{{#Wiki_filter:N Nebraska Public Power District "Always there when you need us" NLS2008098 December 15, 2008 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
{{#Wiki_filter:}}
 
==Subject:==
Decommissioning Cost Analysis Cooper Nuclear Station, Docket'No. 50-298, DPR-46
 
==Reference:==
Letter from Stewart B. Minahan (Nebraska Public Power District) to the U.S.
Nuclear Regulatory Commission dated September 24, 2008, "License Renewal Application" (NLS2008071)
 
==Dear Sir or Madam:==
 
The purpose of this correspondence is to transmit the Nebraska Public Power District's (NPPD)
Decommissioning Cost Analysis pursuant to the requirements of 10 CFR 50.75(f)(3), "Reporting and Recordkeeping for Decommissioning Planning."
NPPD submitted a License Renewal Application for Cooper Nuclear Station (CNS) (Reference).
Although NPPD is seeking license renewal, the Preliminary Decommissioning Cost Estimate is submitted based on the current operating license expiration date of January 18, 2014. When the license for CNS is renewed, this 2008 Decommissioning Cost Estimate for the 2014 plant shutdown scenario would no longer be applicable.
Should you have any questions concerning this matter, please contact me at (402) 825-2904.
Sincerely, David W. Van Der Kamp Licensing Manager
/Jo Enclosure COOPER NUCLEAR STATION                            kg P.O. Box 98 / Brownville, NE 68327-0098 Telephone: (402) 825-3871 / Fax: (402) 825-5211 www.nppd corn
 
NLS2008098 Page 2 of 2 cc:  Regional Administrator w/enclosure USNRC - Region IV Cooper Project Manager w/enclosure USNRC - NRR Project Directorate IV-1 Senior Resident Inspector w/enclosure USNRC - CNS NPG Distribution w/o enclosure CNS Records w/enclosure
 
ATTACHMENT 3                    LIST OF REGULATORY COMMITMENTS@
ATTACHMENT 3 LIST OF REGULATORY COMMITMENTS© Correspondence Number:                NLS2008098 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.
COMMITMENT      COMMITTED DATE COMMITMENT                          NUMBER          OR OUTAGE None
                                                      +              4
                                                      +              4
                                                      +              4 I  PROCEDURE      0.42                                  REVISION 22          PAGE 18 OF 25 1
 
Document N01-1590-002, Rev. 1 DECOMMISSIONING COST ANALYSIS for the COOPER NUCLEAR STATION preparedfor the NEBRASKA PUBLIC POWER DISTRICT prepared by TLG Services, Inc.
Bridgewater, Connecticut December 2008
 
CooperNuclear Station                            DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                  Page ii of xvii APPROVALS Project Manager William A. Cloutier, JP-/    Date Project Engineer William J. Dietz            Date Technical Manager                                            1A      S Francis W. Sey uoe          Dte" DAte' Quality Assurance Manager J  eph JJer d&-
                              'ýH TLG Services, Inc.
 
CooperNuclear Station                                                                        Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                            Pageiii of xvii TABLE OF CONTENTS SECTION - PAGE EXECUTIVE
 
==SUMMARY==
..................................................................................                        vii-xvii
: 1. INTRODUCTION .....................................................................................................              1-1 1.1 Objectives of Study ...........................................................................................              1-1 1.2 Site Description .................................................................................................          1-1 1.3 Regulatory Guidance ...................................................................................                      1-2 1.3.1 Nuclear W aste Policy Act ......................................................................                    1-4 1.3.2 Low-Level Radioactive W aste Act ........................................................                            1-6 1.3.3 Radiological Criteria for License Termination ....................................                                  1-7
: 2. DECOMMISSIONING ALTERNATIVES ..............................................................                                      2-1 2.1 D E C ON ..............................................................................................................      2-2 2.1.1 Period 1 - Preparations .........................................................................                    2-2 2.1.2 Period 2 - Decommissioning Operations ..............................................                                  2-4 2.1.3 Period 3 - Site Restoration ....................................................................                    2-7 2.1.4 ISFSI Operations and Decommissioning ............................................                                    2-8 2.2 SAFSTOR and Delayed Decommissioning .....................................................                                    2-9 2.2.1 Period 1 - Preparations .......................................................................                    2-10 2.2.2 Period 2 - Dormancy ............................................................................                  2-11 2.2.3 Periods 3 and 4 - Deferred Decommissioning .................                                                      2-12 2.2.4 Period 5 - Site Restoration ..................................................................                      2-13
: 3. COST ESTIMATES ...................................................................................................              3-1 3.1 Basis of Estimates ............................................................................................              3-1 3.2 Methodology ......................................................................................................          3-1 3.3 Financial Components of the Cost Model .......................................................                              3-3 3.3.1 Contingency ...........................................................................................              3-4 3.3.2 Financial Risk ........................................................................................              3-5 3.4 Site-Specific Considerations .............................................................................                  3-6 3.4.1 Spent Fuel Management .......................................................................                        3-6 3.4.2 Reactor Vessel and Internal Components ...........................................                                  3-9 3.4.3 Primary System Components .............................................................                            3-10 3.4.4 Main Turbine and Condenser .............................................................                          3-11 3.4.5 Transportation Methods .....................................................................                      3-11 3.4.6 Low-Level Radioactive W aste Conditioning and Disposal ...............                                            3-12 3.4.7 Site Conditions Following Decommissioning ....................................                                    3-13 TLG Services, Inc.
 
CooperNuclearStation                                                                            Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                                                                              Page iv of xvii TABLE OF CONTENTS (continued)
SECTION - PAGE 3.5 A ssumptions ....................................................................................................            3-14 3.5.1 Estim ating Basis ............................................................................                        3-14 3.5.2 L abor C osts ..........................................................................................              3-14 3.5.3 D esign Conditions ................................................................................                  3-15 3.5.4 G eneral .................................................................................................            3-16 3.6 Cost Estim ate Sum m ary ...............................................................................                      3-18
: 4. S C H E D UL E ...............................................................................................................      4-1 4.1 Schedule Estim ate Assum ptions .....................................................................                          4-1 4.2 Project Schedule ................................................................................................              4-2
: 5. RADIOA CTIVE WASTES ........................................................................................                        5-1
: 6. R E S ULT S .................................................................................................................      6-1
: 7. R E F E R E NC E S ..  *....................................................................................................... 7-1 TABLES Cost Summary, 2014 Cessation of Operations ...............................................                                        xvi Cost Summary, 2034 Cessation of Operations ..............................................                                        xvii 3.1  2014 DECON, Schedule of Total Annual Expenditures ...............................                                              3-19 3.2  2014 Delayed DECON, Schedule of Total Annual Expenditures ................                                                      3-21 3.3  2014 SAFSTOR, Schedule of Total Annual Expenditures ...........................                                                3-23 3.4  2034 DECON, Schedule of Total Annual Expenditures ...............................                                              3-25 3.5  2034 Delayed DECON, Schedule of Total Annual Expenditures ................                                                      3-26 3.6  2034 SAFSTOR, Schedule of Total Annual Expenditures ...........................                                                3-28 5.1  Decommissioning Waste Summary .................................................................                                  5-3 5.2  2014 DECON, Decommissioning Waste Summary ........................................                                                5-4 5.3  2014 Delayed DECON, Decommissioning Waste Summary ..........................                                                      5-5 5.4  2014 SAFSTOR, Decommissioning Waste Summary .....................................                                                5-6 5.5  2034 DECON, Decommissioning Waste Summary ........................................                                                5-7 5.6  2034 Delayed DECON, Decommissioning Waste Summary ..........................                                                      5-8 5.7  2034 SAFSTOR, Decommissioning Waste Summary .....................................                                                5-9 TLG Services, Inc.
 
CooperNuclearStation                                                                        Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                            Page v of xvii TABLE OF CONTENTS (continued)
SECTION - PAGE TABLES (continued) 6.1  Cost Summary, 2014 Cessation of Operations ...............................................                                  6-4 6.2  Cost Summary, 2034 Cessation of Operations ...............................................                                  6-5 FIGURES 4.1  2014 DECON Activity Schedule.......................................................................                          4-3 4.2  2014 Delayed DECON Activity Schedule ........................................................                                4-6 4.3  2014 SAFSTOR Activity Schedule ...................................................................                          4-9 4.4  2034 DECON Activity Schedule .....................................................................                        4-12 4.5  2034 Delayed DECON Activity Schedule ......................................................                                4-15 4.6  2034 SAFSTOR Activity Schedule .................................................................                          4-18 4.7  D E C O N Tim elines .........................................................................................            4-21 4.8  Delayed DECON and SAFSTOR Timelines ..................................................                                    4-22 APPENDICES A. Unit Cost Factor Development .......................................................................                        A-1 B. Unit Cost Factor Listing ................................................................................                    B-1 C. Detailed Cost Analyses, 2014 Cessation of Operations .................................                                      C-1 T able C -1, D E C ON ................................................................................................      C -2 Table C-2, Delayed DECON ...........................................................................                      C-13 Table C-3, SAFSTOR                                    ......................................                              C-24 D. Detailed Cost Analyses, 2034 Cessation of Operations .................................                                      D-1 T able D -1, D E C O N ................................................................................................ D -2 Table D -2, Delayed D ECON ...............................................................................                D -13 Table D -3, SAFSTO R ..........................................................................................          D -24 E. Work Difficulty Adjustment Factors ................................................................                          E-1 F. Area M aps ..........................................................................................................        F -1 TLG Services, Inc.
 
Cooper NuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                              Page vi of xvii REVISION LOG No'R~.  ~          1      t    R    d          R    f - 'Revso 0                    10-08-08                                  Original Issue Pages xvii-xviii Tables 3.1 through 3.6 1T73-0804  12-08-08      Tables 6.1 and 6.2    Corporate Overhead Costs Revised Tables C-1, C-2, C-3 Tables D-1, D-2, D-3 TLG Services, Inc.
 
CooperNuclearStation                                                    Document N01-1590-002,Rev. 1 DecommissioningCost Analysis                                                            Page vii ofxvii EXECUTIVE
 
==SUMMARY==
 
This report presents estimates of the cost to decommission the Cooper Nuclear Station (Cooper) for the selected decommissioning scenarios following a scheduled cessation of plant operations. The estimates are designed to provide Nebraska Public Power District (NPPD) with the information needed to assess its financial obligations as they pertain to the eventual decommissioning of the nuclear station. This report is also designed to meet the requirements of 10 CFR 50.75(f)(3) in that it includes an assessment of the major factors that could affect the cost to decommission.
The primary goal of the decommissioning is the removal and disposal of the contaminated systems and structures so that the plant's operating license can be terminated. The cost analysis recognizes that spent fuel will be stored at the site in the plant's storage pool and/or in an independent spent fuel storage installation (ISFSI) until such time that it can be transferred to the U.S. Department of Energy (DOE).
Consequently, the estimates also include those costs to manage and subsequently decommission these interim storage facilities.
The estimates are based on numerous fundamental assumptions, including regulatory requirements, project contingencies, low-level radioactive waste disposal practices, high-level radioactive waste management options, and site restoration requirements.
The estimates incorporate a minimum cooling period for the spent fuel that resides in the storage pool when operations cease. Any residual fuel remaining in the pool after the cooling period is transferred directly to the DOE or relocated to the ISFSI for interim storage. The estimates also include the dismantling of site structures and non-essential facilities and the limited restoration of the site.
Alternatives and Regulations The Nuclear Regulatory Commission (NRC) provided general decommissioning guidance in a rule adopted on June 27, 1988.[1] In this rule, the NRC set forth technical and financial criteria for decommissioning licensed nuclear facilities. The regulations addressed planning needs, timing, funding methods, and environmental review requirements for decommissioning. The rule also defmed three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB.
DECON is defined as "the alternative in which the equipment, structures, and portions of a facility and site containing radioactive contaminants are removed or decontaminated to a level that permits the 1  U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72 "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988 TLG Services, Inc.
 
CooperNuclear Station                                                  Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                        Page viii of xvii property to be released for unrestricted use shortly after cessation of 2
operations."[ ]
SAFSTOR is defined as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely    stored      and      subsequently          decontaminated        (deferred decontamination) to levels that permit release for unrestricted use."[3]
Decommissioning is required to be completed within 60 years, although longer time periods will be considered when necessary to protect public health and safety. The safe-storage periods in the Delayed DECON analyses are selected to coincide with the removal of spent fuel from the site.
ENTOMB is defined as "the alternative in which radioactive contaminants are encased in a structurally long-lived material, such as concrete; the entombed structure is appropriately maintained and continued surveillance is carried out until the radioactive material decays to a level permitting unrestricted release of the property."[4] As with the SAFSTOR alternative, decommissioning is currently required to be completed within 60 years, although longer time periods will also be considered when necessary to protect public health and safety.
The 60-year restriction has limited the practicality for the ENTOMB alternative at commercial reactors that generate significant amounts of long-lived radioactive material. In 1997, the Commission directed its staff to re-evaluate this alternative and identify the technical requirements and regulatory actions that would be necessary for entombment to become a viable option. The resulting evaluation provided several recommendations, however, rulemaking has been deferred pending the completion of additional research studies (e.g., on engineered barriers).
In 1996, the NRC published revisions to its general requirements for decommissioning nuclear power plants to clarify ambiguities and codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process.[5 ] The amendments allow for greater public participation and better defme the transition process from operations to decommissioning. Regulatory Guide 1.184, issued in July 2000, further described the methods and procedures that are acceptable to the NRC 2  Ibid. Page FR24022, Column 3 3  Ibid.
4  Ibid. Page FR24023, Column 2 5  U.S. Code of Federal Regulations, Title 10, Parts 2, 50, and 51, "Decommissioning of Nuclear Power Reactors," Nuclear Regulatory Commission, Federal Register Volume 61, (p 39278 et seq.), July 29, 1996 TLG Services, Inc.
 
CooperNuclearStation                                            Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                  Page ix of xvii staff for implementing the requirements of the 1996 revised rule that relate to the initial activities and the major phases of the decommissioning process. The costs and schedules presented in this analysis follow the general guidance and sequence in the amended regulations.
Decommissioning Scenarios The following alternatives were evaluated and are representative of the alternatives available to the owner:
: 1. DECON: The plant is decommissioned shortly after the permanent cessation of plant operations. Spent fuel, that is not transferred directly to the DOE, is relocated to the ISFSI for interim storage. Spent fuel storage operations continue at the site until the transfer of the fuel to the DOE is completed.
: 2. Delayed DECON: In the second scenario, the unit is prepared for an abbreviated period of storage. As in the first scenario, spent fuel storage operations continue at the site until the transfer of the fuel to the DOE is completed. Once completed, decommissioning operations are initiated.
: 3. SAFSTOR: The third scenario is similar to the second scenario in that the unit is placed in safe-storage with concurrent spent fuel storage operations. However, in this scenario, decommissioning is deferred beyond the fuel storage period to the maximum extent possible; termination of the license would conclude within the maximum required 60-year period.
Six scenarios were identified for evaluation. As shown below, the six scenarios evaluate a combination of shutdown dates (scheduled and anticipated) and decommissioning alternative (prompt or deferred).
Shutdown                                  Spent Fuel          Operating Scenario          Date              Option                Transfer          License Completed          Terminated 1          2014              DECON                    2046              2020 2          2014          Delayed DECON                2046              2053 3          2014            SAFSTOR                    2046              2074 4          2034              DECON                    2061              2040 5          2034          Delayed DECON                2061              2068 6          2034            SAFSTOR                  2061              2094
_ _    _ I __          _ I _  _    _    _    _  I _ _    _    _  I _    _
TLG Services, Inc.
 
CooperNuclearStation                                                Document N01-1590-002,Rev. 1 Decommissioning Cost Analysis                                                        Pagex of xvii Methodology The methodology used to develop the estimates described within this document follows the basic approach originally presented in the cost estimating guidelines[6] developed by the Atomic Industrial Forum (now Nuclear Energy Institute). This reference describes a unit cost factor method for estimating decommissioning activity costs. The unit cost factors used in this analysis incorporate site-specific costs and the latest available information about worker productivity in decommissioning.
The estimates are area-based estimates, i.e., the plant inventory has been correlated with site-specific area working conditions, and the plant work activities organized into discrete areas to better reflect the manner in which the decommissioning will be conducted. The areas were determined on the basis of "common" conditions or attributes. Each area was evaluated for work difficulty, including affects of radiation, external surface contamination, and access. This evaluation was used to adjust the work difficulty factors for removing equipment in a given area. A data base was constructed and identified the installed equipment in each area. This data base contains a list of components that have a unique identifier, such as valves, tanks, electrical equipment, and heat exchangers. It also contains bulk commodities such as piping, ventilation ductwork, cable tray, electrical conduit, and supports.
The inventory was organized according to its proposed disposition. There were three primary waste streams identified for the Cooper inventory: (1) clean material (expected to meet the release criteria without any decontamination), (2) contaminated material with recovery potential or requiring additional processing for disposal (expected to be sent to an off-site waste processor), and (3) contaminated material designated for direct disposal at a controlled low-level radioactive waste disposal site (i.e., material expected to exceed waste processor acceptance criteria or uneconomical to process).
An activity duration critical path was used to determine the total decommissioning program schedule. This was required for estimating the project costs, including program management, administration, field engineering, equipment rental, quality assurance, and security.
This analysis reflects lessons learned from TLG's involvement in the Shippingport Station decommissioning, completed in 1989, as well as the decommissioning of the Cintichem reactor, hot cells, and associated facilities, completed in 1997. In addition, the planning and engineering for the Pathfinder, Shoreham, Rancho Seco, Trojan, Yankee Rowe, Big Rock Point, Maine Yankee, Humboldt Bay-3, Connecticut Yankee, 6    T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986 TLG Services, Inc.
 
CooperNuclearStation                                              Document N01-1590-002,Rev. 1 Decommissioning Cost Analysis                                                      Pagexi of xvii and San Onofre-1 nuclear units have provided additional insight into the process, the regulatory aspects, and the technical challenges of decommissioning commercial nuclear units.
Contingency Consistent with standard cost estimating practice, contingencies are applied to the decontamination and dismantling costs developed as "specific provision for unforeseeable elements of cost within the defined project scope, particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur."[7 ] The cost elements in the estimates are based on ideal conditions; therefore, the types of unforeseeable events that are almost certain to occur in decommissioning, based on industry experience, are addressed through a percentage contingency applied on a line-item basis. This contingency factor is a nearly universal element in all large-scale construction and demolition projects. It should be noted that contingency, as used in this analysis, does not account for price escalation and inflation in the cost of decommissioning over the remaining operating life of the station.
Contingency funds are expected to be fully expended throughout the program. As such, inclusion of contingency is necessary to provide assurance that sufficient funding will be available to accomplish the intended tasks.
Low-Level Radioactive Waste Disposal The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is classified as low-level radioactive waste, although not all of the material is suitable for shallow-land disposal. With the passage of the "Low-Level Radioactive Waste Disposal Act" in 1980 and its Amendments of 1985,[8] the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.
Until recently, there were two facilities available to NPPD for the disposal of low-level radioactive waste generated by Cooper. As of July 1, 2008, however, the facility in Barnwell, South Carolina was closed to generators outside the Atlantic Compact (comprised of the states of Connecticut, New Jersey and South Carolina). This leaves the facility in Clive, Utah, operated by EnergySolutions, as the only available destination for low-level radioactive waste requiring controlled disposal.
7  Project and Cost Engineers' Handbook, Second Edition, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, p. 239 8  "Low-Level Radioactive Waste Policy Amendments Act of 1985," Public Law 99-240, 1/15/86 TLG Services, Inc.
 
CooperNuclearStation                                                Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                                      Pagexii of xvii For the purpose of this analysis, the EnergySolutions' facility is used as the basis for estimating the disposal cost for the majority of the radioactive waste (Class A [91).
EnergySolutions does not have a license to dispose of the more highly radioactive waste (Classes B and C), for example, generated in the dismantling of the reactor vessel. As a proxy, the disposal cost for this material is based upon the last published rate schedule for non-compact waste for the Barnwell facility.
The dismantling of the components residing closest to the reactor core generates radioactive waste considered unsuitable for shallow-land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste. However, to date, the federal government has not identified a cost for disposing of GTCC or a schedule for acceptance. As such, the GTCC radioactive waste has been packaged and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel.
A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This waste can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt. The estimates for Cooper reflect the savings from waste recovery/volume reduction.
High-Level Radioactive Waste Management Congress passed the "Nuclear Waste Policy Act"[' 01 (NWPA) in 1982, assigning the federal government's long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the DOE. The NWPA provided that DOE would enter into contracts with utilities in which DOE would promise to take the utilities' spent fuel and high-level radioactive waste and utilities would pay the cost of the disposition services for that material. NWPA, along with the individual contracts with the utilities, specified that the DOE was to begin accepting spent fuel by January 31, 1998.
9  U.S. Code of Federal Regulations, Title 10, Part 61, "Licensing Requirements for Land Disposal of Radioactive Waste" 10  "Nuclear Waste Policy Act of 1982 and Amendments," DOE's Office of Civilian Radioactive Management, 1982 TLG Services, Inc.
 
CooperNuclear Station                                                  Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                          Pagexiii of xvii Since the original legislation, the DOE has announced several delays in the program schedule. By January 1998, the DOE had failed to accept any spent fuel or high level waste, as required by the NWPA and utility contracts. Delays continue and, as a result, generators have initiated legal action against the DOE in an attempt to obtain compensation for DOE's breach of contract.
Operation of DOE's yet-to-be constructed repository is contingent upon the review and approval of the facility's license application by the NRC and the successful resolution of pending litigation. The DOE submitted its license application to the NRC on June 3, 2008, seeking authorization to construct the repository at Yucca Mountain, Nevada.
Assuming a timely review, and adequate funding, the DOE expects that receipt of fuel could begin by 2020.[111 It is generally necessary that spent fuel be actively cooled and stored for a minimum period at the generating site prior to transfer. As such, the NRC requires that licensees establish a program to manage and provide funding for the management of all irradiated fuel at the reactor site until title of the fuel is transferred to the Secretary of Energy, pursuant to 10 CFR Part 50.54(bb).[121 This funding requirement is fulfilled through inclusion of certain cost elements in the decommissioning estimates, for example, associated with the isolation and continued operation of the spent fuel pool and ISFSI.
At shutdown, the spent fuel pool is expected to contain freshly discharged assemblies (from the most recent refueling cycles) as well as the final reactor core. Over the following 51/2 years the assemblies are packaged into multipurpose canisters for transfer to the DOE or to the ISFSI. It is assumed that this period provides the necessary cooling for the final core to meet the storage system requirements and/or transport system requirements for decay heat.
DOE's contracts with utilities generally order the acceptance of spent fuel from utilities based upon the oldest fuel receiving the highest priority. For purposes of this analysis, acceptance of commercial spent fuel by the DOE is expected to begin in 2020.
NPPD has 1,054 spent fuel assemblies from Cooper in storage at General Electric's wet-pool ISFSI in Morris, Illinois. This analysis assumes that this inventory is preferentially transferred to the DOE, starting in 2022. The first assemblies removed from the Cooper site are assumed to be in 2027. With an estimated rate of transfer of 3,000 metric tons of uranium (MTU)/year, completion of the removal of fuel from the site is projected to be in the year 2046 for a 2014 shutdown and year 2061 for a 2034 11  "Testimony of Edward Sproat, Director, Office of Civilian Radioactive Waste Management, before a U.S. House of Representatives subcommittee on the status of Yucca Mountain, July 15, 2008 12 U.S. Code of Federal Regulations, Title 10, Part 50, "Domestic Licensing of Production and Utilization Facilities," Subpart 54 (bb), "Conditions of Licenses" TLG Services, Inc.
 
CooperNuclear Station                                        DocumentN01-1590-002, Rev. 1 0 DecommissioningCost Analysis                                              Pagexiv of xvii shutdown. Consequently, costs are included within the estimates for the long-term caretaking of the spent fuel at the Cooper site until the transfer is completed.
An ISFSI, which can be operated under a separate and independent license, has been constructed to support continued plant operations and future decommissioning. As such, the facility will be designed to accommodate the dry storage modules needed to off-load the wet storage pool so that dismantling activities can proceed. Once emptied, the Reactor Building can be either decontaminated and dismantled or prepared for long-term storage.
NPPD's position is that the DOE has a contractual obligation to accept Cooper's fuel earlier than the projections set out above consistent with its contract commitments. No assumption made in this study should be interpreted to be inconsistent with this claim. However, at this time, including the cost of storing spent fuel in this study is the most reasonable approach because it insures the availability of sufficient decommissioning funds at the end of the station's life if, contrary to its contractual obligation, the DOE has not performed earlier.
. Site Restoration Prompt dismantling of site structures (once the facilities are decontaminated) is clearly the most appropriate and cost-effective option. It is unreasonable to anticipate that these structures would be repaired and preserved after the radiological contamination is removed. The cost to dismantle site structures with a work force already mobilized on site is more efficient than if the process is deferred. Site facilities quickly degrade without maintenance, adding additional expense and creating potential hazards to the public and the demolition work force. Consequently, this study assumes that site structures are removed to a nominal depth of three feet below the local grade level wherever possible. The site is then to be graded and stabilized.
Summary The costs to decommission Cooper assumes the removal of all contaminated and activated plant components and structural materials such that the owner may then have unrestricted use of the site with no further requirements for an operating license.
Low-level radioactive waste, other than GTCC waste, is sent to a commercial processor for treatment/conditioning or to a controlled disposal facility.
Decommissioning is accomplished within the 60-year period required by current NRC regulations. In the interim, the spent fuel remains in storage at the site until such time that the transfer to a DOE facility is complete. Once emptied, the storage A facilities are also decommissioned.
TLG Services, Inc.
 
CooperNuclearStation                                        Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                              Pagexv of xvii The decommissioning scenarios are described in Section 2. The assumptions are presented in Section 3, along with schedules of annual expenditures. The major cost contributors are identified in Section 6, with detailed activity costs, waste volumes, and associated manpower requirements delineated in Appendices C and D. The major cost components are also identified in the cost summary provided at the end of this section.
The cost elements in the estimates are assigned to one of three subcategories: NRC License Termination, Spent Fuel Management, and Site Restoration. The subcategory "NRC License Termination" is used to accumulate costs that are consistent with "decommissioning" as defmed by the NRC in its financial assurance regulations (i.e.,
10 CFR Part 50.75). The cost reported for this subcategory is generally sufficient to terminate the unit's operating license, recognizing that there may be some additional cost impact from spent fuel management.
The "Spent Fuel Management" subcategory contains costs associated with the containerization and transfer of spent fuel to the ISFSI and the management of the ISFSI until such time that the transfer of all fuel from this facility to an off-site location (e.g., geologic repository) is completed.
O "Site Restoration" is used to capture costs associated with the dismantling and demolition of buildings and facilities demonstrated to be free from contamination. This includes structures never exposed to radioactive materials, as well as those facilities that have been decontaminated to appropriate levels. Structures are removed to a depth of three feet and backfilled to conform to local grade.
It should be noted that the costs assigned to these subcategories are allocations.
Delegation of cost elements is for the purposes of comparison (e.g., with NRC financial guidelines) or to permit specific financial treatment (e.g., Asset Retirement Obligation determinations). In reality, there can be considerable interaction between the activities in the three subcategories. For example, an owner may decide to remove non-contaminated structures early in the project to improve access to highly contaminated facilities or plant components. In these instances, the non-contaminated removal costs could be reassigned from Site Restoration to an NRC License Termination support activity. However, in general, the allocations represent a reasonable accounting of those costs that can be expected to be incurred for the specific subcomponents of the total estimated program cost, if executed as described.
As noted within this document, the estimates were developed and costs are presented in 2008 dollars. As such, the estimates do not reflect the escalation of costs (due to inflationary and market forces) over the remaining operating life of the reactor or during the decommissioning period.
TLG Services, Inc.
 
CooperNuclear Station                                              Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                        Pagexvi of xvii COST
 
==SUMMARY==
 
2014 Cessation of Operations (thousands of 2008 dollars)
Delayed Cost Element                                            DECON            DECON            SAFSTOR Decontamination                                            12,832            18,547          18,399 Removal                                                    73,606            74,005          75,346 Packaging                                                  13,340              9,827          9,577 Transportation                                                8,571            6,672          6,346 Waste Disposal                                              75,482            43,839          44,260 Off-site Waste Processing                                  35,573            42,626          42,743 Program Management [R1                                    360,232          426,204        490,053 Corporate A&G                                              15,657            10,100          10,100 Spent Fuel Management [21                                  77,077            69,839          69,839 Insurance and Regulatory Fees                              53,616            62,853          76,914
.Energy                                                      6,141          10,408          12,641 Characterization and Licensing Surveys                      16,568          16,568          16,568 Miscellaneous Equipment                                    23,364            31,112          34,923 Total [31                                                  772,0581          822,600        907,708 Cost Element License Termination                                        506,078          475,790        674,963 Spent Fuel Management                                      231,584          309,463        195,398 Site Restoration                                            34,396            37,347        37,347 Total [3]                                                  772,058          822,600        907,708 I'] Includes engineering and security costs
[21 Excludes program management costs (staffing) but includes costs for spent fuel loading/packaging/spent fuel pool O&M and EP fees
[31 Columns may not add due to rounding TLG Services, Inc.
 
CooperNuclearStation                                                Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                        Pagexvii of xvii COST
 
==SUMMARY==
 
2034 Cessation of Operations (thousands of 2008 dollars)
Delayed Cost Element                                            DECON            DECON            SAFSTOR Decontamination                                              12,832          18,581          18,438 Removal                                                    74,270            74,184          76,329 Packaging                                                    13,342            9,820          9,871 Transportation                                                8,571            6,704          6,578 Waste Disposal                                              75,618            46,649          44,999 Off-site Waste Processing                                  35,573            42,626          42,743 Program Management [1W                                    340,929          400,786        479,929 Corporate A&G                                                15,657          10,100          10,100 Spent Fuel Management [2]                                  53,484            47,535          47,535 Insurance and Regulatory Fees                              46,578            54,706          72,081 Energy                                                        6,141            9,875        12,641 Characterization and Licensing Surveys                      16,568          16,568          16,568 Miscellaneous Equipment                                    23,408            30,280          34,989 Total [3]                                                  722,972          768,414        872,803 Cost Element License Termination                                        506,207          476,185        676,510 Spent Fuel Management                                      182,368          254,881        158,945 Site Restoration                                            34,396          37,348          37,348 Total [3]                                                  722,972          768,414        872,803
[R] Includes engineering and security costs
[2] Excludes program management costs (staffing) but includes costs for spent fuel loading/packaging/spent fuel pool O&M and EP fees
[3] Columns may not add due to rounding TLG Services, Inc.
 
CooperNuclear Station                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 1, Page I of 8
: 1. INTRODUCTION This report presents estimates of the costs to decommission the Cooper Nuclear Plant (Cooper) following a scheduled cessation of plant operations. The estimates are designed to provide Nebraska Public Power District (NPPD), the plant's owner, with the information needed to assess its financial obligations, as they pertain to the eventual decommissioning of the nuclear station. It is not a detailed engineering document, but a financial analysis prepared in advance of the detailed engineering that will be required to carry out the decommissioning.
1.1 OBJECTIVES OF STUDY The objectives of this study were to prepare comprehensive estimates of the costs to decommission Cooper, to provide a sequence or schedule for the associated activities, and to develop waste stream projections from the decontamination and dismantling activities.
The construction permit for Cooper was issued in June of 1968, with commercial operation in July of 1974. For the purposes of this study, two shutdown dates were evaluated: the current license expiration date of January 18, 2014 and a projected date assuming license renewal of January 18, 2034.
These dates were used in scheduling the decommissioning activities.
1.2 SITE DESCRIPTION Cooper is a single unit facility located on the west bank of the Missouri River between the villages of Brownville and Nemaha, Nebraska. The nuclear station is owned and operated by NPPD, a public corporation and political subdivision of the state of Nebraska engaging in generation, transmission, distribution, and sale of electric energy.
The station is comprised of a single cycle, forced circulation, boiling water reactor designed by the General Electric Company, producing steam for direct use in the steam turbine: The original supporting facilities were engineered and constructed by Burns and Roe, Inc. The Multi-Purpose Facility, Office Building Addition, Warehouses, Flammable Liquid Storage Building and other on-site structures were designed and built by others.
The reactor vessel and the recirculation piping system are contained within the drywell of a pressure suppression system housed within the Reactor Building.
The pressure suppression system consists of a drywell, a pressure suppression chamber which stores a large volume of water and a connecting submerged TLG Services, Inc.
 
CooperNuclear Station                                            DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                            Section 1, Page2 of 8 vent system between the drywell and water pool, isolation valves, containment cooling systems and other service equipment. The Reactor Building encloses the primary containment system thereby providing a secondary containment.
Heat produced in the reactor is converted to electrical energy by the power conversion system. A turbine-generator system converts the thermal energy of the steam produced in the reactor into mechanical shaft power and then into electrical energy. The turbine consists of one high-pressure, double-flow turbine element, and two low-pressure, double-flow turbine elements all aligned in tandem. The generator is a direct-driven, 1,800 rpm hydrogen-cooled synchronous generator. The turbine is operated in a closed feedwater cycle, which condenses the steam; the heated feedwater is returned to the reactor.
The heat rejected to the main condenser is removed by the circulating water system. Based upon the recent power uprate, Cooper's generating capacity will be approximately 836 Megawatts electric (MWe).
The circulating water system provides the heat sink required for removal of waste heat in the power plant's thermal cycle. The system has the principal function of removing heat by absorbing this energy in the main condenser.
Circulating water is drawn from the Missouri River with heated cooling water returned to the river.
1.3 REGULATORY GUIDANCE The Nuclear Regulatory Commission (NRC or Commission) provided initial decommissioning requirements in its rule "General Requirements for Decommissioning Nuclear Facilities," issued in June 1988. 1
* This rule set forth financial criteria for decommissioning licensed nuclear power facilities.
The regulation addressed decommissioning planning needs, timing, funding methods, and environmental review requirements. The intent of the rule was to ensure that decommissioning would be accomplished in a safe and timely manner and that adequate funds would be available for this purpose.
Subsequent to the rule, the NRC issued Regulatory Guide 1.159, "Assuring the Availability of Funds for Decommissioning Nuclear Reactors,"[21 which provided additional guidance to the licensees of nuclear facilities on the financial methods acceptable to the NRC staff for complying with the requirements of the rule. The regulatory guide addressed the funding requirements and provided guidance on the content and form of the financial assurance mechanisms indicated in the rule.
* References provided in Section 7 of the document TLG Services, Inc.
 
CooperNuclearStation                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 1, Page 3 of 8 The rule defined three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB. The DECON alternative assumes that any contaminated or activated portion of the plant's systems, structures and facilities are removed or decontaminated to levels that permit the site to be released for unrestricted use shortly after the cessation of plant operations.
The rule also placed limits on the time allowed to complete the decommissioning process. For SAFSTOR, the process is restricted in overall duration to 60 years, unless it can be shown that a longer duration is necessary to protect public health and safety. The guidelines for ENTOMB are similar, providing the NRC with both sufficient leverage and flexibility to ensure that these deferred options are only used in situations where it is reasonable and consistent with the definition of decommissioning. At the conclusion of a 60-year dormancy period (or longer for ENTOMB if the NRC approves such a case), the site would still require significant remediation to meet the unrestricted release limits for license termination.
The ENTOMB alternative has not been viewed as a viable option for power reactors due to the significant time required to isolate the long-lived radionuclides for decay to permissible levels. However, with rulemaking permitting the controlled release of a site,[3] the NRC has re-evaluated this alternative. The resulting feasibility study, based upon an assessment by Pacific Northwest National Laboratory, concluded that the method did have conditional merit for some, if not most reactors. However, the staff also found that additional rulemaking would be needed before this option could be treated as a generic alternative. The NRC had considered rulemaking to alter the 60-year time for completing decommissioning and to clarify the use of engineered barriers for reactor entombments.[4] However, the NRC's staff has recommended that rulemaking be deferred, based upon several factors, e.g., no licensee has committed to pursuing the entombment option, the unresolved issues associated with the disposition of greater-than-Class C material (GTCC), and the NRC's current priorities, at least until after the additional research studies are complete. The Commission concurred with the staffs recommendation.
In 1996, the NRC published revisions to the general requirements for decommissioning nuclear power plants.[51 When the decommissioning regulations were adopted in 1988, it was assumed that the majority of licensees would decommission at the end of the facility's operating licensed life.
Since that time, several licensees permanently and prematurely ceased operations. Exemptions from certain operating requirements were required once the reactor was defueled to facilitate the decommissioning. Each case was handled individually, without clearly defined generic requirements. The NRC amended the decommissioning regulations in 1996 to clarify ambiguities and TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002,Rev. 1 DecommissioningCost Analysis                                      Section 1, Page 4 of 8 codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process. The amendments allow for greater public participation and better define the transition process from operations to decommissioning.
Under the revised regulations, licensees will submit written certification to the NRC within 30 days after the decision to cease operations. Certification will also be required once the fuel is permanently removed from the reactor vessel.
Submittal of these notices will entitle the licensee to a fee reduction and eliminate the obligation to follow certain requirements needed only during operation of the reactor. Within two years of submitting notice of permanent cessation of operations, the licensee is required to submit a Post-Shutdown Decommissioning Activities Report (PSDAR) to the NRC. The PSDAR describes the planned decommissioning activities, the associated sequence and schedule, and an estimate of expected costs. Prior to completing decommissioning, the licensee is required to submit an application to the NRC to terminate the license, which will include a license termination plan (LTP).
1.3.1 Nuclear Waste Policy Act Congress passed the "Nuclear Waste Policy Act"[6] (NWPA) in 1982, assigning the federal government's long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the DOE. The NWPA provided that DOE would enter into contracts with utilities in which DOE would promise to take the utilities' spent fuel and high-level radioactive waste and utilities would pay the cost of the disposition services for that material. NWPA, along with the individual contracts with the utilities, specified that the DOE was to begin accepting spent fuel by January 31, 1998.
Since the original legislation, the DOE has announced several delays in the program schedule. By January 1998, the DOE had failed to accept any spent fuel or high level waste, as required by the NWPA and utility contracts. Delays continue and, as a result, generators have initiated legal action against the DOE in an attempt to obtain compensation for DOE's breach of contract.
Operation of DOE's yet-to-be constructed repository is contingent upon the review and approval of the facility's license application by the NRC and the successful resolution of pending litigation. The DOE submitted its license application to the NRC on June 3, 2008, seeking authorization to construct the repository at Yucca Mountain, Nevada. Assuming a TLG Services, Inc.
 
CooperNuclear Station                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                        Section 1, Page5 of 8 timely review, and adequate funding, the DOE expects that receipt of fuel could begin by 2020.[71 It is generally necessary that spent fuel be actively cooled and stored for a minimum period at the generating site prior to transfer. As such, the NRC requires that licensees establish a program to manage and provide funding for the management of all irradiated fuel at the reactor site until title of the fuel is transferred to the Secretary of Energy, pursuant to 10 CFR Part 50.54(bb).[8 1 This funding requirement is fulfilled through inclusion of certain cost elements in the decommissioning estimate, for example, associated with the isolation and continued operation of the spent fuel pool and ISFSI.
At shutdown, the spent fuel pool is expected to contain freshly discharged assemblies (from the most recent refueling cycles) as well as the final reactor core. Over the following 5Y years the assemblies are packaged into multipurpose canisters for transfer to the DOE or to the ISFSI. It is assumed that this period provides the necessary cooling for the final core to meet the storage system requirements and/or transport system requirements for decay heat.
DOE's contracts with utilities generally order the acceptance of spent fuel from utilities based upon the oldest fuel receiving the highest priority. For purposes of this analysis, acceptance of commercial spent fuel by the DOE is expected to begin in 2020.
NPPD has 1,054 spent fuel assemblies from Cooper in storage at General Electric's wet-pool ISFSI in Morris, Illinois. This analysis assumes that this inventory is preferentially transferred to the DOE, starting in 2022. The first assemblies removed from the Cooper site are assumed to be in 2027. With an estimated rate of transfer of 3,000 metric tons of uranium (MTU)/year from the commercial generators, completion of the removal of fuel from the Cooper site is projected to be in the year 2046 for a 2014 shutdown and year 2061 for a 2034 shutdown. Consequently, costs are included within the estimates for the long-term caretaking of the spent fuel at the Cooper site until the transfer is completed.
An ISFSI, which can be operated under a separate and independent license, is constructed to support plant operations and decommissioning.
As such, the facility will be designed to accommodate the dry storage modules needed to off-load the wet storage pool so that dismantling TLG Services, Inc.
 
CooperNuclear Station                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 1, Page 6 of 8 activities can proceed. Once emptied, the Reactor Building can be either decontaminated and dismantled or prepared for long-term storage.
NPPD's position is that the DOE has a contractual obligation to accept Cooper's fuel earlier than the projections set out above consistent with its contract commitments. No assumption made in this study should be interpreted to be inconsistent with this claim. However, at this time, including the cost of storing spent fuel in this study is the most reasonable approach because it insures the availability of sufficient decommissioning funds at the end of the station's life if, contrary to its contractual obligation, the DOE has not performed earlier.
1.3.2 Low-Level Radioactive Waste Acts The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is classified as low-level (radioactive) waste, although not all of the material is suitable for "shallow-land" disposal. With the passage of the "Low-Level Radioactive Waste Policy Act" in 1980,[91 and its Amendments of 1985,110] the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.
Until recently, there were two facilities available to NPPD for the disposal of low-level radioactive waste generated by Cooper. As of July 1, 2008, however, the facility in Barnwell, South Carolina was closed to generators outside the Atlantic Compact (comprised of the states of Connecticut, New Jersey and South Carolina). This leaves the facility in Clive, Utah, operated by EnergySolutions, as the only available destination for low-level radioactive waste requiring controlled disposal.
For the purpose of this analysis, the EnergySolutions' facility is used as the basis for estimating the disposal cost for the majority of the radioactive waste (Class A[ 1"]). EnergySolutions does not have a license to dispose of the more highly radioactive waste (Class B and C), for example, generated in the dismantling of the reactor vessel. As a proxy, the disposal costs for this material are based upon the last published rate schedule for non-compact waste for the Barnwell facility.
The dismantling of the components residing closest to the reactor core generates radioactive waste considered unsuitable for shallow land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C TLG Services, Inc.
 
CooperNuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                        Section 1, Page 7 of 8 radioactive waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste.
However, to date, the federal government has not identified a cost for disposing of GTCC or a schedule for acceptance. As such, the GTCC radioactive waste has been packaged and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel.
A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This waste can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt. The estimates for Cooper reflect the savings from waste recovery/volume reduction.
1.3.3 Radiological Criteria for License Termination In 1997, the NRC published Subpart E, "Radiological Criteria for License Termination,"[121 amending 10 CFR Part 20. This subpart provides radiological criteria for releasing a facility for unrestricted use.
The regulation states that the site can be released for unrestricted use if radioactivity levels are such that the average member of a critical group would not receive a Total Effective Dose Equivalent (TEDE) in excess of 25 millirem per year, and provided that residual radioactivity has been reduced to levels that are As Low As Reasonably Achievable (ALARA).
The decommissioning estimates assume that the Cooper site will be remediated to a residual level consistent with the NRC-prescribed level.
It should be noted that the NRC and the Environmental Protection Agency (EPA) differ on the amount of residual radioactivity considered acceptable in site remediation. The EPA has two limits that apply to radioactive materials. An EPA limit of 15 millirem per year is derived from criteria established by the Comprehensive Environmental 13 Response, Compensation, and Liability Act (CERCLA or Superfund).[ 1 An additional and separate limit of 4 millirem per year, as defined in 40 CFR §141.16, is applied to drinking water.[141 TLG Services, Inc.
 
CooperNuclearStation                                    Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                    Section 1, Page8 of 8 On October 9, 2002, the NRC signed an agreement with the EPA on the radiological decommissioning and decontamination of NRC-licensed sites. The Memorandum of Understanding (MOU)[' 5] provides that EPA will defer exercise of authority under CERCLA for the majority of facilities decommissioned under NRC authority. The MOU also includes provisions for NRC and EPA consultation for certain sites when, at the time of license termination, (1) groundwater contamination exceeds EPA-permitted levels; (2) NRC contemplates restricted release of the site; and/or (3) residual radioactive soil concentrations exceed levels defined in the MOU.
The MOU does not impose any new requirements on NRC licensees and should reduce the involvement of the EPA with NRC licensees who are decommissioning. Most sites are expected to meet the NRC criteria for unrestricted use, and the NRC believes that only a few sites will have groundwater or soil contamination in excess of the levels specified in the MOU that trigger consultation with the EPA. However, if there are other hazardous materials on the site, the EPA may be involved in the cleanup. As such, the possibility of dual regulation remains for certain licensees. The present study does not include any costs for this occurrence.
TLG Services, Inc.
 
CooperNuclearStation                                          DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                          Section 2, Page1 of 13
: 2. DECOMMISSIONING ALTERNATIVES Detailed cost estimates were developed to decommission the Cooper nuclear unit for the scenarios described below. Although they differ with respect to technique, process, cost, and schedule, they attain the same result: the ultimate release of the site for unrestricted use.
The following alternatives were evaluated (for both a 2014 and 2034 cessation of plant operations) and are representative of the alternatives available to the owner:
: 1. DECON: The plant is decommissioned shortly after the permanent cessation of plant operations. Spent fuel, that is not transferred directly to the DOE, is relocated to the ISFSI for interim storage. Spent fuel storage operations continue at the site until the transfer of the fuel to the DOE is completed.
: 2. Delayed DECON: In the second scenario, the unit is prepared for an abbreviated period of storage. As in the first scenario, spent fuel storage operations continue at the site until the transfer of the fuel to the DOE is completed. Once completed, decommissioning operations are initiated.
: 3. SAFSTOR: The third scenario is similar to the second scenario in that the unit is placed in safe-storage with concurrent spent fuel storage operations. However, decommissioning is deferred beyond the fuel storage period to the maximum extent possible; termination of the license would conclude within the maximum required 60-year period.
Six scenarios were identified for evaluation. As shown below, the six scenarios evaluate a combination of shutdown dates (scheduled and anticipated) and decommissioning alternative (prompt or deferred).
Shutdown                                  Spent Fuel        Operating Scenario        Date              Option              Transfer            License Completed        Terminated 1          2014              DECON                  2046                2020 2          2014        Delayed DECON                2046                2053 3          2014            SAFSTOR                  2046                2074 4          2034              DECON                  2061                2040 5          2034        Delayed DECON                2061                2068 6          2034            SAFSTOR                  2061                2094 TLG Services, Inc.
 
CooperNuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 2, Page2 of 13 The following sections describe the basic activities associated with each alternative.
Although detailed procedures for each activity identified are not provided, and the actual sequence of work may vary, the activity descriptions provide a basis not only for estimating but also for the expected scope of work, i.e., engineering and planning at the time of decommissioning.
The conceptual approach that the NRC has described in its regulations divides decommissioning into three phases. The initial phase commences with the effective date of permanent cessation of operations and involves the transition of both plant and licensee from reactor operations (i.e., power production) to facility de-activation and closure. During the first phase, notification is to be provided to the NRC certifying the permanent cessation of operations and the removal of fuel from the reactor vessel. The licensee is then prohibited from reactor operation.
The second phase encompasses activities during the storage period or during major decommissioning activities, or a combination of the two. The third phase pertains to the activities involved in license termination. The decommissioning estimates developed for Cooper are also divided into phases or periods; however, demarcation of the phases is based upon major milestones within the project or significant changes in the projected expenditures.
2.1 DECON The DECON alternative, as defined by the NRC, is "the alternative in which the equipment, structures, and portions of a facility and site containing radioactive contaminants are removed or decontaminated to a level that permits the property to be released for unrestricted use shortly after cessation of operations." This study does not address the cost to dispose of the spent fuel residing at the site; such costs are funded through a surcharge on electrical generation. However, the study does estimate the costs incurred with the interim on-site storage of the fuel pending shipment by the DOE to an off-site disposal facility.
2.1.1 Period 1 - Preparations In anticipation of the cessation of plant operations, detailed preparations are undertaken to provide a smooth transition from plant operations to site decommissioning. Through implementation of a staffing transition plan, the organization required to manage the intended decommissioning activities is assembled from available plant staff and outside resources. Preparations include the planning for permanent defueling of the reactor, revision of technical specifications applicable to the operating conditions and requirements, a TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                      Section 2, Page3 of 13 characterization of the facility      and major components,        and the development of the PSDAR.
Engineering and Planning The PSDAR, required within two years of the notice to cease operations, provides a description of the licensee's planned decommissioning activities, a timetable, and the associated financial requirements of the intended decommissioning program. Upon receipt of the PSDAR, the NRC will make the document available to the public for comment in a local hearing to be held in the vicinity of the reactor site. Ninety days following submittal and NRC receipt of the PSDAR, the licensee may begin to perform major decommissioning activities under a modified 10 CFR §50.59 procedure, i.e., without specific NRC approval. Major activities are defined as any activity that results in permanent removal of major radioactive components, permanently modifies the structure of the containment, or results in dismantling components (for shipment) containing GTCC, as defined by 10 CFR §61. Major components are further defined as comprising the reactor vessel and internals, large bore reactor recirculation system piping, and other large components that are radioactive. The NRC includes the following additional criteria for use of the §50.59 process in decommissioning. The proposed activity must not:
            " foreclose release of the site for possible unrestricted use,
* significantly increase decommissioning costs,
* cause any significant environmental impact, or
* violate the terms of the licensee's existing license.
Existing operational technical specifications are reviewed and modified to reflect plant conditions and the safety concerns associated with permanent cessation of operations. The environmental impact associated with the planned decommissioning activities is also considered.
Typically, a licensee will not be allowed to proceed if the consequences of a particular decommissioning activity are greater than that bounded by previously evaluated environmental assessments or impact statements.
In this instance, the licensee would have to submit a license amendment for the specific activity and update the environmental report.
The decommissioning program outlined in the PSDAR will be designed to accomplish the required tasks within the ALARA guidelines (as defined in 10 CFR §20) for protection of personnel from exposure to TLG Services, Inc.
 
