| issue date = 09/28/2006
| issue date = 09/28/2006
| title = 2006/09/28-Summary of a Telephone Conference Call on August 7, 2006, Between the U.S. Nuclear Regulatory Commission & Entergy Nuclear Operations, Inc., Concerning Information Pertaining to Vermont Yankee Nuclear Power Station License Renewa
| title = Summary of a Telephone Conference Call on August 7, 2006, Between the U.S. Nuclear Regulatory Commission & Entergy Nuclear Operations, Inc., Concerning Information Pertaining to Vermont Yankee Nuclear Power Station License Renewal Applicati
| author name = Rowley J
| author name = Rowley J
| author affiliation = NRC/NRR/ADRO/DLR/RLRB
| author affiliation = NRC/NRR/ADRO/DLR/RLRB
Line 13: Line 13:
| document type = Letter, Meeting Summary, Note to File incl Telcon Record, Verbal Comm
| document type = Letter, Meeting Summary, Note to File incl Telcon Record, Verbal Comm
| page count = 7
| page count = 7
| project =
| stage = Other
}}
}}


=Text=
=Text=
{{#Wiki_filter:September 28, 2006 LICENSEE:       Entergy Nuclear Operations, Inc.
{{#Wiki_filter:September 28, 2006 LICENSEE:
FACILITY:       Vermont Yankee Nuclear Power Station
Entergy Nuclear Operations, Inc.
FACILITY:
Vermont Yankee Nuclear Power Station


==SUBJECT:==
==SUBJECT:==
==SUMMARY==
==SUMMARY==
OF A TELEPHONE CONFERENCE CALL HELD ON AUGUST 7, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operation, Inc., held a telephone conference call on August 7, 2006, to discuss and clarify the applicants response to questions asked during the staffs audits associated with the Vermont Yankee Nuclear Station license renewal application. The conference call was useful in clarifying the staffs questions. provides a listing of the conference call participants. Enclosure 2 contains a listing of the issues discussed with the applicant, including a brief description on the status of the items.
OF A TELEPHONE CONFERENCE CALL HELD ON AUGUST 7, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operation, Inc., held a telephone conference call on August 7, 2006, to discuss and clarify the applicants response to questions asked during the staffs audits associated with the Vermont Yankee Nuclear Station license renewal application. The conference call was useful in clarifying the staffs questions. provides a listing of the conference call participants. Enclosure 2 contains a listing of the issues discussed with the applicant, including a brief description on the status of the items.
The applicant had an opportunity to comment on this summary.
The applicant had an opportunity to comment on this summary.
                                      /RA/
/RA/
Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271
Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271


==Enclosures:==
==Enclosures:==
As stated cc w/encls: See next page
As stated cc w/encls: See next page


ML062710359 OFFICE     PM:RLRB               LA:RLRB                 BC:RLRB NAME       Jrowley /RA/           Iking /RA/             Jzimmerman
ML062710359 OFFICE PM:RLRB LA:RLRB BC:RLRB NAME Jrowley /RA/
                                                            /RA/
Iking /RA/
DATE         09/27/06             09/26/06               09/28/06
Jzimmerman
/RA/
DATE 09/27/06 09/26/06 09/28/06


