{{Adams
#REDIRECT [[RS-13-030, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)]]
| number = ML13060A125
| issue date = 02/28/2013
| title = Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)
| author name = Kaegi G T
| author affiliation = Exelon Generation Co, LLC
| addressee name =
| addressee affiliation = NRC/Document Control Desk, NRC/NRR
| docket = 05000237, 05000249
| license number = DPR-019, DPR-025
| contact person =
| case reference number = EA-12-051, RS-13-030
| document type = Letter, Operating Plan
| page count = 11
| project =
| stage = Other
}}
 
=Text=
{{#Wiki_filter:Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation (SFPI)
Overall Integrated Plan Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Overall Integrated Plan Applicability:
Dresden Station is a two unit BWR Station. The two units each have a dedicated, unconnected Spent Fuel Pool (SFP) located in the Reactor Building (RB). Normal SFP water level is approximately elevation 612.
the spent fuel racks is approximately elevation 589and top of active fuel is approximately elevation 5877 .
 
Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Overall Integrated Plan Level adequate to support operation of the normal fuel pool cooling system (Level 1):
Level adequate to provide substantial radiation shielding for a person standing on the spent fuel pool operating deck (Level 2):
Level where fuel remains covered (Level 3):
fuel seated Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Overall Integrated Plan Primary (fixed) instrument channel:
Backup instrument channel:
Arrangement:
Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Mounting:
Qualification:
Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Overall Integrated Plan Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Overall Integrated Plan Independence:
Power Supplies:
Accuracy:
Testing:Display:
Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Overall Integrated Plan Program Features Training:
Procedures:
Testing and Calibration:
Dresden Nuclear Power Station, Units 2 and 3 Reliable Spent Fuel Pool Instrumentation Overall Integrated Plan 3.NEI 12-02, Industry Guidance for Compliance Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation", Revision 1, dated August8}}