CooperNuclear Station                                      Document N01-1590-002,Rev. 1 0 DecommissioningCost Analysis                                      Section 2, Page4 of 13 radiation hazards. It will also address the continued protection of the health and safety of the public and the environment during the dismantling activity. Consequently, with the development of the PSDAR, activity specifications, cost-benefit and safety analyses, work packages and procedures, would be assembled to support the proposed decontamination and dismantling activities.
Site Preparations Following final plant shutdown, and in preparation for                actual decommissioning activities, the following activities are initiated:
* Characterization of the site and surrounding environs. This includes radiation surveys of work areas, major components (including the reactor vessel and its internals), internal piping, and sacrificial shield cores.
* Isolation of the spent fuel storage pool and fuel handling systems, such that decommissioning operations can commence on the balance of the plant. The pool will remain operational for approximately 51/2 years following the cessation of operations before the inventory resident at shutdown can be transferred to the ISFSI.
* Specification of transport and disposal requirements for activated materials and/or hazardous materials, including shielding and waste stabilization.
            " Development of procedures for occupational exposure control, control and release of liquid and gaseous effluent, processing of radwaste (including dry-active waste, resins, filter media, metallic and non-metallic components generated in decommissioning), site security and emergency programs, and industrial safety.
2.1.2 Period 2 - Decommissioning Operations This period includes the physical decommissioning activities associated with the removal and disposal of contaminated and activated components and structures, including the successful termination of the 10 CFR §50 operating license. Significant decommissioning activities in this phase include:
Construction of temporary facilities and/or modification of existing facilities to support dismantling activities. This may include a centralized processing area to facilitate equipment removal and component preparations for off-site disposal.
TLG Services, Inc.
 
CooperNuclearStation                                        DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 2, Page 5 of 13 Reconfiguration and modification of site structures and facilities as needed to support decommissioning operations. This may include the upgrading of roads (on- and off-site) to facilitate hauling and transport. Modifications may be required to the containment structure to facilitate access of large/heavy equipment. Modifications may also be required to the refueling area of the Reactor Building to support the segmentation of the reactor vessel internals and component extraction.
          " Design and fabrication of temporary and permanent shielding to support removal and transportation activities, construction of contamination control envelopes, and the procurement of specialty tooling.
o    Procurement (lease or purchase) of shipping canisters, cask liners, and industrial packages for the disposition of low-level radioactive waste.
* Decontamination of components and piping systems as required to control (minimize) worker exposure.
* Removal of piping and components no longer essential to support decommissioning operations.
* Disconnection of the control blades from the drives on the vessel lower head. Blades are transferred to the spent fuel pool for packaging.
o    Transfer of the steam separator and dryer assemblies to the dryer-separator pool for segmentation. Segmentation will maximize the loading of the shielded transport casks, i.e., by weight and activity.
The operations are conducted under water using remotely operated tooling and contamination controls.
* Disassembly, segmentation and packaging of the core shroud and in-core guide tubes. Some of the material is expected to exceed Class C disposal requirements. As such, those segments will be packaged in a modified fuel canister for geologic disposal. Interim storage can be in the pool, as space permits, or in the ISFSI.
o    Removal and segmentation of the remaining internals including the jet pump assemblies, fuel support castings and core plate assembly.
* Draining and decontamination of the reactor well and permanently sealing of the spent fuel transfer gate. Install shielded platform for segmentation of reactor vessel. Cutting operations are performed in air using remotely operated equipment within a contamination control envelope, with the water level maintained just below the cut TLG Services, Inc.
 
CooperNuclear Station                                      Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                        Section 2, Page 6 of 13 to minimize the working area dose rates. Sections are transferred to the dryer-separator pool for packaging and interim storage.
* Disconnection of the control rod drives and instrumentation tubes from reactor vessel lower head. The lower reactor head and vessel supporting structure will then be segmented.
* Removal of the reactor recirculation pumps. Exterior surfaces are decontaminated and openings covered. Components can serve as their own burial containers provided that all penetrations are properly sealed.
          " Demolition of the sacrificial shield activated concrete by controlled demolition.
At least two years prior to the anticipated date of license termination, an LTP is required. Submitted as a supplement to the Final Safety Analysis Report (FSAR) or its equivalent, the plan must include: a site characterization, description of the remaining dismantling activities, plans for site remediation, procedures for the final radiation survey, designation of the end use of the site, an updated cost estimate to complete the decommissioning, and any associated environmental concerns. The NRC will notice the receipt of the plan, make the plan available for public comment, and schedule a local hearing. LTP approval will be subject to any conditions and limitations as deemed appropriate by the Commission. The licensee may then commence with the final remediation of site facilities and services, including:
          " Removal of remaining plant systems and associated components as they become nonessential to the decommissioning program or worker health and safety (e.g., waste collection and treatment systems, electrical power and ventilation systems).
* Removal of the steel liners from the drywell, disposing of the activated and contaminated sections as radioactive waste. Removal of any activated/contaminated concrete.
* Removal of the steel liners from the steam separator and dryer pool, reactor well and spent fuel storage pool.
* Surveys of the decontaminated areas of the containment structure.
            " Removal of the contaminated equipment and material from the Turbine and Radwaste buildings and any other contaminated facility.
Use radiation and contamination control techniques until radiation surveys indicate that the structures can be released for unrestricted access and conventional demolition. This activity may necessitate the TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 0 DecommissioningCost Analysis                                      Section 2, Page 7 of 13 dismantling and disposition of most of the systems and components (both clean and contaminated) located within these buildings. This activity will facilitate surface decontamination and subsequent verification surveys required prior to obtaining release for demolition.
Incorporated into the LTP is the Final Survey Plan. This plan identifies the radiological surveys to be performed once the decontamination activities are completed and is developed using the guidance provided in the "Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM)."[ I6 This document incorporates the statistical approaches to survey design and data interpretation used by the EPA. It also identifies state-of-the-art, commercially available instrumentation and procedures for conducting radiological surveys. Use of this guidance ensures that the surveys are conducted in a manner that provides a high degree of confidence that applicable NRC criteria are satisfied. Once the survey is complete, the results are provided to the NRC in a format that can be verified. The NRC then reviews and evaluates the information, performs an independent confirmation of radiological site conditions,
* and makes a determination on final termination of the license.
The NRC will terminate the operating license if it determines that site remediation has been performed in accordance with the LTP, and that the terminal radiation survey and associated documentation demonstrate that the facility is suitable for release.
2.1.3 Period 3 - Site Restoration Following completion of decommissioning operations, site restoration activities will begin. Efficient removal of the contaminated materials and verification that residual radionuclide concentrations are below the NRC limits will result in substantial damage to many of the structures.
Although performed in a controlled, safe manner, blasting, coring, drilling, scarification (surface removal), and the other decontamination activities will substantially degrade power block structures including the reactor, augmented radwaste, radwaste and turbine buildings.
Under certain circumstances, verifying that subsurface radionuclide concentrations meet NRC site release requirements will require removal of grade slabs and lower floors, potentially weakening footings and structural supports. This removal activity will be necessary for those facilities and plant areas where historical records, when available, indicate the potential for radionuclides having been present in the soil, where system failures have been recorded, or where it is required to TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                      Section 2, Page8 of 13 confirm that subsurface process and drain lines were not breached over the operating life of the station.
Prompt dismantling of site structures is clearly the most appropriate and cost-effective option. It is unreasonable to anticipate that these structures would be repaired and preserved after the radiological contamination is removed. The cost to dismantle site structures with a work force already mobilized on site is more efficient than if the process were deferred. Site facilities quickly degrade without maintenance, adding additional expense and creating potential hazards to the public as well as to future workers. Abandonment creates a breeding ground for vermin infestation as well as other biological hazards.
This cost study presumes that non-essential structures and site facilities are dismantled as a continuation of the decommissioning activity.
Foundations and exterior walls are removed to a nominal depth of three feet below grade. The three-foot depth allows for the placement of gravel for drainage, as well as topsoil, so that vegetation can be established for erosion control. Site areas affected by the dismantling activities are restored and the plant area graded as required to prevent ponding and inhibit the refloating of subsurface materials.
Non-contaminated concrete rubble produced by demolition activities is processed to remove reinforcing steel and miscellaneous embedments.
The processed material is then used on site to backfill foundation voids.
Excess non-contaminated materials are trucked to an off-site area for disposal as construction debris.
2.1.4 ISFSI Operations and Decommissioning The ISFSI will continue to operate under a separate and independent license (10 CFR §72) following the termination of the §50 operating license. Assuming the DOE starts accepting fuel from commercial generators in 2020, transfer of spent fuel from the ISFSI to the DOE would begin in 2027, with the transfer completed by 2046 for a 2014 shutdown and year 2061 for a 2034 shutdown.
At the conclusion of the spent fuel transfer process, the ISFSI will be decommissioned. The Commission will terminate the §72 license when it determines that the remediation of the ISFSI has been performed in accordance with an ISFSI license termination plan and that the final radiation survey and associated documentation demonstrate that the TLG Services, Inc.
 
CooperNuclear Station                                      DocunentN01-1590-002,Rev. 1 DecommissioningCost Analysis                                      Section 2, Page9 of 13 facility is suitable for release. Once the requirements are satisfied, the NRC can terminate the license for the ISFSI.
The assumed design for the ISFSI is based upon the use of a multi-purpose canister and a horizontal concrete module for pad storage. For purposes of this cost analysis, it is assumed that once the inner canisters containing the spent fuel assemblies have been removed, any required decontamination performed on the storage modules (some minor activation is assumed), and the license for the facility terminated, the modules can be dismantled using conventional techniques for the demolition of reinforced concrete. The concrete storage pad is then removed and the area regraded.
2.2 SAFSTOR AND DELAYED DECOMMISSIONING The NRC defines SAFSTOR as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use." The facility is left intact (during the dormancy period), with structures maintained in a sound condition. Systems not required to operate in support of the spent fuel pool or site surveillance and security are drained, de-energized, and secured.
Minimal cleaning/removal of loose contamination and/or fixation and sealing of remaining contamination is performed. Access to contaminated areas is secured to provide controlled access for inspection and maintenance.
The engineering and planning requirements are similar to those for the DECON alternative, although a shorter time period is expected for these activities due to the more limited work scope. Site preparations are also similar to those for the DECON alternative. However, with the exception of the required radiation surveys and site characterizations, the mobilization and preparation of site facilities is less extensive.
The following discussion is appropriate for both the SAFSTOR and Delayed DECON scenarios, the primary differences being in the length of the dormancy period. In the Delayed DECON scenario, decommissioning operations are assumed to begin once fuel is off site. By contrast, in the SAFSTOR scenario, the plant remains in safe-storage after the fuel is removed from site. Decommissioning operations are initiated such that the license is terminated within the required 60-year time period.
TLG Services, Inc.
 
CooperNuclearStation                                        Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 2, Page 10 of 13 2.2.1 Period 1 - Preparations Preparations for long-term storage include the planning for permanent defueling of the reactor, revision of technical specifications appropriate to the operating conditions and requirements, a characterization of the facility and major components, and the development of the PSDAR.
The process of placing the plant in safe-storage includes, but is not limited to, the following activities:
* Isolation of the spent fuel storage services and fuel handling systems located in the Reactor Building so that safe-storage operations may commence on the balance of the plant. This activity may be carried out by plant personnel in accordance with existing operating technical specifications. Activities are scheduled around the fuel handling systems to the greatest extent possible.
* Relocation of the spent fuel from the spent fuel storage pool to the ISFSI.
* Draining and de-energizing of the non-contaminated systems not required to support continued site operations or maintenance.
* Disposing of contaminated filter elements and resin beds not required for processing wastes from layup activities for future operations.
              " Draining of the reactor vessel, with the internals left in place and the vessel head secured.
* Draining and de-energizing non-essential, contaminated systems with decontamination as required for future maintenance and inspection.
* Preparing lighting and alarm systems whose continued use is required; de-energizing portions of fire protection, electric power, and HVAC systems whose continued use is not required.
* Cleaning of the loose surface contamination from building access pathways.
* Performing an interim radiation survey of plant, posting warning signs where appropriate.
* Erecting physical barriers and/or securing all access to radioactive or contaminated areas, except as required for inspection and maintenance.
TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590.002,Rev. 1 DecommissioningCost Analysis                                    Section 2, Page 11 of 13 Installing security and surveillance monitoring equipment and relocating security fence around secured structures, as required.
2.2.2 Period 2 - Dormancy The second phase identified by the NRC in its rule addresses licensed activities during a storage period and is applicable to the dormancy phases of the deferred decommissioning alternatives. Dormancy activities include a 24-hour security force, preventive and corrective maintenance on security systems, area lighting, general building maintenance, heating and ventilation of buildings, routine radiological inspections of contaminated structures, maintenance of structural integrity, and a site environmental and radiation monitoring program.
Resident maintenance personnel perform equipment maintenance, inspection activities, routine services to maintain safe conditions, adequate lighting, heating, and ventilation, and periodic preventive maintenance on essential site services.
An environmental surveillance program is carried out during the dormancy period to ensure that releases of radioactive material to the environment are prevented and/or detected and controlled.
Appropriate emergency procedures are established and initiated for potential releases that exceed prescribed limits. The environmental surveillance program constitutes an abbreviated version of the program in effect during normal plant operations.
Security during the dormancy period is conducted primarily to prevent unauthorized entry and to protect the public from the consequences of its own actions. The security fence, sensors, alarms, and other surveillance equipment provide security. Fire and radiation alarms are also monitored and maintained. While remote surveillance is an option, it does not offer the immediate response time of a physical presence.
The transfer of the spent fuel to a DOE facility continues during this period until complete. After an optional period of storage (such that license terminations are accomplished within 60 years of final shutdown), it is required that the licensee submit applications to terminate the license, along with an LTP (described in Section 2.1.2),
thereby initiating the third phase.
TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                    Section 2, Page 12 of 13 2.2.3 Periods 3 and 4 - Delayed Decommissioning Prior to the commencement of decommissioning operations, preparations are undertaken to reactivate site services and prepare for decommissioning. Preparations include engineering and planning, a detailed site characterization, and the assembly of a decommissioning management organization. Final planning for activities and the writing of activity specifications and detailed procedures are also initiated at this time.
Much of the work in developing a termination plan is relevant to the development of the detailed engineering plans and procedures. The activities associated with this phase and the follow-on decontamination and dismantling processes are detailed in Sections 2.1.1 and 2.1.2. The primary difference between the sequences anticipated for the DECON and deferred scenarios is the absence, in the latter, of any constraint on the availability of the fuel storage facilities located within the Reactor Building for decommissioning.
Variations in the length of the dormancy period are expected to have little effect upon the quantities of radioactive wastes generated from system and structure removal operations. Given the levels of radioactivity and spectrum of radionuclides expected from forty to sixty years of plant operation, no plant process system identified as being contaminated upon final shutdown will become releasable due to the decay period alone, i.e., there is no significant reduction in the waste generated from the decommissioning activities. However, due to the lower activity levels, a greater percentage of the waste volume can be designated for off-site processing and recovery.
The delay in decommissioning also yields lower working area radiation levels. As such, the estimates for the delayed scenarios incorporate reduced ALARA controls for the lower occupational exposure potential.
Although the initial radiation levels due to 6°Co will decrease during the dormancy period, the internal components of the reactor vessel will still exhibit sufficiently high radiation dose rates to require remote sectioning under water due to the presence of long-lived radionuclides such as 94Nb, 59 Ni, and 63Ni. Therefore, the dismantling procedures described for the DECON alternative would still be employed during deferred scenarios. Portions of the sacrificial shield will still be radioactive due to the presence of activated trace elements with long half-lives (152 Eu and 154Eu). Decontamination will require controlled TLG Services, Inc.
 
Cooper NuclearStation                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                    Section 2, Page13 of 13 removal and disposal. It is assumed that radioactive corrosion products on inner surfaces of piping and components will not have decayed to levels that will permit unrestricted use or allow conventional removal.
These systems and components will be surveyed as they are removed and disposed of in accordance with the existing radioactive release criteria.
2.2.4 Period 5 - Site Restoration Following completion of decommissioning operations, site-restoration activities can begin. If the site structures are to be dismantled, dismantling as a continuation of the decommissioning process is clearly the most appropriate and cost-effective option, as described in Section 2.1.3. The basis for the dismantling cost in the deferred scenarios is consistent with that described for DECON, presuming the removal of structures and site facilities to a nominal depth of three feet I
below grade and the limited restoration of the site.
TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 3, Page 1 of29
: 3. COST ESTIMATES The estimates prepared for decommissioning Cooper consider the unique features of the site, including the nuclear steam system supply, electric power generating systems, structures, and supporting facilities. The basis of the estimates, including the sources of information relied upon, the estimating methodology employed, site-specific considerations, and other pertinent assumptions, is described in this section.
3.1 BASIS OF ESTIMATES The current estimates are area-based estimates, i.e., the plant inventory has been correlated with site-specific area working conditions, and the plant work activities organized into discrete areas to better reflect the manner in which the decommissioning will take place. The areas were determined on the basis of "common" conditions or attributes. Each area was evaluated for work difficulty, including affects of radiation, external surface contamination, and access. This evaluation was used to adjust the work difficulty factors for removing equipment in a given area.
3.2 METHODOLOGY The methodology used to develop the estimates follows the basic approach originally presented in the cost estimating guidelines developed by the Atomic Industrial Forum (now Nuclear Energy Institute). The "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," (AIF/NESP-036) [17] and the DOE "Decommissioning Handbook."[' 8 ]
describe a unit cost factor method for estimating decommissioning activity costs. The unit cost factors used in this analysis were developed using these guidance documents, updated for more recent decommissioning experience and modified to incorporate site-specific costs.
The activity-dependent costs were then estimated with the item quantities (cubic yards and tons), developed from plant drawings and plant design information. A data base was constructed identifying the installed equipment in each designated work area. This data base contains a list of components that have a unique identifier, such as valves, tanks, electrical equipment, and heat exchangers. It also contains bulk commodities such as piping, ventilation ductwork, cable tray, electrical conduit, and supports. Data base categories were consistent with unit cost factors described previously.
TLG Services, Inc.
 
Cooper NuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                        Section 3, Page 2 of29 Removal rates and material costs for the conventional disposition of components and structures relied upon information available in the industry publication, "Building Construction Cost Data," published by R.S. Means.[1 91 The unit factor method provides a demonstrable basis for establishing reliable cost estimates. The detail provided in the unit factors, including activity duration, labor costs (by craft), and equipment and consumable costs, ensures that essential elements have not been omitted. Appendix A presents the detailed development of a typical unit factor. Appendix B provides the values contained within one set of factors developed for this analysis.
The inventory was also organized according to its proposed disposition. There were three primary waste streams identified for the Cooper inventory: (1) clean material (expected to meet the release criteria without any decontamination),
(2) contaminated material with recovery potential or requiring additional processing for disposal (expected to be sent to an off-site waste processor), and (3) contaminated material designated for direct disposal at a controlled low-level radioactive waste disposal site (i.e., material expected to exceed waste processor acceptance criteria or uneconomical to process).
An activity duration critical path was used to determine the total decommissioning program schedule. This is required for calculating the carrying costs, which include program management, administration, field engineering, equipment rental, quality assurance, and security. This systematic approach for assembling decommissioning estimates ensures a high degree of confidence in the reliability of the resulting costs.
This analysis reflects lessons learned from TLG's involvement in the Shippingport Station decommissioning, completed in 1989, as well as the decommissioning of the Cintichem reactor, hot cells, and associated facilities, completed in 1997. In addition, the planning and engineering for the Pathfinder, Shoreham, Rancho Seco, Trojan, Yankee Rowe, Big Rock Point, Maine Yankee, Humboldt Bay-3, Connecticut Yankee, and San Onofre-1 nuclear units have provided additional insight into the process, the regulatory aspects, and the technical challenges of decommissioning commercial nuclear units.
Work Difficulty Factors TLG has historically applied work difficulty adjustment factors (WDFs) to account for the inefficiencies in working in a power plant environment. WDFs are assigned to each unique set of unit factors, commensurate with the working conditions. The ranges used for the WDFs are as follows:
TLG Services, Inc.
 
CooperNuclear Station                                    DocumentN01-1590-002, Rev. 1 Decommissioning CostAnalysis                                      Section 3, Page3 of 29 o  Access Factor                                    0% to 30%
        " Respiratory Protection Factor                      0% to 50%
o Radiation/ALARA Factor                            0% to 100%
* Protective Clothing Factor                          0% to 50%
o Work Break Factor                                      8.33%
The factors and their associated range of values were originally developed in conjunction with the AIF/NESP-036 study. The factors (and their suggested application) are discussed in more detail in Appendix E.
Scheduling Program Durations Area activity durations are used to develop the total decommissioning program schedule. The unit cost factors, adjusted for WDFs as described above, are applied against the inventory of materials to be removed in each defined work area. The work area is then evaluated for the most efficient number of workers/crews for the identified decommissioning activities. The adjusted unit cost factors are then compared against the available manpower so that an overall duration for removal of components and piping from each work area can be calculated.
The schedule is used to assign carrying costs, which include program management, administration, field engineering, equipment rental, and support services such as quality control and security.
3.3 FINANCIAL COMPONENTS OF THE COST MODEL TLG's proprietary decommissioning cost model, DECCER, produces a number of distinct cost elements. These direct expenditures, however, do not comprise the total cost to accomplish the project goal (i.e., license termination and site restoration).
Inherent in any cost estimate that does not rely on historical data is the inability to specify the precise source of costs imposed by factors such as tool breakage, accidents, illnesses, weather delays, and labor stoppages. In the DECCER cost model, contingency fulfills this role. Contingency is added to each line item to account for costs that are difficult or impossible to develop analytically. Such costs are historically inevitable over the duration of a job of this magnitude; therefore, this cost analysis includes funds to cover these types of expenses.
TLG Services, Inc.
 
Cooper NuclearStation                                    Document N01-1590-002, Rev. 1 DecommissioningCostAnalysis                                      Section 3, Page 4 of 29 3.3.1 Contingency The activity- and period-dependent costs are combined to develop the total decommissioning cost. A contingency is then applied on a line-item basis, using one or more of the contingency types listed in the AIF/NESP-036 study. "Contingencies" are defined in the American Association of Cost Engineers "Project and Cost Engineers' Handbook"[201 as "specific provision for unforeseeable elements of cost within the defined project scope; particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur." The cost elements in this analysis are based upon ideal conditions and maximum efficiency; therefore, consistent with industry practice, contingency is included. In the AIF/NESP-036 study, the types of unforeseeable events that are likely to occur in decommissioning are discussed and guidelines are provided for percentage contingency in each category. It should be noted that contingency, as used in this analysis, does not account for price escalation and inflation in the cost of decommissioning over the remaining operating life of the station.
Contingency funds are an integral part of the total cost to complete the decommissioning process. Exclusion of this component puts at risk a successful completion of the intended tasks and, potentially, subsequent related activities. For this study, TLG examined the major activity-related problems (decontamination, segmentation, equipment handling, packaging, transport, and waste disposal) that necessitate a contingency. Individual activity contingencies ranged from 10% to 75%,
depending on the degree of difficulty judged to be appropriate from TLG's actual decommissioning experience. The contingency values used in this study are as follows:
* Decontamination                                            50%
            "  Contaminated Component Removal                            25%
            "  Contaminated Component Packaging                          10%
            "  Contaminated Component Transport                          15%
o Low-Level Radioactive Waste Disposal                        25%
o  Reactor Segmentation                                      75%
* NSSS Component Removal                                    25%
o  Reactor Waste Packaging                                    25%
* Reactor Waste Transport                                    25%
o  Reactor Vessel Component Disposal                          50%
              "  GTCC Disposal                                              15%
TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                    Section 3, Page5 of 29 o    Non-Radioactive Component Removal                        15%
o Heavy Equipment and Tooling                                  15%
            " Supplies                                                    25%
            " Engineering                                                  15%
o Energy                                                      15%
o    Characterization and Termination Surveys                  30%
o Construction                                                15%
o Taxes and Fees                                              10%
o Insurance                                                    10%
o Staffing                                                    15%
The contingency values are applied to the appropriate components of the estimates on a line item basis. A composite value is then reported at the end of each detailed estimate (as provided in Appendices C and D).
3.3.2 Financial Risk In addition to the routine uncertainties addressed by contingency, another cost element that is sometimes necessary to consider when bounding decommissioning costs relates to uncertainty, or risk.
Examples can include changes in work scope, pricing, job performance, and other variations that could conceivably, but not necessarily, occur.
Consideration is sometimes necessary to generate a level of confidence in the estimate, within a range of probabilities. TLG considers these types of costs under the broad term "financial risk." Included within the category of financial risk are:
Transition activities and costs: ancillary expenses associated with eliminating 50% to 80% of the site labor force shortly after the cessation of plant operations, added cost for worker separation packages throughout the decommissioning program, national or company-mandated retraining, and retention incentives for key personnel.
Delays in approval of the decommissioning plan due to intervention, public participation in local community meetings, legal challenges, and national and local hearings.
Changes in the project work scope from the baseline estimate, involving the discovery of unexpected levels of contaminants, contamination in places not previously expected, contaminated soil previously undiscovered (either radioactive or hazardous material TLG Services, Inc.
 
CooperNuclear Station                                      Document N01-1590-002, Rev. 1 0 Decommissioning CostAnalysis                                        Section 3, Page6 of 29 contamination), variations in plant inventory or configuration not indicated by the as-built drawings.
            " Regulatory changes, for example, affecting worker health and safety, site release criteria, waste transportation, and disposal.
            " Policy decisions altering national commitments (e.g., in the ability to accommodate certain waste forms for disposition), or in the timetable for such, for example, the start and rate of acceptance of spent fuel by the DOE.
o Pricing changes for basic inputs such as labor, energy, materials, and disposal. Items subject to widespread price competition (such as materials) may not show significant variation; however, others such as waste disposal could exhibit large pricing uncertainties, particularly in markets where limited access to services is available.
It has been TLG's experience that the results of a risk analysis, when compared with the base case estimate for decommissioning, indicate that the chances of the base decommissioning estimate's being too high is a low probability, and the chances that the estimate is too low is a higher probability. This is mostly due to the pricing uncertainty for low-level radioactive waste burial, and to a lesser extent due to schedule increases from changes in plant conditions and to pricing variations in the cost of labor (both craft and staff). This cost study, however, does not add any additional costs to the estimate for financial risk, since there is insufficient historical data from which to project future liabilities. Consequently, the areas of uncertainty or risk are revisited periodically and addressed through repeated revisions or updates of the base estimates.
3.4 SITE-SPECIFIC CONSIDERATIONS There are a number of site-specific considerations that affect the method for dismantling and removal of equipment from the site and the degree of restoration required. The cost impact of the considerations identified below is included in this cost study.
3.4.1 Spent Fuel Management The cost to dispose the spent fuel generated from plant operations is not reflected within the estimates to decommission Cooper. Ultimate disposition of the spent fuel is within the province of the DOE's Waste Management System, as defined by the Nuclear Waste Policy Act. As such, the disposal cost is financed by a 1 mill/kWhr surcharge paid into TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002,Rev. 1 DecommissioningCost Analysis                                    Section 3, Page 7 of 29 the DOE's waste fund during operations. However, the NRC requires licensees to establish a program to manage and provide funding for the management of all irradiated fuel at the reactor site until title of the fuel is transferred to the Secretary of Energy. This funding requirement is fulfilled through inclusion of certain high-level waste cost elements within the estimates, as described below.
Completion of the decommissioning process is highly dependent upon the DOE's ability to remove spent fuel from the site. The timing for removal of spent fuel from the site is based upon the DOE's most recently published annual acceptance rates of 400 MTU/year for year 1, 3,800 MTU total for years 2 through 4 and 3,000 MTU/year for year 5 and beyond.[211 The DOE contracts provide mechanisms for altering the oldest fuel first allocation scheme, including emergency deliveries, exchanges of allocations amongst utilities and the option of providing priority acceptance from permanently shutdown nuclear reactors.
Because it is unclear how these mechanisms may operate once DOE begins accepting spent fuel from commercial reactors, this study assumes that DOE will accept spent fuel in an oldest fuel first order.
Morris Wet-Pool Storage Facility NPPD has 1,054 spent fuel assemblies from Cooper in storage at General Electric's wet-pool ISFSI in Morris, Illinois. This analysis assumes that this inventory is preferentially transferred to the DOE, starting in 2022. Completion of the transfer would be in year 2027. At that time, the transfer of spent fuel would be exclusively from the Cooper site.
ISFSI The ISFSI, constructed to support plant operations, will continue to operate throughout decommissioning, and beyond the termination of the operating license in the DECON decommissioning scenario, until such time that the transfer of spent fuel to the DOE can be completed.
Assuming that DOE commences repository operation in 2020, and Morris fuel is transferred first, spent fuel from the Cooper site is projected to be removed beginning in 2027. The process is expected to be completed by the year 2046 for a 2014 shutdown and year 2061 for a 2034 shutdown. The process is similar for the Delayed DECON and SAFSTOR scenarios; however, based upon the expected completion date for fuel transfer, the ISFSI will be emptied prior to the commencement of decommissioning operations.
TLG Services, Inc.
 
CooperNuclearStation                                        DocumentN01-1590-002, Rev. 1 Decommissioning Cost Analysis                                      Section 3, Page8 of 29 Operation and maintenance costs for the ISFSI are included within the estimate and address the cost for staffing the facility, as well as security, insurance, and licensing fees. The estimates include the costs to purchase, load, and transfer the fuel storage canisters. Costs are also provided for the final disposition of the facility once the transfer is complete.
Storage Canister Design The design and capacity of the ISFSI is based upon the NUHOMS system, with a 61 fuel assembly capacity. A unit cost of $785,000 is used for pricing the internal multi-purpose canister (MPC) and the horizontal concrete storage module.
Canister Loading and Transfer An average cost of $440,000 is used for the labor and equipment to seal each spent fuel canister once it is loaded and for the labor to transfer the spent fuel canister from the pool into a DOE transport cask or onto the ISFSI pad. For estimating purposes, 50% of this cost is used to estimate the cost to transfer the fuel from the ISFSI into a DOE transport cask.
Operations and Maintenance An annual cost (excluding labor) of approximately $746,000 and $85,000 are used for operation and maintenance of the spent fuel pool and the ISFSI, respectively. Pool operations are expected to continue approximately 51/2 years after the cessation of operations. ISFSI operating costs are based upon expectations of DOE performance, as described previously.
ISFSI Design Considerations A multi-purpose (storage and transport) dry shielded storage canister with a horizontal, reinforced concrete storage module is used as a basis for the cost analysis. The final core off load, equivalent to 8 modules, are assumed to have some level of neutron-induced activation as a result of the long-term storage of the fuel (i.e., to levels exceeding free-release limits). The steel support structure is assumed to be removed from these modules for controlled disposal. The cost of the disposition of this material, as well as the demolition of the ISFSI facility, is included in the estimates.
TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                      Section 3, Page9 of 29 GTCC The dismantling of the reactor internals generates radioactive waste considered unsuitable for shallow land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)).
The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste. Although there are strong arguments that GTCC waste is covered by the spent fuel contact with DOE and the fees being paid pursuant to that contract, DOE has taken the position that GTCC waste is not covered by that contract or its fees and that utilities will have to pay an additional fee for the disposal of their GTCC waste. However, to date, the federal government has not identified a cost for disposing of GTCC or a schedule for acceptance. As such, the GTCC radioactive waste has been packaged and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel.
For purposes of this study, GTCC is packaged in the same canisters used to store spent fuel. Disposal costs are based upon a cost equivalent to that envisioned for the spent fuel. It is not anticipated that the DOE would accept this waste prior to completing the transfer of spent fuel.
Therefore, until such time the DOE is ready to accept GTCC waste, it is reasonable to assume that this material would remain in storage with the spent fuel in the ISFSI at the Cooper site (for the DECON alternative). In the Delayed DECON and SAFSTOR scenarios, the GTCC material is shipped directly to a DOE facility as it is generated since the fuel has been removed from the site prior to the start of decommissioning and the ISFSI deactivated.
3.4.2 Reactor Vessel and Internal Components The reactor pressure vessel and internal components are segmented for disposal in shielded, reusable transportation casks. Segmentation is performed in the dryer-separator pool, where a turntable and remote cutter are installed. The vessel is segmented in place, using a mast-mounted cutter supported off the lower head and directed from a shielded work platform installed overhead in the reactor well.
Transportation cask specifications and transportation regulations dictate the segmentation and packaging methodology.
TLG Services, Inc.
 
CooperNuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                    Section 3, Page 10 of 29 Intact disposal of reactor vessel shells has been successfully demonstrated at several of the sites currently being decommissioned.
Access to navigable waterways has allowed these large packages to be transported to the Barnwell disposal site with minimal overland travel.
Intact disposal of the reactor vessel and internal components can provide savings in cost and worker exposure by eliminating the complex segmentation requirements, isolation of the GTCC material, and transport/storage of the resulting waste packages. Portland General Electric (PGE) was able to dispose of the Trojan reactor as an intact package (including the internals). However, its location on the Columbia River simplified the transportation analysis since:
* the reactor package could be secured to the transport vehicle for the entire journey, i.e., the package was not lifted during transport,
* there were no man-made or natural terrain features between the plant site and the disposal location that could produce a large drop, and
* transport speeds were very low, limited by the overland transport vehicle and the river barge.
As a member of the Northwest Compact, PGE had a site available for disposal of the package - the US Ecology facility in Washington State.
The characteristics of this arid site proved favorable in demonstrating compliance with land disposal regulations.
It is not known whether this option will be available when the Cooper unit ceases operation. Future viability of this option will depend upon the ultimate location of the disposal site, as well as the disposal site licensee's ability to accept highly radioactive packages and effectively isolate them from the environment. Consequently, the study assumes the reactor vessel will require segmentation, as a bounding condition.
With lower levels of activation, the vessel shell can be packaged more efficiently than the curie-limited internal components. This will allow the use of more conventional waste packages rather than shielded casks for transport (although some shielded casks are still required).
3.4.3 Primary System Components In the DECON scenario, the reactor recirculation system components are assumed to be decontaminated using chemical agents prior to the start of dismantling operations. This type of decontamination can be TLG Services, Inc.
 
CooperNuclear Station                                      Document N01-1590-002,Rev. 1 DecommissioningCost Analysis                                      Section 3, Page 11 of 29 expected to have a significant ALARA impact, since in this scenario the removal work is done within the first few years of shutdown. A decontamination factor (average reduction) of 10 is assumed for the process. Disposal of the decontamination solution effluent is included within the estimate as a "process liquid waste" charge. In the SAFSTOR scenario, radionuclide decay is expected to provide the same benefit and, therefore, a chemical decontamination is not included.
Reactor recirculation piping is cut from the reactor vessel once the water level in the vessel (used for personnel shielding during dismantling and cutting operations in and around the vessel) drops below the nozzle zone. The piping is boxed and shipped by shielded van. The reactor recirculation pumps and motors are lifted out intact, packaged, and transported for processing or disposal.
3.4.4 Main Turbine and Condenser The main turbine is dismantled using conventional maintenance procedures. The turbine rotors and shafts are removed to a laydown area. The lower turbine casings are removed from their anchors by controlled demolition. The main condensers are also disassembled and moved to a laydown area. Material is then prepared for transportation to an off-site recycling facility where it is surveyed and designated for either decontamination or volume reduction, conventional disposal, or controlled disposal. Components are packaged and readied for transport in accordance with the intended disposition.
3.4.5 Transportation Methods Contaminated piping, components, and structural material other than the highly activated reactor vessel and internal components will qualify as LSA-I, II or III or Surface Contaminated Object, SCO-I or II, as described in Title 49.[221 The contaminated material will be packaged in Industrial Packages (IP-1, IP-2, or IP-3, as defined in subpart 173.411) for transport unless demonstrated to qualify as their own shipping containers. The reactor vessel and internal components are expected to be transported in accordance with Part 71, as Type B. It is conceivable that the reactor, due to its limited specific activity, could qualify as LSA II or III. However, the high radiation levels on the outer surface would require that additional shielding be incorporated within the packaging so as to attenuate the dose to levels acceptable for transport.
TLG Services, Inc.
 
CooperNuclearStation                                      Document N01.1590-002, Rev. 1 DecommissioningCostAnalysis                                      Section 3, Page 12 of 29 Any fuel cladding failure that occurred during the lifetime of the plant is assumed to have released fission products at sufficiently low levels that the buildup of quantities of long-lived isotopes (e.g., l3 7 Cs, 9 0Sr, or transuranics) has been prevented from reaching levels exceeding those that permit the major reactor components to be shipped under current transportation regulations and disposal requirements.
Transport of the highly activated metal, produced in the segmentation of the reactor vessel and internal components, will be by shielded truck cask. Cask shipments may exceed 95,000 pounds, including vessel segment(s), supplementary shielding, cask tie-downs, and tractor-trailer. The maximum level of activity per shipment assumed permissible was based upon the license limits of the available shielded transport casks. The segmentation scheme for the vessel and internal segments is designed to meet these limits.
The transport of large intact components (e.g., large heat exchangers and other oversized components) will be by a combination of truck, rail, and/or multi-wheeled transporter.
Transportation costs for material requiring controlled disposal are based upon the mileage to the EnergySolutions facility in Clive, Utah.
Transportation costs for off-site waste processing are based upon the mileage to Memphis, Tennessee. Truck transport costs are estimated using published tariffs from Tri-State Motor Transit.[2 ]
3.4.6 Low-Level Radioactive Waste Conditioning and Disposal To the greatest extent practical, metallic material generated in the decontamination and dismantling processes is processed to reduce the total cost of controlled disposal. Material meeting the regulatory and/or site release criterion, is released as scrap, requiring no further cost consideration. Conditioning (preparing the material to meet the waste acceptance criteria of the disposal site) and recovery of the waste stream is performed off site at a licensed processing center. Any material leaving the site is subject to a survey and release charge, at a minimum.
The mass of radioactive waste generated during the various decommissioning activities at the site is shown on a line-item basis in the detailed Appendices C and D, and summarized in Section 5. The quantified waste summaries shown in these tables are consistent with 10 CFR Part 61 classifications. Commercially available steel containers are presumed to be used for the disposal of piping, small components, TLG Services, Inc.
 
CooperNuclear Station                                      Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                      Section 3, Page 13 of 29 and concrete. Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations. The volumes are calculated based on the exterior package dimensions for containerized material or a specific calculation for components serving as their own waste containers.
The more highly activated reactor components will be shipped in reusable, shielded truck casks with disposable liners. In calculating disposal costs, the burial fees are applied against the liner volume, as well as the special handling requirements of the payload. Packaging efficiencies are lower for the highly activated materials (greater than Type A quantity waste), where high concentrations of gamma-emitting radionuclides limit the capacity of the shipping canisters.
Disposal fees are based upon estimated charges, with surcharges added for the highly activated components, for example, generated in the segmentation of the reactor vessel. The cost to dispose of the majority of the material generated from the decontamination and dismantling activities is based upon the current cost for disposal at EnergySolutions facility in Clive, Utah. Disposal costs for the higher activity waste (Class B and C) were based upon the last published rate schedule for non-compact waste for the Barnwell facility (as a proxy).
3.4.7 Site Conditions Following Decommissioning The NRC will terminate (or amend) the site license if it determines that site remediation has been performed in accordance with the license termination plan, and that the terminal radiation survey and associated documentation demonstrate that the facility is suitable for release. The NRC's involvement in the decommissioning process ends at this point.
Building codes and state environmental regulations dictate the next step in the decommissioning process, as well as the owner's own future plans for the site.
Structures are removed to a nominal depth of three feet below grade.
Concrete rubble generated from demolition activities is processed and made available as clean fill. The Intake Structure is assumed to be removed back to the riverbank. The riverbank and the station grounds will be regraded such that the site will have a final contour consistent with adjacent surroundings, i.e., the configuration of the Missouri River levee will be maintained. The large underground tunnels between the water intake and Turbine Building will be isolated, sealed, and abandoned in place. Site utilities and service piping are abandoned in TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                    Section 3, Page 14 of 29 place. Electrical manholes are backfilled with suitable earthen material and abandoned. Asphalt surfaces in the immediate vicinity of site buildings are broken up and removed.
The existing electrical switchyard and access roads will remain in support of the electrical transmission and distribution system. The site access road will be left intact.
The estimates do not assume the remediation of any contaminated soil.
This assumption may be affected by continued plant operations and/or future regulatory actions, such as the development of site-specific release criteria.
3.5 ASSUMPTIONS The following assumptions were made in the development of the estimates for decommissioning the Cooper unit.
3.5.1 Estimating Basis The study follows the principles of ALARA through the use of work duration adjustment factors. These factors address the impact of activities such as radiological protection instruction, mock-up training, and the use of respiratory protection and protective clothing. The factors lengthen a task's duration, increasing costs and lengthening the overall schedule. ALARA planning is considered in the costs for engineering and planning, and in the development of activity specifications and detailed procedures. Changes to worker exposure limits may impact the decommissioning cost and project schedule.
3.5.2 Labor Costs The craft labor required to decontaminate and dismantle the nuclear unit is acquired through standard site contracting practices. The current cost of labor at the site is used as an estimating basis.
NPPD, as the licensee, will continue to provide site operations support, including decommissioning program management, licensing, radiological protection, and site security. A Decommissioning Operations Contractor (DOC) will provide the supervisory staff needed to oversee the labor subcontractors, consultants, and specialty contractors needed to perform the work required for the decontamination and dismantling effort. The DOC will also provide the engineering services needed to develop TLG Services, Inc.
 
CooperNuclear Station                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                    Section 3, Page 15 of 29 activity specifications, detailed procedures, detailed activation analyses, and support field activities such as structural modifications.
Personnel costs are based upon average salary information provided by NPPD. Overhead costs are included for site and corporate support, reduced commensurate with the staffing of the project.
Security, while reduced from operating levels, is maintained throughout the decommissioning for access control, material control, and to safeguard the spent fuel.
3.5.3 Design Conditions Any fuel cladding failure that occurred during the lifetime of the plant is assumed to have released fission products at sufficiently low levels that the buildup of quantities of long-lived isotopes (e.g., 137 Cs, 90 Sr, or transuranics) has been prevented from reaching levels exceeding those that permit the major NSSS components to be shipped under current transportation regulations and disposal requirements.
The curie contents of the vessel and internals at final shutdown are derived from those listed in NUREG/CR-3474.[ 241 Actual estimates are derived from the curie/gram values contained therein and adjusted for the different mass of the Cooper components, projected operating life, and different periods of decay. Additional short-lived isotopes were derived from CR-0130[251 and CR-0672,[ 261 and benchmarked to the long-lived values from CR-3474.
The disposal cost for the control blades removed from the vessel with the final core load is included within the estimates. Disposition of any blades stored in the pools from operations is considered an operating expense and therefore not accounted for in the decommissioning estimates.
Activation of the Reactor Building structures is confined to the area around the sacrificial shield. More extensive activation (at very low levels) of the interior structures within containment has been detected at several reactors and the owners have elected to dispose of the affected material at a controlled facility rather than reuse the material as fill on site or sending it to a landfill. The ultimate disposition of the material removed from the Reactor Building will depend upon the site release criteria applied, as well as the designated end use for the Site.
TLG Services, Inc.
 
CooperNuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 3, Page 16 of 29 3.5.4 General Transition Activities Existing warehouses are cleared of non-essential material and remain for use by NPPD and its subcontractors. The plant's operating staff performs the following activities at no additional cost or credit to the project during the transition period:
Drain and collect fuel oils, lubricating oils, and transformer oils for recycle and/or sale.
Drain and collect acids, caustics, and other chemical stores for recycle and/or sale.
Process operating waste inventories, i.e., the estimates do not address the disposition of any legacy wastes; the disposal of operating wastes during this initial period is not considered a decommissioning expense.
Scrap and Salvage The existing plant equipment is considered obsolete and suitable for scrap as deadweight quantities only. NPPD will make economically reasonable efforts to salvage equipment following final plant shutdown.
However, dismantling techniques assumed by TLG for equipment in this analysis are not consistent with removal techniques required for salvage (resale) of equipment. Experience has indicated that some buyers wanted equipment stripped down to very specific requirements before they would consider purchase. This required expensive rework after the equipment had been removed from its installed location. Since placing a salvage value on this machinery and equipment would be speculative, and the value would be small in comparison to the overall decommissioning expenses, this analysis does not attempt to quantify the value that an owner may realize based upon those efforts.
It is assumed, for purposes of this analysis, that any value received from the sale of scrap generated in the dismantling process would be more than offset by the on-site processing costs. The dismantling techniques assumed in the decommissioning estimates do not include the additional cost for size reduction and preparation to meet "furnace ready" conditions. For example, the recovery of copper from electrical cabling may require the removal and disposition of any contaminated insulation, an added expense. With a volatile market, the potential profit margin in TLG Services, Inc.
 
CooperNuclear Station                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                    Section 3, Page 17 of 29 scrap recovery is highly speculative, regardless of the ability to free release this material. This assumption is an implicit recognition of scrap value in the disposal of clean metallic waste at no additional cost to the project.
Furniture, tools, mobile equipment such as forklifts, trucks, bulldozers, and other property is removed at no cost or credit to the decommissioning project. Disposition may include relocation to other facilities. Spare parts are also made available for alternative use.
Energy For estimating purposes, the plant is assumed to be de-energized, with the exception of those facilities associated with spent fuel storage.
Replacement power costs are used to calculate the cost of energy consumed during decommissioning for tooling, lighting, ventilation, and essential services.
Insurance Costs for continuing coverage (nuclear liability and property insurance) following cessation of plant operations and during decommissioning are included and based upon current operating premiums. Reductions in premiums, throughout the decommissioning process, are based upon the guidance and the limits for coverage defined in the NRC's proposed rulemaking "Financial Protection Requirements for Permanently Shutdown Nuclear Power Reactors."[271 The NRC's financial protection requirements are based on various reactor (and spent fuel) configurations.
Taxes The only tax payment (or fee) included in the estimates is associated with the river levee maintenance costs.
Site Modifications The perimeter fence and in-plant security barriers will be moved, as appropriate, to conform to the Site Security Plan in force during the various stages of the project.
TLG Services, Inc.
 
CooperNuclearStation                                          Document N01-1590-002,Rev. 1 Decommissioning Cost Analysis                                        Section 3, Page 18 of 29 3.6 COST ESTIMATE
 
==SUMMARY==
 
Schedules of expenditures are provided in Tables 3.1 through 3.6. The tables delineate the cost contributors by year of expenditures as well as cost contributor (e.g., labor, materials, and waste disposal).
Decommissioning costs are reported in 2008 dollars. Costs are not inflated, escalated, or discounted over the period of expenditure (or projected lifetime of the plant). The schedules are based upon the detailed activity costs reported in Appendices C and D, along with the timelines presented in Section 4.
In the appendices, the cost elements are also assigned to one of three subcategories: "License Termination,.... Spent Fuel Management," and "Site Restoration." The subcategory "License Termination" is used to accumulate costs that are consistent with "decommissioning" as defined by the NRC in its financial assurance regulations (i.e., 10 CFR §50.75). The cost reported for this subcategory is generally sufficient to terminate the unit's operating license, recognizing that there may be some additional cost impact from spent fuel management.
The "Spent Fuel Management" subcategory contains costs associated with the construction of an ISFSI, the containerization and transfer of spent fuel to the ISFSI over the five and one-half years of post-shutdown pool operations, and the management of the ISFSI until such time that the transfer of all fuel from this facility to an off-site location (e.g., geologic repository) is complete.
    "Site Restoration" is used to capture costs associated with the dismantling and demolition of buildings and facilities demonstrated to be free from contamination. This includes structures never exposed to radioactive materials, as well as those facilities that have been decontaminated to appropriate levels. Structures are removed to a depth of three feet and backfilled to conform to local grade.
TLG Services, Inc.
 
