{{#Wiki_filter:Inspection / Activity Plan Page 1 of 2 03/04/2009 09:17:02 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hatch OL EXAM
- INITIAL EXAM PREP 6
1 HATCH/APRIL 2009 EXAM AT POWER FACILITIES V23311 03/30/2009 04/03/2009 OL EXAM
- INITIAL EXAM - WEEK 1 4
1 HATCH/APRIL 2009 EXAM AT POWER FACILITIES V23311 04/20/2009 04/24/2009 EB1-CDBI
- COMPONENT DESIGN BASIS INSPECTION 9
1, 2 IP Component Design Bases Inspection 7111121 04/20/2009 04/24/2009 1, 2 IP Component Design Bases Inspection 7111121 05/04/2009 05/08/2009 1, 2 IP Component Design Bases Inspection 7111121 05/18/2009 05/22/2009 1, 2 IP Component Design Bases Inspection 7111121 06/01/2009 06/05/2009 OL EXAM
- INITIAL EXAM - WEEK 2 4
1 HATCH/APRIL 2009 EXAM AT POWER FACILITIES V23311 04/27/2009 05/01/2009 PI&R
- PRE INSPECTION 1
1, 2 IP Identification and Resolution of Problems 71152B 08/31/2009 09/04/2009 PI&R
- PROBLEM IDENTIFICATION AND RESOLUTION 6
1, 2 IP Identification and Resolution of Problems 71152B 10/05/2009 10/09/2009 1, 2 IP Identification and Resolution of Problems 71152B 10/19/2009 10/23/2009 OL EXAM
- INITIAL EXAM PREP 7
1 HATCH/OCTOBER 2009 EXAM AT POWER FACILITIES V23320 10/05/2009 10/09/2009 PSB1EP
- EMERGENCY PREPAREDNESS EXERCISE 3
1, 2 IP Exercise Evaluation 7111401 10/12/2009 10/16/2009 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 10/12/2009 10/16/2009 1, 2 IP Performance Indicator Verification 71151 10/12/2009 10/16/2009 OL EXAM
- INITIAL EXAM - WEEK 1 5
1 HATCH/OCTOBER 2009 EXAM AT POWER FACILITIES V23320 10/26/2009 10/30/2009 OL EXAM
- INITIAL EXAM - WEEK 2 5
1 HATCH/OCTOBER 2009 EXAM AT POWER FACILITIES V23320 11/02/2009 11/06/2009 PSB1-RP
- RP PUBLIC RADIATION PROTECTION BASELINE 3
1, 2 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 01/25/2010 01/29/2010 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 7112201 01/25/2010 01/29/2010 1, 2 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 7112203 01/25/2010 01/29/2010 1, 2 IP Performance Indicator Verification 71151 01/25/2010 01/29/2010 PSB1-RP
- RP GROUNDWATER PROTECTION 1
1, 2 IP Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2515/173 02/01/2010 02/05/2010 EB3 HS
- HEAT SINK INSPECTION 1
1, 2 IP Heat Sink Performance 7111107T 02/22/2010 02/26/2010 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
 
Inspection / Activity Plan Page 2 of 2 03/04/2009 09:17:02 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hatch PSB1-RP
- RP ACCESS CONTROLS 1
1, 2 IP Access Control to Radiologically Significant Areas 7112101 03/08/2010 03/12/2010 EB1-MODS
- MODIFICATIONS-10CFR50.59 2
1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 05/17/2010 05/21/2010 1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 05/24/2010 05/28/2010 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
 
Inspection / Activity Plan Page 1 of 1 03/04/2009 09:27:48 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site 07200036 - SOUTHERN NUCLE ISFSI
- ISFSI PREOPERATIONAL INSPECTION 1
1 IP Preoperational Testing Of An ISFSI 60854 06/01/2009 07/15/2009 ISFSI
- ISFSI PAD CONSTRUCTION 2
1 IP On-Site Fabrication Of Components And Construction On An ISFSI 60853 04/01/2010 06/30/2010 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure}}

Latest revision as of 12:59, 14 January 2025

Enclosure, Hatch, Inspection/Activity Plan, Report 22 - 03/01/2009 - 06/30/2010
ML090630144
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 03/04/2009
From:
Division Reactor Projects II
To:
Shared Package
ML090630128 List:
References
Download: ML090630144 (3)


