{{#Wiki_filter:1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
{{#Wiki_filter:UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
___________________________________In the Matter of Tennessee Valley Authority   Docket Nos. 50-438 and 50-439   Bellefonte Nuclear Power Plant Units 1 and 2
___________________________________
___________________________________PETITIONERS' MOTION FOR ADDITIONAL TIME IN WHICH TO (1) FILE A NOTICE OF APPEARANCE OF COUNSEL AND (2) REPLY TO TVA AND NRC STAFF ANSWERS TO PETITION FOR INTERVENTIONPetitioners hereby request leave of the Atomic Safety and Licensing Board
In the Matter of Tennessee Valley Authority                             Docket Nos. 50-438 and 50-439 Bellefonte Nuclear Power Plant Units 1 and 2
("Board") to file the attached PETITIONERS' REPLY TO TVA AND NRC STAFF ANSWERS TO PETITION FOR INTERVENTION and NOTICE OF APPEARANCE of undersigned attorney James B. Dougherty out of time. The reason that Petitioners were late in filing said documents is that they were diligently attempting to secure the services of counsel to represent them henceforth in this proceeding. As they are all non-profit organizations, even in good times it is difficult to secure sufficient funds to have legal representation in administrative proceedings. Due to the current downturn in the economy, however, Petitioners and most non-profits have faced unusually trying financial circumstances. Petitioners attempted to secure representation from pro bono counsel, but without success.
___________________________________
PETITIONERS MOTION FOR ADDITIONAL TIME IN WHICH TO (1) FILE A NOTICE OF APPEARANCE OF COUNSEL AND (2) REPLY TO TVA AND NRC STAFF ANSWERS TO PETITION FOR INTERVENTION Petitioners hereby request leave of the Atomic Safety and Licensing Board (Board) to file the attached PETITIONERS REPLY TO TVA AND NRC STAFF ANSWERS TO PETITION FOR INTERVENTION and NOTICE OF APPEARANCE of undersigned attorney James B. Dougherty out of time. The reason that Petitioners were late in filing said documents is that they were diligently attempting to secure the services of counsel to represent them henceforth in this proceeding. As they are all non-profit organizations, even in good times it is difficult to secure sufficient funds to have legal representation in administrative proceedings. Due to the current downturn in the economy, however, Petitioners and most non-profits have faced unusually trying financial circumstances. Petitioners attempted to secure representation from pro bono counsel, but without success.
It was only last week that the undersigned attorney agreed to represent Petitioners in this proceeding. The undersigned represents that future Board-established deadlines will be met.
It was only last week that the undersigned attorney agreed to represent Petitioners in this proceeding. The undersigned represents that future Board-established deadlines will be met.
2Respectfully submitted, Signed (electronically) this 16 th day ofFebruary, 2009, in Washington, D.C.James B. Dougherty709 3rd St. S.W.
1
Washington, D.C. 20024


202-488-1140 (v)
Respectfully submitted, Signed (electronically) this 16th day of February, 2009, in Washington, D.C.
James B. Dougherty 709 3rd St. S.W.
Washington, D.C. 20024 202-488-1140 (v) 202-484-1789 (f) jimdougherty@aol.com Counsel for Petitioners Blue Ridge Defense League, et al.
2


202-484-1789 (f) jimdougherty@aol.com Counsel for Petitioners
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
 
___________________________________
Blue Ridge Defense League, et al.
In the Matter of Tennessee Valley Authority                             Docket Nos. 50-438 and 50-439 Bellefonte Nuclear Power Plant                         February 16, 2010 Units 1 and 2
3 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD
___________________________________In the Matter of Tennessee Valley Authority   Docket Nos. 50-438 and 50-439   Bellefonte Nuclear Power Plant February 16, 2010 Units 1 and 2
___________________________________
___________________________________
CERTIFICATE OF SERVICEI hereby certify that copies of the foregoing Petitioners' Motion for Additional Timewereserved this day on the following persons via Electronic Information Exchange:
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Petitioners Motion for Additional Time were served this day on the following persons via Electronic Information Exchange:
Office of the Secretary ATTN: Docketing and Service
Office of the Secretary                           Bellefonte Efficiency & Sustainability ATTN: Docketing and Service                       Team Mail Stop 0-16C1                                   185 Hood Drive US Nuclear Regulatory Commission                   Crossville, TN 28555 Washington, DC 20555-0001                         (E-mail: lgorenflo@gmail.com)
 