CooperNuclear Station                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                  Section 3, Page19 of 29 TABLE 3.1 2014 DECON SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials    Energy    Burial      Other        Total 2014          47,079      9,874      1,016          87      7,982      66,039 2015          63,173    21,674        1,573      22,361    13,287      122,069 2016          49,998    21,848        1,004      41,033      9,480      123,362 2017          44,806    11,549          799      12,824      6,767      76,745 2018          44,806    11,549          799      12,824      6,767      76,745 2019          39,861    10,474          617      13,219      5,473      69,643 2020          25,445      3,467        181          49      2,123      31,266 2021          16,129      6,815        107          0      1,730      24,781 2022            9,078      3,166          44          0      1,764      14,052 2023            4,046        562          0          0      1,788        6,397 2024            4,057        564          0          0      1,793        6,414 2025            4,046        562          0          0      1,788        6,397 2026            4,046        562          0          0      1,788        6,397 2027            4,046        562          0          0      1,788        6,397 2028            4,057        564          0          0      1,793        6,414 2029            4,046        562          0          0      1,788        6,397 2030            4,046        562          0          0      1,788        6,397 2031            4,046        562          0          0      1,788        6,397 2032            4,057        564          0          0      1,793        6,414 2033            4,046        562          0          0      1,788        6,397 2034            4,046        562          0          0      1,788        6,397 2035            4,046        562          0          0      1,788        6,397 2036            4,057        564          0          0      1,793        6,414 2037            4,046        562          0          0      1,788        6,397 2038            4,046        562          0          0      1,788        6,397 2039            4,046        562          0          0      1,788        6,397 2040            4,057        564          0          0      1,793        6,414 2041            4,046        562          0          0      1,788        6,397 2042            4,046        562          0          0      1,788        6,397 2043            4,046        562          0          0      1,788        6,397 2044            4,057        564          0          0      1,793        6,414 2045            4,046        562          0          0      1,788        6,397 2046            4,061      1,334          0            1    10,384      15,779 TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                  Section 3, Page20 of 29 TABLE 3.1 (continued) 2014 DECON SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials    Energy    Burial      Other        Total 2047            1,819        868          0          68      1,597        4,352 439,379    115,564      6,141      102,465  108,509      772,058 TLG Services, Inc.
 
Cooper Nuclear Station                                      Document N01-1590-002, Rev. 1 Decommissio~ning Cost Analysis                                  Section 3, Page 21 of 29 TABLE 3.2 2014 Delayed DECON SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor      Materials    Energy      Burial      Other          Total 2014          38,591        9,434      1,016          87      7,982      57,111 2015          38,786      10,829          676        1,988      11,278      63,557 2016            12,446        5,991        214          62      3,851      22,564 2017            12,412        5,974        213          62      3,841      22,503 2018            12,412        5,974        213          62      3,841      22,503 2019            9,150        3,617        164          60      2,877      15,869 2020            5,297          824        107          58      1,739        8,025 2021            5,282          822        107            58      1,735        8,003 2022            5,282          822        107            58      1,735        8,003 2023            5,282          822        107            58      1,735        8,003 2024            5,297          824        107            58      1,739        8,025 2025            5,282          822        107            58      1,735        8,003 2026            5,282          822        107            58      1,735        8,003 2027            5,282          822        107            58      1,735        8,003 2028            5,297          824        107            58      1,739        8,025 2029            5,282          822        107            58      1,735        8,003 2030            5,282          822        107            58      1,735        8,003 2031            5,282          822        107            58      1,735        8,003 2032            5,297          824        107            58      1,739        8,025 2033            5,282          822        107            58      1,735        8,003 2034            5,282          822        107            58      1,735        8,003 2035            5,282          822        107            58      1,735        8,003 2036            5,297          824        107            58      1,739        8,025 2037            5,282          822        107            58      1,735        8,003 2038            5,282          822        107            58      1,735        8,003 2039            5,282          822        107            58      1,735        8,003 2040            5,297          824        107            58      1,739        8,025 2041            5,282          822        107            58      1,735        8,003 2042            5,282          822        107            58      1,735        8,003 2043            5,282          822        107            58      1,735        8,003 2044            5,297          824        107          .58      1,739        8,025 2045    1      5,282          822        1071          58      1,735        8,003 2046    1      5,360          824 1      109 158                1,732        8,082 TLG Services, Inc.
 
CooperNuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                  Section 3, Page22 of 29 TABLE 3.2 (continued) 2014 Delayed DECON SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials    Energy    Burial      Other        Total 2047          33,523      1,412      1,066          77        743      36,822 2048          43,779    15,439        1,042      16,243      6,546      83,049 2049          40,386    14,058          931      25,770      8,761      89,906 2050          39,158      6,342        799      15,542      3,274      65,116 2051          39,158      6,342        799      15,542      3,274      65,116 2052          24,949      3,036        221        819        759      29,785 2053          13,322      6,769        107          0          38      20,236 2054            7,993      4,062          64          0          23      12,141 508,866    121,495      10,408      77,874    103,957      822,600 TLG Services, Inc.
 
Cooper Nuclear Station                                      Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                    Section 3, Page 23 of 29 TABLE 3.3 2014 SAFSTOR SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials    Energy    Burial        Other          Total 2014            38,591      9,434      1,016          87      7,982        57,111 2015            38,786    10,829          676        1,988      11,278        63,557 2016            12,446      5,991        214          62      3,851        22,564 2017            12,412      5,974        213          62      3,841        22,503 2018            12,412      5,974        213          62      3,841        22,503 2019            9,150      3,617        164          60      2,877        15,869 2020            5,297        824        107          58        1,739        8,025 2021            5,282        822        107          58        1,735        8,003 2022            5,282        822        107          58        1,735        8,003 2023            5,282        822        107          58        1,735        8,003 2024            5,297        824        107          58        1,739        8,025 2025            5,282        822        107          58        1,735        8,003 2026            5,282        822        107          58        1,735        8,003 2027            5,282        822        107          58        1,735        8,003 2028            5,297        824        107          58        1,739        8,025 2029            5,282        822        107          58        1,735        8,003 2030            5,282        822        107          58        1,735        8,003 2031            5,282        822        107          58        1,735        8,003 2032            5,297        824        107          58        1,739        8,025 2033            5,282        822        107          58        1,735        8,003 2034            5,282        822        107          58        1,735        8,003 2035            5,282        822        107          58        1,735        8,003 2036            5,297        824        107          58        1,739        8,025 2037            5,282        822        107          58        1,735        8,003 2038            5,282        822        107          58        1,735        8,003 2039            5,282        822        107          58        1,735        8,003 2040            5,297        824        107          58        1,739        8,025 2041            5,282        822        107          58        1,735        8,003 2042            5,282        822        107          58        1,735        8,003 2043            5,282        822        107          58        1,735        8,003 2044            5,297        824        107          58        1,739        8,025 2045            5,282        822        107          58        1,735        8,003 2046            5,276        821        107          58        1,732        7,993 TLG Services, Inc.
 
Cooper Nuclear Station                                      Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                    Section 3, Page 24 of 29 TABLE 3.3 (continued) 2014 SAFSTOR SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
                          .Equipment &
Year          Labor      Materials    Energy    Burial        Other          Total 2047            3,063          249        107          56          671        4,146 2048            3,072          249        107          57          673        4,157 2049            3,063          249        107          56          671        4,146 2050            3,063          249        107          56          671        4,146 2051            3,063          249        107          56          671        4,146 2052            3,072          249        107          57          673        4,157 2053            3,063          249        107          56          671        4,146 2054            3,063          249        107          56          671        4,146 2055            3,063          249        107          56          671        4,146 2056            3,072          249        107          57          673        4,157 2057            3,063          249        107          56          671        4,146 2058            3,063          249        107          56          671        4,146 2059            3,063          249        107          56          671        4,146 2060            3,072          249        107          57          673        4,157 2061            3,063          249        107          56          671        4,146 2062            3,063          249        107          56          671        4,146 2063            3,063          249        107          56          671        4,146 2064            3,072          249        107          57          673        4,157 2065            3,063          249        107          56          671        4,146 2066            3,063          249        107          56          671        4,146 2067            3,063          249        .107          56          671        4,146 2068            25,078        1,070        801          72          725      27,745 2069            41,529      10,664      1,054        7,391        3,362      64,001 2070            40,733      17,502        981      30,409      11,019      100,644 2071            39,109        6,285        799      15,410        3,229      64,833 2072            39,216        6,303        802      15,453        3,238      65,011 2073            30,623        3,074        387        4,609        1,507      40,200 2074            13,962        6,534        112            3          72      20,683 2075            11,278        5,731          90            0          32      17,131
______        572,411      126,422      12,641      78,413      117,822      907,708 TLG Services, Inc.
 
Cooper Nuclear Station                                    Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                  Section 3, Page 25 of 29 TABLE 3.4 2034 DECON SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials    Energy    Burial      Other          Total 2034            44,992      3,613      1,016          87      7,982        57,690 2035            62,426    19,434        1,573      22,403      13,287      119,124 2036            49,346    19,889        1,004      41,120      9,480      120,838 2037            44,584    10,883          799      12,824      6,767        75,857 2038            44,584    10,883          799      12,824      6,767        75,857 2039            39,850    10,440          617      13,219      5,473        69,598 2040            25,569      3,838        181          49      2,142        31,779 2041            16,225      7,102        107            0      1,793      25,227 2042            9,093      3,211          44            0      1,790      14,139 2043            4,003        435          0            0      1,788        6,226 2044            4,014        436          0            0      1,793        6,243 2045            4,003        435          0            0      1,788        6,226 2046            4,003        435          0            0      1,788        6,226 2047            4,003        435          0            0      1,788        6,226 2048            4,014        436          0            0      1,793        6,243 2049            4,003        435          0            0      1,788        6,226 2050            4,003        435          0            0      1,788        6,226 2051            4,003        435          0            0      1,788        6,226
  .2052            4,014        436          0            0      1,793        6,243 2053            4,003        435          0            0      1,788        6,226 2054            4,003        435          0            0      1,788        6,226 2055            4,003        435          0            0      1,788        6,226 2056            4,014        436          0            0      1,793        6,243 2057            4,003        435          0            0      1,788        6,226 2058            4,003        435          0            0      1,788        6,226 2059            4,003        435          0            0      1,788        6,226 2060            4,014        436          0            0      1,793        6,243 2061            4,023      1,212          0            1    10,384        15,620 2062            2,269      1,080          0          75      1,664        5,088 415,076      99,415        6,141    102,601      99,739      722,972 TLG Services, Inc.
 
Cooper Nuclear Station                                    Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                  Section 3, Page 26 of 29 TABLE 3.5 2034 Delayed DECON SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials  Energy    Burial      Other          Total 2034            36,504      3,172      1,016          87      7,982      48,762 2035            38,173      8,992        676        1,988      11,278      61,108 2036            12,064      4,843        214          62      3,851      21,034 2037            12,031      4,830        213          62      3,841      20,977 20:38          12,031      4,830        213          62      3,841      20,977 2039            8,934      2,969        164          60      2,877      15,004 2040            5,276        763        107          58      1,739        7,944 2041            5,262        761        107          58      1,735        7,922 2042            5,262        761        107          58      1,735        7,922 2043            5,262        761        107          58      1,735        7,922 2044            5,276        763        107          58      1,739        7,944 2045            5,262        761        107          58      1,735        7,922 2046            5,262        761        107          58      1,735        7,922 2047            5,262        761        107.          58      1,735        7,922 2048            5,276        763        107          58      1,739        7,944 2049            5,262        761        107          58      1,735        7,922 2050            5,262        761        107          58      1,735        7,922 2051            5,262        761        107          58      1,735        7,922 2052            5,276        763        107          58      1,739        7,944 2053            5,262        761        107          58      1,735        7,922 2054            5,262        761        107          58      1,735        7,922 2055            5,262        761        107          58      1,735        7,922 2056            5,276        763        107          58      1,739        7,944 2057            5,262        761        107          58      1,735        7,922 2058            5,262        761        107          58      1,735        7,922 2059            5,262        761        107          58      1,735        7,922 2060            5,276        763        107          58      1,739        7,944 2061            5,339        763        109          58      1,732        8,001 2062            33,523      1,412      1,066          77        743      36,822 2063            43,666    15,393      1,039      17,523        6,519      84,140 2064            40,561    14,137        934      27,554        8,817      92,002 2065            39,319      6,395        799      15,559        3,313      65,385 2066            39,319      6,395        799      15,559        3,313      65,385 TLG Services, Inc.
 
CooperNuclearStation                                    Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                  Section 3, Page 27 of 29 TABLE 3.5 (continued) 2034 Delayed DECON SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year        Labor    Materials    Energy    Burial      Other        Total 2067        24,928        2,963        221        820        761        29,693 2068          13,393      6,872        107          0        38        20,410 2069          8,014      4,112          64          0        23        12,213
___            478,387    104,080        9,875      80,685    95,387      768,414 TLG Services, Inc.
 
Cooper Nuclear Station                                    Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                    Section 3, Page 28 of 29 TABLE 3.6 2034 SAFSTOR SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials    Energy    Burial      Other        Total 2034            36,504      3,172      1,016          87      7,982        48,762 2035            38,173      8,992        676        1,988      11,278        61,108 2036            12,064      4,843        214          62      3,851        21,034 2037            12,031      4,830        213          62      3,841        20,977 2038            12,031      4,830        213          62      3,841        20,977 2039            8,934      2,969        164          60      2,877        15,004 2040            5,276        763        107          58      1,739        7,944 2041            5,262        761        107          58      1,735        7,922 2042            5,262        761        107          58      1,735        7,922 2043            5,262        761        107          58      1,735        7,922 2044            5,276        763        107          58      1,739        7,944 2045            5,262        761        107          58      1,735        7,922 2046            5,262        761        107          58      1,735        7,922 2047            5,262        761        107          58      1,735        7,922 2048            5,276        763        107          58      1,739        7,944 2049            5,262        761        107          58      1,735        7,922 2050            5,262        761        107          58      1,735        7,922 2051            5,262        761        107          58      1,735        7,922 2052            5,276        763        107          58      1,739        7,944 2053            5,262        761        107          58      1,735        7,922 2054            5,262        761        107          58      1,735        7,922 2055            5,262        761        107          58      1,735        7,922 2056            5,276        763        107          58      1,739        7,944 2057            5,262        761        107          58      1,735        7,922 2058            5,262        761        107          58      1,735        7,922 2059            5,262        761        107          58      1,735        7,922 2060            5,276        763        107          58      1,739        7,944 2061            5,256        760        107          58      1,732        7,912 2062            3,063        249        107          56        671        4,146 2063            3,063        249        107          56        671        4,146 2064            3,072        249        107          57        673        4,157 2065            3,063        2491        107          56        671        4,146 2066            3,063        2491        107 156          1      671        4,146 TLG Services, Inc.
 
CooperNuclearStation                                      DocumentN01.1590-002, Rev. 1 DecommissioningCostAnalysis                                    Section 3, Page29 of 29 TABLE 3.6 (continued) 2034 SAFSTOR SCHEDULE OF TOTAL ANNUAL EXPENDITURES (thousands, 2008 dollars)
Equipment &
Year          Labor    Materials    Energy    Burial      Other        Total 2067            3,063        249        107          56        671        4,146 2068            3,072        249        107          57        673        4,157 2069            3,063        249        107          56        671        4,146 2070            3,063        249        107          56        671        4,146 2071            3,063        249        107          56        671        4,146 2072            3,072        249        107          57        673        4,157 2073            3,063        249        107          56        671        4,146 2074            3,063        249        107          56        671        4,146 2075            3,063        249        107          56        671        4,146 2076            3,072        249        107          57        673        4,157 2077            3,063        249        107          56        671        4,146 2078            3,063        249        107          56        671        4,146 2079            3,063        249        107          56        671        4,146 2080            3,072        249        107          57        673-      4,157 2081            3,063        249        107          56        671        4,146 2082            3,063        249        107          56        671        4,146 2083            3,063        249        107          56        671        4,146 2084            3,072        249        107          57        673        4,157 2085            3,063        249        107          56        671        4,146 2086            3,063        249        107          56        671        4,146 2087            3,063        249        107          56        671        4,146 2088            25,078      1,070        801          72        725      27,745 2089            41,651    10,681        1,054        7,544      3,410      64,340 2090            41,223    17,574          981      30,995      11,207      101,980 2091            39,269      6,326        799      15,413      3,257      65,064 2092            39,376      6,343        802      15,456      3,266      65,243 2093            30,670      3,086        387        4,610      1,515      40,268 2094            13,995      6,615        112            3        72      20,796 2095            11,307      5,802          90            0        32      17,231 557,843    110,367      12,641      79,152    112,799      872,803 TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                    Section 4, Page 1 of 22
: 4. SCHEDULE The schedules for the decommissioning scenarios considered in this analysis follow the general sequence presented in the AIF/NESP-036 study, with minor changes to reflect recent experience and site-specific constraints. In addition, the scheduling has been revised to reflect the spent fuel management plans described in Section 3.4.1.
Schedules or the individual sequence of activities for each scenario are presented in Figures 4.1 through 4.6. The schedules reflect the six scenarios identified in Section
: 2. The key activities listed in the schedules do not reflect a one-to-one correspondence with those activities in the detailed cost tables (shown in the Appendices C and D), but divide some activities for clarity and combine others for convenience. The schedule was prepared using "Microsoft Project Professional 2003" computer software. [28]
4.1 SCHEDULE ESTIMATE ASSUMPTIONS The schedules are generated using a precedence network and associated software. Activity durations are based upon the actual man-hour estimates calculated for each area (Appendix F). The schedules are assembled by sequencing the work areas, consider work crew availability and material access/egress. The following assumptions were made in the development of the decommissioning schedule(s).
o  The fuel handling area of the Reactor Building is isolated until such time that all spent fuel has been discharged from the spent fuel pool to the DOE and/or the ISFSI. Decontamination and dismantling of the fuel handling area is initiated once the pool is emptied (DECON scenarios).
      " All work (except vessel and internals removal) is performed during an 8-hour workday, 5 days per week, with no overtime.
      " Reactor and internals removal activities are performed by using separate crews for different activities working on different shifts, with a corresponding backshift charge for the second shift.
* Multiple crews work parallel activities to the maximum extent possible, consistent with optimum efficiency, adequate access for cutting, removal and laydown space, and with the stringent safety measures necessary during demolition of heavy components and structures.
TLG Services, Inc.
 
CooperNuclearStation                                    Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                    Section 4, Page 2 of 22 For plant systems removal, the systems with the longest removal durations in areas on the critical path are considered to determine the duration of the activity.
4.2 PROJECT SCHEDULE The period-dependent costs presented in Appendices C and D are based upon the durations developed in the various schedules for decommissioning.
Durations are established between several milestones in each project period; these durations are used to establish a critical path for the entire project. In turn, the critical path duration for each period is used as the basis for determining the period-dependent costs.
Scenario timelines are provided as Figures 4.2 and 4.3. Milestone dates are based on either a 2014 or 2034 shutdown. In all cases, the fuel pool is emptied approximately 5Y years after shutdown, with ISFSI operations continuing at the site until the DOE can complete the transfer of assemblies to its geologic repository.
TLG Services, Inc.
 
CooperNuclearStation                                                                          Document N01-1590-002 Rev. 1 DecommissioningCost Analysis                                                                          Section 4, Page3 of22 FIGURE 4.1 2014 DECON ACTIVITY SCHEDULE Cooper Nuclear Station 2014 hUlmOWn                                                                  -    I--
PLANTSHUTDOWN DATE- January 18, 2014 Wet Storage Delay 5 years. 6 months
                                                                                                  ....
                                                                                          .........
                                                                                            .
                                                                                                  ......
                                                                                                    ..
                                                                                                    .......
                                                                                                        .
                                                                                                  ........
                                                                                                  ...
                                                                          %-----  ----------------
                                                                                            ............
Preparaoton tar reactor vessel removal
                                                                                ------
                                                                                    --------
                                                                                        -----
Reactor vessel 8 internals Recirt Pumps and Piping
                                                                                            ----------
_-----
Drywell (Systems Pemoval)
TORUS
                                                                                                ...
                                                                                                  .........
                                                                                                      ............. I Clean Structures Demolition in support of systems removal Reactor 903 Elevation Reactor El 903 Areal Turbine 932 Elevation Main Turtine/Generator
                                                                                    ............
                                                                                        ..          ......
                                                                                                        ....
Turbine El 932 Areal Turbine El 932 Area2
                                                                                                              .......
                                                                                                                  ......
                                                                                                                      .....
Turbine El 932 Area3 Turbine 903 Elevation
                                                                                        ..........            ----
                                                                                                                  ---
                                                                                                                    ---
Main Condenser Dry fuel operations Fuel storage pool operations Muoti-Purpose Building Multi-Purpose Facility Mula-Purpose FacilityDECON APW Building
                                                                          ....
                                                                          ....        --    ..........
                                                                                          ------------
Augmented Radwaste El 929 Augmented RtoowasteEl 918 Augmented Racwaste El 903 Augmented Padwaste El 877 Augmented Radlwaste Decon Protected Area
                                                                                        ..................
                                                                                              ...
                                                                                                .            .....
                                                                                                                .....
Yard (contaminated structmures Dhwell Lner Reactor 859 Elevation
                                                                                                    ...........
Reactor El 859 Area2 Reactor El 859 Areal Reactor El 859 Area3 Reactor El 859 Area4 Reactor El 859 Area5 Reactor 903 Elevation Reactor El 903 Area2 Reactor El 903 Area3 Reactor El 903 Area4                                                                          v          V I
TLG Services, Inc.
 
CooperNuclear Station                          Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                        Section 4, Page4 of 22 FIGURE 4.1 2014 DECON ACTIVITY SCHEDULE (continued)
TLG Services, Inc.
 
CooperNuclear Station                                                              Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                              Section 4, Page5 of 22 FIGURE 4.1 2014 DECON ACTIVITY SCHEDULE (continued)
DESCRIPTION Y-6  IY-2  MY3  Ii17 IyU IY15 Y19
                                                                                          . Y23  1Y27 1Y31 Reactor 976 Elevation Reactor El 976 Areal ReactorEl976Areti2 Reactor 1001 Elevation Reactor El 1001 Areal PostFuelDECON Dry fuel operations Building demolitons, backlill and landscaping Demolition0fOtherStructures Demolition0f Turbine,  Cnntiol&ReactorBldg LantiscapeSite Per~oS 3c Fuel Storage Operallons &Snipping Peno Periotd 3d GTCC Snipping 3eISF5 Decontamnination
                                    ,..oo.  ,,*,,o.......                          ........        . !
Penod 3' ISFSI Site Restoration Epd ofProject July , 2047 TLG Services, Inc.
 
Cooper NuclearStation                                                                                          Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                                    Section 4, Page6 of 22 FIGURE 4.2 2014 Delayed DECON ACTIVITY SCHEDULE aECiFNlI                                          IYS        IY9    Y13  IY17        IY21        IY25      IY29              I Y3            !Y7        IY41 Plant Shutdown January 18, 2014 Pe0od 13Shutdown Through Transibon Period tOLimited DECON ACtroles Period lc Preparations for SAFS TOP Period 20 SAFS TOP Dormancy / Wet Fuel
                                                                ..........
:'. 1 Peirold 2 SAFSTOP Dormancy/ Dry Fuel 1
Period 2c SAFSTOI Donmancy / No Fuel Reactrvate Site
                                                                                                                    ..........
                                                                                . .....
                                                                            ....
Reconfigure plant                                                                                                                          ......
Site speotic decommissioning cost estimate submitted
                                                                          ----------
                                                                                -                                ..................
                                                                                                                            ..
Pecontgure plant (continued)
Prepare detailed worn procedures Decon NSSS                                                                                                                                            J
                                                                                                  ..... ........
Preparation for reactor vessel remroval Reactor vessel & internals Pecirc Pumps &Piping Orywell (Systems Removal)
TORUS                                                                                                                                                  0, Turbine 932 Elevation
                                                                                                          ....................
                                                                                                                            ...
Main Turnine/Generator Turbine El 932 Areal TurbIne El 932 Are32 I
Turbine El 932 Area3
                                                                                        ....
                                                                                          ..........
Turbine 903 Elevaton Main Condenser APW Building
                                                                                                                        .....
                                                                                                                          .........
Augmented Pactwaste EP 929 Areal Augmented Padoaste El 916 Arear Augmented Radwaste El 903 Arear Augmented Radwaste El 877 Areal Augmented Radwaste Decon Protected Area Yard (contaminated structures)
I4; , :ý " 7* ,1,      t, Drywell Liner Reactor 903 Elevaton
                                                                                                                                  .. .............. ... ..... .... h ........
Reactor El 903 Areal Reactor El 903 Area2 Reactor 859 Elevation Reactor El 859 Area2 Reactor El 859 Areal                                                                                                                  ------ -
                                                                                                                                                    --
Reactor El 859 Area,?
ReItrEl89Ira'Ii TLG Services, Inc.
 
CooperNuclearStation                                                            DocumentNO1-1590-OO Rev. 1 Decommissioning Cost Analysis                                                                            Section 4, Page 7 of 22 FIGURE 4.2 2014 Delayed DECON ACTIVITY SCHEDULE (continued)
)ESCRIPTION                          i    yl  I      y5          (r 113  IYl7 I 21    IY25                IY29                Y33          IY37      IY41 Reac~or E1u59 Area4 Reactor El 859Area5 Reactor 903 Elevation Reactor El 903 Area3
                                                                                  ...........                                        .......
Reactor El 903 Area4 Reactor 931 Elevation
                                                                                                                          .............  ...................
                                                                                                                                                    ........
Reactor El 931 Areal Reactor El 931 Area2 Reactor El 931 Area3 Reactor El 931 Areat
                                      ..........          .............
                                                                .......
Reactor El 931 Area5 Reactor 958 Elevation Reactor El 958 Areal Reactor El 958 Area2 Reactor El 958 Area3 Reactor 976 Elevation Reactor El 976 Areal
                                                                                                                                              ...I Reactor El 976 Area2 Reactor  t001Elevation Reactor El 1001Areal Post Fuel DECON Reactor Building DECON irhrip. 903 Flevatlnn Turbine El 903 Areal Turbine El 903 N.e32 Turbine El 903 Area3 Turbine El 903 Nea4                                                                                                                l "
                                              ---- -------                                    ..... .. ...
                                                                                                        . .. ...... .. ..... .. ... ........
Turbine 802 Elevation                                                                                                                    -      ... ... .... . .....
Turbine El 882 Areal Turbine El 882 Area2 Turbone El 82 Area3 Turbine Bl0g . DECON                                                                                                              a Control Bulding Control El 932 Areal
                                                                                                      ........i
                                                                                                        ..... ....... .......... ~ 1.            i ,,,..... .. .
Control El 918 Areal Control El 903 Areal 082 Areal Control El Radwaste Building RacW3ste El 949 Areal Racteraste El 934 Area2 Radwaste El 934 Areal Radwaste El 918 Areal Raclwaste El 918 Area2 Pactwaste El 918 Area3
                                                  ...........
Ractwaste El 903 Area3 Raitwaste El 903 Area2 TLG Services, Inc.
 
CooperNuclearStation                                                                                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                                                Section 4, Page8 of22 FIGURE 4.2 2014 Delayed DECON ACTIVITY SCHEDULE (continued) 3 DESCRIPTION                                                  YI        IY5        I9M        Iy1      IY17      Y21        !Y25          IY29    ]Y33    Y37  IY41 Ractwaste  El 903Areal Radw~aste  El .877Areal RadwasteEl 877Area2 Raileaste El 877Area3 Racreaste-DECON Multi-Purpose  Buldiog                                                    .          .                                                            .      :  .
Multi-Purpose Facilyit Multi-Purpose  FacilityDEC00 Protected Area Yad(emoians truturerstr)ue Uicense Terminated B8011dlgdem olrttons. tiacIk1l1and lanldscaping..      .......  .........    .......  .... ..  . . . ...  ... .....  .  . .......    .... . . .  .  ..
Demoltinounof Turoine. Control & Reactor 81dgs Landscape Site ieRestoraton Complete- August 8. 2r04e TLG Services, Inc.
 
CooperNuclearStation                                                                                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                                            Section 4, Page9 of 22 FIGURE 4.3 2014 SAFSTOR ACTIVITY SCHEDULE cecoluninNi                                                  T ooperNaucear Station 2034 Shutdown Plant Shutdown January 18, 2014 Period la Shutdown Through Transiion Perod lb ULmitedDECON Actir4es Perod Ic Preparations for SAFS TOP Period 2a SAFSTOR Dormancy I Wet Fuel Peirod 2b SAFSTOR Dormancy/ODi Fuel Period 2c SAFSTO: Dormancy / No Fuel Reactvate Site Date set at 1/18184
                                                                ...........
                                                                        .......
                                                                            ..........                            .......
                                                                                                                        .....                      ..
                                                                                                                                                    ........
51vr-  Lr-~vteý t'
                                                                ............
                                                                        ..........
                                                                                .....
                                                                                    ......              .....
                                                                                                          .....
                                                                                                            ...
                                                                                                              ............
                                                                                                                        ................
                                                                                                                                ...........
                                                                                                                                      .........
Reconfigure plant Site specific decommissioning cost estimate submitted
                                                                ........
                                                                    ..              .............  ........
                                                                                                        ......    -
                                                                                                              ...........
Pecoengure plant (continued)
Prepare detailed work procedures Decon NSSS
                                                                        ........
                                                                            .......              .......
                                                                                                      ....    ....
                                                                                                                ......
                                                                                                                      . ...... - ......
                                                                                                                            ......        -
                                                                                                                                    ........
                                                                                                                                          ..
Preparabon for reactor vessel removal Reactor vessel & internals Recirt Pumps &Piping Drwell (Systems Removal)
TORUS Tiriune 032 FlPiatinn Main Turbine/Generator Turbine E1932 Areal Turbine El 932 Area2 Turbine E1932 Area3
                                                                              ....  -
                                                                                ..........
Turbine 903 Elevation                                                                                                                ---- - - ----
Main Condenser ARW Building
                                                                          ....
                                                                            ..........            ......
Augmented Raomaste El 929 Areal Augmented Radtwaste El 918 Areal Augmented Ractwaste El 903 Areal Augmented Racwaste El 877 Areal Augmented Radwaste Decon                                                                                                                    I Protected Area Yard (contaminated structures)
                                                                                ......
                                                                                    ..........
                                                                                          ......
                                                                                              .                        .......
                                                                                                                            .....
Drywell Uner Reactor 903 Elevation Reactor El 903 Areal Reactor El 903 Area2 Reactor 859 Elevation Reactor El 859 Area2 Reactor El 859 Areal Reactor El 859 Area3 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                              Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                                                                          Section 4, Page 10 of22 FIGURE 4.3 2014 SAFSTOR ACTIVITY SCHEDULE (continued)
DESCRIPTION Y?          1Y5    IY9          IY13          IY17        IY21    1Y25    1(29      IY33        IY37    IY41        1'(45  1Y49  I Y53        1Y57    IY61 Reactor El 859 Areat                                                            ..-.
ReactorEl 859ArearO Reactor 903 Elevation Reactor El 903 Area3 Reactor El 903 Area4 Reactor 931 Elevation Reactor El 931 Areal Reactor El 931 Area2 Reactor El 931 Area3 Pe el. c o l9 8 A                          .. .. ........... ............. ..-------                                                        ...        ........                [...
Reactor El 931 Areat Reactor El 931 Are'a Reactor 958 Elevatl  ON RPeactor El 908 Areal Reactor El 908 Area2 Reactor El 908 Area3 Reactor976Elevation Reactor El 976 Areal Reactor El 976 Area2 Reactor1 Elev  Areatio PostFuelDECOR ReactorBuildingDECOR TIM-,0 9113Flevorio Turbine El903    Areat Tur**ne El 903 Area2 TurbineEl 903Ar003 Turbine El 903    irea4 Turbine882Elevat~on TurbinfeE01882  ArealI Tur*iane E1862 Nea2r I* a~iw s te B Uld
                                                            . ....
l .....
                                                                    *J                            . ..... . .. . .... .......      ...... .. .... ... .... .. ..  ..  . . .... .        .        ..... ........          ...
TurbilneEl1882 Area3 Turbine 8ldg9-DECOR    Nl ControlBuiling.
ControlEl 922Areal ControlEl 918Areal ControlEl 903Areal Control        Areal 901882                                                ....
RactwasteBuilding RaltwasateEl1949 Areal RactreasteEl 934Area2 Ractreaste El 934Areal Ractwaste  El 918Areal Rartwaste El 918Aea2 01l~~e l918 Area3 Radaraste 01903Nea33 Radineaste El1903Area2 0
TLG Services, Inc.
 
CooperNuclear Station                                                                                      Document N01-1590-002,Rev. 1 DecommissioningCost Analysis                                                                                        Section 4, Page 11 of 22 FIGURE 4.3 2014 SAFSTOR ACTIVITY SCHEDULE (continued)
DESCRIPTION Yl  IY5  IY9    1Y 13 JYl7 IY21  IY25 IY29 lY33 IY37 IY41 1Y45 IY49 Y53 Y57 Y61 Padwaste El 903 Areal MaI*-oste El -877neal RadtwaSteEl 877 Area2 Ractwaste El 877 Area3 Radreaste-DECON                                                                                                          1 MUlti-Purpose Facility[
Mutlr-Purpose Facility DEC ON Protected Area Yard (clean structures)
Intake License Termination Survey NRC Review License Terminated 60 yr after shutdown - January 18,.2074                                                    ......            ........
Building demoaitions, backfill and landscaping D emoliton of 010CerStructures Demolition of Turbine. Control &Reactor Elctgs Landscape Site Site Restoration Complete - ictooer 30, 2095              -
TLG Services, Inc.
 
CooperNuclear Station                          Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                        Section 4, Page 12 of 22 FIGURE 4.4 2034 DECON ACTIVITY SCHEDULE TLG Services, Inc.
 
CooperNuclearStation                                                                                DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                                Section 4, Page 13 of 22 FIGURE 4.4 2034 DECON ACTIVITY SCHEDULE (continued)
DESCRIPTION                                          Y-6      ]Y-2    IY*    IY?    IYll      IY15              IY19                IY23                IY27 IY31 Reactor~ec~
El 9903 Ar.-.-.-...-.-.---..
Areaa 3                                                                i    iiiiii!iiiiiiiiiiiiii~iiiiiiiiiiiii  -.-.-.-.--.-...-.
Reactor 931 Elevation Reactor El 931 Areal Reactor El 931 Area2                                                                    --------
Reactor El 931 Area3 Reactor938Elevation ReactorEl 938Areal ReactorEl 958Area2
                                                                                                ...
                                                                                            ......  . ..                                            .. .. ......      ..
                                                                                                                                                                      ..
ReactoreEl 9031  Neal Reactor El 958 Area3 Reactor BuillOlngDEC09                                            ""
r.rlne El 903 ,.ea2                                                    ..
TurbineC983 Elevation Tea -DErOuldng Poractoe  El 903E Area4 Reac-nte  8 Elevatron Turbirre  El 983 Area3 earatoe El 958 Areal Reactore El 958 Area2 Reacste El 958 Area3 urbainaste El 97Aneal Trbinase El903 Nreal Raurbaste El903 Area2 Trabiane82Elev877onel-Trbinte El 903 Area2
                                    ,.93          ...                  -n...
                                                                      ......  .. .....                                                  ..
                                                                                                                                        ... .
CoTuroln El 832Area3 Tuatroe El 903Area3 RtadwrasteElru934* Dealn RCoentro    El Ut8Neng PRoatec ted AEa14        Ae aeraite El 877AreaI                          c.....n          -ar
                                                                              ..            .tr.ct....
ard cnteEl 877Areas TLG Services, Inc.
 
CooperNuclearStation                                                                          DocumentN01.1590-002, Rev. 1 Decommissioning Cost Analysis                                                                      Section 4, Page 14 of 22 FIGURE 4.4 2034 DECON ACTIVITY SCHEDULE (continued)
IFOOPITIfN                                                I 11 -
Dry fuel operations I...........
                                                                                                              ...........
Fuel storage pool operations
                                                                                                            ......
                                                                                                                ............
Reactor 976 Elevation Reactor El 976 Areal I...........
                                                            .......... ......
Reactor El 976 Area2 Reactor 1001 Elevabon Reactor El 1001 Areal Post Fuel DECON Dry fuel operations p
ULcense Terminaton Survey NRC Review Dry fuel operations Building demolitions, backfill and landscaping Demoohton of Other Structures Demolition of Turbine. Control &Reactor Bldg Landscape SOte Period 3: Fuel Storage Operations &Shipping Period 3d GTCC Snipping
                                                                                          .........
                                                                                            ........
Period 3e ISFSI Decontamrnaton Period 3 ISFSI Site Pestoration End of ProjectJuly 1, X62                                                                                        4 TLG Services, Inc.
 
CooperNuclear Station                                                                                            DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                                      Section 4, Page 15 of 22 FIGURE 4.5 2034 Delayed DECON ACTIVITY SCHEDULE r                                                                                                      1
                                                                ýy-I    IY5        IY9        IY13        JY17          IY21        I Y25    IY29      IY33          i Cooper Nuclear Station 2034 Shutdown
                                                                                                                                                    ........
                                                                                                                                                        .......
                                                                                                                                                            ...  ----'I Plant Shutdowndanuary 18, 2034
                                                                                                      ...  - ..............
                                                                                                        ......
                                                                                                          ..        -.- ..........                -
                                                                                                                                                ......
Penod la Shutdown Through Transion
                                                                                                    ........
                                                                                                        .......
                                                                                                              ...............
                                                                                                                        ...... -
                                                                                                                            .....        ..........
Period I0 Limited Decon Activties Period Ic Preparations for SAFSTOR                              n Pelod 2a SAFSTOR Dormancy/Wet Fuel Peirod 21bSAFSTOR Dormancy/Dry Fuel Period 2c - N ot Used Reactriate Site Date set at 1/18154
                                                                                            ....
                                                                                                ...
                                                                                                  ......                                      ......
                                                                                                                                                  .......
                                                                                                          ...      ..
                                                                                                          ...............
                                                                                                                    ..............
                                                                                                                              ..............      ...............
                                                                                                                                                          ...
Reconftgure plant Site specific decormlssionlng cost estimate submitted Recontfgure plant (continued)
Prepare detailed worli procedures Decon NSSS
                                                                                                          .....
                                                                                                              .............                              ....
                                                                                                                                                            .......
                                                                                                                                                                .
Preparation for reactor vessel removal
                                                                                                  ...
                                                                                                    .........
Reactor vessel & internals Recirc Pumps &Piping Dryiell (Systems Removal)
                                                                            ................
TORUS
                                                                            ..........
                                                                                  ...
Turbine 932 Elevation Main Turbine/Generator Turbine El 932 Areal
                                                                                                                ........... ........
                                                                                                                                  ....
Turtine El 932 A/ea2 Turbine El 932 Area3 Turbine 903 Elevation Main Condenser ARW Building
                                                                                                                        ..........
                                                                                                                              ......
Augmented Radwaste El 929 AreaI Augmented Radeaste El 918 AreaI Augmented Paciarste El 903 Areal Augmented Radwaste El 877 Areal Augmented Ractwaste Decon Protected Area
                                                                                      .......
                                                                                          ...
Yard (contaminated struc tures)
                                                                            ...........
                                                                                                                              .......
                                                                                                                                  .....
                                                                                                                                      .
Drywell Lner Reactor 903 Elevation Reactor El 903 Areal Reactor El 903 Area2 Reactor 859 Elevation Reactor El 859 Area2 TLG Services, Inc.
 
CooperNuclearStation                                                                                DocumentN01-1590-002, Rev. 1 DecommissioningCostAnalysis                                                                                                Section 4, Page 16 of 22 FIGURE 4.5 2034 Delayed DECON ACTIVITY SCHEDULE (continued)
Pnrtor F! 909 Area I    I Reactor El 859 Area3 Reactor El 859 Area4 Reactor El 859 Area5 Reactor 903 Elevation Reactor El 903 Area3
                                                                                ... ...
                                                                                ....            ............
                                                                                                          ...
Reactor El 903 Area4
                                    .................
                                            ............                    .- - -- ..........
                                                                    .........
                                                                        ......
Reactor 931 El evareon Reactor El 931 Area]
                                  .......
                                    ..............                                  ..
                                                                                    ...... -
                                                                                        ........
Reactor El 931 Area2
                                              ............. ..                                            ...........
Reactor El 931 Area3 Reactor El 931 Area4 Reactor El 931 Area5 Reactor 958 Elevaton Reactor El 958 Areal
                                  ......................
                                            .....      ...........
                                                                  ...... .............                                  ............
Reactor El 958 Area2
                                                                                        ......................                ....                        ............
Reactor El 958 Area3
                                                                        - ..........
                                                                  ..........
                                                                        ..              ..... ............
                                                                                                    .....
Reactor 976 Elevation
                                          ...........
                                                  ..........                                                                        ..........
Reactor El 976 Areal
                                                      .............    ..      ................. ..............
                                                                        .........
                                                                              ..
Reactor El 976 Area2 Reactor 1001 Elevation Reactor El 1001 Areal
                                                                                        ......                      ...............                    ...... ....
                                                                                  ..........        ..........
Post Fuel DECON
                                                ...........                                            .........................
Reactor Building DECON
                                                                                        ........... ............        ........
                                                                                                                              ..
                                                                                                                              ............    ....  -
                                                                                                                                                  ..........
Turbine 903 Elevation
                                          ................-                                          ................................
                                                                                                                                    -..........              ......
Turbine El 903 Areal Turbine El 903 Area2 Turbine El 903 ANea3 Turbine El 903 Area4 Tu~rtlne 882 Elevation
                                                --- -------------------        ................
                                                                                              ..............            ...........
                                                                ---- ---------    -.............  ..........                      ..... ........
                                                                                                                                    ..........
Turbine El 882 Areal Turbine El 882 Area2 Turbine El 882 Area3 Turbine Bldg - DECON Control Building Control El 932 AreaI
                                                        ..........                                                                        ......
                                                                                                                                        .......
Control El 918 Areat
                                                                      .........
                                                                          ....
                                                                              ...
                                                                                .....
                                                                                    ....
                                                                                      ..............
                                                                                              ..............  ......
Control El 903 Areal
                                                                                                ........
                                                                                                    .........
Control El 882 Area I
                                                            ...........
                                                                .      ......
                                                                          ..........
                                                                                  ....                                                ............................
RoadwasteBuilding
                                                                                                                        .......
                                                                                                                            ........
Radwaste El 949 Areal Ractwaste El 934 Area2 Raowaste El 934 Areal Radwaste El 918 Areal TLG Services, Inc.
 
CooperNuclear Station                                                                          Document N01-1590-002,Rev. 1 Decommissioning Cost Analysis                                                                              Section 4, Page 17 of 22 FIGURE 4.5 2034 Delayed DECON ACTIVITY SCHEDULE (continued) iFOCOiDTifltJ                                                T
                                                                                    -    _______________        _____________
Radwaste El 9IiArea2 Radlwaste El 918 Area3
                                                                                            ---------------------
Radwaste El 903 Area3 Racteaste El 903 Area2 Pa3ctrwasteEl 903 Areal Radwaste El -877 Area1 Padwaste El 877 Area2 Radwaste El 877 Area3
                                                                                                          ..........
Pactwaste-DE CON Multi-Purpose Building Multi-Purpose Facility
                                                                                          .......
                                                                                              ....
                                                                                                ...........
Multi-Purpose Facility DECON Protected Area Yard (clean structures)
Intake Ucense Termination Survey
                                                                              .......
                                                                                ...                        . ...........
NRC Review ucense Terminated Building demolitions, backfill and landscaping Demolition of Oiler Structures Demolition of Turline. Control & PeactOr Slugs Landscape Site Site Restoration Complete - August P. 2069
_____________________________                              J____________            - ____________          - ____________
TLG Services, Inc.
 
CooperNuclearStation                                                                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                          Section 4, Page 18 of 22 FIGURE 4.6 2034 SAFSTOR ACTIVITY SCHEDULE
______                                                        V_____________
I11                                              49          ,
Ii
                                                                                                              -.- -- ...
                                                                                                                      ...
                                                                                                                        ....      ...............
                                                                                                                                          ..
Plant ShutdowneJanuary 18, 2034 Period la Shutdown Through Transicon Period    b imited DECON Acdtes Perod Ic Preparations for SAFSTOR
                                                                ............x........-
                                                                            .......
                                                                                  ..
                                                                                    ...
                                                                                    .....-....
                                                                                              ...
                                                                                                ....
                                                                                                  . ..
                                                                                                        -....
                                                                                                      ...
Pe0od 2a SAFSTOR Dormancy / Wet Fuel Peirod bSAFSTOR Dormancy/Dry Fuel Perod 2 SAFSTOR Dormancy /No Fuel Reactrvate Site Reconfigure plant Site specific decommissioning cost estimate sucmitted Reconfigure plant (conbnued)
                                                                                          ..
                                                                                  ..............
Prepare detailed work procedures Decon NSSS
                                                                          ............
Preparabon tor reactor vessel ren uval
                                                                              -------------
Reactor vessel &internals Recire Pumps &Piping Driwell (Systems Remov3l)
TORUS
                                                                            ...
                                                                              .......
Turbine 932 Elevabon Main Turoine/Generator
                                                                                  ---------------
                                                                                          -
Turbine El 932 Areal Turbine El 932 Area2 Turbine El 932 Area3 Turbine 903 Elevation Main Condenser ARW Building Augmented Radwaste El 929 Areat Augmented Padwaste El 918 Areal Augmented Racdaste El 903 Areal
                                                                          ....................
Augmented Raroaste El 877 Areal Augmented Pacwaste Decon Protected Area Yard (contaminated structures)
        ,£j it , tl:- ":r:-,r , It'r                                          ------ ------
Drywell Liner Reactor 903 Elevabon
                                                                                ---
                                                                                  -----------
                                                                                          ---      --
                                                                                                ------
                                                                                          ..........
Reactor El 903 Areal Reactor El 903 Area&
Reactor 059 Elevation Reactor El 859 Area2 TLG Services, Inc.
 
CooperNuclear Station                          DocumentN01-1590-002, Rev. 1 Decommissioning CostAnalysis                        Section 4, Page19 of 22 FIGURE 4.6 2034 SAFSTOR ACTIVITY SCHEDULE (continued)
TLG Services, Inc.
 
CooperNuclearStation                                                                                        Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                                          Section 4, Page20 of 22 FIGURE 4.6 2034 SAFSTOR ACTIVITY SCHEDULE (continued)
DESCRIPTION Y!    IY5  I Y9 IY13 IY17  IY21 IY25  1Y29 IY33 IY37 IY41 IY45 IY49 lY53  IY57  IY61 Radwaste El 918 Area2 Padw~aste  El 918Ate33 Racwaste El 903 Area3 Raiwaste El 903 Area2 Rad'waste El 903 Areal Radwaste El -877 Areal                                        i        .    ..        ..                                          .
Radwaste El 877 Area2 Rardwaste  El 877Area3I-Radwaste-DECON Mult-Purpose Building Mult-Purpose Facility Multi-urpose Faclity DECON Protected Area Yard (clean structures)
Intake License Termllation Survey NPC Review License Terminated 60 yr after shutdown - January 18,                              i 2094 Buildingdemolitions.
Bo~~ld~~og~
o ,,a molooos*~
                                            ,od a,o.
tiacllflll san landscaping
                                                                  . .. ... ...........  ..        .....
                                                                                                      ....                      1121
                                                                                                                                  .... iiiiii] ..
                                                                                                                                    .......
Demolition of Other Structures Demolition of Turtine. Control & Reactor Bl.gs Ltnesc ape Stee Site Restoration Comrplete  - Octoter 30. 2095 TLG Services, Inc.
 
0 CooperNuclear Station                                                                                                                                                            DocumentN01-1590-002, Rev. I DecommissioningCost Analysis                                                                                                                                                              Section 4, Page21 of 22 FIGURE 4.7 DECON TIMELINES SCENARIO 1                  1 Shutdown 2014          Y ISFS1with capacity of 50 casks Prompt Decommissioning ISFSI Operational Post - Decomrassionng ISFSI Operations I
2014 Decon        Part110Licens                                                                                                                                    ISFSIDemolition
                                                                                                                *rt 7* I i*n*
Part 72 License In          lb            2a        2b            2c          2e            3b          3c            3d          3e            3f        End 18-Jan-14    18-Jan-15    19-Jul-15  27-Jan-17      18-Jul-19    16-Dec-19    15-Sep-20    06-Jun-22    17-Dec-46    31-Dec-46    01-May-47    02-Jul-47 Sub Period Duratin            1.0        0.50            1.5        2.5          0.41        0.75            1.7      24.53          0.04        0.33        0.17 Elapsed Time                                1.5          3.0        5.5          5.9          6.7            8.4        32.9          33.0        33.3        33.5 SCENARIO 4
S  Shutdown 2034 Prompt Decommissioning ISFSI Operational                          F          Post - Decommissioning ISFSI Operations ISFSI with capacjty of 79 casks T  f 2034 Decon        iP'aar  uLinwn                                                                      7 Part 72 License                                                  ISFSI Deioittion la            lb          2a        2b            2c          2e            3b          3c            3d          30            3f        End 18-Jan-34    18-Jan-35    19-Jul-35  27-Jan-37      18-Jul-39    16-Dec-39    15-Sep-40    06-Jun-42    17-Dec-61    31-Dec-61    01-May-62    02-Jul-62 Sub Period Duration            1.0        0.50            1.5        2.5          0.41        0.75            1.7      19.53          0.04        0.33        0.17 Elapsed Time                                1.5          3.0        5.5          5.9          6.7            8.4        27.9          28.0        28.3        28.5 TLG Services, Inc.
 