Vermont Yankee Nuclear Power Station cc:
Vermont Yankee Nuclear Power Station cc:
Regional Administrator, Region I       Ms. Carla A. White, RRPT, CHP U. S. Nuclear Regulatory Commission     Radiological Health 475 Allendale Road                     Vermont Department of Health King of Prussia, PA 19406-1415         P.O. Box 70, Drawer #43 108 Cherry Street Mr. David R. Lewis                     Burlington, VT 05402-0070 Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, N.W.                     Mr. James M. DeVincentis Washington, DC 20037-1128               Manager, Licensing Vermont Yankee Nuclear Power Station Mr. David OBrien, Commissioner        P.O. Box 0500 Vermont Department of Public Service    185 Old Ferry Road 112 State Street                        Brattleboro, VT 05302-0500 Montpelier, VT 05620-2601 Resident Inspector Mr. James Volz, Chairman                Vermont Yankee Nuclear Power Station Public Service Board                    U. S. Nuclear Regulatory Commission State of Vermont                        P.O. Box 176 112 State Street                        Vernon, VT 05354 Montpelier, VT 05620-2701 Director, Massachusetts Emergency Chairman, Board of Selectmen            Management Agency Town of Vernon                          ATTN: James Muckerheide P.O. Box 116                            400 Worcester Rd.
Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Mr. David R. Lewis Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, N.W.
Vernon, VT 05354-0116                  Framingham, MA 01702-5399 Operating Experience Coordinator        Jonathan M. Block, Esq.
Washington, DC 20037-1128 Mr. David OBrien, Commissioner Vermont Department of Public Service 112 State Street Montpelier, VT 05620-2601 Mr. James Volz, Chairman Public Service Board State of Vermont 112 State Street Montpelier, VT 05620-2701 Chairman, Board of Selectmen Town of Vernon P.O. Box 116 Vernon, VT 05354-0116 Operating Experience Coordinator Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 G. Dana Bisbee, Esq.
Vermont Yankee Nuclear Power Station    Main Street 320 Governor Hunt Road                  P.O. Box 566 Vernon, VT 05354                        Putney, VT 05346-0566 G. Dana Bisbee, Esq.                    Mr. John F. McCann Deputy Attorney General                Director, Licensing 33 Capitol Street                      Entergy Nuclear Operations, Inc.
Deputy Attorney General 33 Capitol Street Concord, NH 03301-6937 Chief, Safety Unit Office of the Attorney General One Ashburton Place, 19th Floor Boston, MA 02108 Ms. Deborah B. Katz Box 83 Shelburne Falls, MA 01370 Ms. Carla A. White, RRPT, CHP Radiological Health Vermont Department of Health P.O. Box 70, Drawer #43 108 Cherry Street Burlington, VT 05402-0070 Mr. James M. DeVincentis Manager, Licensing Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Resident Inspector Vermont Yankee Nuclear Power Station U. S. Nuclear Regulatory Commission P.O. Box 176 Vernon, VT 05354 Director, Massachusetts Emergency Management Agency ATTN: James Muckerheide 400 Worcester Rd.
Concord, NH 03301-6937                  440 Hamilton Avenue White Plains, NY 10601 Chief, Safety Unit Office of the Attorney General          Mr. Gary J. Taylor One Ashburton Place, 19th Floor        Chief Executive Officer Boston, MA 02108                        Entergy Operations 1340 Echelon Parkway Ms. Deborah B. Katz                    Jackson, MS 39213 Box 83 Shelburne Falls, MA 01370
Framingham, MA 01702-5399 Jonathan M. Block, Esq.
Main Street P.O. Box 566 Putney, VT 05346-0566 Mr. John F. McCann Director, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213


Vermont Yankee Nuclear Power Station cc:
Vermont Yankee Nuclear Power Station cc:
Mr. John T. Herron                   Ms. Stacey M. Lousteau Sr. VP and Chief Operating Officer   Treasury Department Entergy Nuclear Operations, Inc. Entergy Services, Inc.
Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue                  639 Loyola Avenue White Plains, NY 10601               New Orleans, LA 70113 Mr. Oscar Limpias                   Mr. Raymond Shadis Vice President, Engineering         New England Coalition Entergy Nuclear Operations, Inc. Post Office Box 98 440 Hamilton Avenue                 Edgecomb, ME 04556 White Plains, NY 10601 Mr. James P. Matteau Mr. Christopher Schwartz             Executive Director Vice President, Operations Support   Windham Regional Commission Entergy Nuclear Operations, Inc. 139 Main Street, Suite 505 440 Hamilton Avenue                 Brattleboro, VT 05301 White Plains, NY 10601 Mr. William K. Sherman Mr. Michael J. Colomb               Vermont Department of Public Service Director of Oversight               112 State Street Entergy Nuclear Operations, Inc. Drawer 20 440 Hamilton Avenue                 Montpelier, VT 05620-2601 White Plains, NY 10601 Mr. Michael D. Lyster Mr. Travis C. McCullough             5931 Barclay Lane Assistant General Counsel           Naples, FL 34110-7306 Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue                 Ms. Charlene D. Faison White Plains, NY 10601               Manager, Licensing 440 Hamilton Avenue Mr. Ted Sullivan                     White Plains, NY 10601 Site Vice President Entergy Nuclear Operations, Inc. Mr. James Ross Vermont Yankee Nuclear Power Station Nuclear Energy Institute P.O. Box 0500                       1776 I Street, NW, Suite 400 185 Old Ferry Road                  Washington, DC 20006-3708 Brattleboro, VT 05302-0500 Diane Curran, Esq.*
440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher Schwartz Vice President, Operations Support Entergy Nuclear Operations, Inc.
Mr. James H. Sniezek                Harmon, Curran, Spielberg 5486 Nithsdale Drive                  & Eisenberg, L.L.P.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.
Salisbury, MD 21801                  1726 M Street, NW., Suite 600 Washington, DC 20036
440 Hamilton Avenue White Plains, NY 10601 Mr. Travis C. McCullough Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Ted Sullivan Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. James H. Sniezek 5486 Nithsdale Drive Salisbury, MD 21801 Ms. Stacey M. Lousteau Treasury Department Entergy Services, Inc.
639 Loyola Avenue New Orleans, LA 70113 Mr. Raymond Shadis New England Coalition Post Office Box 98 Edgecomb, ME 04556 Mr. James P. Matteau Executive Director Windham Regional Commission 139 Main Street, Suite 505 Brattleboro, VT 05301 Mr. William K. Sherman Vermont Department of Public Service 112 State Street Drawer 20 Montpelier, VT 05620-2601 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Ms. Charlene D. Faison Manager, Licensing 440 Hamilton Avenue White Plains, NY 10601 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Diane Curran, Esq.*
Harmon, Curran, Spielberg
& Eisenberg, L.L.P.
1726 M Street, NW., Suite 600 Washington, DC 20036


