ENS 42216: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 12/06/2005 23:00 CST
| event date = 12/06/2005 23:00 CST
| last update date = 12/21/2005
| last update date = 12/21/2005
| title = Invalid Specified System Actuation - "A" Auxiliary Feedwater
| title = Invalid Specified System Actuation - "a" Auxiliary Feedwater
| event text = This report is being made in lieu of an LER per the guidance of 10CFR50.73(a)(2)(iv)(A).  The `A' train Motor Driven Auxiliary Feedwater pump received an invalid auto-start signal due to a failed safeguards driver board in the A train Solid State Protection System (SSPS).  This was a complete actuation of the 'A' train of auxiliary feedwater, and all components functioned as designed.  The pump was manually secured and no other systems were affected.  The plant entered an 8 hour LCO for an inoperable train of SSPS.  The safeguards driver board was replaced and the plant exited the LCO.  Investigation of the cause of the card failure is in progress.
| event text = This report is being made in lieu of an LER per the guidance of 10CFR50.73(a)(2)(iv)(A).  The `A' train Motor Driven Auxiliary Feedwater pump received an invalid auto-start signal due to a failed safeguards driver board in the A train Solid State Protection System (SSPS).  This was a complete actuation of the 'A' train of auxiliary feedwater, and all components functioned as designed.  The pump was manually secured and no other systems were affected.  The plant entered an 8 hour LCO for an inoperable train of SSPS.  The safeguards driver board was replaced and the plant exited the LCO.  Investigation of the cause of the card failure is in progress.
The licensee notified the NRC Resident Inspector.
The licensee notified the NRC Resident Inspector.

Latest revision as of 21:19, 1 March 2018

ENS 42216 +/-
Where
Farley Southern Nuclear icon.png
Alabama (NRC Region 2)
Reporting
10 CFR 50.73(a)(1), Submit an LER, Invalid Actuation
Time - Person (Reporting Time:+347.45 h14.477 days <br />2.068 weeks <br />0.476 months <br />)
Opened: Richard Wells
16:27 Dec 21, 2005
NRC Officer: Bill Gott
Last Updated: Dec 21, 2005
42216 - NRC Website