CooperNuclear Station                                                                                                                                                                                  Document N01-1590-002, Rev. I Decomnmissoning Cost Analysis                                                                                                                                                                                    Section 4, Page 22 of 22 FIGURE 4.8 DELAYED DECON and SAFSTOR TIMELINES I
SCENARIO                                                                                            Wet & Dry Fue Doo-acoy ISFSI Ope*..onal                                    Delayed Decomnisng 2
2014 Delayed      ISPSIoeth caoy, of 50 canE,                                                                                                                                                          iSFSI DeoIo4bo De-o-        Part 50 U~oln 1l                                lb              1C          2a                                                3a        3b        4a          4b          40          5b        End 184Jon-14                          18-J-n15      18-Ap-15      18-Jui-t5                18-Jul.19    31-D.,-46 31-Dec-46 31-D.-47  01-Juo48    14-Aul.49    18-Jan-52  20-Ot-52    08-Aug-54 db S0b PenKt DOat              10                              025            025            40                      2746                    100      050      1 12        243          0.75        180 Elapsed T.e.                                                    12            15          55                      330                    339      34.5      356          380          388        40.6 SCENARIO I
Delayed Demo:nosnlng 3                                  201                                                    Opetbott0 SF51--                        Dottony tSFSIOn8tc~,onty of 500mb.                                                                                                                                                            ISFSI Demotbon 2014 Safator    P8,150 L.o.nn lb              1C          2a                        2b            2c        30        3b        4a          4b          4e          5b        End 18-J-n-14                          18-Jon-I15    l-_Aor-l5    18-JuO-15                18-Ju-19      31-Dec-46 12-Aprt-8 12-Apr-09 12-Oct-6S    08-Nov-70    19-Apt-73  18-Jan-74    06-Nov-75 Sub Pew Donsod                10                              0.25          0.25          40                      2746          21 28      1.00      050      107          2.44        0.75        1.80 Elapsed Time                                                    12            1S5          5.5                      33.0          54.2      552      557      50.0        59.2        600        61.8 SCENARIO                Stloidoon                                f.p*ast Wet & Dry Fuel Ontn80y 2034                            Sal                                                                                              Delayed Deco.      -Vnooo 5                                                                                f                ISFSI Opte~aSorl 2O34          "hfe-Oto9age IOPSI W405  caao~ty of 79 0885.
2034 Dedayed                                                                                                                                                                                              ISFSI D*0-loh De-o,        POti 50 Uo.nn 18                                lb              1C          28                        25                      38        3b        48          4b          48          5b End 18-Jan-34                          18-Jan-35      18-Apr-35    18-Jui-35                18-Jul_39              31-Dec-61 31-Dec-62 02-J1.-63    14-Aug-,4    1.-Jan-7  21-Oct.67 08-Au-69 Sub P'iod Doa1-on            10                              0.25          0.25          4.0                    2246                      10      0.50      1 12        2.43        0.75      1.80 ElapsedTime                                                      12            15          55                      280                    290      29.5      306          33.0        33.8      3&6 SCENARIO Delayed Decotmmeconito
                          ,.SF04    capotlyof 79 cas5s                                                                                                                                                      ISFSI Demolbon 203458.0        P8,50Ucn 18                                1b              10                                    2b            20        38        3b        4a          4b          40          5b        End 18-Jan-34                          18-Jar-35      18-Apr-35    18-Jt-35                  18-Jul-39    31-Dec-61 12-Aprt-8 12-Apt-8  12-Oct-89  08-No-90      19-Apt-93  18-Ja-94    06-Nov-95 Sub Petiod Durtoon            10                              0.25          025            40                      2246          2628      1.00      050      107          2.44        0.75      1580 Elapoed Teme                                                    12            15          55                      280          542      852      557      568          59.2        60.0      619 TLG Services, Inc.
 
CooperNuclear Station                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                        Section 5, Page1 of 9
: 5. RADIOACTIVE WASTES The objectives of the decommissioning process are the removal of all radioactive material from the site that would restrict its future use and the termination of the NRC license. This currently requires the remediation of all radioactive material at the site in excess of applicable legal limits. Under the Atomic Energy Act,[2 91 the NRC is responsible for protecting the public from sources of ionizing radiation. Title 10 of the Code of Federal Regulations delineates the production, utilization, and disposal of radioactive materials and processes. In particular, Part 71 defines radioactive material as it pertains to transportation and Part 61 specifies its disposition.
Most of the materials being transported for controlled burial are categorized as Low Specific Activity (LSA) or Surface Contaminated Object (SCO) materials containing Type A quantities, as defined in 49 CFR Parts 173-178. Shipping containers are required to be Industrial Packages (IP-1, IP-2 or IP-3, as defined in 10 CFR
§173.411). For this study, commercially available steel containers are presumed to be used for the disposal of piping, small components, and concrete. Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations.
The volumes of radioactive waste generated during the various decommissioning activities at the site are shown on a line-item basis in Appendices C and D, and summarized in Tables 5.1 through 5.7. The quantified waste volume summaries shown in these tables are consistent with Part 61 classifications. The volumes are calculated based on the exterior dimensions for containerized material and on the displaced volume of components serving as their own waste containers.
The reactor vessel and internals are categorized as large quantity shipments and, accordingly, will be shipped in reusable, shielded truck casks with disposable liners.
In calculating disposal costs, the burial fees are applied against the liner volume, as well as the special handling requirements of the payload. Packaging efficiencies are lower for the highly activated materials (greater than Type A quantity waste),
where high concentrations of gamma-emitting radionuclides limit the capacity of the shipping canisters.
No process system containing/handling radioactive substances at shutdown is presumed to meet material release criteria by decay alone (i.e., systems radioactive at shutdown will still be radioactive over the time period during which the decommissioning is accomplished, due to the presence of long-lived radionuclides).
While the dose rates decrease with time, radionuclides such as 13 7Cs will still control the disposition requirements.
TLG Services, Inc.
 
CooperNuclearStation                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                        Section 5, Page2 of 9 The waste material produced in the decontamination and dismantling of the nuclear units is primarily generated during Period 2 of DECON and Period 4 of SAFSTOR. Material that is considered potentially contaminated when removed from the radiological controlled area is sent to processing facilities in Tennessee for conditioning and disposal. Heavily contaminated components and activated materials are routed for controlled disposal. The disposal volumes reported in the tables reflect the savings resulting from reprocessing and recycling.
For purposes of constructing the estimates, the cost for disposal at the EnergySolutions facility was used as a proxy for future disposal facilities. Separate rates were used for containerized waste and large components. Demolition debris including miscellaneous steel, scaffolding, and concrete was disposed of at a bulk rate. The decommissioning waste stream also included resins and dry active waste.
Since EnergySolutions is not currently able to receive the more highly radioactive components generated in the decontamination and dismantling of the reactor, disposal costs for the Class B and C material were based upon the last published rate schedule for non-compact waste for the Barnwell facility (as a proxy).
Additional surcharges were included for activity, dose rate, and/or handling added as appropriate for the particular package.
TLG Services, Inc.
 
CooperNuclearStation                                            Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                Section 5, Page3 of 9 TABLE 5.1 DECOMMISSIONING WASTE
 
==SUMMARY==
 
Decommissioning Scenario 1          2          3          4            5          6 Waste      Waste      Waste        Waste      Waste      Waste Class    Volume    Volume      Volume      Volume      Volume      Volume Waste Stream                  [1]        (ft3)      (ft3)      (ft3)      (ft3)        (ft3)      (ft3)
Low-Level Radioactive        A        233,906    207,449    277,370      234,031    199,891    227,217 Waste (near-surface disposal)                    B          3,877      1,377      1,377      3,647        4,111      1,252 C              976        344        344      1,205          470        470 Fmq m 1.                            t          I                      I          1-          -t          1 FGreater than Class C (geologic repository)      GTCC            508        508        508        508          508        508 Processed/Conditioned (off-site recycling center)                      A        319,826    384,277    384,676      319,826    384,277    384,676 Total  [2]                            559,092    593,956    614,276      559,217    589,257    614,123
[Il  Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55
[2]  Columns may not add due to rounding.
TLG Services, Inc.
 
CooperNuclearStation                                            Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                              Section 5, Page4 of 9 TABLE 5.2 2014 DECON DECOMMISSIONING WASTE
 
==SUMMARY==
 
Waste Volume            Mass Waste                Cost Basis      Class [1]  (cubic feet)        (pounds)
Low-Level Radioactive          EnergySolutions        A            233,906        17,533,514 Waste (near-surface disposal)                          Barnwell          B                3,877          505,964 Barnwell          C                  976          68,415 Greater than Class C              Spent Fuel (geologic repository)            Equivalent        GTCC                  508          89,497 Processed/Conditioned              Recycling (off-site recycling center)        Vendors            A            319,826        13,449,330 Total [21                                                            559,092        31,646,720
[1]  Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55
[21  Columns may not add due to rounding.
TLG Services, Inc.
 
CooperNuclearStation                                            DocumentN01-1590-002, Rev. 1 Decommissioning Cost Analysis                                            Section 5, Page5 of 9 TABLE 5.3 2014 Delayed DECON DECOMMISSIONING WASTE
 
==SUMMARY==
 
Waste Volume          Mass Waste                Cost Basis      Class [1]  (cubic feet)        (pounds)
Low-Level Radioactive          EnergySolutions      A            207,449        12,564,095 Waste (near-surface disposal)                          Barnwell          B                1,377          166,192 Barnwell          C                  344          41,290 Greater than Class C              Spent Fuel (geologic repository)            Equivalent        GTCC                  508          89,497 Processed/Conditioned              Recycling (off-site recycling center)        Vendors            A            384,277        16,115,520 Total [21                                                            593,956        28,976,594 (Ul  Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55
['a  Columns may not add due to rounding.
0 TLG Services, Inc.
 
CooperNuclear Station                                          DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                              Section 5, Page6 of 9 TABLE 5.4 2014 SAFSTOR DECOMMISSIONING WASTE
 
==SUMMARY==
 
Waste Volume            Mass Waste                Cost Basis      Class [1]  (cubic feet)        (pounds)
Low-Level Radioactive          EnergySolutions        A            227,370        12,678,887 Waste (near-surface disposal)                          Barnwell            B                1,377          166,192 Barnwell            C                  344          41,290 Greater than Class C              Spent Fuel (geologic repository)            Equivalent        GTCC                  508          89,497 Processed/Conditioned              Recycling (off-site recycling center)        Vendors            A            384,676        16,159,800 Total [21                                                            614,276        29,135,666
[1]  Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55
[2]  Columns may not add due to rounding.
TLG Services, Inc.
 
CooperNuclearStation                                            DocumentN01-1590-002, Rev. 1 Decommissioning Cost Analysis                                              Section 5, Page 7 of 9 TABLE 5.5 2034 DECON DECOMMISSIONING WASTE
 
==SUMMARY==
 
Waste Volume            Mass Waste                Cost Basis      Class [1]  (cubic feet)        (pounds)
Low-Level Radioactive          EnergySolutions        A            234,031        17,535,998 Waste (near-surface disposal)                          Barnwell            B                3,647          477,867 Barnwell            C                1,205          96,512 Greater than Class C              Spent Fuel (geologic repository)            Equivalent        GTCC                  508          89,497 Processed/Conditioned              Recycling (off-site recycling center)        Vendors            A            319,826        13,449,330 Total [21                                                            559,217        31,649,204
[11  Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55
[21  Columns may not add due to rounding.
TLG Services, Inc.
 
CooperNuclearStation                                          Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                            Section 5, Page8 of 9 TABLE 5.6 2034 Delayed DECON DECOMMISSIONING WASTE
 
==SUMMARY==
 
Waste Volume            Mass Waste                Cost Basis      Class [1]  (cubic feet)        (pounds)
Low-Level Radioactive          EnergySolutions      A              199,891      12,233,558 Waste (near-surface disposal)                          Barnwell          B                4,111        444,306 Barnwell          C                  470          59,220 Greater than Class C              Spent Fuel (geologic repository)            Equivalent      GTCC                  508          89,497 Processed/Conditioned            Recycling (off-site recycling center)        Vendors            A            384,277      16,115,520 Total [2]                                                          589,257      28,942,101
[1]  Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55
[21  Columns may not add due to rounding.
TLG Services, Inc.
 
CooperNuclearStation                                          DocumentN01-1590-002, Rev. 1 Decommissioning Cost Analysis                                            Section 5, Page9 of 9 TABLE 5.7 2034 SAFSTOR DECOMMISSIONING WASTE
 
==SUMMARY==
 
Waste Volume            Mass Waste                Cost Basis      Class [I]  (cubic feet)        (pounds)
Low-Level Radioactive          EnergySolutions        A            227,217        12,679,105 Waste (near-surface disposal)                          Barnwell          B                1,252          148,262 Barnwell          C                  470          59,220 Greater than Class C              Spent Fuel (geologic repository)            Equivalent      GTCC                  508          89,497 Processed/Conditioned            Recycling (off-site recycling center)        Vendors            A            384,676        16,159,800 Total [21                                                          614,123        29,135,884
[1]  Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55
[21  Columns may not add due to rounding.
TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                      Section 6, Page 1 of 5
: 6. RESULTS The estimates described in this report are based on numerous fundamental assumptions, including regulatory requirements, project contingencies, low-level radioactive waste disposal practices, high-level radioactive waste management options, and site restoration requirements. The decommissioning scenarios assume continued operation of the station's spent fuel pool for a minimum of 51/2 years following the cessation of operations for continued cooling of the assemblies. An ISFSI will be used to safeguard the spent fuel, once sufficiently cooled, until such time that the DOE can complete the transfer of the assemblies to its repository.
The primary cost contributors, identified in Tables 6.1 and 6.2, are either labor-related or associated with the management and disposition of the radioactive waste.
Program management is the largest single contributor to the overall cost. The magnitude of the expense is a function of both the size of the organization required to manage the decommissioning, as well as the duration of the program. It is assumed, for purposes of this analysis, that NPPD will oversee the decommissioning program, using a DOC to manage the decommissioning labor force and the associated subcontractors. The size and composition of the management organization varies with the decommissioning phase and associated site activities.
However, once the operating license is terminated, the staff is substantially reduced for the conventional demolition and restoration of the site, and the long-term care of the spent fuel (for the DECON alternative).
As described in this report, the spent fuel pool will remain operational for a minimum of 51/2 years following the cessation of operations. The pool will be isolated and an independent spent fuel island created. This will allow decommissioning operations to proceed in and around the pool area. Over the 51/2-year period, the spent fuel will be packaged into transportable canisters for loading into a DOE-provided transport cask. The canisters will be stored in concrete modules at the ISFSI until the DOE is able to receive them. Dry storage of the fuel under a separate license provides additional flexibility in the event the DOE is not able to meet the current timetable for completing the transfer of assemblies to an off-site facility and minimizes the associated caretaking expenses.
The cost for waste disposal includes only those costs associated with the controlled disposition of the low-level radioactive waste generated from decontamination and dismantling activities, including plant equipment and components, structural material, filters, resins and dry-active waste. As described in Section 5, disposition of the low-level radioactive material required controlled disposal is at the EnergySolutions' facility. Highly activated components, requiring additional TLG Services, Inc.
 
CooperNuclearStation                                        DocumentN01-1590-002, Rev. 1 Decommissioning Cost Analysis                                        Section 6, Page2 of 5 isolation from the environment (GTCC), are packaged for geologic disposal. The cost of geologic disposal is based upon a cost equivalent for spent fuel.
A significant portion of the metallic waste is designated for additional processing and treatment at an off-site facility. Processing reduces the volume of material requiring controlled disposal through such techniques and processes as survey and sorting, decontamination, and volume reduction. The material that cannot be unconditionally released is packaged for controlled disposal at one of the currently operating facilities. The cost identified in the summary tables for processing is all-inclusive, incorporating the ultimate disposition of the material.
Removal costs reflect the labor-intensive nature of the decommissioning process, as well as the management controls required to ensure a safe and successful program.
Decontamination and packaging costs also have a large labor component that is based upon prevailing wages. Non-radiological demolition is a natural extension of the decommissioning process. The methods employed in decontamination and dismantling are generally destructive and indiscriminate in inflicting collateral damage. With a work force mobilized to support decommissioning operations, non-radiological demolition can be an integrated activity and a logical expansion of the work being performed in the process of terminating the operating license. Prompt demolition reduces future liabilities and can be more cost effective than deferral, due to the deterioration of the facilities (and therefore the working conditions) with time.
The reported cost for transport includes the tariffs and surcharges associated with moving large components and/or overweight shielded casks overland, as well as the general expense, e.g., labor and fuel, of transporting material to the destinations identified in this report. For purposes of this analysis, material is primarily moved overland by truck.
Decontamination is used to reduce the plant's radiation fields and minimize worker exposure. Slightly contaminated material or material located within a contaminated area is sent to an off-site processing center, i.e., this analysis does not assume that contaminated plant components and equipment can be decontaminated for uncontrolled release in-situ. Centralized processing centers have proven to be a more economical means of handling the large volumes of material produced in the dismantling of a nuclear unit.
License termination survey costs are associated with the labor intensive and complex activity of verifying that contamination has been removed from the site to the levels specified by the regulating agency. This process involves a systematic survey of all remaining plant surface areas and surrounding environs, sampling, isotopic analysis, and documentation of the findings. The status of any plant TLG Services, Inc.
 
CooperNuclear Station                                    DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 6C,Page3 of 5 components and materials not removed in the decommissioning process will also require confirmation and will add to the expense of surveying the facilities alone.
The remaining costs include allocations for heavy equipment and temporary services, as well as for other expenses such as regulatory fees and the premiums for nuclear insurance. While site operating costs are greatly reduced following the final cessation of plant operations, certain administrative functions do need to be maintained either at a basic functional or regulatory level.
TLG Services, Inc.
 
CooperNuclearStation                                              Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                                    Section 6, Page4 of 5 TABLE 6.1 COST
 
==SUMMARY==
 
2014 Cessation of Operations (thousands of 2008 dollars)
Delayed Cost Element                                            DECON            DECON            SAFSTOR Decontamination                                            12,832            18,547          18,399 Removal                                                    73,606            74,005          75,346 Packaging                                                  13,340              9,827          9,577 Transportation                                                8,571            6,672          6,346 Waste Disposal                                              75,482            43,839          44,260 Off-site Waste Processing                                  35,573            42,626          42,743 Program Management [1]                                    360,232          426,204        490,053 Corporate A&G                                              15,657            10,100          10,100 Spent Fuel Management [21                                  77,077            69,839          69,839 Insurance and Regulatory Fees                              53,616            62,853          76,914 Energy                                                        6,141          10,408          12,641 Characterization and Licensing Surveys                      16,568            16,568          16,568 Miscellaneous Equipment                                    23,364            31,112          34,923 Total [31                                                  772,058          822,600        907,708 Cost Element License Termination                                        506,078          475,790        674,963 Spent Fuel Management                                      231,584          309,463        195,398 Site Restoration                                            34,396            37,347        37,347 Total [3J                                                  772,058          822,600        907,708
[1] Includes engineering and security costs
[21 Excludes program management costs (staffing) but includes costs for spent fuel loading/packaging/spent fuel pool O&M and EP fees
[31 Columns may not add due to rounding TLG Services, Inc.
 
CooperNuclear Station                                                Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                    Section 6, Page5 of 5 TABLE 6.2 COST
 
==SUMMARY==
 
2034 Cessation of Operations (thousands of 2008 dollars)
Delayed Cost Element                                            DECON            DECON            SAFSTOR Decontamination                                              12,832          18,581          18,438 Removal                                                      74,270          74,184          76,329 Packaging                                                    13,342            9,820          9,871 Transportation                                                8,571            6,704          6,578 Waste Disposal                                                75,618          46,649          44,999 Off-site Waste Processing                                    35,573          42,626          42,743 Program Management [R1                                      340,929          400,786        479,929 Corporate A&G                                                15,657          10,100          10,100 Spent Fuel Management [21                                    53,484          47,535          47,535 Insurance and Regulatory Fees                                46,578          54,706          72,081 Energy                                                        6,141            9,875        12,641 Characterization and Licensing Surveys                        16,568          16,568          16,568 Mfiscellaneous Equipment                                      23,408          30,280          34,989 Total  [31                                                  722,972          768,414        872,803 Cost Element License Termination                                        506,207          476,185        676,510 Spent Fuel Management                                      182,368          254,881        158,945 Site Restoration                                              34,396            37,348        37,348 Total  [31                                                  722,972          768,414        872,803
[M1Includes engineering and security costs
[21 Excludes program management costs (staffing) but includes costs for spent fuel loading/packaging/spent fuel pool O&M and EP fees
[*3 Columns may not add due to rounding TLG Services, Inc.
 
CooperNuclear Station                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                      Section 7, Page1 of 3
: 7. REFERENCES
: 1. U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72, "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988
: 2. U.S. Nuclear Regulatory Commission, Regulatory Guide 1.159, "Assuring the Availability of Funds for Decommissioning Nuclear Reactors," October 2003
: 3. U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, "Radiological Criteria for License Termination"
: 4. U.S. Code of Federal Regulations, Title 10, Parts 20 and 50, "Entombment Options for Power Reactors," Advanced Notice of Proposed Rulemaking, Federal Register Volume 66, Number 200, October 16, 2001
: 5. U.S. Code of Federal Regulations, Title 10, Parts 2, 50 and 51, "Decommissioning of Nuclear Power Reactors," Nuclear Regulatory Commission, Federal Register Volume 61 (p 39278 et seq.), July 29, 1996
: 6.    "Nuclear Waste Policy Act of 1982 and Amendments," U.S. Department of Energy's Office of Civilian Radioactive Management, 1982
: 7. Testimony of Edward Sproat, Director, Office of Civilian Radioactive Waste Management, before a U.S. House of Representatives subcommittee on the status of Yucca Mountain, July 15, 2008
: 8. U.S. Code of Federal Regulations, Title 10, Part 50, "Domestic Licensing of Production and Utilization Facilities," Subpart 54 (bb), "Conditions of Licenses"
: 9.    "Low Level Radioactive Waste Policy Act," Public Law 96-573, 1980
: 10.  "Low-Level Radioactive Waste Policy Amendments Act of 1985," Public Law 99-240, 1986
: 11. Waste is classified in accordance with U.S. Code of Federal Regulations, Title 10, Part 61.55
: 12. U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, "Radiological Criteria for License Termination," Federal Register, Volume 62, Number 139 (p 39058 et seq.), July 21, 1997 TLG Services, Inc.
 
CooperNuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCostAnalysis                                      Section 7, Page 2 of 3
: 7. REFERENCES (continued)
: 13.  "Establishment of Cleanup Levels for CERCLA Sites with Radioactive Contamination," EPA Memorandum OSWER No. 9200.4-18, August 22, 1997
: 14. U.S. Code of Federal Regulations, Title 40, Part 141.16, "Maximum contaminant levels for beta particle and photon radioactivity from man-made radionuclides in community water systems"
: 15.  "Memorandum of Understanding Between the Environmental Protection Agency and the Nuclear Regulatory Commission: Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites," OSWER 9295.8-06a, October 9, 2002
: 16.  "Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM),"
NUREG/CR-1575, Rev. 1, EPA 402-R-97-016, Rev. 1, August 2000
: 17. T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986
: 18. W.J. Manion and T.S. LaGuardia, "Decommissioning Handbook,"                  U.S.
Department of Energy, DOE/EV/10128-1, November 1980
: 19.  "Building Construction Cost Data 2008," Robert Snow Means Company, Inc.,
Kingston, Massachusetts
: 20. Project and Cost Engineers' Handbook, Second Edition, p. 239, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, 1984
: 21. Civilian Radioactive Waste Management System Waste Acceptance System Requirements Document, Revision 5" (DOE/RW-0351) issued May 31, 2007
: 22. U.S. Department of Transportation, Title 49 of the Code of Federal Regulations, "Transportation," Parts 173 through 178, 2007
: 23. Tri-State Motor Transit Company, published tariffs, Interstate Commerce Commission (ICC), Docket No. MC-427719 Rules Tariff, March 2004, Radioactive Materials Tariff, February 2006 TLG Services, Inc.
 
Cooper NuclearStation                                      DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                        Section 7, Page3 of 3
: 7. REFERENCES (continued)
: 24. J.C. Evans et al., "Long-Lived Activation Products in Reactor Materials" NUREG/CR-3474, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. August 1984
: 25. R.I. Smith, G.J. Konzek, W.E. Kennedy, Jr., "Technology, Safety and Costs of Decommissioning a Reference Pressurized Water Reactor Power Station,"
NUREG/CR-0130 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. June 1978
: 26. H.D. Oak, et al., "Technology, Safety and Costs of Decommissioning a Reference Boiling Water Reactor Power Station," NUREG/CR-0672 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. June 1980
: 27.  "Financial Protection Requirements for Permanently Shutdown Nuclear Power Reactors," 10 CFR Parts 50 and 140, Federal Register Notice, Vol. 62, No. 210, October 30, 1997
: 28.    "Microsoft Project Professional 2003," Microsoft Corporation, Redmond, WA.
: 29.    "Atomic Energy Act of 1954," (68 Stat. 919)
TLG Services, Inc.
 
CooperNuclearStation                        Document N01-1590-002,Rev. 1 DecommissioningCost Analysis                    Appendix A, Page I of 4 APPENDIX A UNIT COST FACTOR DEVELOPMENT TLG Services, Inc.
 
CooperNuclearStation                                                  Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                  Appendix A, Page2 of 4 APPENDIX A UNIT COST FACTOR DEVELOPMENT Example:      Unit Factor for Removal of Contaminated Heat Exchanger < 3,000 lbs.
: 1.      SCOPE Heat exchangers weighing < 3,000 lbs. will be removed in one piece using a crane or small hoist. They will be disconnected from the inlet and outlet piping. The heat exchanger will be sent to the waste processing area.
: 2.      CALCULATIONS Activity          Critical Act    Activity                                                        Duration          Duration ID      Description                                                      (minutes)        (minutes)*
a      Remove insulation                                                    60                (b) b      Mount pipe cutters                                                  60                60 c      Install contamination controls                                      20                (b) d      Disconnect inlet and outlet lines                                    60                60 e      Cap openings                                                        20                (d) f      Rig for removal                                                      30                30 g      Unbolt from mounts                                                  30                30 h      Remove contamination controls                                        15                15 i      Remove, wrap, send to waste processing area                          60                60 Totals (Activity/Critical)                                          355              255 Duration adjustment(s):
  + Respiratory protection adjustment (25% of critical duration)                                64
  + Radiation/ALARA adjustment (14% of critical duration)                                      35 Adjusted work duration                                                                        354
  + Protective clothing adjustment (30% of adjusted duration)                                106 Productive work duration                                                                      460
  + Work break adjustment (8.33 % of productive duration)                                      38 Total work duration (minutes)                                                                498
                              *** Total duration = 8.30 hr ***
* alpha designators indicate activities that can be performed in parallel TLG Services, Inc.
 
CooperNuclear Station                                  Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                  Appendix A, Page3 of 4 APPENDIX A (continued)
: 3. LABOR REQUIRED Duration  Rate Crew                            Number          (hours)  ($/hr)        Cost Laborers                          3.00          8.300  $19.65        $489.29 Craftsmen                          2.00          8.300  $44.85        $744.51 Foreman                            1.00          8.300  $46.12        $382.80 General Foreman                    0.25          8.300  $47.12        $97.77 Fire Watch                        0.05          8.300  $19.67          $8.15 Health Physics Technician          1.00          8.300  $43.95        $364.79 Total Labor Cost                                                    $2087.31
: 4. EQUIPMENT & CONSUMABLES COSTS Equipment Costs                                                            none Consumables/Materials Costs
-Blotting paper 50 @ $0.45 sq ft (1}                                  $22.50
-Plastic sheets/bags 50 @ $0.13/sq ft {2}                                $6.50
  -Gas torch consumables 1 @ $8.02/hr x 1 hr (3}                          $8.02 Subtotal cost of equipment and materials                                $37.02 Overhead & profit on equipment and materials @ 16.00 %                    $5.74 Total costs, equipment & material                                      $42.76 TOTAL COST:
Removal of contaminated heat exchanger <3000 pounds:            $2,130.07 Total labor cost:                                                    $2,087.31 Total equipment/material costs:                                        $42.76 Total craft labor man-hours required per unit:                            60.59 TLG Services, Inc.
 
CooperNuclear Station                                  DocumentN01-1590-002, Rev. 1 Decommissioning Cost Analysis                                Appendix A, Page 4 of 4
: 5. NOTES AND REFERENCES
* Work difficulty factors were developed in conjunction with the Atomic Industrial    Forum's (now NEI) program to standardize nuclear decommissioning cost estimates and are delineated in Volume 1, Chapter 5 of the "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986.
* References for equipment & consumables costs:
: 1. McMaster-Carr, Item 7193T88, Spill Control
: 2. R.S. Means (2008) Division 01 56, Section 13.60-0200, page 20
: 3. R.S. Means (2008) Division 01 54 33, Section 40-6360, Reference-10
      " Material and consumable costs were adjusted using the regional indices for Lincoln, Nebraska.
TLG Services, Inc.
 
CooperNuclearStation                            Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                          Appendix B, Page1 of 7 APPENDIX B UNIT COST FACTOR LISTING (DECON: Power Block Structures Only)
TLG Services, Inc.
 
CooperNuclearStation                                          DocumentN01-1590.002, Rev. 1 DecommissioningCost Analysis                                      Appendix B, Page2 of 7 APPENDIX B DECON UNIT COST FACTOR LISTING (Power Block Structures Only)
Unit Cost Factor                                                          Cost/Unit($)
Removal  of clean  instrument and sampling tubing, $/linear foot                    0.26 Removal  of clean  pipe 0.25 to 2 inches diameter, $/linear foot                    2.59 Removal  of clean  pipe >2 to 4 inches diameter, $/linear foot                      3.97 Removal  of clean  pipe >4 to 8 inches diameter, $/linear foot                      8.81 Removal  of clean  pipe >8 to 14 inches diameter, $/linear foot                    16.12 Removal  of clean  pipe >14 to 20 inches diameter, $/linear foot                    20.96 Removal  of clean  pipe >20 to 36 inches diameter, $/linear foot                    30.84 Removal  of clean  pipe >36 inches diameter, $/linear foot                          36.64 Removal  of clean  valve >2 to 4 inches                                            56.13 Removal  of clean  valve >4 to 8 inches                                            88.12 Removal  of clean  valve >8 to 14 inches                                          161.25 Removal  of clean  valve >14 to 20 inches                                        209.60 Removal  of clean  valve >20 to 36 inches                                        308.39 Removal  of clean  valve >36 inches                                              366.43 Removal  of clean  pipe hanger for small bore piping                                17.53 Removal  of clean  pipe hanger for large bore piping                                58.45 Removal  of clean  pump, <300 pound                                              148.39 Removal  of clean  pump, 300-1000 pound                                          437.99 Removal  of clean  pump, 1000-10,000 pound                                      1,691.23 Removal  of clean  pump, >10,000 pound                                          3,269.60 Removal  of clean  pump motor, 300-1000 pound                                    184.32 Removal  of clean  pump motor, 1000-10,000 pound                                  704.73 Removal  of clean  pump motor, >10,000 pound                                    1,585.64 Removal  of clean  heat exchanger <3000 pound                                    908.50 Removal  of clean  heat exchanger >3000 pound                                  2,285.25 Removal  of clean feedwater heater/deaerator                                    6,439.66 Removal  of clean moisture separator/reheater                                  13,235.93 Removal  of clean tank, <300 gallons                                              190.93 Removal  of clean tank, 300-3000 gallon                                          602.49 Removal  of clean tank, >3000 gallons, $/square foot surface area                    5.37 TLG Services, Inc.
 
CooperNuclear Station .                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                        Appendix B, Page3 of 7 APPENDIX B DECON UNIT COST FACTOR LISTING (Power Block Structures Only)
Unit Cost Factor                                                            Cost/Unit($)
Removal of clean  electrical equipment, <300 pound                                  81.09 Removal of clean  electrical equipment, 300-1000 pound                            300.10 Removal of clean  electrical equipment, 1000-10,000 pound                          600.21 Removal  of clean  electrical equipment, >10,000 pound                            1,457.82 Removal  of clean  electrical transformer < 30 tons                              1,012.43 Removal  of clean  electrical transformer > 30 tons                              2,915.64 Removal  of clean  standby diesel generator, <100 kW                              1,034.12 Removal  of clean  standby diesel generator, 100 kW to 1 MW                      2,308.21 Removal  of clean  standby diesel generator, >1 MW                                4,778.47 Removal  of clean  electrical cable tray, $/linear foot                              7.57 Removal  of clean  electrical conduit, $/linear foot                                  3.31 Removal  of clean  mechanical equipment, <300 pound                                  81.09 Removal  of clean  mechanical equipment, 300-1000 pound                            300.10 Removal  of clean  mechanical equipment, 1000-10,000 pound                          600.21 Removal  of clean  mechanical equipment, >10,000 pound                            1,457.82 Removal  of clean  HVAC    equipment, <300 pound                                    81.09 Removal  of clean  HVAC    equipment, 300-1000 pound                                300.10 Removal  of clean  HVAC    equipment, 1000-10,000 pound                            600.21 Removal  of clean  HVAC    equipment, >10,000 pound                              1,457.82 Removal  of clean  HVAC    ductwork, $/pound                                          0.28 Removal  of contaminated    instrument and sampling tubing, $/linear foot            0.74 Removal  of contaminated    pipe 0.25 to 2 inches diameter, $/linear foot          10.42 Removal  of contaminated    pipe >2 to 4 inches diameter, $/linear foot            17.53 Removal  of contaminated    pipe >4 to 8 inches diameter, $/linear foot            30.13 Removal  of contaminated    pipe >8 to 14 inches diameter, $/linear foot            56.53 Removal  of contaminated    pipe >14 to 20 inches diameter, $/linear foot          67.65 Removal  of contaminated    pipe >20 to 36 inches diameter, $/linear foot          92.88 Removal  of contaminated    pipe >36 inches diameter, $/linear foot                109.76 Removal  of contaminated    valve >2 to 4 inches                                  225.71 Removal  of contaminated    valve >4 to 8 inches                                  275.44 TLG Services, Inc.
 
CooperNuclearStation                                        DocumentN01-1590-002, Rev. 1 Decommissioning CostAnalysis                                      Appendix B, Page 4 of 7 APPENDIX B DECON UNIT COST FACTOR LISTING (Power Block Structures Only)
Unit Cost Factor                                                          CostlUnit($)
Removal of contaminated  valve >8 to 14 inches                                  531.78 Removal of contaminated  valve >14 to 20 inches                                  675.48 Removal of contaminated  valve >20 to 36 inches                                  895.33 Removal of contaminated  valve >36 inches                                      1,064.12 Removal of contaminated  pipe hanger for small bore piping                        57.98 Removal of contaminated  pipe hanger for large bore piping                      175.66 Removal of contaminated  pump, <300 pound                                        474.63 Removal of contaminated  pump, 300-1000 pound                                  1,131.61 Removal of contaminated  pump, 1000-10,000 pound                              3,609.88 Removal of contaminated  pump, >10,000 pound                                  8,757.44 Removal of contaminated  pump motor, 300-1000 pound                              494.41 Removal of contaminated  pump motor, 1000-10,000 pound                        1,474.09 Removal of contaminated  pump motor, >10,000 pound                            3,326.88 Removal of contaminated  heat exchanger <3000 pound                            2,130.07 Removal of contaminated  heat exchanger >3000 pound                            6,206.46 Removal  of contaminated feedwater heater/deaerator                          15,545.56 Removal  of contaminated moisture separator/reheater                          33,630.07 Removal  of contaminated tank, <300 gallons                                      790.67 Removal  of contaminated tank, >300 gallons, $/square foot                        16.09 Removal  of contaminated electrical equipment, <300 pound                        362.30 Removal  of contaminated electrical equipment, 300-1000 pound                    899.95 Removal  of contaminated electrical equipment, 1000-10,000 pound              1,736.08 Removal  of contaminated electrical equipment, >10,000 pound                  3,557.00 Removal  of contaminated electrical cable tray, $/linear foot                      17.95 Removal  of contaminated electrical conduit, $/linear foot                          8.46 Removal  of contaminated mechanical equipment, <300 pound                        412.08 Removal  of contaminated mechanical equipment, 300-1000 pound                  1,027.95 Removal  of contaminated mechanical equipment, 1000-10,000 pound              1,985.03 Removal  of contaminated mechanical equipment, >10,000 pound                  3,557.00 Removal  of contaminated HVAC equipment, <300 pound                              412.08 TLG Services, Inc.
 
CooperNuclearStation                                        DocumentN01-1590-002, Rev. 1 DecommissioningCostAnalysis                                        Appendix B, Page 5 of 7 APPENDIX B DECON UNIT COST FACTOR LISTING (Power Block Structures Only)
Unit Cost Factor                                                          Cost/Unit($)
Removal of contaminated HVAC equipment, 300-1000 pound                          1,027.95 Removal of contaminated HVAC equipment, 1000-10,000 pound                      1,985.03 Removal of contaminated HVAC equipment, >10,000 pound                          3,557.00 Removal of contaminated HVAC ductwork, $/pound                                      1.13 Removal/plasma arc cut of contaminated thin metal components, $/linear in.          1.97 Additional decontamination of surface by washing, $/square foot                      3.85 Additional decontamination of surfaces by hydrolasing, $/square foot              21.10 Decontamination rig hook up and flush, $/ 250 foot length                      3,504.89 Chemical flush of components/systems, $/gallon                                    12.58 Removal of clean standard reinforced concrete, $/cubic yard                        53.52 Removal  of grade slab concrete, $/cubic yard                                    60.83 Removal  of clean concrete floors, $/cubic yard                                  254.88 Removal  of sections of clean concrete floors, $/cubic yard                      751.47 Removal  of clean heavily rein concrete w/#9 rebar, $/cubic yard                  77.08 Removal  of contaminated heavily rein concrete w/#9 rebar, $/cubic yard        1,154.71 Removal  of clean heavily rein concrete w/#18 rebar, $/cubic yard                104.43 Removal  of contaminated heavily rein concrete w/#18 rebar, $/cubic yard      1,523.99 Removal  heavily rein concrete w/#18 rebar & steel embedments, $/cubic yard 327.04 Removal  of below-grade suspended floors, $/cubic yard                          146.31 Removal  of clean monolithic concrete structures, $/cubic yard                  626.97 Removal of contaminated monolithic concrete structures, $/cubic yard            1,150.82 Removal of clean foundation concrete, $/cubic yard                                493.01 Removal of contaminated foundation concrete, $/cubic yard                      1,071.14 Explosive demolition of bulk concrete, $/cubic yard                                22.86 Removal of clean hollow masonry block wall, $/cubic yard                          56.99 Removal of contaminated hollow masonry block wall, $/cubic yard                  159.69 Removal of clean solid masonry block wall, $/cubic yard                            56.99 Removal of contaminated solid masonry block wall, $/cubic yard                    159.69 Backfill of below-grade voids, $/cubic yard                                        21.24 Removal of subterranean tunnels/voids, $/linear foot                              73.39 TLG Services, Inc.
 
CooperNuclearStation                                        Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                    Appendix B, Page6 of 7 APPENDIX B DECON UNIT COST FACTOR LISTING (Power Block Structures Only)
Unit Cost Factor                                                          Cost/Unit($)
Placement of concrete for below-grade voids, $/cubic yard                        112.21 Excavation of clean material, $/cubic yard                                          2.30 Excavation of contaminated material, $/cubic yard                                  24.06 Removal of clean concrete rubble (tipping fee included), $/cubic yard            174.10 Removal of contaminated concrete rubble, $/cubic yard                              16.10 Removal  of building by volume, $/cubic foot                                        0.23 Removal  of clean building metal siding, $/square foot                              0.60 Removal  of contaminated building metal siding, $/square foot                        1.87 Removal  of standard asphalt roofing, $/square foot                                  1.23 Removal  of transite panels, $/square foot                                          1.45 Scarifying contaminated concrete surfaces (drill & spall), $/square foot            8.02 Scabbling contaminated concrete floors, $/square foot                                4.06 Scabbling contaminated concrete walls, $/square foot                                10.43 Scabbling contaminated ceilings, $/square foot                                      35.09 Scabbling structural steel, $/square foot                                            3.70 Removal  of clean overhead crane/monorail < 10 ton capacity                      449.46 Removal  of contaminated overhead crane/monorail < 10 ton capacity              1,017.50 Removal  of clean overhead crane/monorail >10-50 ton capacity                  1,078.74 Removal  of contaminated overhead crane/monorail >10-50 ton capacity            2,442.15 Removal  of polar crane > 50 ton capacity                                      4,565.92 Removal  of gantry crane > 50 ton capacity                                    18,222.75 Removal  of structural steel, $/pound                                              0.15 Removal  of clean steel floor grating, $/square foot                                3.51 Removal  of contaminated steel floor grating, $/square foot                        7.70 Removal  of clean free standing steel liner, $/square foot                          8.05 Removal of contaminated free standing steel liner, $/square foot                    18.86 Removal of clean concrete-anchored steel liner, $/square foot                        4.02 Removal of contaminated concrete-anchored steel liner, $/square foot                21.87 Placement of scaffolding in clean areas, $/square foot                              11.97 Placement of scaffolding in contaminated areas, $/square foot                      16.37 TLG Services, Inc.
 
CooperNuclear Station                                  Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                Appendix B, Page 7 of 7 APPENDIX B DECON UNIT COST FACTOR LISTING (Power Block Structures Only)
Unit Cost Factor                                                      CostlUnit($)
Landscaping with topsoil, $/acre                                          19,274.92 Cost of CPC B-88 LSA box & preparation for use                            1,407.31 Cost of CPC B-25 LSA box & preparation for use                            1,235.45 Cost of CPC B-12V 12 gauge LSA box & preparation for use                  1,209.41 Cost of CPC B-144 LSA box & preparation for use                            7,583.15 Cost of LSA drum & preparation for use                                      102.27 Cost of cask liner for CNSI 14 195 cask                                      106.24 Cost of cask liner for CNSI 8 120A cask (resins)                          5,700.21 Cost of cask liner for CNSI 8 120A cask (filters)                            581.58 Decontamination of surfaces with vacuuming, $/square foot                      0.41 TLG Services, Inc.
 
CooperNuclear Station                                                                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                                                          Appendix C, Page 1 of 35 APPENDIX C DETAILED COST ANALYSES 2014 CESSATION OF OPERATIONS T able C -1, D E C O N ............................................................................................... C -2 Table C-2, Delayed DECON ...............................................................................              C-13 T able C -3, SA FSTO R ..........................................................................................      C -24 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                Document N01.1590-002, Rev. I Appendix C, Page 2 of 35 DecamnmieaioningCost Analysis Table C-i Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars) off-Site  LLRW                                      NRC        Spent Fuel      Site    Processed            Burial Volumes            Burial I            Utility and
                                          -              Devon Removal  Packaging Transport Processing Disposal  Other        Total    Total  Lit. Term. Managenment  Restoraton  Volume  Clans A  Class B    ClassC  GTCC    Processed  Craft  Contractor A-c-nty                                            Cst  cost      Costs    Costs      Costs    Costs    Csts    Colnuoun,,  Costs    Costs        Cots        Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Fet  Cu. Faet  WL. Lbs. Manhours  Manhourst ex                    A. v          0I  n PERIOD Is - Shutdown through Transition Period 1a Direct Decommissioning Activites 1:.1.1      Prepare preliminary decommissioning cost                                                              130            20    150          150                                                                                                      1,300 I 1.2
        ,      Notificationof Cessation of Operations l.1 .3      Remove ue & source material                                                                                                rd.8 Ia.1.4      Notification of Permanent Defueling la.1.5      Deactivate plant systems &process waste la.1.6      Prepare and submit PSDAR                                                                            200            30    230          230                                                                                                      2.000 4600            69    529          529                                                                                                      4,600 la.1.7      Review plant dwgs &specs.
10.,1.8    Perform detailed red survey 100            15    115          115                                                                                                      1,000 10.1.9      Estimate by-product inventory 100            15    115          115                                                                                                      1,000 1:.1.10    End product description 130            20    150          150                                                                                                      1,300 I0.1,11    Detailed by-productinventory 750            113    863          863                                                                                                      7.500 la.1.12    Define major work sequence 310            47    357          357                                                                                                      3.100 10.1.13 Perform SER and EA 75    575          575                                                                                                      5,000 l.1e--14. Perform Site-Specitic Cost Study                                                                      500 410            61    471          471                                                                                                      4.096 1a.1.15 Prepare/submit License Termination Plan la.1.16    Receive NRC approval of termnnation plan                                                                                    a Activty Specifcations 492            74    566          509                        57                                                                            4.920 la.1.17.t Plant & tenporary facilities                                                                                                                                                                                                                        4,167 Ia.1.17.2 Plart systems                                                                                        417            63    479          431                        48 50            8    58            58                                                                                                        500 la.1.17.3 NSSS Decontamination Flush 710          107    517          817                                                                                                      7,100 la.1.17.4 Reactor ieamte                                                                                                                                                                                                                                      6,500 la.1.17.5 Reactr essel                                                                                          650            98    748          748 5D            8    58            58                                                                                                        5oo 10.1.17.6 Sacrificial shield                                                                                      100 15    115          115                                                                                                      1,000
: 1. 1.17.7 Moisture soparatoesnrheaters 160            24    184            92                        92                                                                            1,600 1a.1.17,8 Reinforced concrete 209            31    240          240                                                                                                      2,088 1a.1.17.9 Main Turline 209            31    240          240                                                                                                      2,088 la.1.17.10 Main Condensers                                                                                                                                                                                                                                    2,000 la.1.17.11 Pressure suppression structure                                                                        200            30    230          230 160            24    184          184                                                                                                      1,600 la.1.17.12 Drpwell 312            47    359          179                        179                                                                            3,120 Ia.1.1713 Plantstructures &buildings 460            69    529          529                                                                                                      4.600 la.1.17.14 Waste managernt                                                                                        90 14    104            52                        52                                                                              900 1a.1.17.15 Facility& site doseaout 4.268          640  4,909        4.481                        428                                                                          42.683 1a.1.17    Total PlRnning& Site Preparations 240            36    276          276                                                                                                      2,400 la 1.18 Prepare dimantling seqience 1l.1.19    Plant prep. &temp. svtes                                                                            Z,700          405  3,105        3,105 140            21    161          161                                                                                                      1.400 1a.1.20    Desig watermdeanup system 1.1.21    RiggiugfCord. Cntd Envlpsntoofingletc.                                                              2,100          315  2,415        2.415 123            18    141          141                                                                                                      1.230 la.1.22    Procure casksilinens &containers 12.661        1,899 14.560      14,132                        428                                                                          78.609 la.1      Subtotal Period la Actirty Cots Period la  Collateral Costs 1a.3.1    Spent Fuel Capital and Transfer                                                                    10,335        1,550 11.886                      11,888 1a.3.2    Corporate Overheads                                                                                3,105          468  3,570        3,570 2,016 15,458        3,570        11,888 10.3      Subtotal Period la Collateral Costs                                                                13.440 Period 10 Period-Dependent Costs 18.4.1    Insurance                                                                                          1,600          160  1,760        1,760 1.4.2      Property taxes                                                                                          4            0      4            4 la.4.3    Health jorysics supplies                            370                                                              93    463          463 10.4A      Heavy equiplent rental                              368                                                              55    423          423 TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                                                                                          DocumentN01-1590-002, Rev. I DecoomissioningCodt Analysis                                                                                                                                                                                                                          Appendix C, Page 3 of 35 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sit. LLRW                                        NRC        Spent Fuel      Site    Processed            Burial Volumes            Burial I              Utiity and Activity                                          Decon    Removal  Packaging  Transport  Processing Disposal    Other      Total        Total  Lic.Term. Management  Restoration  Volume  Clans A Class B Class C    GTCC Processed        Craft    Contractor Index                    Activity Description      Cost      Cost      Costs      Costs      Costs    Costs      Costs    Contllnency  Costs    Costs        Costs        Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet - Wt. Lbs. Manhours    Manhours Period la  Period-Dependert Costs (continued) 1a.4.5      Disposal of DAWgenerated                                                                              73                        19    100        100                                          1,575                                14,445 la.4.6      Plant energy budget                                                                                            927            139  1,066      1,066 la.4.7      NRC Fees                                                                                                      706              71    776        776 1a.4.8      Emergency Planning Fees                                                                                      1-185            118  1.303                      1,303 1a.4.9      Spent Fuel Pool O&M                                                                                            745            112    857                        857 la.4.10    ISFSI Operating Costs                                                                                            85            13    88                        98 la.4.11    Secuity Staff Cost                                                                                          5,483            822  6,306      6,306                                                                                                    157,471 la.4.12    UtilityStaff Cost                                                                                          22.690          3.403  26.093    260.03                                                                                                      423,400 la.4        Subtotal Period la Period-Oependemt Costs                738          5          3                  73    33.424          5,006  39,249    30,991          2.258                          1,575                                14,445          5    580,871 1a.0        TOTAL PERIOD la COST                                    738          5          3                  73    59,525          8.921  69,265    54,693          14,144        428              1,575                                14,445          5    659.480 PERIOD lb - Decommissioning Preparations Period 1b Direct Decommissioning Activities Detailed Wor Procedures lb.1.1.1    Plant systems                                                                                                  473              71    544        490                        54                                                                            4,733 lb.1.1,2    NSSS Decontamiation Flush                                                                                      100            15    115        115                                                                                                        1,000 lb.1.1.3 Reactor intemals                                                                                                400              s0    460        460                                                                                                        4,000 It.1.1.4 Remaining buildings                                                                                              135            20    155            39                      116                                                                            1,350 lb.1.1.5 CRDhousings &Nts                                                                                                100              15    115        115                                                                                                        '1.000 10.1.1.6 Inore instrumaentation                                                                                            100            15    115        115                                                                                                        1,000 1b.1.1.7 Removal primnarycontainment                                                                                      200              30    230        230                                                                                                        2,000 1b.1.1.8 Reactor yessel                                                                                                  363              54    417        417                                                                                                        3,630 1b.1.1.6 Facility closeout                                                                                                120              18    138          69                        69                                                                            1.200 1b.1.1.10 Sacrificial shield                                                                                              120            18    138        138                                                                                                        1,200 1b.1.1.11 Reinforced conete                                                                                                100            15    115            so                      58                                                                            1,000 1b.1.1.12 Man Turbine                                                                                                    208              31    239        239                                                                                                        2,080 lb.1.1.13 Main Condensers                                                                                                  209              31    240        240                                                                                                        z088 1b.1.1.14 Moisture separators &reheaters                                                                                  200              30    230        230                                                                                                        2.000 1b.1.1.15 Raortasta building                                                                                              273              41    314        283                        31                                                                            2,730 lb.1.1.16 Reactor building                                                                                                273              41    314        283                        31                                                                            2,730 1b.1.1    Total                                                                                                        3,374            506  3,880      3,520                        300                                                                  -        33,741 Ib.1.2    Decon NSSS                                  348                                                                              174    523        523                                                                                          1.067 I1b.1      Subtotal Period lb AcxtvityCosts            348                                                            3,374            680  4.403      4,043                        360                                                              1,067        33,741 Period b Addriional Costs 1b.2.1    Spent Fuel Pool Isolation                                                                                    9.407          1.411  10,818      10.818 I b.2.2    Site Charcterization                                                                                -      5,395          1,619  7.014      7,014 1b.2.3    Asbestos Insulation Disposal                            773          1        65                558        -            265  1,662      1.662                                        10,333                              134.329    10,002 lb.2      Subtotal Period lb Additional Costs                      773          1        65                558    14,802          3,295  19,493      19,493                                        10,333                              134.329    10,002 Period lb  Collateral Costs lb.3.1    Decon equipment                              713                                                                              107    820        820 lb.3.2    DOC staff relocation expenses                                                                                  912            137  1,049      1,049 1b.3.3    Process liquid waste                          64        -          48      249                1,800                      525  2,690      2,690                                          427      543                        85.905        189 1b.3.4      Small tool allouwance                                    "11                                                                    2      12          12 lb.3.5    Pipe cutting equipment                            -    1,000                                                                  150  1,150      1,150 lb,3.6    Decon rig                                  1,400                                                                            210  1,610      1,610 1b.3.7    Spent Fuel Capital and Transfer                                                                              3,054            458  3,512          -          3,512 1b.3.*8    Corporate Overheads                                                                                  -      1,554            233  1,787      1,787 249                1,806      5,520          1,822  12,631      9,118          3,512                            427      543                        85,905        186 1b.3      Subtotal Period lb Collateral Costs        2,177      1.011          48 TLG Services, Inc.
 