(E-mail: hearingdocket@nrc.gov)
Mail Stop 0-16C1 US Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: hearingdocket@nrc.gov
Kathryn M. Sutton, Esq.
)Office of Commission Appellate Adjudication US Nuclear Regulatory Commission Washington, DC 20555-0001 (E-mail: ocaamail@nrc.gov
Office of Commission Appellate                    Lawrence J. Chandler, Esq.
)Patrick A. Moulding, Esq.
Adjudication                                      Morgan, Lewis & Bockius LLP US Nuclear Regulatory Commission                  1111 Pennsylvania Ave., NW Washington, DC 20555-0001                          Washington, DC 20004 (E-mail: ocaamail@nrc.gov)                        (E-mail: ksutton@morganlewis.com, lchandler@morganlewis.com)
Ann P. Hodgdon, Esq.
Patrick A. Moulding, Esq.
US Nuclear Regulatory Commission
Ann P. Hodgdon, Esq.                              Martin J. ONeill, Esq.
 
US Nuclear Regulatory Commission                  Morgan, Lewis & Bockius LLP Mail Stop O-15 D21                                1000 Louisiana St., Suite 4000 Washington, DC 20555-0001                          Houston, TX 77002 (E-mail: patrick.moulding@nrc.gov,                E-mail:
Mail Stop O-15 D21 Washington, DC 20555-0001 (E-mail: patrick.moulding@nrc.gov, ann.hodgdon@nrc.gov
ann.hodgdon@nrc.gov)                              martin.oneill@morganlewis.com Edward J. Vigluicci, Esq.
)Louise Gorenflo Bellefonte Efficiency & Sustainability Team 185 Hood Drive
 
Crossville, TN 28555 (E-mail: lgorenflo@gmail.com
)Kathryn M. Sutton, Esq.
Lawrence J. Chandler, Esq.
 
Morgan, Lewis & Bockius LLP
 
1111 Pennsylvania Ave., NW Washington, DC 20004 (E-mail: ksutton@morganlewis.com, lchandler@morganlewis.com
)Martin J. O'Neill, Esq.
Morgan, Lewis & Bockius LLP
 
1000 Louisiana St., Suite 4000
 
Houston, TX 77002 E-mail:
martin.oneill@morganlewis.com Edward J. Vigluicci, Esq.
Scott A. Vance, Esq.
Scott A. Vance, Esq.
Louise Gorenflo                                    Tennessee Valley Authority 3


Tennessee Valley Authority 4400 West Summit Hill Dr., WT 6A-K Knoxville, TN 37902 (E-mail: ejvigluicci@tva.gov, savance@tva.gov
400 West Summit Hill Dr., WT 6A-K Knoxville, TN 37902 (E-mail: ejvigluicci@tva.gov, savance@tva.gov)
)Andrea Z. Jones, Esq.
Andrea Z. Jones, Esq.
Counsel for NRC Staff US Nuclear Regulatory Commission
Counsel for NRC Staff US Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15 D21 Washington, DC 20555-0001          Signed (electronically) this 16th day of February, 2010 in Washington, D.C.
 
James B. Dougherty, Esq.
Office of the General Counsel
709 3rd St. S.W.
 
Washington, D.C. 20024 (202) 488-1140(v)
Mail Stop: O-15 D21 Washington, DC 20555-0001Signed (electronically) this 16 th day ofFebruary, 2010 in Washington, D.C.James B. Dougherty, Esq.709 3rd St. S.W.
(E-mail: jimdougherty@aol.com) 4}}
Washington, D.C. 20024  
 
(202) 488-1140(v)
(E-mail: jimdougherty@aol.com)}}

Revision as of 22:50, 13 November 2019

2010/02/16-Petitioner's Motion for Additional Time in Which to (1) File a Notice of Appearance of Counsel and (2) Reply to TVA and NRC Staff Answers to Petition for Intervention
ML100470492
Person / Time
Site: Bellefonte  Tennessee Valley Authority icon.png
Issue date: 02/16/2010
From: Jay Dougherty
Bellefonte Efficiency & Sustainability Team (BEST), Blue Ridge Environmental Defense League, Southern Alliance for Clean Energy
To:
Atomic Safety and Licensing Board Panel
SECY RAS
Shared Package
ML100470488 List:
References
50-438-CP, 50-439-CP, ASLBP 10-896-01-CP-BD01, RAS 17218
Download: ML100470492 (4)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD

