Line 16: Line 16:
| event date = 03/17/2017 15:17 EDT
| event date = 03/17/2017 15:17 EDT
| last update date = 03/17/2017
| last update date = 03/17/2017
| title = Automatic Actuation Of Emergency Diesel Generator
| title = Automatic Actuation of Emergency Diesel Generator
| event text = At approximately 1517 [EDT], while restoring protective relay power to the 1B Reserve Auxiliary Transformer, a valid undervoltage actuation signal was sent to the 1B Emergency Diesel Generator (EDG). The 1B EDG automatically started and tied to the safety bus (1BA03). The 1BA03 bus was loaded by the automatic load sequencer. This actuation was identified by the Control Room Operators and the 1B EDG was locally monitored while in service.
| event text = At approximately 1517 [EDT], while restoring protective relay power to the 1B Reserve Auxiliary Transformer, a valid undervoltage actuation signal was sent to the 1B Emergency Diesel Generator (EDG). The 1B EDG automatically started and tied to the safety bus (1BA03). The 1BA03 bus was loaded by the automatic load sequencer. This actuation was identified by the Control Room Operators and the 1B EDG was locally monitored while in service.
This actuation is reportable due to the automatic actuation of a system listed in 10 CFR 50.72(b)(3)(iv)(B).
This actuation is reportable due to the automatic actuation of a system listed in 10 CFR 50.72(b)(3)(iv)(B).

Latest revision as of 20:43, 1 March 2018

ENS 52619 +/-
Where
Vogtle Southern Nuclear icon.png
Georgia (NRC Region 2)
Reporting
10 CFR 50.72(b)(3)(iv)(A), System Actuation
Time - Person (Reporting Time:+-2.08 h-0.0867 days <br />-0.0124 weeks <br />-0.00285 months <br />)
Opened: Kevin Lowe
17:12 Mar 17, 2017
NRC Officer: Bethany Cecere
Last Updated: Mar 17, 2017
52619 - NRC Website