0 Cooper NuclearStation                                                                                                                                                                                                                            Document N01-1590-002, Rev. I DeconmirsioningCost Analysis                                                                                                                                                                                                                          Appendix C,Page 4 of85 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                        NRC      Spent Fuel      Site    Processed              Burial Volumes              Burial/              Utility and Activty                                            Decon    Removal  Packaging  Transport  Processing  Disposal    Other      Total        Total LiU.Term. Management    Restoration  Volume    Class A  Class B    Class C  GTCC    Processed    Craft    Contractor Index                    Activity Description    Cost    Cost      Costs    Costs      Costs      Costs      Costs    Continaency    Costs    Costs        Costs        Costs      Cu. Feet  Cu. Feet  Cu. Feet Cu. Foot  Cu. Foot  Wt. Lbs. Manhours  Manhours Period l b Period-Dependmnt Costs 1b.4.1      Decon supplies                                22        4                                                                      5      27        27 1b.4.2      Insurance                                                                                                    244            24      269        269 lb.4.3      Properlty taxes                                                                                                2            0        2          2 lb.4.      Health physics supplies
* 242                                                                  60      302        302 Ib.4.5      Heavy equipment rental                                183                                                                  27      211        211 Disposal of DAW generated                                          3          2                    43                      11      58          58                                            920                                  8.439          3 Ib.4.6 ib.4.7      Plant energy budget                                                                                          924          139    1,063      1,063 Ib.4.8      NRC Fees                                                                                                      352            35      387        387 lb.4.9      Emergency Planning Fees                                                                                      591            59      650                      650 1b.4.10 Spent Fuel Pool O&M                                                                                              372            56      427                      427 lb.4.1      ISFSI Operating Costs                                                                                          42            6      49                        49 Ib.4.12    Security Staff Cost                                                                                        Z734            410    3,144      3,144                                                                                                          78,520 Ib.4.13    DOC Staff Cost                                                                                              4,759          714    5,473      5,473                                                                                                        83.440 Ib.4.14    UitiityStaff Cost                                                                                          S 11,380        1.707  13,086    13,086                                                                                                      212,160 Sb.4      Subtotal Period 1b Penod-Dependent Costs      22      425          3          2                    43    21,400        3,255  25,149    24,023          1,126                              920                                  8,439          3    354,120 1b.0        TOTAL PERIOD 1b COST                      2,547    2,209        49      316                  2,407    45,096        9,052  61,676    56,677          4,638        360              11,680        543                      228,674    11,261    387,861 PERIOD I TOTALS                                        2.547    2.947        54      318                  2.480    104,622        17,973  130,940    111,370        18.782        788              13,255        543                      243,119    11265    1,047.341 PERIOD 2a - Large Component Removal Period 2a Direct Decommissioning Actvities Nucear Steam Supply System Removal 2a.1.1.1 Reciclation System Piping &Valves                90        71        14        20                    303                      142      639        639                                            997                                120,597    4,031 20.1.1.2 Recircudation Pumps & Motom                      33        28        11        29                    321                      109      532        532                                          1.188                                  132,888    1,683 2 .1.1.3 CRDMs & NIs Removal                            133      139        377        92                    317                      232    1,291      1,291                                          6,935                -                126,494    0,209 2L.1.1.4 Reactor Vessel Internals                        110    2,382      5,343    2,09                  16,355        218        11,879  30,285    38,285                                          1,878    1,205      676              376,084    28,075        1,255 2a.1.1.5 Reactor Vessel                                  56    5,457      1,460      762                  5,358        218        7,388  20,700    20,700                                        11,211    2.128                -    1,440,354    28,075        1,255 20.1.1      Totals                                      431      8,058      7,205    2,912                22.653        437        19.751  61,447    61,447                                        22,209    3,334      976            2.196,409    68,073        2,510 Removal of Major Equipment 2a.1.2      Main Turtine/Generator                                171        028      379      6,057        309                    1,188    0,011      9,011                                08,524    1,725                                2,788,381    4,555 2a.1.3      Main Condensers                                        722        552      273      3,773        812                    1,045    7,177      7.177                                36,456    3,604                                1,63.840    19,066 Cascading  Costs from Clean Building Demolition 2a.1A.1    Reactor                                                260                                                                  39      299        299                                                                                            2,488 25                                                                    4      28        28                                                                                              235 2a.1 .4.2  Augmented Radwaste 2a.1A.3      Radsoste                                              43                                                                    7      50          50                                                                                              359 20.1.4. Turbineto                                              285                                                                  43      328        328                                                                                            4,419 2a.l.4      Totals                                                613                                                                  92      705        705                                                                                            7,498 Disposal of Plant Systems 2a.1.5.1 Augmented Radwrste El 877        ArealA                  207        28        28                    432                      167      862        062                                          2,055                                  172,205    5,783 2a.1 5.2 Augmented Redwaste          a 903 ArealA                  68          6          7                    104                      45      230        230                                            460                                  41,606    1,889 2a.1.5.3 Augmented Redwaste 918      al    AralA                    53        10          9                    139                      50      261        261                                            765                                  55.345    1,451 2a.1.5.4 Augmented Radwaste El 929        AmalA                    21          4          5                    73                      25      128        128                                            324                                  29,038      591 2a.1.5.5 Augmented Redwaste El 929        AreaoB                    3          0          0            3        0                        1      8          8                                  38        1                                  1,538        77 28.1.5.0 DRYVVELLArealA                                            534        85        84                  1.289                      477    2,470      2,470                                          5,726                                  513,627    15,069 28.1.5.7 DRYWVELL        AealB                                    134          3          5          54        28                      50      274        274                                  577      126                                  34,718    4,142 2a.1.5.8 Muib-Purpose Facility                                    202          6        15        201          47                      95      566        560                                2,148      214                                105,982    5,547 29.1.5.9 Reactor El 903 AJOelA                                    404        56        42          -        651                      276    1,428      1,428                                          2,892                                  259,190    10,573 2a.1.5.10 Reactor    a  903 ArealB                                462        13        34        443        131                    221    1.305      1,305                                4,739      583                                244,706    12,864 20.1.5.11 Turbine El 032 ArealB                                    332        52        99        882        725                      416    2.505      2.505                                9,442    3,220                                  672,225    9,481 8                                                                    1      9                                    0                                                                    237 2a.5.5.t2 Turbine El 932 Aea2C TLG Servcees, Inc.
 
Cooper Nuclear Stoaton                                                                                                                                                                                                                                    Document N01-1590-002, Rev. I Decommissioning Cost Aoodyaie                                                                                                                                                                                                                                  Appendix C, Page 5 of 35 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sit. LLRW                                          NRC        Spent Fuel      Site      Processed              Burial Volumes              Burial I            Utility and Activity                                            Decon  Removal    Packaging    Transport  Processing  Disposal    Other      Total        Total  Lic. Term. Management    Restoration  Volume    Class A  Class B    Class C  GTCC    Processed    Craft    Contractor Index                    Activity Description      Cost  Cost        Costs        Costs      Costs      Costs      Costs    Continenc      Costs    Costs        Costs        Costs      Cu. Feet  Cu. Feet  Cu. Feet Cu. Feet  Cu. Feet  Wt, Lbs. Manhours  Manhours Disposal of Plast Systems (coninued) 2a.1.5,13 Turbine El 932 Area3C                                    67          .          .            .        .                        10      78                                      78        -        -                                        -      2.083 2a.1.5.14 YardAfealB                                            518          110        284        3.535    1.198                    1,013    6,657        6,657                                  37,846    5,399                                2,014,081    14.477 2a.1.5    Totals                                              3,013          374        612        5,117    4,817                    2.847  16.780      16,693                          87    54.788    21,774                                4,144.259    84,262 2a. 1.6    Scaffolding in support of decommissioning          2,070            24          11        168        23                    553    2,848        2,848                                    1,621      101                                  81,992    28.092 2a.1      Subtotal Penod 2a ActivityCosts              431  14,647        8,983      4,188        15,116  28.694        437      25,476  97,968        97,881                          87    151,388    49.413    3,334      976          11,174,880  212,445        2.510 Period 2a Collateral Costs 2a.3.1    Process liquid waste                        135      -            44        231                    264                      173      847          847                          -          -        921                                  55,244        185          -
2a.3,2    Small tool allowance                                  124                                                                        19    143          129                          14 2a.3.3    Spent Fuel Copital and Transfer                                                                                8.576        1,286    9,862          -          9,862 2a.3.4    Crporate Overheads                                                                                      -      3.202          480    3,682        3,682 2a.3      Subtotal Period 2a Collateral Costs          135      124            44        231                    264    11,778        1,.58  14,534        4,657          ,9982          14                  621                                  55.244        180 Period 2a Perieo-Dependent Costs 2a.4.1    Decce supplies                                81                                                                                  15      78            76 2a.4.2    Insurance                                                                                                        688            69      756          756 2a.4.3    Property taxes                                                                                                      6            1        6            6 2a.4.4    Health physics supplies                            1.262                                                                      315    1,577        1,577 20.4.5    Heavy equipment rental                              2,480                                                                      372    2,852        2,852 2a.4.6    Disposal of DAWgenerated                                              34          19                  537        -            140      730          730                                            11,545                                  105,898        35 2a.4.7    Plant energy budget                                                                                    -      1,235          185    1,420        1,420 2a,4.8    NRC Fees                                                                                                          923            92  1,016        1.016 2a.4.9    Emergency Planning Fees                                                                                          1,183          118    1,301                      1,301 2a.4.10    Spent Fuel Pool O&M                                                                                              1.046          157    1,203                      1,203 2e.4.11    ISFS0Operating Costs                                                                                              119            18    137          -              137 2a,4.12    Security Staff Cost                                                                                            6,631          995    7,626        7,626                                                                                                          185.051 2a.4.13    DOC Staff Cost                                                                                                16,275        2,441  18,718      18.716                                                                                                          222,354 2a.4.14    UtilityStaff Cost                                                                                              22,962        3,444  26,407      26,407                                                                                                          413,989 2a.4      Subtotal Period 2a Pedod.Dependent Costs      61    3,741            34          19                  537    51,067        8,363  63,822      61,182          2,640            1              11,545                  -              105.898        35    821,394 2a.0      TOTALPERIOD 2a COST                          627  18,513        9,060      4,437      15,116    29,494      63.282      35,797  176,325    163,720          12,503          102    151,388    61,878    3.334      976          11,336.020  212,660    823,904 PERIOD 2b - Site Decontamination Period 2b Direct Decommissioning Activities Disposal of Ptant Systems 2b.1.1.1  Control El 882 Arealt                                285            17        42          554      147                      199    1,243        1,243                          -        5,929      674                                  299,222    7,975 2b.1.1.2 Control El 903 AreatC                                  170                                                                        25      185                                    195          -                                                  -      5,155 2b.t1..3 Control Ei 918 ArealC                                    66                                                                        10      76                                      76                                                                  2,100 2b.1.1.4 Control El 932 AmealC                                    22                                                                        3      26                                      26                                                                    702 101                                                                        15      116                                    116                                                            -      3,136 2b.1.1.5 Intake 18Radwraste Cl877 ArealA 2b.1.t.6                                                        405            75        62                    948                      355    1,845        1,845                                            5,097                                  377,917    11.133 2b.1.t.7 Raoteaste 8877 Area2A                                    44            9          7                  113                        41    214          214                                              613                                  44,992    1,207 2b 1.1.8 Radwaste El 877 Area3A                                    84            16          13                  201                        75    388          308                                            1.156                                  79,963    2,349 2b.1.1.9 Radsaste 8 903 AnalA                                    113              9          10                  153                        69    355          355                                              684                                  81,153    3,102 2b.1.1.10 Radastes 8 9D3 Arsa2A                                  192            36          29                  439                      166      961          891                                            1.955                                175.093    5,412 2b.1..t11 Radwaste E 903 Area3A                                    37            6          7                  104                        37      191          191                                              463                                  41,366    1,047 2b.1.1.12 Radwasts [ 9168AalA                                      21            2          2                    30                      13      68            68                                              135                                  12,033        572 2b.1.t.13 Radwast= C 918 Amea2A                                    17            3          3                    39                      15      76            76                                            201                                  15,667      455 2b.1.1.14 Radwasta 8916Atea3A                                    188            23          22                  338                      137      710          710                                            1,690                                134,827    5,152 2b.1.1.15 Rafsts El 934 AreaeA                                    26            3          4                    60                      22      11t          115                                              266                                  23,735      692 2b.1.1.16 Radwaste  : E934 Area2A                              100            11          12                  177                        72    372          372                                              808                                  70,665    2.706 2b.1.1.17 Radwasta ]S49ArealA                                      12            1          2                    24                        9      47            47                                              105                                  9,381        310 TLG Services, Inc.
 
Cooper Nuaclar Station                                                                                                                                                                                                                      Docoarars NOI.-1590.002, Rev. I Decoamss~aioning CoatAnalsayis                                                                                                                                                                                                                    Appendix C, Page6 ef 85 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                    NRC        Spent Fuel    Site      Processed              Burial Volumes              Burial I            Utilityand Activity                                            Decon  Removal  Packaging  Transport  Processing  Disposal  Other    Total      Total Lie.Term. Management Restoration  Volume      ClansA  Class B Class C GTCC      Processed    Craft    Contractor Inde.                  Activity Oscription        Cost    Cost      Costs    Costs      Costs      Costs    Costs  Contiagenco  Costs    Costs        Costs      Costs      Cu. Feet    Cu. Feet Ce.      Cu.Fon Cu. Font CFot              Wt. Lbs. Manhours  Manhouns Disposal of Rant Systems (continued) 2b.1.1.18 Reactor El 859 AralA                                      72        15        16          -        248                    83    432        432                                          1,091                                97,874    2,068 344                  317  1.914      1,914                                7,624      1.526                              448,483    12,746 2b.1.1.19 Reactor Elt59 ArealB                                  449          28        64        712 2b.1.1.20 Reactor El 859 Area2A                                    73        25        26                    401                  125    650        650                                  -      1,780                                159,714    2,137 2b 1.1.21 Reactor El 859 Area2B                                    70          3          8          99      40                    44    264        264                                1,055        177                                58.760    2.009 2b.1.1.22 Reactor El 859 Ara3A                                      48          9          9                  137                    49    252        252                                            6O8                                54,543    1,356 34          2          3          23      23                    18    103        103                                  249        103                                19,362      975 2b.1.1.23 Reactor El 859 Area3B 51          9          8                  117                    44    229        229                                  -        520                                46,666    1,416 2b.1.1.24 Reactor El 859 Area4A 17          1          2          19      14                    11      65          65                                208        62                                14,010      487 2b.1.1.25 Reactor El 659 Area4B 262                  86    445        445                                          1,163                                104,381    1,839 2b,1.1.26 Reactor El 859 Are"SA                                    64        16        17 2b.1.1.27 Reactor El 859 AraSB                                      38          2          3          23      23                    19    107          107                                242        102                                18,927    1,114 4          0          0                    8                    3      14          14                                            26                                  2,372      123 2b.1.1.28 Reactor El 903 Area2A 71          5        12          149        51                    55    342        342                                1,594        225                                84,943    1,983 2b.1.1.29 Reactor EJ903 Area2B 2b.1.1.30 Reactor C 903 Area3A                                      37        10        11        -        167                    54    279        279                                  -        741                                68,516    1,109 2b.1.1.31 ReactorEl 903 Area3B                                      25          2          3          37      17                    17    101          101                                401        77                                23,200      744 2b.1.1.32 Reactor El 903 Area4A                                    31          8          9                  136                    44    229        229                                            608                                54,373      928 2b.1.1.33 Reactor EJ903 Area4B                                      24          1          3          38      17                    17    101        101                                  411        75                                23,408      717 25          3          3        -          52                    20    104          104                                  -        232                                20.858      681 2b.1.1.34 Reactor El 931 ArealA 2b.1.1.35 Reactor El 931 Areal B                                307          22        45        483        256                  222  1,334      1,334                                5,169      1,137                                311.878    8,640 31          2          2        -          35                    17      87          87                                          154                                13,824      881 2b.1.1.36 Reactor Ei931 Area2A 2b.1.1.37 Reactor EC931 Aroe2B                                      3          0          0            1        0                    1      5            5                                    7        1                                    380        91 123          23        22                    336                  120    625        625                                          1.651                                134,007    3,509 2b.1.1.38 Reactor E 931 Area3A 2b.1.1.39 ReactworE 931 Area3B                                      3          0          0            1        0                    1      4            4                                    7        0                                    345        85 2b.1.1.40 Reactor EJ931 Area4C                                      24                                                                4      28                                  28                                                                    767 1      8        -                          8                                                          -        213 2b.1.1.41 ReactorEl 931 AreaSC                                      7 2b.1.1.42 Reactor El 958 ArealA                                    57          9        10                  149                    54    279        279                                  -        662                                59,432    1,492 18          209        88                  100    594        594                                2,238        392                                128,002    4,814 2b.1.1.43 Reactor El 958 ArealB                                  171          8 10        10        -        153                    53    276        276                                  -        681                                61,083    1.425 2b.1.1.44 Reactor El 958 Ar-a2A                                    49 15          1          1            6      14                    8      46          46                                  66      63                                  8,331      430 2b.1.1.45 Reactor EJ 558Area2B 4          3          -        48                    22    116          116                                  -        214                                19,185    1,070 2b.1.1.48 ReactorB 958 Area3A                                      38 17          1          1            6      12                    8      45          45                                  60      54                                  7.250      491 2b.1.1.47 Reactor El 958 AreM33
                                                                                                          -          50                    23    117          117                                  -        222                                19,878    1,028 2b.1.1.48 Turbine El 882 AalA                                      38          3          3 46        95        1,101      476                  402  2.515      2,515                              11,784      2,117                                868.352    11.459 2b.1.1.49 Turbine El 882 AralB                                    394 2b.1.1.50 Turbine El 882 Area2A                                    22          2          2                    29                    13      68          68                                -        129                                11,556      597 10        23          301        89                  125    762        762                                3,227        405                                166,542    5,929 2b51.1.51 Turbine C 882 Area2B                                  213 2          1          -        23                    10      53          53                                -        101                                  9.017      461 2b.1.1.52 Turbine El 882 Ares3A                                    17 633                  637  4,068      4,068                              20,984      2,817                              1.104.460    17,788 2b.1.1.53 Turaln El 882 Area3B                                  820          82      156        1.960 15                    6      33          33                                -          68                                  6.127      239 2b.1.1.54 Turbine E8 903 ArealA                                      9          I          1          -
134      271        2.726    1.717                1,141  6,983      6,983                              29,180      7.631                              1,868,932    28,509 2b.1.1.55 Turbine El 903 Areal B                                995 5                                                                4      20          20                                -          42                                  3,729      145 2b.1.1.56 Turbine El 903 Area2A                                                1          1          -          9 3          a        105        30                    62    355        355                                1,122        133                                57,476    4,141 2".1.1.57 Turbine El 903 Area2B                                  147 3          0          2          33        2                    7      48          48                                357          9                                15,340        97 2.1.1.1.58 Turbine EC903 Area3B 16    124                                  124                                                          -      3,412 2b.1.1.59 Turbine 5  903 Aea3C                                    108 2b.1.1.60 Turbine El 903 Ama4B                                      12          0          2          26        3                    8      50          50                                276        11                                12,251      367 2b.1.1.81 YardAVatIC                                              197                                                                30    227                                  227                                                          -      5,770 21.1.1    Totals                                              6,646        693    1,087        8,611    8,996                8,365 31,398      30,598                      80    92,188    41,682                              7.327,776  189,487 2b.1.2    Scaffolding in support of decommissioning            2,588          30        14        210        28                  691  3.560      3,560                                2,026        126                                102,490    35.115 Decontamination ofSe Buildings 2b.1.3.1  Reactor                                    2,702    1,457        131      320        4,748    1,116                2,767 13.241      13,241                              50,830      16.343                              3,680,298  101.984 32          7        10          23      119                    71    316        316                                  242      2.189                                228,383    2,299 28,1.3.2 Augmented Radwaste                              55 377      174          15        43          759        74                  372  1,815      1,815                                8,129        679                                395,527    13,327 2b.,1.3.3 Miscellaneous Structures - Contaminated 2b.1.3.4 Mueti-urpose Facility                            72        73        11        19        115      172                  118    579        579                                1,234      3,087                                356.985    3.680 167        88        18        26            38      319                  196    850        850                                  404      5,888                                603,975    6.839 2b.1,3.5 Radvaste 2b.1.3.6 Turbine                                        552      267          70        97            64    1,261                  689  3,001      3,001                                  688    23.302                              2,357,288    21,920 2b,1.3    Totals                                      3,924    2.088        252      515        5,747    3,061                4C214 19,801      19,80t                              61,526      51,485                              7,*22,455  150,050 TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                                                                                                      DocumentN01.1590.002, Rev. I De-omrissioning Cost Analysis                                                                                                                                                                                                                                      Appendix C, Page 7 of 35 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                          NRC        Spent Fuel      Site    Processed              Burial Volures              Burial I              Utility and Activity                                                Oe0n    Removal    Packaging  Transport  Processing  Disposal    Other        Total      Total  LIc. Term. Management    Restoration  Volume    Clans A  Class B  Clans C  GTCC    Processed    Craft    Contractor Index                    Activity Description          Cost      Cost        Costs      Coste      Costs      C Cost    Csts      Contin en    Costs    Costs          Costs        Costs      Cu. Feet  Cu. Feet  Cu. Feet Cu.Feet  Cu. Feet  WL. Lbs. Manhours  Manhours 2b.1        Subtotal Pedod 2b Actvity Costs                3,924    11,322          975      1.616      14.567    12,086        -          10,269  54,759      53,960                -        800    155.741    93,273            -            -    15,052,720    374.651          -
Period 2b  Collateral Costs 2b.3.1      Process liquid waste                              164        -            54      283                    323                      211  1.035        1,035                                            1,126                                67,588        220 2b.3.2      Small tool allowance                              -        195          -                                                            29    225          225 2b.3.3      Spent Fuel Capital and Transfer                - -                                                                17.873          2,681  20.554          -          20,554 2b.3A      Corporate Overheads                                .        .          .                                          5,754            863  6,618        6,618 2b.3        Subtotal Period 2b Collateral Costs              164      195            54      283                    323    23,627          3.784  28,431        7,877        20.554                              1,126                                87,588        220 Period 2b  Period-Dependent Costs 2b.4.1      Decon supplies                                1,318        -                                                        -              330  1,648        1,648 2b.4.2      Insurance                                                                                                          1,273            127  1,400        1,400 2b94.3      Property taxes                                                                                                          10            1      11            11 2b.4.4      Health physics supplies                                  2.257                                                      -              564  2,822        2,822 2b.4.5      Heavy equipment rental                                    4,559                                            -                        684  5,243        5,243 2b.48      Disposal of DAWgenerated                                    -            53        29                  835        -              218  1,135        1,135                                          17,954                                164,691          55 2b.4.7      Plant energy budget                                                                                        -      1.805            271  2,076        2,076 2b.48      NRC Fees                                                                                                            1,709            171  1,880        1,880 2b.4.9      Emergency Planning Fees                                                                                            2,190            219  2,409                        2,409 2b.4.10    Spent Fuel Pool O&M                                                                                                1,939            290  2,227          -            2,227 2b.4.1 1    Liquid Radwaste Processing EquipmentlServices                                                                        487            73    560          560 2b.4.12    ISFSI Operating Costs                                                                                                220            33    254          -              254 2b.4.13    Security Staff Cost                                                                                                12,279          1,842  14,120      14,120                                                                                                        342.634 2b.4.14    DOC Staff Cost                                                                                                    29.008          4,351  33,359      33,359                                                                                                          395,451 2b.4.15    UtilityStaff Cost                                                                                                  40,864          8,130  46,993      46.993                                                                                                          734,023 2b.4        Subtotal Petiod 2b Period-Dependent Costs      1,318      6.816            53        29                  835    91,781        15,304 116,137    111,248            4,889                          17,954                                164,691          55  1,472,109 2b.0        TOTAL PERIOD 2b COST                          5,407    18,334        1,081      1,928      14,567    13,243    115,409        29,358 199,327    173,085          25.442          800    155,741  112,354                              15,285,000    374,926  1,472.109 PERIOD 2c - Decontamination Following Wet Fuel Storage Period 2c Direct Decommissioning Acitvities 2c.1.1      Remove spent ftel racks                          267          33          79        89                  1.348                      500  2,316        2,316                                            5,986                                537,141      1,004 Disposal of Plant Systems 2c.1.2.1 Reactor Ff 1001 Amea1A                                          50          7          8                    121                      45    231          231                                      -        537                                48,175      1.273 2c.1.2.2 Reactor El 1001 AremtB                                          64          1          4          54        13                      28    164          164                                    578        57                                28,513      1,737 2c.1.2.3 Reactor l 976 Are1A                                              11          1          1                      16                      7      36            38                                    -        72                                  6,482      304 2c.1.2.4    ReactorElg7  97eArWel                                      ISO            11        27        328        115                      121    752          752                                  3,516        511                                188,501      4,017 2c. 1.2.5 Reactor El 976 Aee2A                                              7          1          1        -            13                      5      26          26                                    -          57                                  5,136      174 2c.1.2.6    Reactor El 976 Are2B                                          38          1          3          42        16                      20    121          121                                    449        72                                24,474      1.056 2c.1.2      Totals                                                      321            23        44        424      293                      226  1,331        1,331                                  4,543      1,305                                301,281      8,561 Decratamivatioa of Site Buddngs 2c 1.3.1    Reactor (post fuel)                            257        510            97      138          163      1.742                      747  3,856        3,656                                  1,749    32,119                              3,281.859    18,302 2c.1.3      Totals                                            257      510            97      138          183      1.742                      747  3,656        3,656                                  1,749    32,119                              3.281,659    18,302 20 1.4    Scaffonldig In support of deconvrvussioning                518            8          3          42          g                    138    712          712                                    405        25                                20,498      7,023 2c.1      Subtotal Peitod 2c ActivityCosts                  525    1,382        205        273          630      3,389                    1,611  8,014        8,014                                  6,697    39,437                              4.140.579    34,890 Period 2c Additional Costs 2c.2.1    Final Site Survey                                                                                                  1.205            362  1,567        1.567                                                                                                            12,480 2c.2        Subtotal Period 2c AdditbonalCosts                                                                                1,205            362    1,567      1,597                                                                                                            12,480 TLG Services, Inc.
 
S Cooper NuclearStation                                                                                                                                                                                                                                    Documenl N01-1590-002, Rev. I Appendix C, Page 8 of"35 DecommssnioningCast Analysis Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                          NRC        Spent Fuel      Site    Processed            BurialVolumes            Burial I              Utilityand Activity                                                Devon  Removal    Packaging  Transport  Processing  Disposal      Other        Total      Total  Lic.Term. Management    Restoration  Volume    Clan A  Clans B Class C GTCC Processed        Craft      Contractor Index                    Activity Description          Cost    Cost        Costs      Costs        Costs    Costs        Costs    Contln Oscy  Costs    Costs          Costs        Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet Cu. Feet Wt. Lbs. Manhours    Manhours Period 2c Collateral Costs 101        -            33      175                    200                        130    639        639                                            696                                41,756      136 2c.3.1      Process liquid waste
                                                                  -            22                                          -                            3      25          25 2c 3.2      Smau tool aliomance                                                                                                                                                                                                                        303.507        88 621        84        -              130    973        973                                  6,000      373 2c.3.3      Decommissiong Equipment Disposition                                      88        50 1,595            239  1,834          -            1,834 2c.3A4      Spent Fuel Capital and Transfer                                                                                                                                                                                                            345.263      224 101          22      121        225          621      284        1,595            503  3,471      1,637          1,834                  6,000    1,069 2c. 3      Subtotal Pennd 2c Colsateral Costs Period 2c Period-Dependent Costs
                                                                                                                                        -              23    113        113 2c.4.1      Decon supplies                                    90 197            20    217        217 2c4.2      Insurance
                                                                                                    -                                      2              0      2            2 2c.4.3      Property taxes 256                                                        -              64    320        320 2C.44      Health physics supplies
                                                                                                      -          -                -                    106    813        813 2c.4.5      Heavy equipment rntal                                      707                                                                                                                                          3,949                                36,227          12 6                  184          -              48    250        250 2c.4.6      Disposal of DAWgenerated                                    -            12
                                                                                                                            -          149            22    172        172 2c.4.7    Plant energy budget 265            27    292        292 2c.4.8    NRC Fees                                                                                                                                                                  373 340            34    373          -
2c.4.9      Emergency Planning Fees 151            23    174        174 2c.4.10    Liquid Radwaste Processing EquipmentrServicos 34              5      29        -              39 2c.4.11    ISFSI Operating Costs                                                                                                                                                                                                                                              27,930 1,159            174    1,333      1,333 2c.4.12 Security Staff Cost                                                                                                                                                                                                                                                    42,000 2c.4.13    DOC Staff Cost                                                                                                      3,126            469  3,595      3,595 705  5,404      5,404                                                                                                      80,220 2c-4.14    UtilityStaff Cost                                                                                                    4,699                                                                                                                                        150,150 1,719  13,096      12,684            413                          3,949                                38,227          12 2c.4      Subtotal Period 2c Penod-Dependent Costs          90      983            12          6                  184      10,123 716    2,367        337        504        1,251    3,858      12,922          4,194  26.148      23.902          2,247                12,697  44,455                            4,522,069    35,126      162,630 2c.0      TOTAL PERIOD 2c COST PERIOD 2e - License Ternination Period 2e Direct Decommissioning Activioes 2e 1.1    ORISE confiratoty survey                                                                                              147            44    191        191 2e 1'2    Terrmnate license 147            44    191          191 2e.1      Subtotal Period 2e ActivityCosts Period 2e Additonal Costs 5,998          1,799  7,797      7,797                                                                                        148,435        6,240 2e.2.1    Final Stte Surney                                                -  -  -          -            -        -                                                                                                                                        148,435        6,240 Subtotal Period 2e Addibonal Costs                              -  ,  -          -            -        -        5,890          1,799  7,797      7,797 2e.2 Period 2e Collateral Costs 2e.3.1      DOC staff relocatio expenses                                                                                          912            137    1,049      1,049 217              33    250          -              250          -          -        -        -        -
2e.3.2      Spent Fuel Capital and Transfer 1,129            169    1,299      1,049            250          -          -        -        -        -
2e.3        Subtotal Period 2e Collateral Costs Period 2e Period-Dependent Costs 327              33    360        360 2e.4.1      Insurance 3              0      3            3 2e.4 2      Property taxes 737          -          -                                                184    921        921 2e.4.3      Health physics supplies                                                                                                                                                                                                                      8,380          3
                                                                              -            3          1                    42                        11      58          58                                          914 2e.4.4      Disposal of DAWgenerated 139              21    160        160 2e.4.5      Plant energy budget 2e.4.6      NRC Fees                                                                                                              530              53    583        583 633            63    696          -              696 2e.4.7      Emergency Planning Fees 64            10      73        -              73 2e.4.8      ISFSI Operatig Costs 2,125            319  2,444      2,444                                                                                                      50,886 2e.4.9      Security Staff Cost                                                                                                                                                                                                                                                57,149 2ed.410    DOC Staff Cost                                                                                                      4,442            666    5,108      5,108 5,071            761    5,832      5,832                                                                                              -        80.634 2e.4.11    UtilityStaff Cost                                                                                                                                                                                                                            8.380          3    1888669 737            3          1                    42    13.334          2.121  16,238      15,468            769                            914 2e.4        Subtotal Period 2e Pedod-Dependent Costs 737            3          1                    42    20,608          4.134  25.525      24,506          1,019                            914                                8,380  148,438      194,909 2e.0        TOTAL PERIOD 2e COST TLG Servicee, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                        Documrent NOI-1590-002, Rev. I DecommissioningCost Analysis                                                                                                                                                                                                                      Appendix C, Page9 of35 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sits .LLRW                                          NRC      Spent Fuel    Sits      Processed            Borial Volurmes            Burial I              Utilityand Actvtty                                            Oeson  Removal  Packaging  Transport Processlng Disposal    Other      Total        Total Lit. Torm  Management  Restoration  Volume    Clan A  Class B Class C GTCC        Processed    Craft    Contractor Index                    Activity Description    Cost    Cost      costs      costs    Costs    Costs      Costs    Continencv      Costs    Costs      Costs      Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Wt. Lbs. Manhours    Manhours PERIOD2TOTALS                                          6.750  39,950      10.481    6,870    30,933  46,637    212,221        73,483  427,325    385,213      41,211        901    319,826  219.601    3,334      976    -    31,151,470  771,150    2.653,551 PERIOD3b - Site Restoration Period 32DirectDecommissioning        Acfiv&#xfd;ies Demolition of Remaining Site Buildngs 3b.1.1.1 Reactr                                                1,473                                                                221    1,694                                1,694                                                              14,089 3b.1.1.2 Augmented Radwaste                                      222                                                                  33    255                                  255                                                                2,119 3b.1.1.3 Control                                                  214                                                                  32    246                                  246                                                                1,655 3b.1.1.4 Intake Structure                                          523                                                                78      602                                  602                                                                5,621 3b.1.1.5 LLRW Storage Pad                                          145                                                                22      167                                  167                                                                1,227 3b.1.1.6 Misceuaneous Structures - Clean                        1,196                                                                179    1,375                                1,375                                                              11.837 3b,1.1.7 Miscellaneous Structures -Contaminrated                    27                                                                  4      30                                    30                                                                  572 3b.1.1.8 Muli-Purpose Facility                                    123                                                                1      141t                                  141                                                                1.982 3b.1.1.9 OWC Gas Generator                                                                                                              3      20                                    20                                                                  283 1t8 3b.1.1.10 Offce                                                    156                                                                23      179                                  179                                                                1,920 3b.1.1.11 Radwaste                                                391                                                                  59    449                                  449                                                                3,229 3b.1.1.12 Seat Well                                                17                                                                  3      20                                    20                                                                  166 3b.1.1.13 Sewage Treatment Area                                      4                                                                  1        5                                    5                                                                    53 3b.1.1.14 Transformer Yard                                          20                                                                  3      24                                    24                                                                  172 3b21.1.15 Tubine                                                2,596                                                                389    2,985                                2,985                                                                40.503 3b.1.1.16 Turbine Pedestal                                        277                                                                42      318                                  318                                                                2.100 3b.1.1.17 Reactor(post fuel)                                        18                                                                  3      21                                    21                                                                  512 3b.1.1    Totals                                              7,418                                                              1,113    8,531                                8,531                                                                88,040 Site Closeout Acivites 3b.1.2    Remove Rubble                                          424                                                                64      488                                  488                                                                3,286 3b. 1.3    Grade &landscape site                                  578                                                  -            87      665                                  665                                                                1,578 3b.14A    Final report to NRC                                                                                        156            23      179        179                                                                                            -S        1,560 3b.1      Subtotal Period 3b Activity Costs                                                                          156        1,286    9,863        179                    9,684                                                                92,904        1.580 8,421 Period 3b Additional Costs 3b.2.1    Conorete Crushing                                      499                                                    a          76      582                                  582                                                                3,045 3b.2.2    Cofferdam                                              458                                                                69      527                                  627                                                                5,130 3b.2      Subtotal Period 3b Additional Costs                    957                                                    8          145    1,109                                1,109                                                                8,175 Period 3b Collateral Costs 3b.3.1    Small tool aflomnce                                      53                                                                  8      61                      -            61 S92183 3b,32      Spent Fuel Capital and Transfer                                                                                            27      211                      211 3b.3      Subtotal Period 3b Collaeral Costs                      53                                                183            35    271                      211          61 Period 3b Period-Dependent Costs 3b.4.1    Insurance                                                                                                  751            75      826                      826 3b24.2    Property taxes                                                                                                7 3b.4.3    Heavy equipment rental                              4,053                                                                608    4,661                                4,681 3b.4.4    Plant energy budget                                                                                  -    160            24      184                      -          184 3b.4.5    NRC ISFSI Fees                                                                                              339            34    373                      373 32,4.8    Emergency Planning Fess                                                                                  1,453          145    1,598                    1,598 3b.4,7    iSFS Operating Costs                                                                                        146            22      168                      18 25.48      Security Staff Cost                                                                                      4.878          732    5,610                    4,937        673                                                                            116,814 3b.4.9    DOC Staff Cost                                                                                            9.777        1,467  11,244                      -      11,244                                                                            122,206 3b.4.10    UtilityStaff Cost                                                                                        5.903          885    6,789          0        1,697      5,091                                                                            97,944 3b.4      Subtotal Period 3b Period-Dependent Costs            4,053                                              23,415        3,993  31,460          8        9,607      21,853                                                                            336.964 3b.0      TOTAL PERIOD 3b COST                                13,483                                              23,762        5,459  42,704        179        9.818      32,707                                                              101,079      338,524 TLG Servicea, Inc.
 
DocurentN01-1590-002, Rev. 1 Cooper NuclearStations Appendix C, Page10 of 35 Decommissuioninrg Coot Anralysis Table C-i Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Ott-Site    LLRW                                          NRC      Spent Fuel      site    Proeessed              Burial volumes                Burial i            Utilrty a Decon Reeontal Packaging  Transport Processing  Disposal      Other        Total        Total  LUc.Term. Management    Restoration  Volume  Class A    Class B      Class C  GTCC    Processed  Craft    Contractor sInde                Activity Oescrlption      Cost  Cost    Costs    Costa        Costs      CasTS      COSts    Contingency    Costs    Costs        Costs        Costs      Cu. Feet Cu. Feet    Cu. Feet Cu. Feet    Cu. Feet  Wt. Lbs. Manhours  Manhours PERIOD 3c -Fuel Storage Operations/Shipping Period 3c Collateral Costs 3c.3.1    Spent Fuel Capital and Transfer                                                                            16,015          2,402  18,418                    18,418 3c.3      Subtotal Period 3c Collateral Costs                                                                        16,01b          2,402  18,418                    18,418 Period 3c Period-Deperdent Costs 3c.4.1    Insurance                                                                                                  10,708          1,071  11.776                    11,776 3C.4.2    Propenty taxes                                                                                                  98            10    108                      108 3c.4.3    Plant energy budget 3c.44      NRC ISFSI Fees                                                                                              6,234            623    6,857                    6,857 3c.4.5    Emergency Planning Fees                                                                                    20,704          2,070  22.774                  22,774 3c.4.6    ISFSI Operating Costs                                                                                      2.085            313    2,398                    2.398 61,192          9,179  70,371                  70,371                                                                                        1,383,017 3c.4.7    Security Staff Cost 3CA4,8      UtilityStaff Cost                                                                                        21,209          3,181  24,390                    24,390                                                                                          345,754 3c.4      Subtotal Period 3c Peiodt-Dependent Costs                                                                122,227        16,447  138,674                  138,674                                                                                        1,728,771 138.242        18,849  157,092                  157,092                                                                                        1.728,771 3c.0      TOTAL PERIOD 3c COST PERIOD 3d - GTCC shipping Period 3d Direct Decommissioning Acilvities Nuclear Steam Supply System Removal 3d.1.1.t Vessel & Internals GTCC Disposal                                  660                            7,470                      1,188    9,316      9.316                                                                          508      89,497 3d.1.1    Totals                                                          660                            7,470                      1,186    9.316      9,316                                                                          508      89.497 660                            7,470                      1.186    9.316      9,316                                                                          508      89,497 3d.1        Subtotal Period 3d Actisly Costs Period 3d Collateral Costs 3d.3.1      Spent Fuel Capital and Transfer                                                *        *        -            78            11      87        -            87                                --                          -
3d.3        Subtotal Period 3d Collateral Costs                                                -    -          -          78            11      87                      87          -        -                    .                  .            -
Period 3d Period-Dependent Costs 3d.4.1      Insurance                                                                                                      17              2      18                      18 3d.4.2      Property taxes                                                                                                  0              0        0                        0 3d.4.3      Plant energy budget 3d.4.4      NRC ISFSI Fees                                                                                                  8              1        8                        8 3d.4.5      Emergency Planning Fees                                                                                        32              3      36                      36 3              0        4                        4 3d..8      ISFSI Operating Costs 3d.4.7      Security Staff Cost                                                                                            96            14      110                      110 3d.4.8      UtilityStaff Cost                                                                                              33              5      38                      38                                      -          . *      *          .          .          540 3M.4        Subtotal Period 3d Period-Dependent Costs                                                                    189            25    214                      214                                      - .        -  *      .                      -        Z700 3d.0        TOTALPERIOD 3d COST                                            660                            7.470          265        1,223    9.618      9,316          302                            *.            .5-089                      89.497        -        2,700 PERIOD 3a - ISFSI Decontamination Period 3e Direct Decommissioning Activites Period 3e Additinal Costs 3e.2.1      ISFSI Decorntamination                              656          4        24                      55      1.192          360    2.290                    2290                          1,050                                      162,629    17,515      2,560 1.050 3e.2        Subtotal Period 3e Additlonal Costs                  656          4        24                      55      1'192          360    2,290                    2!290                                                                    162,629    17,515      2,560 Period 3e Collateral Costs 3a.3.1      Small tool alowaunce                                  9                                                                      1      10                      10
                                                                                                            *
* 0              1        6 3e.32      Spent Fuel Capital and Transfer
                                                                  -    9                                  -
* 6              2      18                      16 30.3      Subtotal Period 3e Cotlateral Costs TLG Service., Ine.
 
Cooper Nuclear Stationa                                                                                                                                                                                                                          Document N01.1590-02, Rev. I Decrommissionting CoastAnsalysis                                                                                                                                                                                                                      Appendix C, Page 11 of"35 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site  LLRW                                        NRC      Spent Fuel      Site    Processed            Burial Volumes              BurialI            Utilityand Activtty                                            Oecon  Removal      Packaging  Transport  Processing Disposal    Other    Total        Total Li. Ter-T. Management  Restoration  Volume    Clans A Class 8 Class C    GTCC Processed        Craft  Contractor Index                    AcvitiitsDescription      Cast      Cost        Costs      Costs      Costs    Costs        ste  Contintesc    Costs  Costs      Costs        Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet  Cu. Feet WI. Lbs. Manhours  Manhours Period 30 Period-Dependent Costs 30.4.1    Insurance                                                                                                        145          14      159                    159 0        1                      1        -
3e.4.2    Propery taxes 30.4.3    Heavy equipment rental                                  232                                                                  35      267                    267 3e.4.4    Plant energy budget 3e.4.5    Securnty Staff Cost                                                                                              303          46      349                    349                                                                                        5,013 3e.4.6    UtilityStaff Cost                                                                                                249          37      287                    287                                                                                        3,803 30.4      Subtotal Period 3e Period-Dependent Costs                232                                                    699          132    1,063                  1,063                                                                                -      68,816 3e.0      TOTALPERIOD 30 COST                                      897            4        24                  55    1,896          495    3,370                  3,370                            1,050                                162,629    17,515    11,376 PERIOD 3f - ISFSI Site Restoration Period 31Direct Deconmissioning Adivities Period 31Additional Costs 3f.2.1    ISFSI Demolition                                        487                                                      44          80      611                                                                                                      4,336        160 3f2        Subtotal Period 3f Additional Costs                      487                                                      44          80      611                    611                                                                              4.336        18S
                                                                    -        2t7 Period 31Collateral Costs 31.3.1    SmaI tool anowance                                                                                                              O        3                      3          -          -        -        -        -      -
                                                                    -        2          -          -
0        3 31.3      Subtotal Period 31Collateral Costs                                                                                                                                3          -          -        -        -        -      -
Period 3f Period-Dependent Costs 3f.4.1    Insurance 3f.4.2    Property taxes                                                                                                      1            0        1                      1 3f.4.3    Heavy equipment rental                                    79                                                                  12        91                      91 3f.4.4    Plant energy budget 3f.4.5    Security Staff Cost                                                                                              155          23      179                      179                                                                                        2,569 3f.4.9    Utaity Staff Cost                                        -                                                      110          16      126                    126                                                                                        1,594 3f.4      Subtotal Period 3WPeriod-Dependent Costs                  79                                                    266          52      396                    396                                                                                        4,163 3f.0      TOTALPERIOD 31 COST                                      568          -          -                              310          132    1,010                  1,010        -                                                                  4.336      4.323 PERIOD 3 TOTALS                                                  14,948          664          24        -      7.524  164.475      26,158  213,793      9,495    171,591      32.707              1.050                -      508    252.126  122,930  2,085,694 TOTALCOST TO DECOMMISSION                              9.296    57,845      11.199      7,212      30.933  56,640    481,317      117.614  772,058    516,078      231,584      34.396    319.826  233,906    3,877      976      508  31,646,710  905,345  5,788.586 TLG Services, Inc.
 
Cooper Nacka, Sotation                                                                                                                                                                                                                            DocumentN01-1590.002, Rev. I De-i-~muioning Cast An.aLyxia                                                                                                                                                                                                                        Appendix C, Page 12 of 35 Table C-1 Cooper Nuclear Station 2014 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Situ    LLRW                                    NRC      Spent Fuel    Situ    Processed          Burial Volumes              Burial I          Utilityand Activity                                                          Decon Removal Packaging Transport  Processing  Disposal    Other      Total    Total LIc.Turm. Management  Restoration  Volume  Class A  Class B Claus C  GTCC      Processed  Craft    Contractor Index                      Activity Descriptin                    Cost  Cost    Costs    Costs      Costs      Costs      Costs    Continaencv Costs  Costs      Costs      Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Wt. Lbs. Manhours  Manhours TOTALCOST TO DECOMMISSIONWITH 17.97% CONTINGENCY:                                          $772,058 thousands of 2008 dollars TOTALNRC UCENSE TERMINATIONCOST IS 65.55% OR:                                              $606,078 thousands of 2008 dollars SPENTFUEL MANAGEMENTCOST IS 30% OR:                                                        $231,584  thousands of 2008 dollars ON-NUCLEARDEMOUTION COST IS 4.46% OR:                                                      $34,396 thousands of 2006 dollars TOTALLOW-LEVE RADIOACTIVEWASTE VOLUMEBURIED (EXCLUDINGGTCC):                                  238,758 cubic feet TOTALGREATER THANCLASS C RADWASTE VOLUMEGENERATED:                                                600 cubic feet TOTALSCRAP METAL REMOVED:                                                                      30,345 tons
      'OTALCRAFT LABOR REQUIREMENTS:                                                                905,346 man-hours End Notes:
Weu- indicates that this actsty not charged as decommissioning expense.
a - indicates that this activity performed by decommissioning staff.
0 - indicates trat this value is less than 0.5 but is non-zero.
a ceal cotaining"-" indicates a zero value TLG Services, Inc.
 