Letter to Licensee Entergy Nuclear Operations, Inc., from Jonathan Rowley dated September 28, 2006
Letter to Licensee Entergy Nuclear Operations, Inc., from Jonathan Rowley dated September 28, 2006


==SUBJECT:==
==SUBJECT:==
==SUMMARY==
==SUMMARY==
OF A TELEPHONE CONFERENCE CALL HELD ON AUGUST 7, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION HARD COPY DLR R/F E-MAIL:
OF A TELEPHONE CONFERENCE CALL HELD ON AUGUST 7, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION HARD COPY DLR R/F E-MAIL:
JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)
JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDeEqvb RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes
SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDeEqvb RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes JRowley RLaufer JShea CAnderson, RI RPowell, RI DScrenci, RI MModes, RI DPelton, Sr. Resident MYoung RidsOpaMail LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION August 7, 2006 PARTICIPANTS AFFILIATIONS Jonathan Rowley U.S. Nuclear Regulatory Commission (NRC)
--------------
Michael Morgan NRC Kaihwa Hsu NRC James DeVincentis Entergy Nuclear Operation, Inc. (ENO)
JRowley RLaufer JShea CAnderson, RI RPowell, RI DScrenci, RI MModes, RI DPelton, Sr. Resident MYoung RidsOpaMail
David Lach ENO Michael Hamer ENO VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION August 7, 2006 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operation, Inc., held a telephone conference call on August 7, 2006, to discuss and clarify the applicants response to questions asked during the staffs aging management program (AMP), aging management review (AMR), and time-limited aging analysis (TLAA) audits associated with the Vermont Yankee Nuclear Station (VYNPS) license renewal application (LRA). The following issues were discussed during the telephone conference call:
 
LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION August 7, 2006 PARTICIPANTS                 AFFILIATIONS Jonathan Rowley               U.S. Nuclear Regulatory Commission (NRC)
Michael Morgan               NRC Kaihwa Hsu                   NRC James DeVincentis             Entergy Nuclear Operation, Inc. (ENO)
David Lach                   ENO Michael Hamer                 ENO Enclosure 1
 
VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION August 7, 2006 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operation, Inc., held a telephone conference call on August 7, 2006, to discuss and clarify the applicants response to questions asked during the staffs aging management program (AMP), aging management review (AMR), and time-limited aging analysis (TLAA) audits associated with the Vermont Yankee Nuclear Station (VYNPS) license renewal application (LRA). The following issues were discussed during the telephone conference call:
: 1. Upon review of revision 3 of the VYNPS AMP/AMR/TLAA Audit Question and Answer database (ADAMS Accession number ML062200562), staff required clarification of the applicants response to audit item 318. Item 318 states:
: 1. Upon review of revision 3 of the VYNPS AMP/AMR/TLAA Audit Question and Answer database (ADAMS Accession number ML062200562), staff required clarification of the applicants response to audit item 318. Item 318 states:
The [cumulative usage factor] CUF values in LRA Table 4.3-1 that are based on NUREG CR 6260 are not applicable to VY and need to be removed and the issue addressed. Please clarify the commitment to perform a fatigue re-analysis to be used to address environmental impact. The re-analysis needs to be made to a single code date.
The [cumulative usage factor] CUF values in LRA Table 4.3-1 that are based on NUREG CR 6260 are not applicable to VY and need to be removed and the issue addressed. Please clarify the commitment to perform a fatigue re-analysis to be used to address environmental impact. The re-analysis needs to be made to a single code date.
The staff requested that the applicant make the appropriate changes to Table 4.3-3 as where done to Table 4.3-1. In addition, the staff disagreed with the wording of the commitment. In part 2 of the commitment, the applicant states that ....locations with a valid CUF may be substituted for... The staffs position is that the locations addressed are a minimum, and that the use of the word substituted is inaccurate. The staff requested that applicant consider modifying its commiment.
The staff requested that the applicant make the appropriate changes to Table 4.3-3 as where done to Table 4.3-1. In addition, the staff disagreed with the wording of the commitment. In part 2 of the commitment, the applicant states that....locations with a valid CUF may be substituted for... The staffs position is that the locations addressed are a minimum, and that the use of the word substituted is inaccurate. The staff requested that applicant consider modifying its commiment.
Discussion: The applicant indicated that the question is clear. The applicant indicated that they would consider the request and modify the response accordingly. The applicant indicated that any changes would appear in the net revision of the question and answer database.
Discussion: The applicant indicated that the question is clear. The applicant indicated that they would consider the request and modify the response accordingly. The applicant indicated that any changes would appear in the net revision of the question and answer database.
: 2. The staff had a question concerning the applicants license renewal commitments #27 and
: 2. The staff had a question concerning the applicants license renewal commitments #27 and
    #29. The staffs position is that the applicant must submit analysis for NRC review and approval two years prior to the period of extended operation. The commitments indicated that only submittal for review was required.
#29. The staffs position is that the applicant must submit analysis for NRC review and approval two years prior to the period of extended operation. The commitments indicated that only submittal for review was required.
Discussion: The applicant indicated that the question is clear and the commitments would be reworded. The revised commitments would appear in a forthcoming letter.
Discussion: The applicant indicated that the question is clear and the commitments would be reworded. The revised commitments would appear in a forthcoming letter.}}
Enclosure 2}}

