{{#Wiki_filter:Date: July 26, 2002 OFFICE OF NUCLEAR REACTOR REGULATION NOTIFICATION OF SIGNIFICANT LICENSING ACTION LICENSEE: Entergy Nuclear Indian Point 2, LLC Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247
 
==SUBJECT:==
PROPOSED ISSUANCE OF A FINAL NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION AND LICENSE AMENDMENT FOR WHICH A HEARING HAS BEEN REQUESTED (TAC NO. MB2414)
This is to inform the Commission that a final no significant hazards consideration determination and license amendment will be issued on or about August 5, 2002, (at least 5 days after Commission notification) to Entergy Nuclear Operations, Inc. for the Indian Point Nuclear Generating Unit No.2 (IP2). This action is being taken in response to the licensees amendment application dated July 13, 2001, submitted by Consolidated Edison Company of New York, Inc. (Con Edison), the former licensee, as supplemented by letters dated November 30, 2001, March 13, April 3, May 30, and June 13, 2002. The amendment will modify License No. DPR-26 for IP2, by making a one-time change to Technical Specification Surveillance Requirement 4.4.A.3 to revise the frequency for the containment integrated leak rate test (ILRT, Type A test) from at least once per 10 years to once per 15 years. The change will apply only to the interval following the last Type A test that was satisfactorily performed in June 1991 at IP2.
On September 6, 2001, Con Edison transferred its ownership interests in IP2 to Entergy Nuclear Indian Point 2, LLC and its operating authority under the IP2 license to Entergy Nuclear Operations, Inc. (ENO). By letter dated September 20, 2001, ENO requested that the U.S.
Nuclear Regulatory Commission (NRC) continue to review and act on all requests before the Commission which had been submitted before the transfer. The subject amendment request was noticed in the Federal Register on August 22, 2001 (66 FR 44165).
Contacts: Patrick Milano, NRR, 415-1457 Daniel Collins, NRR, 415-1427 Samuel Collins, Director, NRR, 415-1270 On March 18, 2002, Riverkeeper, Inc., filed a Petition for Leave to Intervene and Request for
 
Hearing, which it subsequently amended on April 30, 2002. Riverkeepers petition claimed that the then-recent disclosure in the press of discovery of rusted areas in the reactor containment provides justification both for the late filing of its petition and for a hearing. The Atomic Safety and Licensing Board issued an Order dated July 17, 2002, setting a date for the prehearing conference and schedule for amending petition and filing contentions. Pursuant to the Order, the Petitioners have until 5:00 p.m., August 12, 2002, to file an amended petition. Responses from the other parties are then due by 5:00 p.m., August 22, 2002. A prehearing conference is scheduled for August 27, 2002, in White Plains, New York.
The State of New York will be notified.
 
Date: July 26, 2002 On March 18, 2002, Riverkeeper, Inc., filed a Petition for Leave to Intervene and Request for Hearing, which it subsequently amended on April 30, 2002. Riverkeepers petition claimed that the then-recent disclosure in the press of discovery of rusted areas in the reactor containment provides justification both for the late filing of its petition and for a hearing. The Atomic Safety and Licensing Board issued an Order dated July 17, 2002, setting a date for the prehearing conference and schedule for amending petition and filing contentions. Pursuant to the Order, the Petitioners have until 5:00 p.m., August 12, 2002, to file an amended petition. Responses from the other parties are then due by 5:00 p.m., August 22, 2002. A prehearing conference is scheduled for August 27, 2002, in White Plains, New York.
The State of New York will be notified.
Date Amendment Issued: August 5, 2002 Date Received by Licensee: August 5, 2002 1
Do not declare as an Official Agency Record, or notify the Document Management Branch and the PDR until after the amendment has been received by the licensee.
Distribution:
Chairman Meserve                    OPA                DEDR Commissioner Dicus                  OIG                OP CTR Commissioner Diaz                  OCIO              RII Commissioner McGaffigan            AEOD              CFO GPA                                IRM                PUBLIC1 OGC                                NMSS              RIII SECY                                ACRS EDO                                RES OCA                                RI RIV                                NRR DEDS                                OE OI                                  SP
**see previous concurrences Accession NO.: ML021860039                                                                          *concurrence via e-mail OFFICE            PDI-1:PM**        PDI-1:PM**          PDI-1:LA*          PDI-1:SC**      PDI:D**              OGC**
NAME              DCollins          PMilano            TClark for SLittle RLaufer          SRichards            SBrock DATE              07/18/02          07/18/02            07/18/02          07/18/02        07/18/02              07/23/02 OFFICE            D:DLPM**          ADPT:NRR*          D:NRR*            EDO NAME              JZwolinski        BSheron            SCollins          WTravers DATE              07/19/02          07/22/02            07/23/02 OFFICIAL RECORD COPY}}

