barry Elliot NRC Mark Hartzman NRC Joe Pairitz Nuclear Management Company, LLC (NMC)

Mike Aleksey NMC Dave Musolf NMC Enclosure 1

MONTICELLO NUCLEAR GENERATING PLANT LICENSE RENEWAL APPLICATION January 9, 2006 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Nuclear Management Company, LLC (NMC) held a telephone conference call on January 9, 2006, to discuss and clarify the applicants responses to requests for additional information (RAIs) concerning the Monticello Nuclear Generating Plant license renewal application. The following issues were discussed during the telephone conference call:

1. In a letter dated December 16, 2005, the applicant provided a supplemental response to RAI 4.8-2. The applicant provided a proprietary report concerning the investigation of the sliding behavior of a number of alloys under dry and water-lubricated conditions. NRC staff review identified some apparent discrepancies with the data presented in the report. The staff reiterated its position that for the analysis of the stress relaxation of rim hold down bolts time-limited aging analysis (TLAA), a friction coefficient of 0.5 was unacceptably high. The NRC staff referenced Boiling Water Reactor Vessel and Internals Project-25 (BWRVIP-25) which did not include friction in an analysis acceptable to the NRC staff, and Code Case N-730, which used a friction coefficient of 0.2 in an analysis of similar materials in a different geometry. The staff requested the applicant to provide additional information on the GE testing described in the proprietary report, or provide another analysis for the TLAA.

Discussion: The applicant indicated that the question is clear. The applicant will perform an analysis of the stress relaxation in accordance with the process described in BWRVIP-25, and provide the analysis to the staff for its review.

2. In its initial response to RAI 4.2-3, dated October 28, 2005, the applicant provided a table projecting Upper Shelf Energy (USE) data through the period of extended operation. The staff noted the table was missing the data for the nozzles. The applicant referenced BWRVIP-74, which provided USE data for plates. However, the staff noted that nozzles are forged components, not plates, and requested the applicant to provide a technical basis for their position that the plates are the limiting components.

Discussion: The applicant indicated that the question is clear. The applicant will provide the USE information for the nozzles.