Latest revision as of 06:25, 15 January 2025

Summary of a Telephone Conference Call on August 7, 2006, Between the U.S. Nuclear Regulatory Commission & Entergy Nuclear Operations, Inc., Concerning Information Pertaining to Vermont Yankee Nuclear Power Station License Renewal Applicati
ML062710359
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 09/28/2006
From: Rowley J
NRC/NRR/ADRO/DLR/RLRB
To:
Vermont Yankee
Rowley J, NRR/DLR/RLRB, 415-4053
References
%dam200611
Download: ML062710359 (7)


Text

September 28, 2006 LICENSEE:

Entergy Nuclear Operations, Inc.

FACILITY:

Vermont Yankee Nuclear Power Station

SUBJECT:

SUMMARY

OF A TELEPHONE CONFERENCE CALL HELD ON AUGUST 7, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operation, Inc., held a telephone conference call on August 7, 2006, to discuss and clarify the applicants response to questions asked during the staffs audits associated with the Vermont Yankee Nuclear Station license renewal application. The conference call was useful in clarifying the staffs questions. provides a listing of the conference call participants. Enclosure 2 contains a listing of the issues discussed with the applicant, including a brief description on the status of the items.

The applicant had an opportunity to comment on this summary.

/RA/

Jonathan Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271

Enclosures:

As stated cc w/encls: See next page

ML062710359 OFFICE PM:RLRB LA:RLRB BC:RLRB NAME Jrowley /RA/

Iking /RA/

Jzimmerman

/RA/

DATE 09/27/06 09/26/06 09/28/06

Vermont Yankee Nuclear Power Station cc:

Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Mr. David R. Lewis Pillsbury, Winthrop, Shaw, Pittman, LLP 2300 N Street, N.W.

Washington, DC 20037-1128 Mr. David OBrien, Commissioner Vermont Department of Public Service 112 State Street Montpelier, VT 05620-2601 Mr. James Volz, Chairman Public Service Board State of Vermont 112 State Street Montpelier, VT 05620-2701 Chairman, Board of Selectmen Town of Vernon P.O. Box 116 Vernon, VT 05354-0116 Operating Experience Coordinator Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 G. Dana Bisbee, Esq.

Deputy Attorney General 33 Capitol Street Concord, NH 03301-6937 Chief, Safety Unit Office of the Attorney General One Ashburton Place, 19th Floor Boston, MA 02108 Ms. Deborah B. Katz Box 83 Shelburne Falls, MA 01370 Ms. Carla A. White, RRPT, CHP Radiological Health Vermont Department of Health P.O. Box 70, Drawer #43 108 Cherry Street Burlington, VT 05402-0070 Mr. James M. DeVincentis Manager, Licensing Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Resident Inspector Vermont Yankee Nuclear Power Station U. S. Nuclear Regulatory Commission P.O. Box 176 Vernon, VT 05354 Director, Massachusetts Emergency Management Agency ATTN: James Muckerheide 400 Worcester Rd.

Framingham, MA 01702-5399 Jonathan M. Block, Esq.