0 Cooper NuclearStalin                                                                                                                                                                                                                            DocumentN01.1590-002, Rev. I Appendix r, Page 13 of 35 DecommissioningCoal Analysis Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Situ  LLRW                                        NRC        Spent Fuel      Site    Processed            Burial Volumes              Burial IaUoiy              end I Activity II Ind..                      A*tlvllv I*&#xa2;* ;'inl]nn Decon Cnst Removal cost Packaging costs Transport costs Processing Costs Disposal Costs Other Costs Total Continaeny Total Casts Lic. Term.
Costs Management Costs Restoration Costa Volume Cu. Feet Class A Cu. Feet Class B    Class C Cu. Feet Cu. Feet GTCC Cu. Feet Processed Wt. Lbs.
Craft Manhours Contractor Manhours Index                    Acdvttv Description I
PERIOD Ia -Shutdown through Transition Peried 1a Direct Decommissioning Activties Sa.1.1    SAFSTOR site characterization survey                                                                        346            104    450        450 130            20    150        150                                                                                                        1,300 la. 1.2    Prepare preliminary decommissioning cost la.1.3      Notificion of Cessation of Operations                                                                                              a la.1.4      Remove fuel &source material la.1.5      Notilicationof Permanent Defueling                                                                                                  a la.e  16    Deactivate plant systems &process waste 200            30    230        230                                                                                                        2,000 la.1.7      Prepare and submit PSDAR 130            20    10          150                                                                                                        1,300 la.1.8      Review piant dwgs &specs.
1l.1.9      Perform detailed red survey 100            15    115        115                                                                                                        1,000 10.1.10    Estimate by-product inventory 100            15    115        115                                                                                                        1,000 1:.1.11    End product description 150            23    173        173                                                                                                        1,500 la.1.12    Detailed by-product inventory                                                                              100 15    115        115                                                                                                        1,000 la.1.13    Define major work sequence 310            47    357        357                                                                                                        3,100 1.1.14      Perform SER and EA o0o          75    575        575                                                                                                        5,000 1a8..15    Perform SitsSpecttc Cost S"udy Activity Specifcations la.16,1.1 Prepare plant and facilies for SAFSTOR                                                                                        74    566        566                                                                                                        4,920 63    479        479                                                                                                        4,167 Ia.1.16.2 Plant systems                                                                                                417 47    359        359                                                                                                        3,120
      ,a.1-16.3 Plant structures and buildings                                                                                312 200            30    230        230                                                                                                        2,000 18.1.16.4 Waste management
* 200            30    230        230                                                                                                        2,000 la.1.16.5 Facilityand site dormancy
* 1,621            243  1,864      1,864                                                                                                        16,207 la:1.1816 Total Detailed Work Procedures
                                                                                      *    - -                    -          l11            18    136        136                                                                                                        1,183 10.1.17.1 Plantsystems 120            18    138        138                                                                                                        1,200 10.1.17.2 Facilitiycloseout &dormancy                                          *    -              -      -
238            36    274        274                                                                                                        2.383 la.1.17    Total                                                              -    -                .      -
la.1.18    Procure vacuum drying system                                                                                  10            2    12          12                                                                                                          1]0o 1l.1,19    Draintde-energize non-cont. systems la 1,20    Drain &dry NSSS 1I.1.21    Drainlde~energbe contaminated systems                                                                                              a 1:.122      Oeconssecure contaminated systems                                                                                                                                                                                                                      35.890 3,935            642  4.577      4,577 la.1        Subtotal Period 1aActivity Costs Penod 18 Collateral Costs 18.3.1      Spent Fuel Capital and Transfer                        -        -                      -      -        10,335          1,550 11,886                    11.888 6
la.3.2      Corporate Overheads                                      *  -                          -      -        3,105            468  3,570      3,570 18.3        Subtotal Period 18 CoUeateralCosts                      -        .        -                    -        13.440          2,016 15,456      3.570        11,888 6
Period 18 Period-Dependent Costs la.4.1      Insurance                                                                                                1,600            160  1,760      1,760 10.4.2      Property taues                                                                                                  4            0      4            4 la,4.3    Health physics supplies                            370                                                                    93    463        463 la.4.4      Heavy equipment rental                              368                                                                    55    423        423 73          -              19    100        100                                          1,575                                  14,445              1 18.4.5      Disposealof DAW generated 18.4.6    Plant energy budgel                                                                                        927            139  1,066      1,066 1a.4.7    NRC Fees                                                                                                    706            71    776        776 a8.4.8  Emergency Planning Fees                                                                                  1,185            118  1,303 10.4.9      Spent Fuel Pool OAM                                                                                        745            112    857                      857
        'a.4.10  ISFSI Operating Costs                                                                                          85          13    98          -              98 6,021            903  6.924      6,24                                                                                                      157,471 1..4.11    Security Staff Cost TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                                                                                              Document NI01.1590-002, Rev. 1 DecomnmissionintgCast Annalysis                                                                                                                                                                                                                          Appendix C, Page 14 of 35 Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollarsu)
Off-Site  LLRW                                          NRC        Spent Fuel      Site    Processed          Burial Volumes              Burial I            Utility and I I Activity                                              Decon    Removal  Packaging  Transport  Processing Disposal      Other        Total      Total Lic. Tenn. Management  Restoration  Volume  Class A  Class B  Class C  GTCC    Processed    Craft    Contractor m  InnA*                    A*nYl*
* nn1*n        Cost    Cost      Costs      Costs      Costs    Cests        Costs    Contingencv  costs    Costs        Costs        Costs      Co. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Wt. Lbs. Manhours  Manhours n ex                    Ac &#xfd;        c at n Period la Period-Dependent Costs (continued) la.4.12    UtilityStaff Cost                                                                                    -        22,690          3,403 26,093      26,093                                                                                  S-        -      423.400 1a.4        Subtotal Period Ia Period-Dependent Costs              738                                            73      33,962          5,087 39,867      37,609          2,258                          1.575                                14.445          5    580,871 la.0        TOTAL PERIOD oa COST                                    738                                            73      51,338          7.745 59,901      45,757        14,144                          1,575                                14,445          5    616,761 PERIOD lb - SAFSTOR Limited DECON Activities Period l b Direct Decornmissiornng Actevities Decartarinaion of Site Buildings lb.1.1.1    Reactor                                      2,929      -                                                                    1.465  4,394        4,394                                                                                  -    68,438          -
l1b.1.1.2 Augmented Radwaste                                52                                                                              26      78            78                                                                                        1,562 lb.1.1.3 Miscellaneous Struaurns - Contaminated            376                                                                              188    565          565                                                                                          8.542 lb.1.1.4    Mult-Purpese Facility                            68                                                                              34    101          101                                                                                        2.036 lb.1.1.5 Radwaste                                          158                                                                                79    237          237                                                                                          4.761 lbit.1.6 Turbine                                          520                                                                              260    780          780                                                                                        15.667 1.1.1      Totals                                      4.103                                                                            2,052  6,155        6,155                                                                                        101,008 10b.1      Subtotal Period lb Activity Costs            4.103                                                                            2,052  6.155        6,155                                                                                        101.006 Period lb Additional Costs lb.2.1      Spent Fuel Pool Isolation                                .-                                                    9,407          1,411 10,818      10,818                                                                              134,329    10.002 1b.2.2      Asbestos Insulation Disposal                            773            1        65                  558          -            265  1,662        1,662                                        10,333 0b.2      Subtotal Period l b Additional Costs                    773            1        65                  558        9,407          1,676 12,480      12,480                                        10.333                                134.329    10,002 Period lb Collateral Costs lb.3.1      Decon equipment                                713                                                                              107    820          820 l b.3.2    Process liquid waste                          229                    74        392                448                          293  1,436        1,436                                        1.561                                93,644      304 10b3.3 Small tool allowance                                -          70                                                                    11      81            81 1b.3.4      Spent Fuel Capital and Transfer                                                                                1,510            227  1,737          -          1.737 lb.3.5      Corporate Overheads                                                                                  -            768            115    880          880 1b.3        Subtotal Period l b Collateral Costs          942        70        74        392                448        2,276            752  4,954        3,217          1,737                          1,561                                93,644        304 Perod lb Period-Dependent Costs lb.4.1      Decon supplies                              1,156                                                                              289  1,445        1,445 1b.4.2      Insurance                                                                                                        121            12    133          133 lb.4.3      Property tones                                                                                              -        1            0      1            1 1b.4.4      Health physics supplies                                473                                                                      118    592          592 1b.4.5      Heavy equipment rental                                    91                                                                    14    104          104 1b0.4      Disposal of DAW generated                                              5          3                    81          -              21    110          110                                        1,741                                15.968          5 0b.4.7 Plant energy budget                                                                                                  229            34    203          263 1b.4.6      NRC Fees                                                                                                          174            17    191          191 lb4.9      Emergency Planning Fees                                                                                          292            29    321                        321 1b04.10 Spent Fuel Pool O&M                                                                                                  184            28    211                        211 1b.4.11 ISFSI Operating Costs                                                                                                    21            3      24          -              24 1b.4.12 Security Staff Cost                                                                                                1.485            223  1,707      1,707                                                                                                      X30829 1b.4.13 Utlity Staff Cost                                                                                              -    5,595            839  8,434        8.424                                                                                                    104,400 10.4        Subtotal Period 1b Peoitod-Dependent Costs  1,156      564            5          3                    81      8,101          1,628 11.538      10,981            557                          1,741                                15,908          5    143,229 1b.0        TOTAL PERIOD Ib COST                        6.201    1.407          850      480                1,087      19.783          8,107 35,126      32,833          2,294                        13,635                                243,942  111,318      143,229 TLG Services, lne,
 
Cooper Nuclear Station                                                                                                                                                                                                                                    Document NO1.1590-002,Rev. I Deromnmissonieong Cost Analysis                                                                                                                                                                                                                                Appendix C, Page 15 of 35 Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                            NRC      Spent Fuel      Site    Processed            Burial Volumes              Burial /            Utilty and Activity                                            Decon  Removal  Packaging      Transport  Processing  Disposal    Other        Total        Total  LIc. Term. Management  Restoration  Volume  Class A  Class B    Class C  GTCC    Processed    Craft    Contractor Index                    Activt Description        Cost    Cost        Costs          Costs      Costs      Costs      Costs    Contln en      costs    costs            s      Costs      Cu. Feet Cu. Feet Cu. Feet Co. Feet  Co. Feel  Wt Lbs. Manhours  Manhours PERIOD lc - Preparations for SAFSTOR Dormancy Period 1c Direct Decommissioning Activities 1c.1.1      Prepare support equipment for storage                  387                                                                          58      445        445                                                                                          3.000 1c.1 .      Inslall containment pressure equal. lines              31                                                                                                                                                                                                700 5      36            36 Ic.1.3      Interim survey prior to dormancy                                                                                    733            220      953          953                                                                                        15,696 1c.1.4    Secure building accesses                                                                                                                      a 1c. 1.5    Prepare &submit interim report                                                                                          58            9      67            67                                                                                                        583 1c.1        Subtotal Period 1cActivity Costs                      419                                                            791            291    1,501        1,501                                                                                        19,396          583 Period Ic  Collateral Costs Ic.3.1      Process iquid oaste                          235                    76        403                    460                        301    1,475        1,475                                        1,603                                  96.195        313 ic.3.2      Small to0 altuwance                                                                                                                  0        3            3 1c.3.3      Spent Fuel Capital and Transfer                                                                                    1,527            229    1,756          -          1,756 1c.3.4    Corporate Overneads                                                                                      -          774            116      890          890 lc.3      Subtotal Period lc Collatera Costs            235                    76        403                    460      2,301            646    4,124        2,368        1,756                          1,603                                  96,195        313 Period 1 c Period-Dependent Costs 0l.4.1    Insurance                                                                                                            122            12      134          134 1c.4.2    Property taces                                                                                                          1            0        1            1 IC.4.3    Helth physics supplies                                160                                                                          40      200          200 1c.4.4    Heavy equipment rental                                  92                                                -                          14      105          105                                          393 lc.4 5    Disposal of DAW generated                                                                                  18        -                5      25            25                                                                              3,601          1 lc.4.6      Plant energy budget                                                                                                  231            35      266          266 lc.4.7    NRC Fees                                                                                                              176            18    194          194 1c.4.8    Emergency Planning Fees                                                                                              295            30      325          -            325 le.4.9    Spent Fuel Pool O&M                                                                                                  186            28      214                        214 1.4.10      ISFS1Operatong Costs                                                                                                    21            3      24          -            24 1c.4.11    Security Staff Cost                                                                                                1,501            225    1,726        1,726                                                                                                      39,260 1C.4.12 U~ty Staff Cost                                                                                                      5,657            849    6,505        6,505                                                                                                    105,560 1c.4      Subtotal Period Ic Period-Dependent Costs              252            1            1                      18    8,191          1257    9,720        9,157          563                            393                                  3,601          1    144,820 1c.0      TOTALPERIOD 1c COST                          235    673            77        404                    478      11.283          2,195  15,345      13,026        2,319                          1,996                                  99,796    19,710    145,403 PERIOD I TOTALS                                        8.437    2,818          162          866                  1,638      82,404        16,047  110,372      91,616        18,757                        17,205                                358,183  131.033    905,393 PERIOD 2a - SAFSTOR Dormancy wRh Wet Spent Fuel Storage Period 2a Direct Decommissioning Activities 2a.1.1      QuarteplyInspection 2a.1.2      Sermi-annualenvionmental survey 2a. 1.3    Prepare reports 2a 1.4      Bituminous roof replacement                                  -      -  .        .            .          -            63            9      72            72 20.1.5      Maintenance supplies                                        -              .    .            .503                                126      629        629 2a.1        Subtotal Period 2a ActivityCosts                            -      . .          .            .          .          568            135      701        701 Period 2a Co/Lateral Costs 2B.3.1      Spent Fuel Capital and Transfer                            -                      .            .          -      26.468          3,970  30,435          -        30,435                            -        -
2a.32      Corporate Overheads                                        *                    .            .          -        4,139            621    4,759        4,759 20.3        Subtotal Period 2a Collateral Costs                        -.                    -            .          -      30,604          4,501  35,195        4,759        30,435                    .      -
Period 2a Period-Dependent Costs 2a.4.1      Insurance                                                                                                          1,962            196    2,158                      2,158                                    .          -
2a.4.2      Property laces                                                                                                          16            2      18          -            18 2a.4.3      Health physics supplies                                344                                                                          88      430          430 4LG Services, Inc.
 
0 DocumentN01-1590-002, Rev. I Coop~er Nuclear Station Appendix C, Page 16 of 35 Decomsmissioning CastAnaslysis Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site  LLRW                                        NRC      Spent Fuel      Site    Processed            Burial Volumes              Burial /            Utility and Decon Removal  Packaging  Transport  Processing Disposal    Other      Total        Total Lic. Teom. Management  Restoration  Volume  Class A  Class B    Class C  GTCC    Processed  Craft    Contractor IActivity                                                                                                                  Continmescy    Costs    Costs      Costs        Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Cu. Feet  Wt, Lbs. Manhours  Manhours E  In*BX                    AC*V*  *cno[*      H      Cost  Cost    Costs      Costs      Cost. Costs    Costs n ex Peoted 2a  Period-Dependent Costs (continued) 2a.4.4      Disposal of DAWgenerated                                          13                            198        -              52    270        270          -                            4.267                                  39,139        13 2a.4.5      Plant energy budget                                                                                      742            111    853        -            853 20a.4.6    NRC Fees                                                                                                  807            81    887        887          -
2a.4.7      Emergency Planning Fees                                                                                3,374          337    3,712                    3.712 2a.4.8      Spent Fuel Pool O&M                                                                                    2,984          448    3,431                    3,431 2a.4.9      ISFSI Operating Costs                                                                                    340            51    391                      391 20.4.10    Security Staff Cost                                                                                    17,728        2,659  20,387                  20,387                                                                                    444,561 2a.4.11    Utity Staff Cost                                                                                      18.816        2,822  21,639                  21,639                            -      -329,769 20.4        Subtotal Period 2a Period-Dependent Costs            344        13                            198    46,768        6,845  54,176      1,587      52,588                          4,267                                  39,139        13    774,330 344        13                            198    77,939        11,571  90,072      7,048      83,024                          4.267                                  39,139        13    774,330 20.0        TOTALPERIOD 2a COST PERIOD 2b. SAFSTOR Dormancy with Dry Spent Fuel Storage Period 2b  Direct Decommissioning Activities 2b.1.1      Quarterly Inspection 2b.1.2      Semi-annual environmental survey                                                                                                  a 2b.1.3      Prepare reports 2b.1.4      Bituminous roof replacement                                                                              432            65    497        497 2b..1.5    Maintenance supplies                                                                                    3,453          863    4,317      4,317 2b.1        Subtotal Period 20 ActivityCosts                                                                        3,886          928    4,814      4,814 Pertod 2b Collateral Costs 2b.3.1      Spent Fuel Capital and Transfer                                                                        18.092        2,714  20.806                  20,806 2b.3        Subtotal Period 2b Collateral Costs                                                                    18,092        2,714  20,806                  20,800 Period 2b  Period-Dependent Costs 2b.4.1      InsuSrnce                                                                                              S11.977        1,198  13.174                  13.174 2b.4.2      Property tooas                                                                                            110            11    121          -          121 2b.4.3      Health physics supplies                            1,981                                        -                      495    2,476      2,476 2b.4A.      Dopoe l of DAWgenerated                                          80        44                1,268        -            332    1,725      1,725          -                          27,278                                250,212        84 2b.4.5      Plant energy budget                                                                                    2,546          382    2,928                    2,928 2b.4.6    NRC Fees                                                                                                5,536          554    6,090      6,090 20.4.7    Emergency Planning Fees                                                                                23,161        2,316  25,477                  25,477 20.4.8      ISFS1Operating Costs                                                                                    2,332          350    2,682                    2,682 2).4.9    Security Staff Cost                                                                                    70,072        10,511  80,583                  80,583                                                                                  1,547,177 2b.4.10    UtilityStaff Cost                                                                                      51,313        7,697  59,010          -        59,010                                                                                    916.846 1,981        80        44                1.268  167,047        23,845  194,266      10,290      183,976                        27,278                                250.212        84  2.464,023 2b.4      Subtotal Period 20 Peorid-Dependent Costs 2b.0      TOTALPERIOD 2b COST                                1,981        80        44                1.268  189,025        27,487  219,886      15,104      204,781                        27.278                                250.212        84  2.464,023 31,545                                289,351        97  3,238,353 PERIOD 2 TOTALS                                                2.325        93        51                1.467  266.964        39,058  30%,957    22,152      287,805 PERIOD 3 - Reactivate Sits Following SAFSTOR Dormancy Peaod 3a Direct Decommissioring Acrvities 32.1.1    Prepare preliminary decommnssioning cOst                                                                  130            20    150        150                                                                                                      1,300 3a.1.2    Review plant dwgs &specs.                                                                                460            69    529        529                                                                                                      4,600 3a.1.3    Perform detailed red survey 3a.1.4    End product description                                                                                    100            15    115        115                                                                                                      1,000 3a.1.5    Detailed by-product inventory                                                                              130            20    150        150                                                                                                      1,300 3a.1.6    Define major work sequence                                                                                750          113    863        863                                                                                                      7,500 310            47    357        357                                                                                                      3,100 3a.1.7    Perform SER and EA 3a.1.0    Perform Site-Speolc Cost Study                                                                            500            75    575        575                                                                                                      5,000 3a.1.9    Prepare/submit License Termination Plan                                                                  410            61    471        471                                                                                                      4,090 3a.1.10    Receive NRC approval of termination plan                                                                                          a TLG Service., Inc.
 
Doeumnent N01-1590.002, Rev. I Cooper NuclearStation Appendix C, Page 17 of 35 DecommissioningCost Analysis Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sits  LLRW                                          NRC      Spent Fuel    Site      Processed          Burial Volures            Burial I            Utilityand Activity                                            Decon Removal  Packaging  Transport Processing Disposal    Other        Total        Total  Lic.Term. Management Restoration  Volume  Class A Class B Class C    GTCC Processed      Craft    Contractor Index                    ActivSitDescription        Cost  Cost    Costs    Costs      Costs    Costs      Costs    Contingenc    Costs    Costs      Costs      Costs      Cu. Feet Cu. Foet Co.Fecl Ca. Fot  Cu. Feet  WLtLbs. Manhours  Manhours ActivitySpecifiations 737            ill      848        763                      85                                                                          7,370 3a.1.11.1 Re-activate plant &temporary facilities                                                                                                                                                                                                              4,167 30.1.11.2 Plant systems                                                                                              417            63      479        431                      48 710            107      817        817                                                                                                  7,100 3a.1.11.3 Reactor internals 650            98      748        748                                                                                                  6,500 3a.1.11,4 Reactor vessel                                                                                                                                                                                                                                          O5D 3a.1.11.5 Sacrif-al shield                                                                                              50              8      58          58 100              15      115        115                                                                                                  1,00O 3a.1.1 1.6 Moisture separatorslroheateo                                                                                                                                          "92 160            24      184          92                                                                                                  1.600 3a 11, 7 Relnforced concrete 209              31    240        240                                                                                                  2,088 3a.,. 1.1 Main Turbie                                                                                                                                                                                                                                          2,088 3a.1.11.9 Main Condelsers                                                                                            209              31    240        240 200              30    230        230                                                                                                  2,000 3a. 1.11.10 Pressure suppression structure 160            24      184        184                                                                                                  1,600 3a.1.1111 Dryrele                                                                                                                                                                                                                                              3,120 3a 1.11 2 Plant structures & buildings                                                                              312            47      359        179                      179 3a.11.13 Wastse asagement                                                                                            460            69      529        529                                                                                                  4.600 14    104          52                      52                                                                            900 3a.1.1 1.14 Facility & site    ciut                                                                                  90                                                                                                                                    44,633 4.463            669    5,133      4,677                    456        -              -                -
3.1.11      Total Plann & site Preparations 240              36    276        276                                                                                                  2,400 3a.1.12    Prepare dismantling sequence 3a. 1.13 Plant prep. &temp. svces                                                                                  2,700            405    3,105      3.105 140              21    181          161                                                                                                  t1,400 3s.1,14    Design vater ciearnup system 3a.1.15    Rigging/Cont Cntt Envlps/totlitgletc.                                                                  2,100            315    2,410      2,415 3a..116    Procure casks/finers & containers                                                                        123              18    141          141                                                                                                  1.230 3a, 1      Subtotal Period 3a Acivity Costs                                                                      12,558          1,883  14,439      13.683                    456        -                          -      -                              77,559 Perod 3a Period-Dependent Costs 3a.4.1      'osuraro                                                                                                420            42      462        462 3a.4-2      Propefry tanes                                                                                              4              0      4          4 324                                                                                    405 3..4.3      Healt physics supplies                                                                                                    81    405 3a.4.4      Heavy equipment rental                              368                                                                  55    423        423 4        2                  62        -              16      84          84                                      1.329                              12,190        4 3a.4.5      Disposal of DAWgenerated 3a.4.6      Plant energy budget                                                                                      927            139    1,066      1,066 3a.4.7      NRC Fees                                                                                                249              25    274        274 2,855            428    3,283      3,283                                                                                                  65,179 3a.4.8      Security Staff Cost
                                                                                                                -      14,190          2,128  16,318      16,318                                                                                                2 258,629 3a.4.9      UtilityStaff Cost 691          4        2                  62    18,644          2,915  22,318      22,318                                        1,329                              12.190        4    323,807 3a.4        Subtotal Period 3a Period-Dependeol Costs 3a.0        TOTAL PERIOD 3a COST                          -      691          4        2                  62    31,200          4,799  36,758      36,302                    456                1,329                              12.190        4    401,366 PERIOD 3b - Decomrissioning Preparations Penod 3b Direct Decommissioning Activities Detailed Work Procedures 3b.1.1.1 Plant systems                                                                                              473              71    544        490                                                                                                  4,733 400              60    460        460                                                                                                  4,000 3b.1.1.2 Reactor internals 135              20      155          39                    118                -      -                -                              1,350 3b.1.1.3 Remaining budings 100              15      115        115                                                                                                  t1.000 3b.1.1.4 CRDousigs & Nis 100              15      115        115                                                                                                  1,000 3...1. 5    Incoreinstumrentation 200              30    230          230                                                                                                  2.000 31,.1. 6 Removal primary cosotarnmnt 363              54    417        417                                                                                                  3,630 3b.1.1.7    Reactor vessel 120              18      138          69                      69        -              -                                                1,200 3b.1.1.8 Faciity ckOo*out 120            18      138        138                                                                                                  1,200 31b.1 .9 Sacriofna shreld 100            15      115          56                                                                                                  1,000 3b.1.1.10 Reinforced concrete 3b.1 111 Main Turbie                                                                                                208              31    239          239                                                                                                  2,080 209              31    240          240                                                                                                  2,088 3b.1.1.12 Man Condensers TLG Services, Inc.
 
Cooper Nuclear Statdion                                                                                                                                                                                                                            Document NO1-1590-002,Rev. 1 DecuraraissioniagCost Anobait.                                                                                                                                                                                                                          Appendix C, Page 18 of 35 Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
On-site    LLRW                                        NRC      Spent Fuel    Site    Processed            Burial Volumes              Burial I            UUtty and I jA tinvti                                              D0con  Removal  Packaging    Transport  Processing  Disposal    Other      Total      Total Lie. Termo  Management  Restoreaton  Volume    Class A  Class B    Class C  GTCC    Processed    Craft    Contractor n  exU                  *V*      L~~    l      Cost    Cost      Costs        Costs      Costs      Costs      Costs    Contingency  Costs    Costs        Costs      Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet  Cu. Feet  WL. Lbs. Manhourm  Manaoure I Detaied Work Procedures (continued) 3b.1.1.13 Moisture separators& reheatars                                                                                      200            30    230        230                                                                                                      2,000 3b.1.1.14 Radwaste building                                                                                                  273            41    314        283                      31                                                                            2.730 3b.1.1.15 Reactor building                                                                                                    273            41    314        283                      31                                                                            2,730 3b.1.1      Total                                                                                                          3.274            491  3,765      3,405                      360                                                                            32,741 3b.1        Subtotal Period 3b Acivity Costs                                                                                3,274            491  3,765      3,405                      360                                                                            32,741 Period 3b Additioeal Costs 3b.2.1      Site Characterization                                                                                          5,395          1,619  7,014      7,014 3b.2        Subtotal Period 3b Additional Costs                                                                            5,390          1.619  7,014      7,014 Pedod 30 Collateral Costs 3b.3.1      Decon equipment                              713                                                                                107    820        820 3b.3.2      DOC ldaff relocation expenses                                                                                    912            137  1,049      1,049 3b.3.3      Pipe cutting equipment                                t1,000                                                                    150  1,150      1,150 3b.3        Subtotal Period 3b Collateral Costs          713    1,000                                                      912            394  3,019      3.019 Period 3b Period-Dependent Costs 3b.4.1      Decon srupplas                                22                    -                                            -                5    27          27 3b.4.2      Insurance                                                                                                        246            25    270        270 3b.4.3      Property tuaes                                                                                                      2              0      2          2 3b.4.4      Health physics supplies                                179                                                                      45    224        224 3b.4.5      Heavy equipment rental                                  184                                            -                        28    212        212 3b.4.6      Disposal of DAW generated                                                                                35      -                9    48          48                                          754                                  6,913          2 3b.4.7      Plant energy budget                                                                                              465            70    534        034 3b.4.8      NRC Fees                                                                                                        125              12    137        137 3b.4.9      Security Staff Cost                                                                                            1,431            215  1,648      1,646                                                                                                    32,679 3b.4.10      DOC Staff Cost                                                                                                4,378            657  5.035      5.035                                                                                                    58,560 3b.4.11      Utlity Staff Cost                                                                                      -      7.114          1,067  8,181      8.181                                                                                  -        -      129,669 3b.4        Subtotal Period 3b Period-Dependent Costs    22      363                                              35  13,781          2,133  16,317      16,317                                          754                                  6.913          2  220,907 3W.0        TOTAL PERIOD 3b COST                          735    1,363                                              35  23,342          4,830  30,115      29,755                      360                754                                  6,913          2  253,648 PERIOD 3 TOTALS                                          735    2,055                      3                      97  54,542          9,435  68,872    66.056                      816              2,083                                  19,104          6  655,014 PERIOD 4a -Large Component Removal Period 4a Diract DecomnmissioningActivites Nuclear Steam Supply System Removal 4a.1.1.1    Recirculation System Piping & Valves          18        70            14        14            25      272                      101    512        512                                100      897                                119,606    2,487 4a.1.1.2 Recircutatio Pumps &Motors                          6      28            11        26                    321                        95    488        488                                -      1,188                                132,880    1,125 4a.1.1.3 CRDMs &Nis Removal                                24      139        377          68                    317                      174  1,099      1,099                                        6,935      -          -              126,494    3,972 4a,1.1.4 ReactorVessel Internals                          86    1.959      3,871        912                  4,981        155          5,222  17,185      17,185                                        1,878    1.377      344      -      359,044    18,900        888 4a.1.1.5 Vessel &Internals GTCC Disposal                                                          -              7,470        -            1,120  8,590      8,590                                                            -        508      89,497        -          -
4a.1.1.6 Reactor Vessel                                          5,054        906        351                  3,006        155          5,631  15,103      15,103                                -    14,106      -          -      -    1,447,089    18,900        888 4a.1.1      Totals                                        132    7,.50      5,179      1,371            25  16,367        309        12,343  42,977    42,977                                  100  25.004    1,377      344      508  2,274,810    45,384      1,776 Removal of Major Equipment 4a. 1.2    Main TurbiterGeneatorr                                  167        845        372        6.376                              1,138  8,898      8,898                              61,604                                        2,772,179    4,438 4a. 1 .3    Main Condensers                                        708        588        259        4,439                                940  6,932      6,932                              42,889                                        1,930,000    18,519 Cascading  Costs from Clean Budding Demolition 4a.1.4.1    Reactor                                                260                                                                      39    299        299                                                                                          2,486 4a.1,4.2    Augmented Radheuste                                      25                                                                        4    28          28                                                                                            235 4a.1.4.3    Radwaste                                                43                                                                        7    50          50                                                                                            359 TLG Servivea, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                                  Document N01-1590-002,Rev. I DeconmissioningCost Analysis                                                                                                                                                                                                                                                Appendix C, Page 19 of 35 Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars) off-Site    LLRW                                            NRC        Spent Fuel    Site        Processed                  Burial Volumes                Burial I            Utility and Decon    Removal      Packaging  Transport  Processing Disposal      Other        Total          Total Lit. Term. Management Restoration    Volume      Class A    Class B    Class C  GTCC    Processed    Craft    Contractor 1
IActivity I*MAY                    A*VJ*
* MnT* M C,..s    Cos          Cost.      Coo.          uts Costs        C      os*
c*ts    Contlononen      Crste    Costs        Coto      Centst        C... Feat    Co. Feet  Cu. Feet  Co. Feet Co. Feet  WE Lbs. Munoutoos  Monhouts ex                      v        c of It          cost      cast        costs      costs      costs      C;0sts      Costs    ContInQencv      costs    costs        costs      costs        Cu Feet      Cu Fast    Cu Feet Cu Feet    Cu Fast    WL Lbs. Manhours  Manhours Cascading Costs from Clean Building Demolition (coninued) 4a.1.4.4 Turbine                                                  -    285                                  -                                      43      328          328                                                                                                  4.419 4a 1 .4    Totals                                                      613-                                  .                                      92      705          705                                                                                                  7,498 Disposal of Plant Systems 4a.1.5.1    Augmented Radwaste El 877AreslA                              203            28        28                    432                        166      857          857                                              2,055                                    172,205    5,668 4a. 1.5.2 Augmented Radwaste El 903 Ar.elA                                66            6          7                    104                        44      228          228                                                469                                    41,608    1,842 4a.1.5.3 Augmented Radmuste El 918 ArealA                                  52          10          9                    139                        50      260          260                                                765                                    55,345    1,432 4a.1.5.4 Augmented Radwaste El 929 ArealA                                  21            4          5          -            73                        25      127          127                                      -.        324                                    29,038      579 4a.1.5.5 Augmented Radwaste El 929 Aeal B                                  3            O          0            4      -                            1        8            8                                      38                                              1,529        75 4a.1.5.6 DRYWELLArealA                                                  457            85        84                  1,289                        458    2,373        2,373                                              5,726                                    513.627    12,634 4a. 1.5.7 DRYWELLArea16                                                  112              1        5            75          2                        41      235          235                                    806          10                                  33,576    3,384, 4a.1 .5'8 Turbine El 932 ArealB                                          324            16        86        1.477        -                          317    2,220        2,220                      -          15.808                                              641,963    9,170 4a 1.5.9 Turbine El 932 Area2C                                                                                                                          1        9                                      9                                                                -        237 4a 1.5.10 Turbine El 932 Ara3C                                            67                                                                          10      78                                    78                                                                -      2,083 4a. .5 11 YardArealB                                                    518            00      264        4,517        -                          852    6,201        6,201                      -          48,385        -                                  1,964,114    14,340 4a15        Totats                                                    1,831          202        487        6.073    2,040                      1,964  12,597      12,510                        87      65,016      9,348                                  3,453,003    51.444 4a 1.6      Scaffolding in support of decommissioning          -      2,049            24        11          168          23                      547    2,821        2.821                                  1,621        101                                    81,992    27,411 4a.1        Subtotal Period 4a Acviaty Costs                  132    12,816        6,828      2,500      17,081    18,430        309          17,025  74,831      74,844                        117    171,229      34,453      1,377        344      508  10,511,780  155,694        1,776 Period 4a Coulateml Costs 4a.3.1      Process iquid aste                                  61        -            21        113                    129                        82      409          408                      -                        451                            -        27,075        88          -
48.3.2      Small tool allowance                              -            90                                                                          14    104            94                      10                      -
4a.3        Subtotal Period 4a Collateral Costs                61        90          21        113                    129                        96      512          502                        10                    451                                    27,075        88 Perod 4a  Perod-Dependent Costs 4a.4.1      Decon supplies                                      49                                                                                    12      61            61 4a4.2      Insurance                                                                                                                549              55      604          604 4a4.3      Property laxes                                                                                                              4              0        5            4                        0 4.4.4      Health physics supplies                                      944                                                                        236    1,180        1,180 4as4.5      Heavy equipment rental                                    1,981                                                                        297    2,278        2,278 4a.4.6      Disposal of DAWgenerated                                                    26        14                    405        -              106      551          551                                              8,708                                    79,878        27 4a.47      Plant energy budget                                                                                                      9-87            148    1,135        1,135 484.8      NRC Fees                                                                                                                737              74      811          811 4a.4.9      Liquid Radwaste Processing Equipment/Services                                                                            420              63      483          483 4a.4.10    Security Staff Cost                                                                                                    3,199            480    3,679        3,679                                                                                                              73,036 4a'4.11    DOC Staff Cost                                                                                                        11,638          1,746  13,384      13,384                                                                                                            161,263 4.4.812    Uility Steff Cost                                                                                                    16,014          2,402  18,416      18,416                                                                                                            292,143 4a.4        Subtotal Period 4a Period-Dependent Costs          49    2,925            26        14                    405      33,548          5,619  42,586      42,585                          0            -      8,708        -                            79,878        27    526,441 4a.0        TOTALPERIOD 4o COST                              242    15,631          6.885      2,628      17,081    18,964      33,858          22,740  118,029      117,931                        98      171,229      43,613      1,377        344      508  10,618,740  155,809    528,217 PERIOD 4b - Site Decontamination Period 4b Direct Decommissioning Actvities 4b81.1      Remove spent fuel rocks                          262          33          78        68          -      1,348                        498    2,306        2,308                                              5,986                            -      537,141    1,004 Disposal of Plant Systems 4b.1.2.1 ContrlElO2 Areul-                                              280            7        39          674                                  176    1,176        1,178                      -          7.213                                              292,908    7,797 4b1 .2.2 Contro El 03 Amel C                                              8170                                                                      25      195          -                        195                                                                        5,155 4b.1.2.3 Control El 918 AealC                                              66                                                                          10      76                                    76                                                                        2,100 4b.1.2.4 Control El 932 AmealC                                            22                                                                          3      28                                    26                                                                          702 4b5.1.2.5 Intake                                                        101                                                                          15    118                                    116                                                                  -      3,136 4b.1,2.6 Mult-Purpose Fauility                                          198            3        14          239                                    88      541          541                                  2,558                                              103,862    5,430 4b 12.7 Radwaste El 877 ArealA                                          398            75        62          -        949                        353    1,838        1,836                                      -      5,097                                    377,917    10,930 MTG Services, Inc.
 
CooperNuclear Station                                                                                                                                                                                                                  Document N01.1590-002, Rev. I Appendix C, Page20 of 35 Decommissioning Cost Analysis Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Decon Removal Packaging Transport    Processing  Disposal    Other      Total      Total Lic. Tero. Management Restoration  Volume      Class A    Class B    Class C  GTCC    Processed      Craft      Contractor IActivity                                  Cost  Cost    Costs    Costs        Off-Sits Costs      LLRW Costs      Costs  Contingeney  Costs    NRC Costs      spent Fuel Costs      Sit e Costs    Processed Ca. Feet    Co. Feet    Cu.Burial Feet Volume ws Cu. Feet Cu. Feet  turLbs.
WtL  ialIU Manhours        tiita .. I Manhours n as                  - .-  Y-  I-..                                                                                                                                                                                                                -
Disposal of Plant Systems (continued) 4b.1.2.8 Radwaste EJ877 Aea2A                                                7                    113                      41    213        213                                            613                                      44.992      1,189 13                      201                      72    372          372                                          M,56                                      79.963      1,969 4b.1.2.9 Redwaste El 877 Area3A 10                      153                      68    351          351                                            684                                      61,153      3,015 4b.1,210 Radwase El 903 AnealA 29                      439                    165    856        856                                          1.955                                    175.093      5,282 4b11.2.11 Radwaste El 903 Area2A 7                    104                      37    190        190                                            463                                      41.66        1,029 4b.1.2.12 RadweseEl 903 Area3A 2                      30                      12      64          64                                            135                                    12.033        477 4b.1.2.13 Radwaste El 918 ArealA 3                    39                      15      75          75                                          201                                      15,667        448 4b.1.2.14 Radwasas El 918 Area2A 22                      338                    136    705        705                                          1,690                                    134,827      5,045 4b.1,2.15 Radwaste E 918 Area3A 4                      60                      22    115        115                                            266                                      23.735        680 41,h*2.16 Rawasis El 934 ArealA 12                      177                      72    370          370                                            808                                      70,665      Z663 4b.1.2.17 Radwaste El 934 A0ea2A 2                    24                      9      47          47                                            105                                      9.381        305 4b.1t...18 Radwaste El 949 ArealA                                                                                                                                                                                                    48,175      1,261 4b.1.2.19 Reactor El 1001 ArealA                                            8                    121                      45    230        230                                              537 4          64                                26    157        157                                689                                                27,979      1,681 4b.1.2.20 Reactor EC1001 Areal B 16                    246                      83    430        430                                  -      1.091                                      97,074      2,024 41b12.21 Reactor El 859ArealA 58            994      -                      269  1,771      1.U71                              10,641                                                432,136      12,411 41,b.2.22 Reactor EC859 ArealB 26                      401                    125    648        648                                  -      1,780                                    159,714      Z094 41b.12.22 Reactor El 859 Area2A 8          131                                38    247        247                                1,406        -                                      57,093      1,954 41,1.2.24 Reactor El 859 Area2B 9          -        137                      48    251          251                                            608                                      54,543      1,321 4b1,.2,25 Reactor al 859 Area3A 2          42                                15      93          93                                453                                                18,381        951 41.1.2.26 Reactor C 8599Ae3B 8                    117                      44    227        227                                  -          520                                    46,666      1,374 4b.1.2.27 Reactor El 859 Area4A 2          31      -                        9      59          59                                331        -                                      13,424        476 4b.1.2.28 Reactor El 859 Area4B                                                                                                                                                                                                                    1,798 17                      262                      85    443        443                                          1.163                                    104,381 41,1.2.29 Reactor El 859 Area5A 2          41      -                        16      98          98                                442                                                17.962      1,087 41,1.2.30 Reactor E 859 AreaSB 42            -        651                    275  1,424      1.424                                  -      2,892                                    259,190      10,497 4b11.2.31 Reactor El 903 AreaA 32            550                              201  1,240      1,240                              5,890        -                                      239.197      12.496 4b.1.2.32 Reactor El 903 ArealB 4b.1.2.33 Reactor EC903 Area2A                                              O                      6                      3      14            14                                -            226                                    2,372        120 11            190                                48    320          320                              2,039        -                                      82,815      1,915 4b,1.2.34 Reactor E 903 Area2B iI            -        167                      52    272          272                                  -          741                                    66,518        929 4b.1.2.35 Reactor EC903 Area3A 3            52      -                        14      90          90                                553        -                                      22,464        618 41.1.2.38 Reactor EC903 Area3B 4b.1.2.37 Reactor EC903 Area4                                                9                    136                      43    223          223                                            606                                      54,373        776 3            52                              14      90          90                                558                                                22,692        597 4b,1.2.38 Reactor El 903 Area4B 3                    52                      20    104        164                                            232                                      20,858        670 41,1.2.39 Reactor E6931 ArealA 40            692      -                      186  1,227      1,227                              7.412                                                301,017      8,410 4b,1.2.40 Reactor El931ArealB 2                    35                      14      74          74                                -          154                                    13,824        544 4b.1.2.41 Reactor E 931 Amea2A 0            I        0                      1      3            3                                  9          0                                        371          53 4b.1.2.42 Reactor El 931 Area2B 22                      336                    109    567          567                                          1,651                                    134,007      2,165 41,1.2.43 Reactor EC931 Area3A 1                                                                                        8-                                                  340          49 4b.1.2.44 Reactor El 931 Area3e                                              0                                              1      3            3 4      28                                                                                                                767 41.1.2.45 Reactor EC631Aea4C 1      8          -                                                                                          -          213 4b.1,.2.46 Reactor El 931 Area5C 10                    149                      54    278          278                                            662                                      59,432      1,472 4b.,1.2.47 Reactor EC959 ArealA 16          281      -                        87    554        554                                3,009                                              122,212      4,693 4b1,12.48 Reactor El 958 ArealB 4b1.1 .49 Reactor EC958 Arem2A                                            10          -        153                      49    253          253                                  -        681                                      61,083        080 1            12        7                      6      37            37                                125          33                                    8,024        263 41b1.2.50 Reactor El 958 Area2B 3                    48                      21    109        109                                            214                                    19,185        898 4b.1.2.51 Reactor El 958 Area3A 1            10        6                      7      39            39                                109          29                                    7,011        410 4b.1.2.52 Reactor El 958 Afem3B 41b1.2.53 Reactor El 976 ArealA                                              1                      16                      7      36            36                                            72                                    6,482        298 25            422                              104    703          703                              4,521                                                183,615      3,931 4b.1.2.54 Reactor El 976 ArealB 1                      13                      5    26          26                                              57                                      5,136        172 4b.1.2.55 Reactor El 976 Area2A 3            55      -                        18    114        114                                586                                                23,813      1,033 4b.1.2.56 Reactor El 976 Arma2B 3          -          50                    23    118        116                                  -          222                                    19,878      1,004 4b.1.2.57 Turbine 8SU2 ArealA 87          1,490      -                      335  2,313      2,313                              15,948                                                647.659      11,113 4b.1.2.58 Turbine El 812 AreamB 2          -          29                      13      67          67                                -          129                                    11,556        984 4b,1.2.59 Turbine El 812 Area2A 4b.1.2.60 TurObn El 892 Area2B                                            22            374      -                      112    721          721                              4,006                                                162,678      5,781 4b.1.2.61 Turbine C 882 Area3A                                              1          -          23                      10      52            52                                          101                                      9,017        451 145        2,478        -                      548  3,805      3,805                              26,533        -                                    1,077,531      17,302
          .3.62 Turbine EC882 Area3B 4b1,2 4b.1.2.63 Turbine EC903 ArealA                                              I          -          15                      6      32            32                                S          6988                                  6,127        232 TLG Services, Inc.
 
CooperNuclear Station                                                                                                                                                                                                                                              DocumentN01-1590.002, Rev. I Decommissioning Coast Analysis                                                                                                                                                                                                                                            Appendix C, Page 21 of 35 Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sits    LLRW                                            NRC        Spent Fuel      Sits        Processed              Burial Volumes              Burial I              Utilty and Activity                                                Decon    Removal  Packaging    Transport  Processing  Disposal    Other        Total        Total  Lie. Tanm. Management  Restoration    Volume    Class A  Class B    Class C  GTCC    Processed    Craft      Contractor SIndex                    Activt'y Description          Cost      Cost      Costs        Costs      Costs      Costs      Costs      Continocv    Costs    Costs        Costs        Costs        Cu. Foot  Ca        CFoFt Co.Foal    Cu. Feet Co. Feet  WI. Lbs. Manhours    Manhours Disposal of piord Systems (contnued) 4b.12.64 Turbine El 903 ArealB                                          974          46        241        4.133        "                        904    6,299        6,299                                  44,251                                          1,797,054    27.874 4b.1 .2.65 Turbine El 903 Area2A                                          5            1          1                                                  4      20            20                                      - -        42                                    3.729      142 4b. 1.2.66 Turbine El 903 Area2B                                        144            1          7          128                                    56    337          337                                    1,375                                              55,851      4.040 4b. 1.2.67 Turbine El 903 Area3B                                          3            0          2            35                                    9      47            47                        S
                                                                                                                                                                                                          -            376                                            15,251          97 4bd1.2.68 Turbine El 903 Area3C                                        108                                                                          19    124          -                        124            -                                                  -      3,412 4b.1.2.69 Turbine El 903 Ae&a4B                                          12            0          2          29                                    7      49            49                                    299                                              12,139        367 4b.1.2.70 Yard AreaiC                                                  197                                                                          30    227          -                        227            -                                                  -      5,770 4b.1 .2    Totals                                                    7,771        556      1,148        13,202    5,814                      5,535  34,027      33,227                            o00  141,342    27,486                                8,056,388    218,627 4b.1.3      Scaffolding in support of decommissioning        -      3,073          36          17          252        34                      821    4,232        4,232                                    2,431        151                                  122,986    41,117 Decontamination of Site Buildings 4b.1.4.1    Readsr                                        2.880      1,820        202        422        4,911    2.376                      3,310  15,922      15,922                                    52,579    39,538                                6,069,283    115,053 4b.1.4.2 Augmented Radwuast                                    52        19            4          6          23        60                        51    215          215                                      242      1,099                                  119,386      1,978 4b.1.4.3 Miscetanleous Strutures - Contaminated              368        167            15        42          759        62                      363    1,777        1,777                                    8,129      452                                  372,774    12,956 41.1 4.4 MuS-Purpose Facility                                  68        55            6        12          115        89                        90    437          437                                    1,234      1,567                                  205,066      3,237 4b 14.5 Radwasto                                            159          50            9        14          38      161                        141    572          572                                      404      2,953                                  310,769      5,9963 41,4.6 Turbine                                              526        142          35          51          64      633                        477    1,928        1.928                                      688    11,664                                1,193,496    18,679 4b.1.4      Totals                                        4,055      2,253        271        547        5,910    3,382                      4,432  20,850      20,850                                    63.275    57,271                                8,270.774    157,766 4b.1        Subtotal Period 4b ActivityCosts              4,318    13,131        942      1,800        19,364    10,578                    11,285  61,417      60,618                        800      207.048    90,895                                16,987.290    418,513 Period 4b Addiaonal Costs 49.2.1      ISFSI Decontamination                                      656            4        24                      55    1.192            369    2,290          -.          2,290          *            -      1,050                                  162,629    17,515        2,560 4b.2.2      Final Site Survey                                                        *          -                        -        1,205            362    1,567        1,567                                                                                          -          -        12.480 4b.2        Subtotal Period 4b Additional Costs                        656            4        24                      55      2.397            722    3,857        1,567          2,290                                1.050                                  162,829    17,515        15.040 Period 4b Collateral Costs 4b.3.1      Process liquid waste                            128        -            45        238                    271                        172    853          853                                                945                                  56,728        184 4b.3.2      Swall tool allowance                                        230                                                                          35    265          265 40.3.3      Decommissioning Equipment Disposition            -          -            99          50          62.1        94                        130    973          973                                    6.000        373                                  303,507          88 4b.3        Subtotal Period 4b Collateral Costs              128        230        133        287          621      355                        337    2,091        2,091                                    69000      1.319                                  360,233        272 Period 49  Period-Depondent Costs 4b.4.1      Decon supplies                                1,252        -                                                                        313    1,594        1,564 4b.4.2      Insurance                                        -                                                                  1,192            119  1,312        1,312 4b.4.3      Property tares                                              -                                                            10            1      11            11 4.4.4      Health physics supplies                                  2,373                                                                        593    2,966        2,968 4b.4.5      Heavy equipment rental                                    4,270                                                                        641    4,911        4,911 4b.4.6      Disposal of DAWgenerated                              -                  55          31                    876          -            229    1,191        1,191                                              18.832                                  172,741          58 4b.4.7      Plant energy budget                                                                                          -        1,691            254    1,945        1.945 4b.4.8      NRC Fees                                                                                                              1,601            160  1,761        1,761 4b.4.9      Liquid Radwaste Processng Equipment/Seruices                                                                            913            137  1,049        1,049 4b.4.10    Security Staff Cost                                                                                                  6.945          1,042    7,987        7,987                                                                                                              158,571 4b.4.11    DOC Staff Cost                                                                                                      24.622          3,693  28,315      28.315                                                                                                              339.977 4b.4.12    Utity Staff Cost                                                                                                    33,080          4,992  38,042      38,042                                                                                                              598,766 4b.4        Subtotal Period 49 Period-Dependent Costs      1,252      6,43            55          31                    879      70,053        12,144  91,053      91,053                                              18,832                                  172,741          59  1,097.314 4b.0        TOTALPERIOD 4b COST                            5.697    20.681      1,134      2,141        19,985    11,863      72,450        24,487  158,419    155,329          2,290        800      213.046    112.096                                17,682,890    436,358    1,112,354 PERIOD 4* - License Termination Perod4o    Direct Decommissioning Activities 4e. 1.1    ORISE confinrutary survey                                                                                                147            44    191          191 4e.1.2      Tenninatolicense 4e. 1      Subtotal Period 4e ActivityCosts                                                                                        147            44    191          191 TLG Services, Inc.
 