___________________________________

In the Matter of Tennessee Valley Authority Docket Nos. 50-438 and 50-439 Bellefonte Nuclear Power Plant Units 1 and 2

___________________________________

PETITIONERS MOTION FOR ADDITIONAL TIME IN WHICH TO (1) FILE A NOTICE OF APPEARANCE OF COUNSEL AND (2) REPLY TO TVA AND NRC STAFF ANSWERS TO PETITION FOR INTERVENTION Petitioners hereby request leave of the Atomic Safety and Licensing Board (Board) to file the attached PETITIONERS REPLY TO TVA AND NRC STAFF ANSWERS TO PETITION FOR INTERVENTION and NOTICE OF APPEARANCE of undersigned attorney James B. Dougherty out of time. The reason that Petitioners were late in filing said documents is that they were diligently attempting to secure the services of counsel to represent them henceforth in this proceeding. As they are all non-profit organizations, even in good times it is difficult to secure sufficient funds to have legal representation in administrative proceedings. Due to the current downturn in the economy, however, Petitioners and most non-profits have faced unusually trying financial circumstances. Petitioners attempted to secure representation from pro bono counsel, but without success.

It was only last week that the undersigned attorney agreed to represent Petitioners in this proceeding. The undersigned represents that future Board-established deadlines will be met.

1

Respectfully submitted, Signed (electronically) this 16th day of February, 2009, in Washington, D.C.

James B. Dougherty 709 3rd St. S.W.

Washington, D.C. 20024 202-488-1140 (v) 202-484-1789 (f) jimdougherty@aol.com Counsel for Petitioners Blue Ridge Defense League, et al.

2

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD

___________________________________

In the Matter of Tennessee Valley Authority Docket Nos. 50-438 and 50-439 Bellefonte Nuclear Power Plant February 16, 2010 Units 1 and 2

___________________________________

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Petitioners Motion for Additional Time were served this day on the following persons via Electronic Information Exchange:

Office of the Secretary Bellefonte Efficiency & Sustainability ATTN: Docketing and Service Team Mail Stop 0-16C1 185 Hood Drive US Nuclear Regulatory Commission Crossville, TN 28555 Washington, DC 20555-0001 (E-mail: lgorenflo@gmail.com)

(E-mail: hearingdocket@nrc.gov)

Kathryn M. Sutton, Esq.

Office of Commission Appellate Lawrence J. Chandler, Esq.

Adjudication Morgan, Lewis & Bockius LLP US Nuclear Regulatory Commission 1111 Pennsylvania Ave., NW Washington, DC 20555-0001 Washington, DC 20004 (E-mail: ocaamail@nrc.gov) (E-mail: ksutton@morganlewis.com, lchandler@morganlewis.com)

Patrick A. Moulding, Esq.

Ann P. Hodgdon, Esq. Martin J. ONeill, Esq.

US Nuclear Regulatory Commission Morgan, Lewis & Bockius LLP Mail Stop O-15 D21 1000 Louisiana St., Suite 4000 Washington, DC 20555-0001 Houston, TX 77002 (E-mail: patrick.moulding@nrc.gov, E-mail:

ann.hodgdon@nrc.gov) martin.oneill@morganlewis.com Edward J. Vigluicci, Esq.

Scott A. Vance, Esq.

Louise Gorenflo Tennessee Valley Authority 3

400 West Summit Hill Dr., WT 6A-K Knoxville, TN 37902 (E-mail: ejvigluicci@tva.gov, savance@tva.gov)

Andrea Z. Jones, Esq.

Counsel for NRC Staff US Nuclear Regulatory Commission Office of the General Counsel Mail Stop: O-15 D21 Washington, DC 20555-0001 Signed (electronically) this 16th day of February, 2010 in Washington, D.C.

James B. Dougherty, Esq.

709 3rd St. S.W.

Washington, D.C. 20024 (202) 488-1140(v)

(E-mail: jimdougherty@aol.com) 4