Text

Inspection / Activity Plan Page 1 of 2 03/04/2009 09:17:02 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hatch OL EXAM

- INITIAL EXAM PREP 6

1 HATCH/APRIL 2009 EXAM AT POWER FACILITIES V23311 03/30/2009 04/03/2009 OL EXAM

- INITIAL EXAM - WEEK 1 4

1 HATCH/APRIL 2009 EXAM AT POWER FACILITIES V23311 04/20/2009 04/24/2009 EB1-CDBI

- COMPONENT DESIGN BASIS INSPECTION 9

1, 2 IP Component Design Bases Inspection 7111121 04/20/2009 04/24/2009 1, 2 IP Component Design Bases Inspection 7111121 05/04/2009 05/08/2009 1, 2 IP Component Design Bases Inspection 7111121 05/18/2009 05/22/2009 1, 2 IP Component Design Bases Inspection 7111121 06/01/2009 06/05/2009 OL EXAM

- INITIAL EXAM - WEEK 2 4

1 HATCH/APRIL 2009 EXAM AT POWER FACILITIES V23311 04/27/2009 05/01/2009 PI&R

- PRE INSPECTION 1

1, 2 IP Identification and Resolution of Problems 71152B 08/31/2009 09/04/2009 PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION 6

1, 2 IP Identification and Resolution of Problems 71152B 10/05/2009 10/09/2009 1, 2 IP Identification and Resolution of Problems 71152B 10/19/2009 10/23/2009 OL EXAM

- INITIAL EXAM PREP 7

1 HATCH/OCTOBER 2009 EXAM AT POWER FACILITIES V23320 10/05/2009 10/09/2009 PSB1EP

- EMERGENCY PREPAREDNESS EXERCISE 3

1, 2 IP Exercise Evaluation 7111401 10/12/2009 10/16/2009 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 10/12/2009 10/16/2009 1, 2 IP Performance Indicator Verification 71151 10/12/2009 10/16/2009 OL EXAM

- INITIAL EXAM - WEEK 1 5

1 HATCH/OCTOBER 2009 EXAM AT POWER FACILITIES V23320 10/26/2009 10/30/2009 OL EXAM

- INITIAL EXAM - WEEK 2 5

1 HATCH/OCTOBER 2009 EXAM AT POWER FACILITIES V23320 11/02/2009 11/06/2009 PSB1-RP

- RP PUBLIC RADIATION PROTECTION BASELINE 3

1, 2 IP Radiation Monitoring Instrumentation and Protective Equipment 7112103 01/25/2010 01/29/2010 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 7112201 01/25/2010 01/29/2010 1, 2 IP Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program 7112203 01/25/2010 01/29/2010 1, 2 IP Performance Indicator Verification 71151 01/25/2010 01/29/2010 PSB1-RP

- RP GROUNDWATER PROTECTION 1

1, 2 IP Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2515/173 02/01/2010 02/05/2010 EB3 HS

- HEAT SINK INSPECTION 1

1, 2 IP Heat Sink Performance 7111107T 02/22/2010 02/26/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Inspection / Activity Plan Page 2 of 2 03/04/2009 09:17:02 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Hatch PSB1-RP

- RP ACCESS CONTROLS 1

1, 2 IP Access Control to Radiologically Significant Areas 7112101 03/08/2010 03/12/2010 EB1-MODS

- MODIFICATIONS-10CFR50.59 2

1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 05/17/2010 05/21/2010 1, 2 IP Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications 7111117T 05/24/2010 05/28/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Inspection / Activity Plan Page 1 of 1 03/04/2009 09:27:48 Report 22 03/01/2009 - 06/30/2010 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site 07200036 - SOUTHERN NUCLE ISFSI

- ISFSI PREOPERATIONAL INSPECTION 1

1 IP Preoperational Testing Of An ISFSI 60854 06/01/2009 07/15/2009 ISFSI

- ISFSI PAD CONSTRUCTION 2

1 IP On-Site Fabrication Of Components And Construction On An ISFSI 60853 04/01/2010 06/30/2010 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.