Latest revision as of 11:10, 26 March 2020

Proposed Issuance of Final No Significant Hazards Consideration Determination & License Amendment for Hearing Requested
ML022330435
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 07/26/2002
From:
Office of Nuclear Reactor Regulation
To:
Entergy Nuclear Indian Point 2
Collins D S, NRR/DLPM, 415-1427
References
TAC MB2414
Download: ML022330435 (5)


Text

Date: July 26, 2002 OFFICE OF NUCLEAR REACTOR REGULATION NOTIFICATION OF SIGNIFICANT LICENSING ACTION LICENSEE: Entergy Nuclear Indian Point 2, LLC Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247

SUBJECT:

PROPOSED ISSUANCE OF A FINAL NO SIGNIFICANT HAZARDS CONSIDERATION DETERMINATION AND LICENSE AMENDMENT FOR WHICH A HEARING HAS BEEN REQUESTED (TAC NO. MB2414)

This is to inform the Commission that a final no significant hazards consideration determination and license amendment will be issued on or about August 5, 2002, (at least 5 days after Commission notification) to Entergy Nuclear Operations, Inc. for the Indian Point Nuclear Generating Unit No.2 (IP2). This action is being taken in response to the licensees amendment application dated July 13, 2001, submitted by Consolidated Edison Company of New York, Inc. (Con Edison), the former licensee, as supplemented by letters dated November 30, 2001, March 13, April 3, May 30, and June 13, 2002. The amendment will modify License No. DPR-26 for IP2, by making a one-time change to Technical Specification Surveillance Requirement 4.4.A.3 to revise the frequency for the containment integrated leak rate test (ILRT, Type A test) from at least once per 10 years to once per 15 years. The change will apply only to the interval following the last Type A test that was satisfactorily performed in June 1991 at IP2.

On September 6, 2001, Con Edison transferred its ownership interests in IP2 to Entergy Nuclear Indian Point 2, LLC and its operating authority under the IP2 license to Entergy Nuclear Operations, Inc. (ENO). By letter dated September 20, 2001, ENO requested that the U.S.

Nuclear Regulatory Commission (NRC) continue to review and act on all requests before the Commission which had been submitted before the transfer. The subject amendment request was noticed in the Federal Register on August 22, 2001 (66 FR 44165).

Contacts: Patrick Milano, NRR, 415-1457 Daniel Collins, NRR, 415-1427 Samuel Collins, Director, NRR, 415-1270 On March 18, 2002, Riverkeeper, Inc., filed a Petition for Leave to Intervene and Request for

Hearing, which it subsequently amended on April 30, 2002. Riverkeepers petition claimed that the then-recent disclosure in the press of discovery of rusted areas in the reactor containment provides justification both for the late filing of its petition and for a hearing. The Atomic Safety and Licensing Board issued an Order dated July 17, 2002, setting a date for the prehearing conference and schedule for amending petition and filing contentions. Pursuant to the Order, the Petitioners have until 5:00 p.m., August 12, 2002, to file an amended petition. Responses from the other parties are then due by 5:00 p.m., August 22, 2002. A prehearing conference is scheduled for August 27, 2002, in White Plains, New York.

The State of New York will be notified.

Date: July 26, 2002 On March 18, 2002, Riverkeeper, Inc., filed a Petition for Leave to Intervene and Request for Hearing, which it subsequently amended on April 30, 2002. Riverkeepers petition claimed that the then-recent disclosure in the press of discovery of rusted areas in the reactor containment provides justification both for the late filing of its petition and for a hearing. The Atomic Safety and Licensing Board issued an Order dated July 17, 2002, setting a date for the prehearing conference and schedule for amending petition and filing contentions. Pursuant to the Order, the Petitioners have until 5:00 p.m., August 12, 2002, to file an amended petition. Responses from the other parties are then due by 5:00 p.m., August 22, 2002. A prehearing conference is scheduled for August 27, 2002, in White Plains, New York.

The State of New York will be notified.

Date Amendment Issued: August 5, 2002 Date Received by Licensee: August 5, 2002 1

Do not declare as an Official Agency Record, or notify the Document Management Branch and the PDR until after the amendment has been received by the licensee.

Distribution:

Chairman Meserve OPA DEDR Commissioner Dicus OIG OP CTR Commissioner Diaz OCIO RII Commissioner McGaffigan AEOD CFO GPA IRM PUBLIC1 OGC NMSS RIII SECY ACRS EDO RES OCA RI RIV NRR DEDS OE OI SP

    • see previous concurrences Accession NO.: ML021860039 *concurrence via e-mail OFFICE PDI-1:PM** PDI-1:PM** PDI-1:LA* PDI-1:SC** PDI:D** OGC**

NAME DCollins PMilano TClark for SLittle RLaufer SRichards SBrock DATE 07/18/02 07/18/02 07/18/02 07/18/02 07/18/02 07/23/02 OFFICE D:DLPM** ADPT:NRR* D:NRR* EDO NAME JZwolinski BSheron SCollins WTravers DATE 07/19/02 07/22/02 07/23/02 OFFICIAL RECORD COPY