Cooper Nuclear    Station                                                                                                                                                                                                                            Docuentes NOI.1590-002, Revr.I Decommsosioninaog    Cast Analyasi                                                                                                                                                                                                                          Appeadiv C, Page 22 vf385 Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                        NRC        Spent Fuel      Site      Processed            Burial Volumes              Burial I                Utilityand Activity                                            Decon  Removal      Packaging  Transport  Processing  Disposal    Other      Total        Total Lic.Term. Management    Restoration    Volume    Class A Class B Class C    GTCC      Processed    Craft      Contractor Index                    Activit Description      Cost    Cost        Costa      Costs      Costs      Costs      Costa    Contingency    Costs    Costs        Costs        Costs        Cu. Feet  Cu. Feet Cu. Feet Cu. Feat Cu. Feet  WL.Lbs. Manhours        Manhours Period 4e AddiStonalCosts 4e.2.1    Final Site Survey                                        *            .          .            -                5.998        1,799    7,797      7,797                                                                                          165,605          6,240 4e.2      Subtotal Period 4e Additional Costs                      *            -          .            .        .        0,900        1,799    7.797      7,797                                                                                          165,605          6.240 Period 4e Collateral Costs 4e.3.1    DOC staff relocation expenses                                                                                      912          137    1,049      1,049 4e.3      Subtotal Period 4o Coiateral Costs                                                                                912          137    1,049      1,049 Period 4e Period-Dependent Costs 4e.4.1    Insurance 4e.4.2    Property taxes                                                                                                      3              0        3          3 4e.4.3    Health physics supplies                                795            -          -                                              199      993        993 4e.4.4    Disposal of DAWgenerated                                                3          1                    42      -                        57          57                                            907                                  8,324          3 11 4e.4.5    Plant energy budget                                                                                                140            21    161        161 4e.4.6    NRC Fees                                                                                                          532            53    585        585 4e.4.7    Security Staff Cost                                                                                              1,012          152    1,164      1,164                                                                                                          18.857 4e.4.8    DOC Staff Cost                                                                                                  4,458          669    5,126      5.126                                                                                                          57,357 4e.4.9    UtilityStaff Cost                                                                                        -      4,895          704    5,399      5,399                                                                                      -          -        74,643 4e.4      Subtotal Period 4e Perrod-Dependent Costs              795              3          1                    42    10,839        1,809  13,489      13,489                                              907                                  8.324          3      150,857 4e.0      TOTAL PERIOD 4e COST                                    795              3          1                    42    17,697        3,789  22,527      22,527                                              907                                  8,324  165.608        157,097 PERIOD 4 TOTALS                                        5,939    37,086        8,022      4,771        37.066  30,870    124,205        51,016  298,974    295,786          2,290        897      384,277  156,617    1,377      344      508  28,309,950  757,775      1,797,669 PERIOD Sb - Site Restoraion Period 5b Direct Decommissioning Activities Demolition of Remrainig Site Buildings 5b 1.1.1 Reactor                                                1,491                                                                      224    1,715                                1,715                                                                14,601 5b. 1.12 Augmented Radwaste                                        222                                                                        33    255                                    255                                                              -  2,119 5b.1.1.3 Control                                                  214                                                                        32    246                                    246                                                                  1,655 5b. 11.4 Intake Structure                                          523                                                                        78    602                                    602                                                                  5,621 5b.1.1.5 LLRW Sturage Pad                                          145                                                                      22      167                                    167                                                                1,227 5b 1.1.6 Miscet-,eous Structures -Clean                          1,196                                                                      179    1,375                                  1,375                                                                11,837 5b.1 .1.7 Miscellaneous Stuctums - Contaminated                      27                                                                      4      30                                      30                                                                  572 56.1.1.8 Mutt-Purpose Faciity                                      123                                                                      10      141                                    141                                                                1,982 5b.1.1.9 OWC Gas Generator                                            s1                                                                      3      20                                      20                                                                  283 5b.1.1.10 Office                                                    156                                                                      23      179                                    179                                                                1,920 5b.1.1.11 Radwaste                                                391                                                                        59    449                                    449                                                                  3,229 5.1.1.2 Seal Well                                                    17                                                                      3      20                                    20                                                                    166 5b.1.1.13 Sewage Treatment Area                                        4                                                                      1        5                                      5                                                                    53 5b.1.1.1.4 TransformnerYard                                          20                                                                      3      24                                      24                                                                  172 5b.1.1.15 Turbine                                                2,596                                                                      389    2,985                                  2,985                                                                40,503 5b.1.1.16 Turbine Pedestal                                        277                                                                        42    318                                    318                                                                  2,100 5b.11      Totals                                                7,418                                                                    1,113    8,531                                  8,531                                                                88,040 Site Closeout Activites 51.1 .2    Reonoe Rubble                                          424                                                                        64    488                                    488                                                                  3,286 5b. 1.3    Grade &landscae site                                    578                                                                        87    665                                    665                                                                  1,578 5b. 1.4    Final report to NRC                                                                                                156            23      179        179                                                                                              -
* 1,560 8,421                                                        156          1,286  9.863          179                                                                                          92.904          1,560 5b. 1      Subtotal Period 5b ActivityCosts                                                                                                                                              9.684 Period 5b Additional Costs 487                                                                              611                        611          -
5b.2.1      ISFSI Demolition                                                                                                                  80                                                                                                                4,336            160 5b.2.2    Concrete Crushing                                      499                                                                        76    582                                    5a2                                                                3,1045 5b.2.3    Cofferdam                                              458                                                                        69    527                                    527                                                                5,130 TLG Services, Inc.
 
Document N01.1590-002, Rev. 1 Cooper NuclearStation Decommisiwoning Coast Analysis                                                                                                                                                                                                                                        Appendix C, Page 23 of"35 Table C-2 Cooper Nuclear Station 2014 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site  LLRW                                        NRC      Spent Fuel    Site      Processed            Burial Volumes              Burial I            Utility and Activity                                                            Decon  Removal    Packaging  Transport  Processing  Disposal    Other      Total      Total Lit. Torm. Management  Restoration  Volume    Class A  Class 8    Class C  GTCC    Processed    Craft  Contractor index                      Activity Description                    Cost    Cost        Costs      Costs        Costs    Costs      Costs    Contingency  Costs    Costs      Costs      Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet  Cu. Feet  WLI Lbs. Manhours  Manhours 5b.2        Subtotal Period 5b Additional Costs                                  1.444                                                      52          224  1,720                    611      1,109                                                                  12,511          160 Perod 5b Collateral Costs 5b.3.1      Smut tool alnwurnce                                                      55                                                                    8      63                                  63 55                                                                    8      63                                  63 5b.3        Subtotal Period 5b CoUateral Costs Period 5b  Period-Dependent Costs 5b.4.1      Insurance 5b.4.2      Property tanes                                                          -                                                        7            1      8                                    8 5b.4.3      Heavy eq.ipment rental                                              4,233                                                      -            635  4,869                              4,869 5b.4.4      Pltat energy budget                                                    -                                                      167            25    192                                192 5b.4.5      Security StuffCost                                                                                                          2.419            363  2,782                              2,782                                                                              45,051 5b 4.6      DOC Staff Cost                                                                                                              10,212          1.532  11,744                              11,744                                                                            127,646 5b.4.7      UtilityStuff Cost                                                                    -                                      4.507            676  5,183                              5.183                                                                              73,209 5bA          Subtotal Period 5b Perlod-Dependent Costs                            4,233                                                  17,312          3.232  24,777                    -        24,777                                                                      -    245.906 50.0        TOTALPERIOD 5b COST                                                14,153                                                  17,520          4.751  36,424        179          611      35,634                                                                105.415    247,626 PERIOD 5 TOTALS                                                                14,153                                                  17,520          4.751  36,424        179          611      35,634                                                                105,415    247,626 TOTAL COST TO DECOMMISSION                                            13,111  58,437        8,282      5,692      37,066  34,071  545,635        120,307 922,600    475.790      309,463      37,347    384,277  207,449    1,377        344      508  28,976,590  994,325  6.844,054 TOTALCOST TO DECOMMISSION WITH17.13% CONTINGENCY:                                                  $822,600 thousands of 2008 dollars TOTALNRC LICENSE TERMINATIONCOST IS 57.84%OR:                                                      $479,790 thousands of 2008 dollars SPENT FUEL MANAGEMENTCOST IS 37.62% OR:                                                            $309,463 thousands of 2008 dollars ON-NUCLEAR DEMOLITIONCOST IS 4.64% OR:                                                              $37,347 thousands of 2008 dollars TOTALLOW4.EVEL RADIOACTIVEWASTE VOLUME BURIED (EXCLUDING GTCC):                                      209,171 cubic feet TOTALGREATER THANCLASS C RADWASTE VOLUMEGENERATED:                                                        508 cubic feet TOTALSCRAP METAL REMOVED:                                                                              30,276 tons TOTALCRAFT LABOR REQUIREMENTS:                                                                        994,329 tnan-hours End Notes:
n/a - indicates that this activity not charged as decommissioning expense.
a - indicates that this activity perorrmed by deconmmissioning staff.
0 - indicates that this value is less than 0.5 but is ron-zero.
a cell contaihing"*. indicates a zero value TLG Servicea, Inc.
 
Coaoper Nuclear Station                                                                                                                                                                                                                        Document N01-1590-00 Rev. I DecommissionaingCastAnalaysis                                                                                                                                                                                                                        Appendix C, Page 24 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommuissioning Cost Estimate (thouisands of 2008 dollars) m                                                                                            Off-Sit.      LLRW                                      NRC      Spent Fuel      Site    Processed            Burial Volumes              Burial I              Utility and Decon Removal  Packaging  Transport Processing    Disposal    Other      Total      Total Lie. Torm. Management    Restoration  Volume  Clan A  Class 5    Claws C  GTCC    Processed    Craft    Contractor IAct ity                                                Cost  Cost    Costs        costs                                    Contlngency  Costs    Costs        Costs        Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Cu. Fast  Wt. Lbs. Manhours  Manhours I    Index                    Actlvltv Descriotlon PERIOD Is - Shutdown through Transition Period Ia Direct DecommissioningActivities la.1.1      SAFSTOR nile characterization su0sy                                                                        346          104    450          450 la.1.2      Prepare preliminary decrimissioning cost                                                                  130            20    150        150                                                                                                        1,300 la.1.3      Notificationof Cessatos of Operations la.14      Remove fuet & sourte material                                                                                                      a la.1.5      Notificationof Permanent Defueling la.1.6      Deactivate plant systems &process waste                                                                                            a la.1.7      Prepare and submit PSDAR                                                                                  200            30    230        230                                                                                                        2,000 ta.1.8      Reoiewplant dwgs & specs.                                                                                  130            20    100        150                                                                                                        1,300 ta.1.9      Perform detailed rod survey Iai.10      Estirate by-product inventory                                                                              100            15    110        115                                                                                                        1,000 la.1.11      End product descrption                                                                                    100            15    115        115                                                                                                        1,o00 la.1.12    Detailed by-product inventory                                                                              150            23    173        173                                                                                                        1,500 ta.1.13    Defne major work sequence                                                                                  100            15    115        115                                                                                                        1,000 ta.1.14    Perform SER and EA                                                                                        310            47    357        357                                                                                                        3,100 1 8.1.15    Perform Site-Specific Cost Study                                                                          500            75    575        575                                                                                                        5,000 Activity Specifcations Ia:l.1..l Prepare plant and facilities for SAFSTOR                                                          *.        492            74    560        566                                                                                                        4,920 Ia.1.16.2 Plant systems                                                                                                417            63    479          479                                                                                                        4,167 la.1.16.3 Plant structures and bu0l0ings                                                                              312            47    359        359                                                                                                        3,120 Ia.1.16.4 Waste management                                                                                            200            30    230        230                                                                                                        2,000 la.1.16.5 Facility and site dormancy                                                                        --        200            30    230        230                                                                                                        2,000 la.1.16    Total                                                                                          *-      1,621          243  1,864      1,884                                                                                                      16,207 Detailed Work Procedures la.1.17.1 Plant systems                                            *      . -        -          -        -        I11            15    136        130                                                                              -    -                    1,183 la.1.17.2 Facility losout & dormancy                              -      . .        .          -        -        120            15    138        138                                                                              -    -                    1,200 ta.1l17 Total                                                      *            -    *          -238                              36    274        274                                                                              -    -          -        2,383 1      8al  Procure vacuum drying system                                                                                10            2      12          12                                                                                *  -                      100 t1o s19    Draundde-energize nos-cont. systems ia.120      Dman &dry NSSS t.1.21      Drain/de-energize cortaminated systems                                                                                            a la.l.22    Decoofsecure contaminated systems 3,930          642  4,077      4,077                                                                                                      35,890 la.t        Subtotal Period la Aztvity Costs Period ta  Collateral Costs la.3.1      Spent Fuel Capital and Transfer                                                                        10,335        1,550  11,880                    11,0006 1a.3.2      Corporate Overheads                                                                                      3,105          468  3,570      3,570
:-.3      Subtotal Period In Colateral Costs                                                                      13,440        2,016  15,456      3,570        11,886 Period ta  Period-Dependent Costs la.4.1      Insurance                                                                                                1,600          160  1,760      1.760 1:.4.2      Propety taxes                                                                                                4            0      4          4 ta.4.3      Health physics supplies                            370                                                                  93    463        463 1:.4.4      Heavy equipment rental                              368                                                                  55    423        423 la.4.5      Disposal of DAWgenerated                                                                          73      -              19    100        100                                        1,575                                  14,445          5 la.4.6      Rant energy budget                                                                                        927          139  1,068      1,060 10.4.7      NRC Fees                                                                                                  706            71    776        776 1t.4.8      Emergency Planning Fees                                                                                  1,185          118  1,303                    1,303 10.4.9      Spent Fuel Pool O&M                                                                                        745          112    857                      857 98 Ia.4.10    ISFSI Operating Costs                                                                                        85            13    98 6,021          903  6,924      6,924                                                                                                    157,471 18.4.11    Securdy Staff COst TLG Services, Inc.
 
Cooper Nucleaor Staton~~                                                                                                                                                                                                                          Docuerant NOI.1590.002, RemrI Deco~rnms,,aioniag Cc"l Analfysis                                                                                                                                                                                                                      Appenadix C, Page 25 of 80 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                      NRC          Spent Fuel      Site    Processed          Burial Volumes            Burial/              Utilty an0 Activity                                              Decon  Removal  Packaging    Transport Processing Disposal    Other      Total      Total Lic. Tenme Management        Restoration  Volume  ClansA  Class B Class C  GTCC Processed      Craft    Contractor index                    Activity Descripton        Cost    Cost      Costs      Costs      Costs      Costs      Costs    Continuencs  Costs    Costs          Costs        Costs      Cm.Feet  Cu. Feet Cu. Feet Cu.Feet Cu. Feet WLtLbs. Manhours  Manhour Period la Period-Dependent Costs (continued) 1a.4.12 Utiity Staff Cost
* 22,690          3.403  26,003    26,093                                                                                                      423.400 73  33.962          5,087  39,867    37,609            2,258                          1,575                              14.445          5    580,871 1a.4        Subtotal Period 1a Period-Dependent Costs              738 738                                            73  51.338          7,745  59.901    45,757            14.144                          1,575                              14.445          5    616,761 18.0        TOTAL PERIOD 10 COST PERIOD lb - SAFSTOR Limied DECON Activities Period 1bDirect Decommissioning Activities Decontamination o1Site Buildings lb.1.1.1    Reactor                                      2,929                                                                        1,465  4,394      4.394                                                                                          68,438 26    78          78                                                                                          1.562 lb.1.1.2 Augmented Radwaste                                52 188    565        565                                                                                            8,542 lb.1.1.3 Mlscetaneous Structures -Contaminated              370 34    101        101                                                                                            2.036 lb.1 .1.4 Muit-Potose Facility                              68 79    237        237                                                                                            4,761 1b1.1.5 Radwaste                                        158 260    780        780                                                                                          15.667 lb,1.1.6 Turbine                                          520 2,052  6,155      6,155                                                                                        101,006 lb.1.1      Totals                                      4,103 2.052  6,155      6,155                                                                                        I01.008 l1b.t      Subtotal Period lb ActivityCosts            4.103 Period Ib Additional Costs lb.2.1      Spent Fuel Poci Isolat*on                                                      -                    -      9,407        1,411  10,818      10,815 1        65                  558                      265  1,662      1.662                                          10,333                            134,329      10,002 b.,2.2    Asbestos Insulation Disposal                            773 773            1        65                  558      9,407        1,676  12,480      12,480                                          10,333                            134.329      10,002 lb.2        Subtotal Period l b Additional Costs Period l b Collateral Costs lb.3.1      Dec0n equipment                                713                  -          -                                              107    820        820 229                  74        392                  448                      293  1,436      1.436                                            1,561                              93,6344        304 lb.3.2      Process liquid waste lb3.3      Small tool allowance                                    70                    -                                              11    91            81 Spent Fuel Capital and Transfer                                                                              1,510          227  1,737          -            1,737 lb.3.4 tb.3.5      Corporate Overheads                                                                                  -        766            115    880            0880 942      70          74        392                  448      2,276          752  4,954      3,217            1,737                          1,561                              93,644        304 lb.3        Subtotal Period lb Collateral Costs Perod 1b Period-Dependent Costs Ib.4.1      Deco0 supplies                              1,156                            -                                            289  1,445      1,445 121            12    133        133 lb.4.2      Insurance
                                                                                                                  *      -            1            0      1            1 lb.4.3      Property tanes lb.4A      Health physics supplies                                473                                                                  118    592        592 Ib.4.5      Heavy equipment rental                                  91                                                                    14    104        104 5        3            -      81                      21    110        110                                            1,741                              15,968          5 1b.4.6      Disposal of DAWgenerated lb,4.7      Rant energy budget                                                                                            229            34    263        263 lb.4.8      NRC Fees                                                                                                        174            17    191        191 292            29    321                          321 lb.4.9      Emergency Plannlig Fees Spent Fuel Pool O&M                                                                                            184            28    211                          211 I b.4.10 b1h4.11 ISFSI Operating Costs                                                                                              21            3    24          -                24 1.485          223  1,707      1,707                                                                                                    -  38,829 lb.4 12    Security Staff Cost
                                                                                                                      - -      5,595          839  6,434      6,434                                                                                                      104,400 lb.4.13    Uidity Staff Cost                                                                                                                                                                                                                                  5    143,229 1,156      564            5        3                    81    8,101        1.628  11,538      10,981              557                          1.741                              15,968 lb.4        Subtotal Period l b Pedtod-Oependent Costs 2,294                          13,635                            243,942    111,318    143,229 lb.0        TOTAL PERIOD lb COST                        6,201    1,407          80      460                1,087    19,783        6,107  35,126      32,833 TLG Services, Inc.
 
CooperNuclearStation                                                                                                                                                                                                                                    Document N01.1590-002,Rev. I Devommissioning Cost Analysis                                                                                                                                                                                                                                Appendix C, Page26 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommrissioning Cost Estimate (thousands of' 2008 dollars)
Off-SIte  LLRW                                            NRC        Spent Fuei      Sit. Processed            Burial Volumes              Burial I              Utilty and Removal  Packaging  Transport  Processing Disposal    Other        Total        Total  Lic. Term. Management    Restoration  Volume  Class A  Class B    Class C  GTCC    Processed    Craft    Contractor IActiolty I    Ind*Y                    A*VI*    *cnnI*N Decon Cust    Cust      Costs      Costs      Costs    Costs      Costs    Continoonnv    Costs    Casts          Costs        Costs      Cu. Feet Cu. Feat Cu. Foot Cu. Feet  Cu. Feet  WL. Lbs. Manhours    ManhoursI n ex                    iZ&66&Q;-.c ri      n        Cost    Cost      Costs      costs                                                    Costs    Costs          Costs        Costs      Cu. Feet Cu.Feet  Cu.Feet Cu.Feet    Cu.Feet    WL. Los. Manhours Manhoom PERIOD 1c - Preparations for SAFSTOR Dormancy Perod Ic Direct Decornmissiounir Activities Ic 1.1      Prepare suppotn equipment for storage                  387                                                                      58    445          445                                                                                            3,000 1C.1.2      Install containment pressure equal. lines                  31                                                    -                5      36            36                                                                                            700 Ic.1.3      Interim survey prior to drmnnncy                        S-                                                    733            220      953          953                                                                                          15,696 lC.1.4      Secure building accesses 58              9      87            67                                                                                              S-          583 lC.1.5      Prepare &submit inteim report lc.1        Subtotal Period lc Activity Costs                      419                                                    791            291    1,501        1,501                                                                                          19,396          583 Period l1 Collateral Costs lc.3.1      Process liquid waste                            235                  76        403                  460                        301    1,475        1,475                                          1,603                                  96,196      313 tc.3.2    Smal tool allowance                                        3                                                                      0        3            3 1c.3.3    Spent Fuel Capital and Transfer                                                                              I1,527            229    1,756          -            1,756 1c.3.4    Corporate Onerheads                                                                                  -        774              116    090          890 235        3        76        403                  460      2,301            646    4,124        2,368          1,756                          1,603                                  96,195      313 1c.3      Subtotal Period Ic Collateral Costs Penod lc  Period-Dependent Costs 1c.4.1      Insurance                                                                                                        122              12    134          134 lc.4.2    Property taoes                                                                                                      1              0        1            1 1c.4.3    Health physics supplies                                  160                                                    -                40    200          200 1c.4.      Heavy equipment rental                                    92                                        -                          14    105          105 1c.4.5    Disposal of DAWgenerated                                                1 .      1                    18      -                5      20            25                                          393                                  3,601 1c.4.6      Plant energy budget                                                                                            231              35    266          266 lc.4.7    NRC Fees                                                                                                        176              18    194          194 lc.4.8    Emergency Planning Fees                                                                                        295              30    325                          325 1c.4.9    Spent Fuel Pool O&M                                                                                              1-6              28    214                          214 lc.4.10    ISFSI Operating Costs                                                                                              21              3      24          -              24 1c.4.11    Security Staff Cost                                                                                            1,501            225    1,726        1,726                                                                                                        39,260 1c.4.12    Utlity Staff Cost                                                                                              5,07            849    6,505        68505                                                                                                      105,560 252            1          1                    18    8:191          1,257    9.720        9,157            563                            393                                  3.601          1    144,820 1c.4      Subtotal Period 1c Period-Dependent Costs 1C.0      TOTAL PERIOD 1cCOST                            235      673          77        404                  478    11283            2.195  15,345      13,026          2,319                                                                96,796    19,710      145,403 PERIOD I TOTALS                                          6,437    2,818        162        866                1,639    82.404          16,047  110,372      91,616          16.757                        17,205                                358,183  131,033      905,393 PERIOD 2a - SAFSTOR Dormancy with Wet Spent Fuel Storage Period 28 Direct Decommissioning Acvtindes 2a.1.1      Quarterly Inspoction 2a. 1.2    Semi-annuai ennironmental sutvey                                                                                                          a 2a .1.3    Prepare reports 2a.1.4      Bituminous roof replacement                                                                                        63              9      72            72 23.1.5      Maitemance supplies                                                                                            503              126    629          629 30.1        Subtotal Period 2a Actioty Costs                                                                                566              135    701          701 Period 2a Collateral Costs 2a.3.1      Spent Fuel Capital and Transfer                                                                              26,466          3,970  30,435          -          30,435          -                          .-
2a.32      Corporate Overheads                                                                                          4,139            821    4,759        4,759 2a.3      Subtotal Period 2a Collateral Costs                                                                          30.604          4,591  35,195        4,759        30,435                                                -      -
Period 2a Period-Dependent Costs 2a.4.1    Insurance                                                                                                      1,962            196  2,158        1,845            310                            .                          -
23.4.2    Property tanes                                            -8                                                      16              2      18            18 2a.4.3      Health physics supplies                                  344                                                                      86    430          430 TLG Services, Inc.
 
Doumnent NOI.1590-002, Re-. I Cooper NucLear Station Appendix C, Page 27 of 35 Dectumissiaoniag Cost An~alysis Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommrissioning Cost Estimiate (thousands of 2008 dollars)
Off-Site  LLRW                                        NRC        Spent Fuel      site    Processed            Burial Volumes              Burial I            Utilty and Decon Removal  Packaging    Transport  Processing Disposal    Other      Total        Total Lic. Term. Management    Restoration  Volume  Class A  Class 8    Class C  GTCC    Processed  Craft    Contractor II Actinvy*
FRQ*X                    ACtlV* *ZCrlD*N              Cost  Cost    Costs      Costs      Costs    Costs    Costs    Contingency    Costs    Costs          Costs        Costs      Cu. Feet Cu. Feet C    e.et Cu. Feet Cu. Feet  Wt, Lbs. Manhours  Mlianhours n as                      c v      scr Pit n Period 2s Period-Dependent Costs (coninued) 2a4.4      Disposal of DAW generated                                          13                            198        -              52    270        270                                          4,267                                  39,138        13 742            111      853        427            427 2a.4.5    Plant energy budget 807              81    887        887 2A.4.6    NRC Fees 3,374            337    3,712          -            3,712 28.4.7    Emergency Planning Fees 2a,48      Spent Fuel Pool O&M                                                                                        2,984            448    3,431                      3,431 340              51    391        -              391 2a.4.9    ISFSI Operating Costs                                                                                                                                                                                                                                    444,561 17,728          2,659  20,387      7,788        12,599 2a.4.10    Security Staff Cost                                                                                                                                                                                                                                      329,769 18.816          2,822  21.639      4,426        17.213 2a.4.11    UtilityStaff Cost                                                                                                                                                                                                                    39,139        13    774,330 344          13                            198    46768          6,845  94.176    16,092          38,083                          4,267 2a.4      Subtotal Period 2a Pedod-Oependent Costs 344                                        198    77,939        11.571  90,072    21,553          68,519                          4,287                                  39,139        13    774,330 2a.o      TOTAL PERIOD 2a COST                                                13 PERIOD 2b - SAFSTOR Dormancy with Dry Spent Fuel Storage Period 2b Direct Decommissioning Activities 2b.1.1    Quarterly Inspecton a
25.1.2    Semi-annual envronmental suorey 2b.1,3    Prepare reports 2b.1.4    Bituminous roof replacement                                                                                  432              65    497        497 25.1.5    Maintenance supplies                                                                                      3,453            863    4,317      4.317 Subtotal Period 2b ActivityCosts                                                                          3,886            928    4,814      4,814 2b.1 Period 2b Collateral Costs 21.3.1    Spent Fuel Capital and Transfer                                                                          18,092          2,714  20,806                    209806 18,092          2,714  20.806                    20.606 2b.3      Subtotal Period 2b Colatsral Costs Period 2b Peiod-Dependent Costs 11,977          1,198  13,174      12,683            491 2b.4.1    Insurance 2b0.2      Property taoes                                                                                                110            11    121        121 1,891                                                    -            495    2,476      2,476 2b.4.3    Health physics supplies                                                                                                                                                                                                            250.212        84 80          44                1,268        -            332    1,725      1,725                                        27,278 2b.4.4    Disposal of DAWgenerated 2,546            382    2,928      2,928 2b.4.5    Plant energy budget 5,536            554    6,090      6,090 2b4.6      NRC Fees 23,161          2,316  25,477                    25,477 2b.4.7    Emergency Plannug Fees 254.8      ISFSI Operating Costs                                                                                      2,332            350    2.682                      2,682 2b.4.9    Security Staff Cost                                                                                      70,072        10,511  80,583    53.452          27,131                                                                                    1.547,177 51,313          7.697  59,010    30,376          28,634                                                                                      916,846 2b.4.10    UtilityStaff Cost 1.981        80          44                1,268  167,047        23,845  194,266    109,850          84.416                          27,278                                250,212        84  2,464,023 20.4      Subtotal Period 2b Pedod-Dependent Costs 2b.0      TOTALPERIOD 2b COST                                  1.981          8o        44                1.268  189,025        27,487  219,886    114,664        105.222                          27,278                                250.212        84  2,464,023 PERIOD2c - SAFSTOR Dormancy without Spent Fuel Storage Period 2c Direct Decomnissioning Activites 2C.1.1    Quarterly Inspection 2c.1.2    Semi-annual environmental survey                                                                                                      a 2C.1.3    Prepare reports 2c.1.4    Bituminous roof epslacenmet                                                                                  335            50    385        385 2c.1.5    Maintenance supplies                                                                                      2,677            669    3,346      3,346 3,012            719    3.732      3,732 2c.1      Subtotal Period 2c ActivityCosts Period 2c Period-Dependent Costs 2C.4.1    Insurance                                                                                                  8,937            894    9.831      9,831 2C.4.2    Property taxes                                                                                                  85            9      94            94 2C.4.3    Health physics supples                              1,444        -          -                                              361  1.805      1,805 2c.4.4    Disposal of DAWgenerated                                            61          34                961                      251    1,308      1,306                                        20.663                                189,540        63 TLG Serviees, Inc.
 
CooperNuclearStation                                                                                                                                                                                                                        Document N01-1590-002, Rev. I Deeommaisionting Coat Analysis                                                                                                                                                                                                                    Appendix C, Page 28 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site  LLRW                                          NRC      Spent Fuel    Site      Processed            BurialVolumes              Burlal I            Utilityand Actvily                                            Decon Removal  Packaging  Transport Processing Disposal      Other      Total        Total Lic.Term. Management  Restoration  Volume    Class A Class B Class C    GTCC      Processed    Craft    Contractor Indei                    Acivit'yDescription        cost  Cost    Costs    Costs      Costs    Costs        Coots  Contintflsco    Costs  Costs        Costs      Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet Cu. Feet  WL.Lbs. Manhtours  Manhourn Period 2c Period-Dependent Costs (contnued) 2c.4.5      Plant energy budget                                                                                    1,974          296    2,270      2,270 2c.4.6      NRC Fees
                                                                                                              - -        3,866          389    4,275      4,275 2c.4.7      Security Staff Cost                                                                                    36.028        5,404  41,432    41,432                                                                                                      666,257 2c.4.8      UtilityStaff Cost                                                                              -      20,474        3,071  23,545    23,545                                                                                    *        -      388,650 1,444        61        34                961      71.384        10,675  84,558    84.558                                          20,663                                189,540        93  1,054,907 2c.4        Subtotal Period 2c Petiod-Dependent Costs 2c.0        TOTALPERIOD 2c COST                                1,444        61        34                961      74.396        11,394  68,289    88,289                                          20,663                                189,540        63  1,054,907 PERIOD 2 TOTALS                                                3,769      154        85              2,427    341,360        50,452  398,247    224,506      173,740                            52.208                                478,891      160  4,293,260 PERIOD Sa. Reactivate Site FoUowing SAFSTOR Dormancy Period 3a Direct Decommissioning Activities 3a.1.1      Prepare preleninary decommissianing cMst                                                                  130          20      150        150                                                                                                        1,300 3a.1.2      Reniew plant dwgs &specs.                                                                                460            69      529        529                                                                                                        4,600 3a 1.3      Perform detailed rad survey 30.1 4      End product descrption                                                                                    100            10    115        115                                                                                                        1,000 30.1.5      Detaied by-product inventory                                                                              130          20      150        1O0                                                                                                        1,300 3a.1.6      Deline malor work sequence                                                                                750          113      863        663                                                                                                        7,500 3a.1.7      Perform SER and EA                                                                                        310          47      357        357                                                                                                        3,100 3a.1.8      Perform Site-Specific Cost Study                                                                          500          75      575        575                                                                                                        5,000 3a.1 .9    Prepare/subrldt Ucerrse Termination Plan                                                                  410            61      471        471                                                                                                        4,099 3aI1AO Receive NRC approval of terrtinatkin plan                                                                                              a Activity Specifications 3a.1.11.1 Re-activate plant &temporary facilities                                                                      737          111      846        763                                                                                                        7,370 3a.1.11.2 Plant systems                                                                                              417            63      479        431                                                                                                        4,167 3a.1.11.3 Reactor internals                                                                                            710          107      817        817                                                                                                        7,100 3a 1.11.4 Reactor vessel                                                                                              650            98      748        748                                                                                                        6,500 3a.1.1. 5 Sacrfiioal Shield                                                                                                            8      58          58                                                                                                        500 3a.1.11.6 Moiture saparators/reheatem                                                                                  100            15    115          115                                                                                                      1.000 3a 111.7 Reinforced concrete                                                                                          160          24      184          92                      92                                                                              1,600 3a.01116 Main Turbine                                                                                                  209          31      240        240                                                                                                        2,088 3 111s MaeinCondersers                                                                                                209            31    240        240                                                                                                        2,018 3a. 1.11.10 Pressure Suppresson structure                                                                              200            30    230        230                                                                                                        23000 3a. 1.11.11 Drywl1                                                                                        --          160          24      184          164                                                                                                      1,600 3a.1.11.12 Plant Structures & bulidings                                                                                312          47      359          179                      179                                                                              3,120 3a, 1.11.13 Waste management                                                                                          460          69      529          529                                                                                                      4,600 3a11.1-14 Facility & site closeout                                                                                                    14    104          52                      52                                                                                900 3a.1.11    Total                                                                                                  4,463          669    5,133      4.677                      456                                                                            44,633 Planning & Site Preparations 3a.1.12    Prepare dismantrng sequence                                                                                240          36      276        276                                                                                                        2,400 3a.1.13    Plant prep. & temp. sVces                                                                              2,700          405    3,105      3,105 3a.1.14    Design water dean-up system                                                                                140          21      161          161                                                                                                      1,400 3a.1.15    Rigging/Coot Cntrl Envlps/tooling/etc.                                                                  2,100          315    2,415      2,415 3a.1.16    Procure casksflaters & containers                                                                          123            16    141          141                                                                                                      1.230 3a. 1      Subtotla Period 3a Activity Costs                                                                      12,558        1,883  14,439      13,983                      456                                                                            77,559 Period 3a Period-Dependent Costs 3a.4.1      Insurance                                                                                                  420          42      462        462 3a.4.2      Property tames                                                                                              4            0      4            4 3a.4.3      Heala physics supplies                              324                                                                81      405        405 30.4.4      Heavy equipment rental                              368                                                                  55    423        423 3a.4.5      Disposal of DAW generated                                                  2                    62                      16      84          84                                    -    1,329                                12.190 TLG Services, Inc.
 
Cooper  Nuadear Sationuo                                                                                                                                                                                                                      Do    sumentN01.1590-002,Rev. I Appendix C, Page29 of"35 Decommissioninsg CoadAnialysis Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars) m                                                                                              Off-Sit. LLRW                                        NRC    Spent Fuel    Site      Processed            Burial Volumes              Burial I              Utilty and IActivity                                            Decon    Removal  Packaging    Transport Processing Disposal    Other      Total        Total Li. Termn. Management Restoration  Volume  Class A  Class B    Class C  GTCC    Processed      Craft    Contractor I Index                      Actlvits Descriotonn      Cost    Cost      Costs      Costs      Costs    Costs      Costs    Contingency    Costs    Costs      Costs      Costs      Cu. Feet Cu.Feet  Cu. Feet Cu. Feet  Cu. Feet  WLt.Lbs. Manhours    Manhour    I Index                    Actlvltv Description Period 3a Pefiod-Dependent Costs (continued) 3a.4.6    Plant energy budget                                                                                          927          139  1,066      1,966 249            25    274        274 3a.4.7    NRC Fees                                                                                                                                                                                                                                                  65,179 2.855          428  3,283      3,283 3a.4.8    Security Staff Cost                                                                                                                                                                                                                  -
* 258,629 3.4.9      UWilyStaff Cost                                                                                    -      14,190        2.128  16,318      16,318 2,915  22.318      22,318                                      1,328                                  12,190            4    323.807 3a.4      Subtotal Period 3a Penod-Dependent Costs              691            4                            62    18,644 36,302                    456              1,329                                  12,190            4    401,366 3s,0      TOTAL PERIOD 3a COST                                  691            4                            62    31.200        4.799  36,758 PERIOD 3b - Decommissioning Preparations Period 3b Direct Decommissioning Activities Detailed Work Procedures 473            71    544        490                      54                                                                                4.733 3b.1.1.1  Plant systems                                                                                                                                                                                                                                              4,000 3b.1.1.2  Reactor ilternals                                                                                            400            60    460        460 20    155        39                                                                                                        1,350 3b.11.3    Remaining buildings                                                                                          135 100            15    115        115                                                                                                        1,000 3b.1.1.4 CRD housngs & NIS                                                                                                                                                                                                                                            1,000 3b.1.1,5 Ilncoreinstrumentation                                                                                          100            15    115        115 200            30    230        230                                                                                                        2.000
: 3. I.1 .6 Removal primawyconitainrent                                                                                                                                                                                                                                  3.630 363            54    417        417 3b51.1,7 Reactor vessel                                                                                                                                                                                                                                                1,200 120            18    138        69                      69 3b.1.1.8 Facilitycloseout                                                                                                                                                                                                                                              1.200 30.1.1.9 Sacrifcial shield                                                                                              120            18    138        138 "58                                                                                1.000 100            15    115        58 3b.1.1.10 Reinforced concrete                                                                                                                                                                                                                                          2,080 35*1.1.11 Man Turbine                                                                                                    208            31    239        239 240                                                                                                        2,088 3b. 1.112 Man Condensers                                                                                                209            31    240 30    230        230                                                                                                        2,000 3b 1.1.13 Moisture separatos & reheaters                                                                                200 41    314        283                      31                                                                                2,730 3b.1.114 Ratwaste building                                                                                              273 273            41    314        283                      31                                                                                2,730 3b.1.1.15 Reactor bulding 3,274          491    3,765      3,405                    360                                                                                32,741 3W.1.1    Total 32,741 3b, 1      Subtotal Period 3b Activity Costs                                                                          3,274          491    3,785      3,405 Period 3bAdditionsalCosts 3b.2.1    Site Characterization                                      -      --        -            -      .        5,395        1,619  7,014      7,014 3b.2      Subtotal Period 3b Additional Costs                        -      -          -                  -        5,395        1,619  7,014      7.014 Period 3b Collateral Costs 3b.3.1    Deown equipment                              713                                                                            107    820        820 3b.3.2    DOC staff relocaton expenses                                                                                  912          137    1,049      1,649 3b.3.3    Pipe cutting equip-met                        -      1.000                                                                150    1.150      1,150 713      1,000                                                  912          394    3.019      3,019 3b.3      Subtotal Period 3b Couataral Costs Period 35 Perind-Dependent Costs 3b.4.1    Decwn supplies                                  22                                                                            5      27        27 3b.42      Insurance                                                                                                    248            25    270        270 Property tanes                                                                                                  2            0      2          2 3b.4.3 3b.4A      Health physics supplies                                179                                                                  45    224        224 3b.4.5    Heavy eciuipment rental                                184                                                                  28    212        212 35                        9      48        48                                        754                                    6.913            2 3b.4.6    Disposal of DAWgenerated                                              2 3b.4.7    Plant energy budget                                                                                          465            70    534        534 3b.4.8    NRC Fees                                                                                                      125            12    137        137 1,431          215    1,646      1,646                                                                                                        32,679 3b.4.9    Security StaffCost                                                                                                                                                                                                                                        58,560 3b.4.10    DOC Staff Cost                                                                                              4,378          657    5,035      5,035
                                                                                                                      -      7,114          1,067  8.181      8,181                                                                                              -      129,669 3b.4.11            Staff Cost tLility                                                                                                                                                                                                                          6,913            2    220,907 22      363                                          35    13,761          2,133 16,317      16,317                                        754 3b.4      Subtotal Period 3b Period-Dependent Costs TLG Services, Ian.
 
Cooper Nuclear Station                                                                                                                                                                                                                                    Document N01-1590-002, Rev. I DecommissioningCoast Analysis                                                                                                                                                                                                                                  Appendix C, Page 30 f835 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site      LLRW                                          NRC      Spent Fuel    Site      Processed                Burial Volumes              Burial /              Utility and Activity                                            Decon  Removal    Packaging    Transport  Processing    Disposal    Other      Total        Total Li, Term. Management Restoration    Volume      Class A    Class B  Class C  GTCC    Processed    Craft    Contractor Index                    Activity Description      Cost    Cost        Costs        Costs      Costs        Costs      Costa    Contingenca    Costs    Costs        Costs      Costs        Cu. Feel    Cu. Feet  Cu. Feet Cu. Feet  Cu. Feet  Wt Lbs. Manhtours  Manhours 3b.0      TOTAL PERIOD 3b COST                        735    1.363              2          1          -          35    23,342          4,636  30,115      29,755                      360          -          754        -                            6,913          2    253,648 PERIOD 3 TOTALS                                        735    2.055            6          3                      97    54,542          9,435  66,872      66,056                      816                    2,083                                    19.104        6    655,014 PERIOD 4a - Large Component Removal Perod 4a Direct Decommissioning Acvlities Nuclear Steam Supply System Removal 4a.1.1.1 Recirculation System Piping &Valves            16        70          14          13        127        151                        86    477        477                                  499        499                                  115,643      2487 4a.1.1.2 Recirculation Pumps & Motors                    6        28          11          26                    321                        95    488        488                                            1.188                                  132,880      1.125 4a.1.1.3 CRDM & Nis Removal                              24      139        377          68                    317        -            174    1,099      1,099                                            6.935        -        -                126,494      3,972          -
4a. 11.4 Reactor Vessel Internals                        60    1,876        3,729        727                  4,679        142          4,912  16,126      16,126                                            2.181      1,377      344      -      361,669    17,025          813 4a.1.1.5 Vessel &Internals GTCC Disposal                          -            -          -                    7.470        -          1,120  8,590      8,590                                                -                  -        508      89.497        -            -
4a.1.1.6  Reaotor Vessel                                      4,972          813        351                  3.006        142          5,544  14,826      14,828                                            14,106                  *        -    1,447,089    17,025          813 4a.1.1    Totals                                      106    7.085        4,945      1,185          127    15.944        283        11,932  41,608      41,608                                  499      24,908      1.377      344      508  2,273,272    41,634        1.626 Removal of Major Equipment 4a. 1.2    Main Turbine/Generator                                167        845        372        6,376        -
* 1,138  8,898      8,898                                61,604                                            2.772,179      4,438 4a.1.3    Main Condensers                                      708          588        259        4.439                                  940  6,932      6,932                                42,889                                            1,930,000    19,519 Cascading  Costs from Clean Building Demolition 4a.1.4.1  Reactor                                              260                                                                          39    299        299                                                                                                  2.486 4a.1.4.2  Augmented Radwesto                                      25                                                                        4      28          28                                                                                                  235 4a.0143    Radwaste                                                43                                                                        7      50          50                                                                                                  359 4a.1.4.4  Turbine                                                285                                                                        43    326        328                                                                                                  4,419 4a. 1.4    Totals                                                613                                                                          92    705        705                                                                                                  7,498 Disposal of Plant Systems 4a.1.5.1  Augmented Ridwaste El 877    ArealA                  203          28          28                    432                        166    857        657                                            2,055                                    172,205    5,668 4a.1.5.2  Augmented Radwaste E1903      ArealA                    66            6          7                    104                        44    228        228                                              469                                    41,606    1,42 4a.1.5.3  Augmented Radwaste El 918    ArealA                    52          10          9                    139                        50    260        260                                              765                                    55,345    1,432 4a.1.5.4  Augmented Radwastse 6929      ArewlA                    21            4          5          -          73                        25    127        127
* 324                                    29,038      579 4a.1.5.5  Augmented Radwaste 6i 929    AresI B                    3            0          0            4      -                          1      8            8                                    386                                              1,529        75 4a.1.5.6  DRYWELLArealA                                          457          65          84          -      1,289                      458    2,373      2,373                                            5,726                                  513,627    12,634 40.1.5.7 DRYIOLL AreaIB                                          112            1          5            75        2                        41    235        235                                  806            10                                  33,578    3,384 4a.1.5.6 Turbine El 932 ArelB                                    324          16          86      1,477                                  317  2,220      2,220                      -        15,808                                              641,963      9,170 4a.1.5.9 Turbine El 932 Area2C                                      8                                                                        1      9                                    9        .                                                              237 4a.1.5.10 Turbine El 932 Area3C                                    67        -          -            -                                    10      78        -                        78          -                                                      -      2,083 4a.1.5.11 Yard ArealB                                            S18          50        264        4,517                                  852  6,201      6.201                      -        48,365          -                                  1,964,114    14,340 40.1.5    Totals                                              1,831          202        487        6,073      2,040                    1,964  12,597      12,510                        87      65,016      9,348                                3,453.003    51,444 4a. 1.6    Scaffolding in support of decomniesioning          2,049            24          11        168          23                      547    2,821      2,821                                  1,621        101                                    81,992    27,411 4a.1      Subtotal Period 4a ActivityCosts            100  12.451        6,604      2,314      17,183    18,007        283        16,614  73,561      73,474                        87    171,628      34,358      1,377      344      508  10,510,450    151,944        1,626 Period 4a Collateral Costs 4a.3.1    Process liquid waste                          38        -            14        76                      86                        53    268        268                                                301                                    18,078        59 4a0.32    Smatl tool allowance                                    87                                                                        13    101          91                      10 4a.3      Subtotal Period 4a Collateral Coos            38        87          14        76                      86                        66    368        358                        10                    301                                    18.076        59 Period 4a Period-Depnent Costs 40.4.1    Deoon supplies                                47                                                                                  12      59          59 4a.42      Insurance                                                                                                        526              53    579        579 4a.4.3    Property loaes                                                                                                      4              0      5            4                        0 4a.4.4    Health physics supplies                                914                                                                      228    1,142      1,142 4a.4.5    Heavy equipment rental                              1,899                                                                        285    2,183      2.183 TLG Servcees, Inc.
 