Main Street P.O. Box 566 Putney, VT 05346-0566 Mr. John F. McCann Director, Licensing Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213

Vermont Yankee Nuclear Power Station cc:

Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher Schwartz Vice President, Operations Support Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Travis C. McCullough Assistant General Counsel Entergy Nuclear Operations, Inc.

440 Hamilton Avenue White Plains, NY 10601 Mr. Ted Sullivan Site Vice President Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. James H. Sniezek 5486 Nithsdale Drive Salisbury, MD 21801 Ms. Stacey M. Lousteau Treasury Department Entergy Services, Inc.

639 Loyola Avenue New Orleans, LA 70113 Mr. Raymond Shadis New England Coalition Post Office Box 98 Edgecomb, ME 04556 Mr. James P. Matteau Executive Director Windham Regional Commission 139 Main Street, Suite 505 Brattleboro, VT 05301 Mr. William K. Sherman Vermont Department of Public Service 112 State Street Drawer 20 Montpelier, VT 05620-2601 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Ms. Charlene D. Faison Manager, Licensing 440 Hamilton Avenue White Plains, NY 10601 Mr. James Ross Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Diane Curran, Esq.*

Harmon, Curran, Spielberg

& Eisenberg, L.L.P.

1726 M Street, NW., Suite 600 Washington, DC 20036

Letter to Licensee Entergy Nuclear Operations, Inc., from Jonathan Rowley dated September 28, 2006

SUBJECT:

SUMMARY

OF A TELEPHONE CONFERENCE CALL HELD ON AUGUST 7, 2006, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND ENTERGY NUCLEAR OPERATIONS, INC., CONCERNING INFORMATION PERTAINING TO THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION HARD COPY DLR R/F E-MAIL:

JFair RWeisman AMurphy RPettis GGalletti DShum GBagchi SSmith (srs3)

SDuraiswamy YL (Renee) Li RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDe RidsNrrDci RidsNrreEemb RidsNrrDeEeeb RidsNrrDeEqva RidsNrrDeEqvb RidsNrrDss RidsNrrDnrl RidsOgcMailCenter RidsNrrAdes JRowley RLaufer JShea CAnderson, RI RPowell, RI DScrenci, RI MModes, RI DPelton, Sr. Resident MYoung RidsOpaMail LIST OF PARTICIPANTS FOR TELEPHONE CONFERENCE CALL TO DISCUSS THE VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION August 7, 2006 PARTICIPANTS AFFILIATIONS Jonathan Rowley U.S. Nuclear Regulatory Commission (NRC)

Michael Morgan NRC Kaihwa Hsu NRC James DeVincentis Entergy Nuclear Operation, Inc. (ENO)

David Lach ENO Michael Hamer ENO VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION August 7, 2006 The U.S. Nuclear Regulatory Commission staff (the staff) and representatives of Entergy Nuclear Operation, Inc., held a telephone conference call on August 7, 2006, to discuss and clarify the applicants response to questions asked during the staffs aging management program (AMP), aging management review (AMR), and time-limited aging analysis (TLAA) audits associated with the Vermont Yankee Nuclear Station (VYNPS) license renewal application (LRA). The following issues were discussed during the telephone conference call:

1. Upon review of revision 3 of the VYNPS AMP/AMR/TLAA Audit Question and Answer database (ADAMS Accession number ML062200562), staff required clarification of the applicants response to audit item 318. Item 318 states:

The [cumulative usage factor] CUF values in LRA Table 4.3-1 that are based on NUREG CR 6260 are not applicable to VY and need to be removed and the issue addressed. Please clarify the commitment to perform a fatigue re-analysis to be used to address environmental impact. The re-analysis needs to be made to a single code date.

The staff requested that the applicant make the appropriate changes to Table 4.3-3 as where done to Table 4.3-1. In addition, the staff disagreed with the wording of the commitment. In part 2 of the commitment, the applicant states that....locations with a valid CUF may be substituted for... The staffs position is that the locations addressed are a minimum, and that the use of the word substituted is inaccurate. The staff requested that applicant consider modifying its commiment.

Discussion: The applicant indicated that the question is clear. The applicant indicated that they would consider the request and modify the response accordingly. The applicant indicated that any changes would appear in the net revision of the question and answer database.

2. The staff had a question concerning the applicants license renewal commitments #27 and
  1. 29. The staffs position is that the applicant must submit analysis for NRC review and approval two years prior to the period of extended operation. The commitments indicated that only submittal for review was required.

Discussion: The applicant indicated that the question is clear and the commitments would be reworded. The revised commitments would appear in a forthcoming letter.