Cooper Nauclear Station                                                                                                                                                                                                                                Documenert  NOI.1590-002, Rev,. I Deeomminioninebg Cost Analysis                                                                                                                                                                                                                              Appendix C, Page 31 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sit    LLKW                                          NKC      Spent fuel    Site      Processed              Burial Voltumes              Burial i              Utility ana Decon  Removal    Packaging  Transport Processing  Disposal    Other      Total        Total  LIc. Term. Management Restoration  Volume    Closs A  Class B    Class C  GTCC    Processed      Craft    Contractor  I J
m IActivity
[gDBX                      *UVIIV
* r [M[*ll        Cost    Cost        Costs      Costss cosCoost  ts                    s    s  Contingency    Costs    Costs      Costs      Costs      Cu. Feet  Cu. Feet  Cu. Feet Cu. Feet    Cu. Feet  WL, Lbs. Manhours  Manhtum    I n ex Perid 4a  Period-Dependent Costs (contrmod) 4a.4.6      DisposalofDAW generated                                              25          14                395                      103      537          537                                        8,501                                    77,973          26 946          142    1,087        1,087 4a.4.7      Plant energy budget 707            71    779          778 4a.4.8      NRC Fees 4a.4.9      Liquid Radwaste Processng Equipmnnt/Sevices                                                                    403            60    463          483 3,066          460    3,526        3,529                                                                                                          70.000 4a.4.10    Security Staff Cost                                                                                                                                                                                                                                            154,560 11,154        1,673  12,828      12,828 4a.4.11    DOC Staff Cost                                                                                                                                                                                                                              -          -      280,000 15,348        2,302  17,650      17,850 4a.4.12    UltilityStaff Cost                                                                                                                                                                                                                      77,973          26    504,560 25          14                395    32,154        5,390  40.837      40,837                        0        -      8,501 4a.4        Subtotal Period 4a Period-Dependent Costs      47    2,812 22,070  114K767    114,669                      97    171,628    43.159    1,377        344      508  10,906,5O0    152.029    506.186 4a.0        TOTALPERIOD 4a COST                            191  15.351        6.643      2.404    17,183  18,488    32,437 PERIOD 4b- Site Decontamination Period 4b Direct Decommissioning Acdivities 4b.1.1      Remove spent fuel racks                        262        33          79          88              1.348                      498    2,308        2.308                                        5,989                                    537,141      1,004 Disposal of Plant Systems 4b.1.2.1 Controtl a 882 AMal1                                        280                      39        674                                178  1,178        1,178                    -        7,213                                              292,908      7,797 25    195                                195                                                                        5,155 4b. 1,22 Control al903 ArealC                                        170 It                                                                    10      76                                  76                                                                      2,100 4b.11.3 Controa El918 AmalC 22                                                                    3      28                                  26                                                                        702 4b. 1.2.4 Control Cl932 Areal C 101                                                                    15    118                                  116                                                              -        3,136 4b.1.2.5 Intake                                                                                                                                                                                                                                    103.862      5,430 198          3          14        239                                88    541          541
* 2,558        -
4b.1.2.6 MuS-Purpose Facility 398          75          62                949                      353  1,836        1.836                                        5,097                                    377,917      10.930 4b.12.7 Radwase El 877 ArealA 9          7                                                                                                            613                                    44,992        1,189 4b.1.2.8 Radwasta        a  877 Asa2A                                43                                          113                      41    213          213 79,983        1,969 4b.1.2.9 Radwaste C 877 Ama3A                                        71          18          13                201                        72    372          372                                        1,158 110          9          10                  153                      68    351          351                                          684                                    61.153      3,015 4b,12.10 RadwastEa l 903 AralA 188          36          29                439                      165    856          856                                        1,955                                    175,093        5,282 4b.1.2.11 Radwasts El 903 Ara2A 37          8          7                  104                      37    190          190                                          453                                    41,366        1,029 4b.1.2.12 Rdwaute El 903 Area3A 18          2          2                  30                      12      64          64                                          135                                    12.033        477 4b.1.2.13 Radwaste E 918 AralA                                                                                                                                                                                                                        15,667        448 16          3          3                  39                      15      75          75                                          201 41.1.2.14 RawwasteB 918 Ama2A 185          23          22                338                      136    705          705                                        1,690                                    134,827      5,045 4b.1.2.1 5 Radwast B StsAea3A                                                                                                                                                                                266 26                      4                  60                        22    115          115                                                                                  23,735        680 4b.1.2.16 Radwasts El 934 ArelA 98          11          12                177                        72    370          370                                          808                                    70,665      2.663 4b.1.2.17 Radwaste C 934 Ama2A                                                    7                                                                                                                                                                  9,381        305 12                      2                  24                        9      47          47                                          105 4b.1.2.18 RadwastaEl 949 AealA 48,175        1,261 4b.1.2.19 Reactod    al  1001 ArealA                                5o                      8                  121                      45    230          230 157                                689 537 27,979        1,681 4b.1.2.20 Reactor El 1001 ArealB                                      62                      4        64                                26    157 246                                                                                -      1,091                                    97,874      2,024 4b.1.2.21 Reactor El 859 ArealA                                      71          15          16                                            83    430          430 269    1,771        1,771                            10.641                                              432,136      12,411 4b.1.2.22 Reactor El 859/AealR                                      440          11          58        994 72          25          26                401                      125    648          648                                -      1.780                                    159.714      2,094 4b.1.2.23 Reactor al859 Area2A 69            1          8        131                                38    247          247                              1,406                                              57.093        1,954 4b.1.2.24 Reactor El 859 Area2B                                                                9                                                                                                    -
S        608 47          9                              137                      48    251          251                                                                                  54,543        1,321 4b.1.2.25 Reactor E 859 Area3A 33          0          2        42                                15      93          93                                453        -                                      18.381        951 4b.1.2.26 Reactor 8599Area3B                                                                                                                                                                        -        520 50          9          8                  117                      44    227          227                                                                                  46.668        1,374 4b.1.2.27 Reactds        859 Area4A 17          0          2        31                                  9      59          59                                331                                              13,424        476 4b.1.2.28 Reactor El 859 Area4B                                                                                                                                                                                                                    104.381      1,798 e3          16          17                282                        85    443          443                                        1,163 4b'1.2.29 Reactor El 859 AreaSA                                                                                                                                                                    442 37          0          2        41                                19      98          98                                                                                  17,962        1,087 4b.12.30 Reactor El 859Area5B 4b.1.2.31 Reactor a 903 ArealA                                      401          56          42                651                      275    1,424        1,424                                -      2.892                                    259,190      10,497 451          6          32        550                                201  1,240        1,240                              5,890                                              239,197      12,496 4b.1.2.32 Reactor El 903 ArealB 4b.12.33 Reactsr El 903 Ara2A                                          4          0          0                    6                        3      14          14                                  -        29                                      2,372        120 69          2          11        190                                48    320          320                              2,039        -                                      82,815        1.915 4b.1.2.34 Reactor El 903 Area2B 32          10          11                  167                      52    272          272                                  -
S      741                                    66,516        929 4b.1.2.35 Reactds E 903 Arwea3A 21                      3        52                                14      90          90                                553                                              22,464        6189 4b.1.2.36 Reactor Ei 903 Area3S                                                    1 27          8          9                  136                      43    223          223                                  -      686                                    54,373        776 4b.12.37 Reactor El 903 Ares4A 21            1                    52                                14      90          90                                559                                              22,692        597 4b.12.38 Reactor E.903 Area4B 4b.1-2.39 Reactor E931 ArealA                                        25          3          3                  52                      20    104          104                                -
S        232                                    20,858        970 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                      Document N01-1590-002, Rev. 1 Decommiasioning Coast Analysis                                                                                                                                                                                                                                  Appendixv C,Page 32 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site      LLRW                                      NRC        Spent Fuel      Site      Processed                  Burial Volumes            Burial/              Utilityand Activity                                        Decon    Removal      Packaging    Transport  Processing    Disposal    Other    Total      Total  Lie.Term. Management      Restoration    Volume          Class A Class B Clans C GTCC Processed          Craft    Contractor Index                    Acltn    Oescritlo    Coot      Coot        Costs        Coats      coste        coste      Coste Continenco    Costs    Costs        Coots        Costs        Cu. Feet        Cu. Feet Cu. Feet Cu. Feet Cu. Feet WL Lbs. Manhoum    Manhours Disposal of Plant Systems (continued) 4b.12.40 Reactor El 931 ArealB                                    300            8          40          692                                186  1,227      1,227                                  7,412                                              301,017    8,410 2            2                      35                    14      74          74                                                  154                                13.824      544 4b.1.2.41 Reactor El 931 Area2A                                      20 1        0                      1        3            3                                          9        0                                  371        53 4b.12,42 Reactor El 931 Area2B                                        2          0            0 77          23            22          -        2336                    109    567        567                                      -          1,651                              134.007    2,165 4b.1.2.43 Reactor El 931 Area3A 0            0                                              1        3            3                                                                                        340        49 4b. 1 2.44 Reactor El 931 Area3B                                      2 4      28                                    28                                                                        767 4b.1.2.45 Reactor El 931 Area4C                                      24                                                                                                                        28 1        8
* 213 4b.1.2.46 Reactor El 931 Avea5C                                        7 9          10                    149                    54    278        278                                                    662                                59,432    1,472 4b.12.47 Reactor El 958 ArealA                                      56 3          16        281                                87    554        554                                  3,009                                              122,212    4,693 4b.1.2.48 Reactor El 958 ArealB                                    167 10          10            12      153                    49    253        253                                                    681                                61,083      880 4b.12.49 Reactor El 958 Area2A                                      31 1          1            12        7        -            6      37          37                                    125            33                                8,024      263 4b,1.2.50 Reactor El 958 Area2B                                      10 48                    21    109        109                                      -.          214                                19,185      898 4b.1.2.51 Reactor El 958 Area3A                                      33            4            3 1          1            10        6                      7      39          39                                    109            29                                7,011      410 4b.1.2.52 Reactor Ea 958 Area3B                                      14 11            1          1                      16                      7      36          36                                                    72                                6.482      298 4b.12.53 Reactor Ea 976 ArealA                                                                                                                                                                                                                          183.615    3,931 4b.1.2.54 Reactor El 976 Areat B                                  147            5          25        422                                104    703        703                                  4,521 1          1                      13                      5      26          26                                      -.            57                                5,136      172 4b.12.55 Reactor El 976 Area2A                                        7 1          3            55                              18    114        114                                      586                                              23,813    1,033 4b.12.56 Reactor El 976 A.rea2B                                    37 3            3
* 50                    23    116        116                                                    222                                19,878    1.004 4b.1.2.57 Turbine El 882 ArealA                                      37 388                                                                      335  2.313      2,313                                  15,948                                              647,659    11,113 4b.1,2.58 Turbin El 882 ArmoIB                                                  16          87      1,490 2            2                      29                    13      67          67                                      -.        129                                11,556      504 4b.1,2.59 Turbine El 892 Area2A                                    21 209            4          22        374                                112    721        721                                  4.006                                              162,678    5,781 4b.1,2.60 Turbine El 882 Area2B                                                                                                                                                                                                                            9,017      451 16          2            1          -          23                    10      52          52                                        -.        101 40.1.2.61 Turbine El 892 Area3A 27        145        2,478                                548  3,805      3,805                                  26,533                                            1,077,531    17.302 4b.1.2.62 Turbine El 882 Area3B                                  607
                                                                  -        9            1          1          -          15                      6      32          32                                        -
S          68                                9,127      232 4b.1.2.63 Turbine El 903 ArealA 974            46        241        4,133                                904  6,299      6,299                                  44,251                                            1,797,054    27.674 4b.1.2.64 Turbine El 903 ArealB                                                                                                                                                                                                                            3,729      142 5            1          1                      9                      4      20          20                                                    42 4b.1.2.65 Turbine El 903 Area2A                                                                                                                                                                                                                            55,851    4,040 144              1          7          128                                56    337        337                                  1,375 4b.12.66 Turbine El 903 Area2B 0            2            35                                6      47          47                                    376                                              15,251        97 4b.12.67 Turbine El 903 Area3B                                        3 16    124          -                          124                                                              -      3,412 4b.1.2.68 Turbine El 903 Area3C                                  108 12          0            2            28                                7      49          49                                    299                                              12,139      367 40.1.2.69 Turbine El 903 Area4B                                                                                                                                                                                                                              -      5,770 197                                                                        30    227          -                        227          -
4b.1.2.70 Yard ArealC 556        1,148      13,202      5,814                  5,535  34,027      33,227                        900      141,342        27.486                            8,056,388  218,627 4b0.12    Totals                                                7.771 3.073            36          17        252          34                    821  4,232      4,232                        -        2,431            151                              122,988    41,117 4b. 1.3  Scaffolding in support of decomnonnl  g Decontamination of Site Buildings 40,1.4.1 Reactor                                    2,880      1.820        202          422        4.911      2,376                  3.310  15.922      15,922                                  52.579        39.536                            6,069,283  115.053 19          4            6            23        60                    51    215        215                                      242          1,099                              119.386    1,978 40b.14.2 Augmented Radwaste                            52 62                    363    1,777      1,777                                  8,129            452                              372.774    12,956 4b,1,4.3 Miscelaneous Structures - Contaminated      368        167            is          42        759 68            55          6          12          115        89                    90    437        437                                  1234          1,567                              205.066    3,237 4b,1.4.4 Muffi-Purpose Faccity                                                                                                                                                                                                                          310,769    5.883 159            50            9          14            38      161                    141    572        572                                      404        2.953 4b.1A.5    Radaste 526        142            35          51            64      833                    477    1,928      1,928                                      688        11,664                            1,193,496    18,679 4b.1.4.6 Turbine 4.055      2,253        271          547        5,910      3,382                  4,432  20,950      20,850                                  63,275        57,271                            8,270,774  157,766 4b.tIA    Totals 11,285  61,417      60.618                        800    207.048        90,895                            16,987,290  418,513 4b.1      Subtotal Period 4b Acivity Costs        4,318      13,131        942        1,800      19,364      10,578 Pened 4b Additional Costs 656              4          24          -          55    1,192          360  2,290                      2290                            -      1,050                              162,629    17.515        2.560 4b.2.1    ISFSI Decontaminatioo                                                                                                                                                                                                                                                12,480 4b.22      Final Site Survey                                      .            .          ..                              1,205          362    1,567      1.567 722    3,857      1,567          2,290                                    1,050                              162,629    17,515      15,040 4b.2      Subtotal Period 4b Addriional Costs                    656              4          24                      55    2,397 Penod 4b Collateml Costs                                                                                                                                                                                                                                                125 30        161                      183                    113    566          566                                                  839                                38,338 4b.3.1    Procens liquid waste                        79        -
4b.32      Small tool allowance                                  230          .                                                            35    265        265 130    973        973                                  6,000            373                              303.507        88 4b.3.3    Decomnussioning Equipment Disposition                                88          50          621        84 278    1,804      1,804                                    ,000          1.012                              341,844      213 4b.3      Subtotal Period 40 Collateral Costs          79        230          118        210            621        267 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                      Document N01-1590-002, Rev. I DecommissioningCoast Analysis                                                                                                                                                                                                                                    Appendix C, Page33 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sits  LLRW                                            NRC        Spent Fuel      Sits      Processed            Burial Volumes              Burial I              Utitty and I Decon  Removal  Packaging  Transport  Processing  Disposal    Other      Total        Total  Lie. Torm,    Management  Restoration    Volume    Class A  Class B    Class C    GTCC    Processed    Craft    Contractor, ImActivity IJlU*X                    A*UVI[V*    fIM[*ll        Coast  Cost      Costs        Costs      Costs    Costs      Costs    Contingency    Costs      Costs        Costs        Costs      Cu. Feet  C. Fet  CF          . Ft  Cu. Fot    WL, Lbs. Mahors      Maours I n ex, Perod 41, Period-Dependent Costs 40.4.1      Decon supplies                                1,252                                                              -            313    1,565        1,565 4b.4.2      Insurance                                                -                                                    1,199            120    1.319        1,319 40.4.3    Property taes                                            -                                                          10            1      11            11 4b.4.4    Health physics supples                                2,378        -                                                          594    2,972        2,972 41.4.5    Heavy equipment rent0l                                4,294        -                                            --            644    4,938        4,938 4b.4.6      Disposal of DAW gereroted                                            55          31                  876        -            229    1,192        1,192                                          18,853                                  172,932          58 4b.4.7    Plant energy budget                                                                                            1,701            255    1,956        1,956 40.4.8    NRC Fees                                                                                                      1,610            161    1.771        1,771 4b.4.9    Uquid Radwaste Processing Equipment/Senvices                                                                    918            138    1,055        1,055 4b.4.10    Security Staff Cost                                                                                            6,984          1.148    8,032        8,032                                                                                                          159,464 4b.4.11    DOC Staff Cost                                                                                                24,760          3,714  28,474      28,474                                                                                                          341,891 4b.4.12    UtilityStaff Cost                                                                                            33,266          4.990  38,256      38,256                                                                                                          602,137 4b.4      Subtotal Period 4b Period-Oependent Costs    1.252    6,672          55          31                  876    70.448        12,207  91,542      91,542                                            18.853                                  172,932          58  1,103,493 4b.0      TOTALPERIOD,4b COST                          5,649  20,689      1.119      2,064      19,985  11.776    72.845        24,492  158,620      155,530          2,290          800    213,048  111,810                              17,664,700  436,298    1,118,533 PERIOD 4e - License Termination Period 4e Direct Decommissioning Acbvtes 4e.1.1    ORISE confmlaatory surcey                        -        .          -                        -                  147            44    191          191 4e.1.2    Terminate icnse                                                                                                                            a 4e.1      Subtotal Period 4e ActivityCosts                                                                                  147            44    191          191 Period 4e AdditionalCosts 40.2.1    Final Site Surtey                                                                                              5,998          1,799    7.797        7,797                                                                                            148,435        6.240 4e.2      Subtotal Period 4e Additional Costs                                                                            5.998          1,799    7,797        7,797                                                                                            148.435        6.240 Period 4e Collateral Costs 4e.3.1    DOC staff relocation expenses                                                                                    912            137  1,049        1,049 4e.3      Subtotal Period 4e Collateral Costs                                                                              912            137  1,049        1.049 64 Period    Perinod-DependentCosts 40.4.1    Insurance                                                                                                        ..                      .            .
48.4.2    Property taxes-                                                                                                      3            0        3            3 4e.4.3    Health physics supplies                                  735              -                          -                          184    010          919 4e.4.4    Disposal of DAWgenarated                                              3          1                    42                        11      57            57                                            904                                    8,294          3 4e.4.5    Plant energy budget                                                                                              139            21    160          160 4e.4.6    NRC Fees                                                                                                        530              53    583          583 4e.4.7    Security Staff Cost                                                                                            1.009            151    1.160        1,160                                                                                                            18,789 4e.4.8    DOC Staff Cost                                                                                                4,442            666    5,108        5,108                                                                                                          57.149 40.4.9    Utity Staf Cost                                                          -            -                -      4.678            702    5,379        5,379                                              -                                        -        -        74,371 40.4        SubtsotalPeriod 4e Period-Dependest Costs                735          3          1                    42    10.800          1,788  13,369      13,369                                              904                                    8,294          3    150,309 4e.0      TOTALPERIOD 40 COST                                      735          3          1                    42    17,857          3,768  22,407      22,407                  -                  -        904      -            -              8,94    148,438      156,549 PERIOD4 TOTALS                                          5,840  36,775      7,765      4,470      37,168  30,307    123.139        50,330  295,793      292,606          2,290            897    384.676  155,874    1,377        344      508  28,279,480  736.765    1,781,267 PERIOD 90 - Sits Restoration Peood 51 Direct Decomissioning Actvities Demoition  of Remaining Site Buildings 5b.1.1.1  Reactor                                                1,491                                                                    224    1,715                                      1,715                                                                14,601 5b.1.1.2  Augmetesd Radwasts                                      222                                                                      33    255                                        255                                                                  2,119 5b.1.1.3  Control                                                  214                                                                      32    246                                        246                                                                  1,655 5b.1.1.4  Intake Structure                                        523                                                                      78    802                                        602                                                                  5,621 TLG Services, Inc.
 
Cooper Nuleear Station                                                                                                                                                                                                                              Document N0-1590.002,Rev. I Decommoissioning Cast Analdysis                                                                                                                                                                                                                        Appendix C, Page34 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                            NRC      Spent Fuel    Site      Processed            Burial Volumes              Burial I            UtUity and I Oemon  Removal  Packaging  Transport Processing  Disposal    Other          Total        Total UC. Term,  Management  Restoration  Volume    Class A  Class B    Class C  GTCC    Pmcessed    Craft    Contractor I I
I Actil.ty I*nOX                    *C*I*
* nO[*  n      Cast    Cost      Costs    Costs      Costs      Costs      Costs        Contlnoenrn    Costs  Costs      Costs      Costs      Cu. Feet  Cu. Fast Cu. Fast Cu. Fast  Cu. Fast  WRt.Lbs. Manhours  Manhours I A              at n                                                                                  'o timacrim    Cr Demolition of Remaining Site Buildings (continued) 5b.1.1.5 LLRW Storage Pad                                          145                                                                      22      167                                167                                                                1,227 5b.1.1.6 Miscellaneous Structures - Clean                        1.198                                                                      179    1,375                              1.375                                                              11,837 5b.1.1.7 Misetlaneous Structures - Contaminated                      27                                                                      4      30                                  30                                                                  572 5b.1.1.8 Muo-Purpose Faciity                                      123                                                                      18      141                                141                                                                1.982 5b.1.t9 OWC Gas Generator                                            18                                                                      3      20                                  20                                                                  283 tOfice 5b. 1..10                                                          156                                                                      23      179                                179                                                                1.920 5b.1 1.11 Radwase                                                  391                                                                      59      449                                449                                                                3,229 5b.1 112 Seal Wetl                                                  17                                                                      3      20                                  20                                                                  166 4                                                                      1        5                                  5                                                                    53 5b.1 1.13 Sewage Treatment Area 5b 1.1.14 Transfomler Yard                                          20                                                                      3      24                                  24                                                                  172 389  2,985                              2,985                                                                40,503 5b.1.115 Turbine                                                2,596 5b.1.1.16 Turbine Pedestal                                        277                                                                      42      318                                318                                                                2,100 5b.1.1      Totals                                              7,418                                                                    1,113  8,531                              8.531                                                                88,040 Site Closeout Activities 5b.12      Remove Rubble                                          424                                                                      84      488                                488                                                                3,286 5b.1.3      Grade &ltadscape site                                  578                                                    .-                87      665        -                      665                                                                1,578 51,.1.4    Finalrepon to NRC                                                                                                  O15          23      179        179                                                                                                      1,560 5b. 1      Subtotal Period 5b Activity Costs                    8.421                                                    156            1,286  9,863        179                  9,684                                                                92,904        1.560 Period 5b Additional Costs 5b.2.1      ISFSI Demolition                                      487                                                        44            80      811                    811                                                                            4.336          160 499                                                                      76      582                                582                                                                3.045          -
5b.2.2      Concrete Crushing 5b.2.3      Collardsm                                              458                                                                      69      527                                527                                                                5,130 5b.2        Subtotal Period 5b AdditionalCosts                  1.444                                              -        52            224    1,720                    611        1,109                                                              12,511          160 Period 5b Collateral Costs 5b.331      Smatl tool allowance                                    55                                                                        a    63                                  63 55                                                                      8      63                                  63 5b.3        Subtotal Period 5b Collateral Costs Period 5b Period-Dependent Costs 5b.4.1      Insurance 7              1        9                                  8 5b.4.2      Property laves 5b.4.3      Heavy equipment rental                              4.233                                                                      635  4,869                              4.869 5b.4.4      Plant energy budget                                                                                          167                25      192                                192 2.782 5b.4.5      Security Staff Cost                                                                                        2,419              363  2,782                                                                                                                45,051 5b.4.8      DOC Staff Cost                                                                                            10,212            1.532  11.744                              11,744                                                                          127,649 5b.4.7      Uaty,Staff Cost                                                                                            4,507              876    5,183                              5.183                                                                          73,209 5b.4        Subtotal Period 5b Period-Dependent Costs            4,233                                                17,312            3,232  24,777                      -      24,777                                                                          245,908 5b.0        TOTAL PERIOD 5b COST                                14,153                                                17,520            4,751  36,424        179        611      35.634                                                              105,415    247,628 PERIOD S TOTALS                                          -    14,153                                                17,520            4,751  38,424        179        611      35,634                                                              105.415    247,625 TOTALCOST TO DECOMMISSION                              13,012  59,570      8,087    5,424      37.168  34,469    618,965            131,014 907,708    674,964      195,398      37,347    384.676  227,370    1,377      344      588 29,135.660  973.379  7,882,560 TLG Services, Inc.
 
CooperNuclear Station                                                                                                                                                                                                                              Document NO].1590.002, Rev. I Decommissioning Cost Analysis                                                                                                                                                                                                                            Appendix C, Page 35 of 35 Table C-3 Cooper Nuclear Station 2014 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                    NRC      Spent Fuel    Sit      Processed            Burial Volumos              Burial I            Utlibty and Decon Removal Packaging Transport  Processing  Disposal    Other    Total      Total LIc. Tenm. Management  Restoration  Volumne  Class A  Class B    Class C  GTCC    Processed  Craft  Contractor
* IActivity InOAY                      A&#xa3;UV*      *cnot*                    Cost  Cost    Costs    Costs      Costs      Costs                                  Costs      Casts      Costs      Cu. Faot Cu. Feat Cu. Foot Cu. Feet  Cu. Feet  WL, Lbs. Manhours  Manhours    I n as                        ciiiiiii6w. t TOTALCOST TO DECOMMISSION WITH16.87% CONTINGENCY:                                          $907,708 thousands of 2008 dollats TOTALNRC UCENSE TERMINATIONCOST IS 74.36% OR:                                              $674,964 thousands of 2008 dollars SPENT FUEL MANAGEMENTCOST IS 21.63% OR:                                                    $195,398 thousands of 2008 dollars MON-NUCLEARDEMOLITIONCOST IS 4.11% OR:                                                      $37,347  thousands of 2008 dollats TOTAL LOW-LEVELRADIOACTIVEWASTE VOLUME BURIED(EXCLUDING GTCC):                                229,092 cublc foot TOTALGREATER THAN CLASS C RADWASTE VOLUMEGENERATED:                                              608 cubic feet TOTALSCRAP METALREMOVED:                                                                      30,276 tons TOTALCRAFT LABOR REQUIREMENTS:                                                                973,379 man-hours End Notes "ia - indicates that thisactivity not charged as decommissioning expense.
      . - indicates that tlbs activity pertosned by decommnssioning staff.
: 0. Indicates that this value is less than 0.5 but is non-zero.
o call containing - - indicates a ze= value TLG Services, Inc.
 
CooperNuclearStation                                                                      Document N01-1590-002, Rev. 1 Decommissioning CostAnalysis                                                                        Appendix D, Page I of 35 APPENDIX D DETAILED COST ANALYSES 2034 CESSATION OF OPERATIONS T able D -1, D E C O N ............................................................................................... D -2 Table D -2, D elayed D ECON ...............................................................................            D -13 Table D -3, SA FSTO R ..........................................................................................      D -24 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                  Document NI01-1590.002, Rev. 1 DeoamnissioningCost Analysis                                                                                                                                                                                                                Appendix D, Page 2 of 35 Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site  LLRW                                      NRC      Spent Fuel      Site      Processed          Burial Volumes              BurlsI              Utiity and Activity                                            Decon Removal  Packaging  Transport Processing Disposal  Other      Total      Total  Lic.Teem. Management    Restoration  Volume  Class A Class B Class C    GTCC      Processed  Craft  Contractor Index                    Activity Description      Cost  Cost      Costs      Costs    Costs    Costs    Costs    Contin ency  Costs    Costs      Costs        Costs      Cu. Feet Co. Feet Cu. Feet Cu. Feet Co. Feet  WI. Lbs. Manhours  Manhours PERIODIa - Shutdown through Transition Period 10Direct Deconvmissioning Activities 18.1.1      Prepare preliminary decommissianing cost                                                                130            20    150        150                                                                                                    1,300 la.I,2      Notifiation of Cessation of Operations                                                                                        51 la.t13      Remove fuel & source material 10a.1.4    Notificationof Permanent Defueling                                                                                            a 1:.1.5      Deactivate plant systems & process waste 1 . 1.6    Prepare and submit PSDAR                                                                                200            30    230        230                                                                                                    24000 460            69    529        529                                                                                                    4,600 10.1.7      Review plant dwgs & specs.
1:.1.8      Perform detailed rad survey                                                                            100                                                                                                                                      1,000 1a.1.9      Eastiate by-product inventory                                                                                          15    115        115 100                                                                                                                                      1,000 1a.1.10 End product description                                                                                                    15    115        115 130            20    150        150                                                                                                    1,300 1a,1.11 Detiailedby-product inventory 750          113    863        063                                                                                                    7,500 la.1.12    Define major work sequence 310            47    357        357                                                                                                    3.100 ta.1.13    Perform SER and EA 0.1.14 Perform Site-Specific Cost Study                                                                          500            75    575        575                                                                                                    5,000
                                                                          -    --        .          -      -        410            61    471        471                                                                                                    4,096 ta.1.15    Prepare/subrmt License Termination Ptan la.1.16      Receive NRC approval of termination plan                                                                                      a ActivitySpecitications 1:.1,17.1 Plant &temporary facitites                                                                                492            74    566        509                        57                                                                          4.920 417            63    479        431                        48                                                                          4,167 1a.1.17.2 Plant systems                                                                                                                                                                                                                                        500 1:.l.117.3 NSS6 Decontamination Flush                                                                                50            a    58          58 710          107    817        817                                                                                                    7.100 la .1.174 Reactor imternas 650            98    748        748                                                                                                    6.500 a.1.t17.5 Reactor vessel                                                                                            50 8    58          58                                                                                                      500 1 .1.17.0 Sacrificil shield 100            15    115        115                                                                                                    1.000 la.1017.7 Maisture separators/reheaters                                                                                                                                        92 160            24    184          92                                                                                                    1,600 1 1.17.8 Reinforced concrete 209            31    240        240                                                                                                    2.088 1:.1.17.9 Man Turbine                                                                                                                                                                                                                                        2.088 10.1 t7.10 Main Cosdensers                                                                                          209            31    240        240 200            30    230        230                                                                                                    2,000 10.1.17.11 Pressure suppression structure                                                                                                                                                                                                                    1,600 10.1.17.12Drpywal                                                                                                  160            24    184        184 312            47    359        179                      179                                                                          3.120 l:.1.17.13 Plant structures& buildings 460            69    529        529                                                                                                    4.600 10.1.17. 14 Waste management 90            14    104          52                        52                                                                            900 1:.1.17.15 Facility &site doseout 4,268          640  4,909      4,481                      428                                                                          42,683 1.1.17      Total Planning&Site Preparations 240            36    276        276                                                                                                    2,400 la.1.18    Prepare dismantling sequence                                                                          2.700 1:.1.19 Plant prep. &tem*. svces                                                                                                  405  3,105      3.105 140            21    161        161                                                                                                    1,400
: 1. 1.20    Design water dean-up system
      ,0.1.21    Rigging/Cord. Cntrl Envlps/toolingletc.                                                              2,100          315  2,415      2,415 123            18    141        141                                                                                                    1,230 10.1.22    Procure caskailineem&containers 12,661        1,899 14,560      14,132                      428                                                                          78,609 la.1        Subtotal Period la ActivityCosts Period Ia  Colateral Costs la.3.1      Spent Fuel Capital and Transfer                        -        --      -          -      -      2,721          400  3,129                    3.129 10.3.2      Corporate Overheads                                    -        --      -          -      -      3,105          466  3,570      3.570 la.3        Subtotal Period 1a Codlateral Costs                    -        --      -          -      -      5.825          874  6,699      3,570        3,129 Period 10 Period-Dependent Costs la.4.1      Insurance                                                                                            1,600          160  1,760      1,760 ta.4.2      Property taxes                                                                                            4            0      4          4 1a.4.3      Hlealth physic supplies                            370                                                                93    463        463 la.4A      Heavy equipment rental                              368                                                                55    423        423 TLG Services, Inc.
 
0 Cooper Nuclear Station                                                                                                                                                                                                                        DocumentN01-1590-002, Rev. I Appendix D, Page 3 of"35 Deesasmiasstaing Coa, Analsuyis Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site  LLRW                                        NRC        Spent Fuel      site      Processed            Burial Volumes              BurialI              Utility and Activity                                          Decon  Removal  Packaging  Transport  Processing Disposal    Other    Total        Total  Lic. Torm. Management    Restoration  Volume  Class A  Class B  Class C  GTCC    Processed    Craft    Contractor Index                    Activity Description    Cost    Cost    Costs      Costs      Costs    Costs      Costs    Continies    Costs    Costs          Costs        Costs      Cu. Feet Cu. Feet  Cu. Feet Cu. Feet Cu. Feet  Wt. Lbs. Manhours  Manhours Period 15 Period-Dependient Costs (cortnuel)                                                                                                                                                                                                  14,445 la.4.5      Disposal of DAWgeneratsd                                                    3        -        73                      19    100          100                                            1,575 1 .4.6      Plant energy budget                                                                                      927          139  1,069        1,066 1a4.7      NRC Fees                                                                                                  706            71    776          770 ta.4.8      Emergency Planning Fees                                                                                1.185            118  1,303          -            1,303 laA.49      Spent Fuel Pool O&M                                                                                      745            112    857                        857 1a.4.10    ISFSI Operating Costs                                                                                      85            13      98          -              98 5,483          822  6,306        6,306                                                                                                      157,471 t:.4.11    Security Staff Cost
                                                                                                        *        .      22.690        3,403  26,093      26.093                                                                                                        423,400 ta.4.t2    UildityStaff Cost 738                    3                  73    33.424        5.006  39,249      36.991            2,258                            1,575                                14,445          5    580,871 la.4        Subtotal Penod la Penod-Dependent Costs la.0        TOTAL PERIOD loCOST                                  738                    3                  73    51,910        7,779  60,508      54,693          5.387        428                1,575                                14,445          5    659,480 PERIOD lb - Decommnissioning Preparations Period lb Direct Decommissioning Activities Detailed Work Procedures lb.1.1.1 Plant systems                                                                                                473            71    544          490                          54                                                        -        .          4,733 100            15    115          110                                                                                                          1,000 1b.1.1.2 NSSS Decontamination Flush                                                                                                                                                                                                                  -                4,000 lb.1.1.3 Reactor internals                                                                                            400            60    460          460 20    155            39                      116                                                                              1,350 lb.1.1.4 Remaining buildings                                                                                          135 100            15    115          115                                                                                                          1,000 lb.1.1.5 CRD housings & Nis                                                                                                                                                                                                                          -      .          1,000 lbt.1.6 Inmore instrumentaton                                                                                        100            15    115          115 lb.1.1.7 Removal primary containment                                                                                  200            30    230          230                                                                                                          2,000 363            54    417          417                                                                                                          3,630 tb*l.1.8 Reactor voesel 120            18    138            69                                                                                                          1.200 lb. 1.9 Facility closeout 120            18    138          138                                                                                                          1.200 lb 1.1.10 Sacrdcial shield                                                                                                                                                            "58                                                                              1,000 lb. 1111 Reinforred conorete                                                                                          100            15    115            58 208            31    239          239                                                                                                          2,080 lb.1.1.12 Main Turbine 209            31    240          240                                                                                                          2Z088 1t.1.1.13 Main Condensers                                                                                                                                                                                                                                              2,000 lb.1.1.14 Moisture separators & reheaters                                                                            200            30    230          230 273            41    314          283                          31                                                                              2.730 lb,1.1,15 Radwaste building 273            41    314          283                          31                                                                              2,730 lb 1116 Reactor building 506  3,880        3.520                        360                                                                    -        33,741 lb,1.1      Total                                                                                                  3,374 348                                                                          174    523          523                                                                                            1,067 1b,1.2      Decon NSSS lb.1        Subtotal Period lb Activity Costs          348                                                        3,374          680  4.403        4,043                                                                                            1,067        33,741 Period lb  Additional Costs lb.2.1      Spent Fuel Pool Isolation                                                                              9,407        1,411  10,818      10.818 1b.22        Site Characterization                                                                                  5,395        1,919  7.014        7,014 773          I        65                                          265  1,662        1,662                                          10.333                                134.329    10,002 1b.2.3      Asbestos insulation Disposal 773          1        65                  009    14,802        3,295  19,493      19,493                                          10,333                                134.329    10,002 15.2        Subtotal Period lb Additional Costs Period lb Collaterl Costs lb.3.1      Decon equipment                            713                                                                          107    820          820 1b,3.2      DOCstaff reocauton expenses                                                                              912            137  1,049      1,049 46      249                1,80.90                    525  2,690        2,690                                              427      543                        85.905      189 i b.3.3      Process liquid waste                        64 Ib.34        Small tool allowance                                "11                                                                  2      12            12 1b.3.5      Pipe cutting equipment                                                                                                  150  1,150      1,150 Ib.3.6      Decon rig                                1,400                                                                          210  1,910      1,610 1b.3.7      Spent Fuel Capital and Transfer                                                                        1,880            282  2,162          -            2,162 Ib.3.8      Corporate O=mreeds                                                                              -      1,554            233  1,787      1,787 1b.3        Subtotal Period 1b Collateral Costs      2,177    1,011        46      249                1.806    4,346        1,646  11,280        9.118          2,162                              427      543                        85,905      189 TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                                                                                            Document N01-1590-002,Rev. I DecommissioningCoast Analysij                                                                                                                                                                                                                            Appendix D, Page 4 of 35 Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars) off-Site      LLRW                                          NRC      Spent Fual      site    Processed              Burial Volumes            Burial I            Utilty and Activity                                          Decon  Removal  Packaging  Transport  Processing    Disposal    Other      Total        Total Lie. Term. Management  Reetoration  Volume    Clans A  Clans B  Class C  GTCC  Processed  Craft    Contractor index                    Activity Descrlptlon    cost    cost      costs      Costs        Costs        Cooss      Cools    ConulnFene    Coots    cost        Cools        canto      Ca. Feet  Ca.u.                          Fee  W. Lbs      nhor    Manhnour Period lb Period-Dependent Costs lb.4.l    Decon supplies                                22        4                                                                        5      27          27 lb.4.2    Insurance                                                                                                        244            24      269          269 lb.4.3    Property taxes                                                                                                    2              0        2            2 lb4.4      Health physics supplies
* 242                                                                      60      302          302 1bA.5      Heavy eqtuipment rental                                183        -          -                                                27      211          211 lb.4.6    Disposal of DAW generated                                            3          2                      43                      11      58          58                                            920                                8.439        3 lb.4.7    Plant energy budget                                                                                              924          139    1,063        1,063 lb.4.5    NRC Fees                                                                                                        352            35      387          387 lb.4.9    Emergency planning Fees                                                                                          591            59      650                        650 lb.4.10    Spent Fuel Pool O&M                                                                                              372            56      427                        427 lb.4.11    ISFSI Operating Costs                                                                                            42              6      49                        49 1b.4.12    Security Staff Cost                                                                                            Z,734          410    3,144        3,144                                                                                                    78,520 lb.4.13    DOC Staff Cast                                                                                                4,759          714    5,473        5,473                                                                                                    63,440 lb.4.14    UtilityStaff Cost                                                                                            11.380        1,707  13,086      13,086                                                                                                  212,160 lb.4      Subtotal Period lb Penod-Dependent Costs      22      425            3          2                      43    21,400        3,255  25,149      24,023        1,126        -                    920                                8.439        3    354,120 lb.0      TOTAL PERIOD 1 COST                        2,547    2,209          49      316                    2,407    43.922        8,876  60,325      56,677        3.288        350                11,680      543                    228,674    11,261    387,861 PERIOD I TOTALS                                      2,547    2,947          54      318                    2.480    95.833      16,655  120.833    111.370          8.675        788                13,255      543                    243,119    11,265  1,047,341 PERIOD 2a - Large Component Removal Period 2a Direct Decommissioning Activities Nudear Steam Supply System Removal 2a.1.1.1 Recirculation System Piping &Valves            90        71          14        20                      303                    142      639          639                                            997                              120,597    4.031 2a.1.1.2    Recirculation Pumps & Motor                  33        28          11        29                      321                    109      532          532                                          1,188                              132,880    1.683 2a.1.1.3 CRDMs &NIs Removal                            133      139        377          92                      317                    232    1,291      1,291                                          6,935      -        -            126,494    8,209 2a.1.1.4 Reactor Vessel Intertals                      119    2,32        5,343      2,009                    16,414      218        11,909  38,374      38,374                                          1,878      976    1,205          378,084    28,075        1,255 2a.1.1.5 Reactor Vessel                                  56    5,457      1,460        762                    5.384      218        7.401  20,739      20.739                                          11,211    2,128        -          1,440,354    28.075        1.255 2a.I.1    Totals                                      431    8,05O      7,205      2,912                  22.739        437        19.714  61,576      61,576                                        22,209    3.104    1,205        2.196,409    68,073      2.510 Removal of Major Equipment 2 .12      Main TurbinelGenerator                                171        928        379        6.057        389                  1,188    9,011        9,011                              58,524      1,725                            2,788,381    4,555 2a.1.3    Main Condensers                                      722        552        273        3.773        812                    1,45    7,177        7.177                              36,456      3,604                            1,963,840    19,966 Cascading  Costs hromClean Building Demolition 2a .1.4.1  Reactor                                              260                                                                        39    299          299                                                                                          2,486 2a.1.4.2  Augmented Radwaste                                      25                                                                        4      28          28                                                                                          235 20.1.4.3    Rodwaste                                              43                                                                        7      50          8o                                                                                          359 20.1.4.4  Turbine                                              285                                                                      43      328          328                                                                                          4.419 2a.1.4    Totals                                                613                                                                      92      705          705                                                                                          7,498 Disposal of Plant Systems 2a.1.5.1 Augmented Radwaste El 877 AnealA                        207          28        28                      432                    167      882          862                                          2,055                              172,205    5,783 2a.1.5.2 Augmented Radwasle El 903 AtaIA                          68          6          7                    104                      45      230          230                                            469                              41,606    1,889 2a.1.5.3 Augmented Radwaste El 918 AjealA                          53          10          9                    139                      50      261          261                                            765                              55,345    1,451 2a.1.5.4 Augmented Raedaste El 929 AnalA                          21          4          5                      73                      25      128          128                                            324                              29.038      591 2a.1.5.5 Augmented Radwaohe El 929 ArealB                          3          0          0            3        0                        1        8            8                                  36        1                                1.538        77 2u.1.5.8 DRYVWELL      ArealA                                  534          85        84          -        1,289                    477    2,470        2,470                                          5,726                              513,627    15,069 20.1.5.7 DRYWELLAreatB                                            134          3          5            54        28                      W0      274          274                                  577        126                              34,718    4,142 20.1.5.8 Multi-Purpose Facility                                  202            6          15        201          47                      95      566          566                                2,148        214                              105,982    5,547 20.1.5.9 Reactor El 903 ArealA                                  404          56        42                    651                      276    1,428      1,428                                  -      2,892                              259.190    10,573 2a.1.5.10 Reactor El 903 ArealB                                  462          13        34          443        131                    221    1,305      1,305                                4,739        583                              244,706    12,864 2a.t.5.11 Turbine El 932 ArealB                                  332          52        99          882        725                    416    2,505        2,505                                9,442      3,220                              672,225    9,481 2a.1.5.12 Turbine El 932 Area2C                                    8                                                                        1        9                                                                                                        237 TLG Servicas, Inc.
 
Cooper Nuaclear Sioiuso                                                                                                                                                                                                                                        D    -      1 NTOJ.13OwdO2 Rer. J Decommissio~ning Cast Anslyais                                                                                                                                                                                                                                          Appensdix D),Page 5 of.55 Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars) m                                                                                                        Off-Site    LLRW                                        NRC          Spent Fuel      Sits      Processed              Burial Volumes              Burial I                Utility and Decon    Removal    Packaging  Transport  Processing  Disposal    Other      Total        Total  sic.Tenm. Management    Restoration    Volume    Clans A  Class B    Class C  GTCC    Processed        Craft    Custractor, I innnl civityn Acuv*
* nmmn              COst    Coot        Cnsts      Costs      Costs      Costs      Costs  Continnaenc    Costs  Costs          Costa        Costs        Ca. Foot  Cu. Fent  Cu. Foet Cu. Feet Cu. Feet  WL Lbs,        Manhours  Manhours I
* n ex                    .. u..v -              --------- 11.&#xfd;          t      Costs      Costs      C'Osts      Costs                                                        osts        costs        Cu. Feet  Cu.Fnt    Cu.Feet Cu.Feet - Cu.Fewt    Wt. Lbs.      Manhours - Manhcurs DiOsposalof Plant Systems (contnued) 2:.1.5.13 Turbine El 932 Ara3C                                              67                  -                                                10      78          -                            78        -        -                                        --        2,083 2 .1.5.14 Yard Areal B                                                    518          110        284        3.535    1.198                    1,013    6,657      6,657                                  37,846    5.399                              2,014,081        14.477 2a.1.5      Totals                                                      3,013          374        612        5,117    4,817                    2,847  16,780    16.693                            87      54,788  21,774                                4,144,259        84,262 2a.1.6    Scaffolding in suppot o1decommissioning                    2,070            24        11          168        23                    553    2,848      2.848                                    1,621      101                                  81,992      28,092 2a. 1      Subtotal Period 2a Activity Costs                  431    14,647        8,983      4,186      15,116    28,780        437        25.519  98,097    98,010                            87    151,388  49,413    3,184      1,205          11.174,880      212,445        2,510 Period 2a Collateral Costs 2.3.1      Process liquid waste                                135        -            44      231                                              173      847        847                          -          -        921                                    55,244          180          -
2a.3.2      Small tool allowance                                          124                                                                      19      143        129                            14 20.3.3      Spent Fuel Capital and Transfer                                                                                        5,279          792    6,070                      6,070 2a.3.4      Corporate Overheads                                                                                          -        3,202          480    3,682      3,682 2a.3        Subtotal Period 2a Collateral Costs                135      124            44      231                    264      8,480        1,463  10,742      4,657          6.070            14                  921                                  55,244          180 Period 2a Period-Dependent Costs 20.4.1      Decen supplies                                        61      -                                                                        15      76            76 20.4.2    Insurance                                                                                                                688            69      756        756 2a.4.3    Property taxes                                                                                                            6              1        6            6 2a.4.4    Health physics supplies                                    1,262                                                                      315    1.577      1,577 2a.4.5    Heavy equipment rental                                      2,480          -                                                          372    2,852      2,852 2a.4,6    Disposal of DAWgenerated                                                    34        19                  537                      140      730        730                                            11,545                                  105,898            35 20.4.7    Plant energy budget                                                                                                    1,235          185    1,420      1,420 20.4.8    NRC Fees                                                                                                                923            92    1,016      1,016 20.4.9    Emergency Planning Fees                                                                                                1,183          116    1.301                      1,301 20.4.10    Spent Fuel Pool O&M                                                                                                    1,046          157    1.203                      1,203 20.4.11    ISFS1Operating Costs                                                                                                    119            18    137                        137 20.4.12    Security Staff Cost                                                                                                    6,631          995    7,626      7,626                                                                                                              185,051 20.4.13    DOC Staff Cost                                                                                                        16.275        2,441  18,716    18,718                                                                                                              222,354 20.4.14    UtilityStaff Cost                                                                                                    22,962        3.444  26,407    26,407                                                                                                              413,989 20.4      Subtotal Period 2a Pedod-Depenadent Costs            61    3,741            34        19                    537    51,067        8.363  63,822    61,182            2,640            1        -    11,545                                  105,898            35    821,394 20.0      TOTALPERIOD 2a COST                                627    18,513        9.060      4,437      15,116    29,580      59,985        35,345  172,662  163,849            8,711          102    151,388  61,878    3,104      1,205          11,336,020      212,660    823,904 PERIOD 2b - Site Decontamination Period 2b Direct Decohmmssioning Activites Disposalof Plant Systems 2b.1.1.1 Control E 882 AmaolB
* 285            17        42        554        147        -            199    1,243      1,243                          -        5.929      674                                299,222        7,975            -
2b. 1.1.2 Control El 903 ArealC                                          170                    -                                                25      195          -                          195                                                            -        5,155 25.1.1.3 Control El 918AreaC                                                66                                                                      10      76                                      76                                                                      2,100 2b.1.1.4 Control El 932 ArealC                                              22                                                                      3      26                                        26                                                                        702 25.1.1.5 Intake                                                          101                                                                      15    116          -                          116                                                              -        3.136 2b.1.1.6 Radwaste El 877 ArealA                                          405            75        62                  949                      355    1.845      1,845                                              5,097                                377,917        11,133 25.1.1.7 Radwaste El 877 Area2A                                            44          9          7                    113                      41      214        214                                                613                                  44,992        1,207 25.1.1.8 Radwaste El 877 Ara3A                                              84          16        13                  201                        75      308        308                                              1,156                                  79,963        2.349 2b.1.1.9 Radwast El 903 ArealA                                            113            9        10                    153                      69      355        355                                                684                                  61,153        3,102 2b.1.1.10 Radwaste El 903 Ama2A                                          192          36        29                  439                      166      861        861                                              1,955                                  175,093        5,412 2b.1.1.11 Radwaste El 903 Area3A                                            37          6          7                    104                      37      191        191                                                463                                  41.366        1,047 2b.1.1.12 Radwaste El 18 ArealA                                            21          2          2                      30                      13      68          68                                              135                                  12.033          572 2b.1.1.13 Radwaste Elt18 Area2A                                            17          3          3                      39                      15      76            76                                              201                                  15,667          455 25.1.1.14 Radwaste El 918 Area3A                                        189            23        22                  338                      137      710        710                                              1,690                                134,827        5,152 2b.1.1.15 Radwaste 934 ArealA                                              26          3          4                      60                      22      115        115                                                266                                  23,735          692 2b.I.1.16 Radwaste El 934 Area2A                                        100            11        12                    177                      72      372        372                                                808                                  70,665        2,706 25.1.1.17 Radwaste El 949 ArealA                                            12          1          2                      24                        9      47            47                                              105                                    9,381          310 TLG Serviceo, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                    Document N01-15900)02,Rev. I DecommissioningCost Analysis                                                                                                                                                                                                                                    Appendix D, Page 6 of"35 Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Silo    LLRW                                        NRC        Spsnt Fuel    site      Processed                Burial Volumes              Burial I              Utility and i IActivity                                              Decon  Removal  Packaging  Transport Processing  Disposal    Other      Total      Total Lic, Trnm. Management  Restoration  Volume      Class A  Class B    Class C  GTCC    Processed    Craft    Contractor iI  tflnAf                    ACflV*
* flOfDN        cost    Cast      Costs    Costs      costs      costs      Costs  Conlineonsv  Costs    Costs          Costs      Costs      Cu. Feet    Cu. Fast  Cu. Feet Cu. Feet  Cu. Feet  Wt. Lbs. Manhours  Manhours I n ex                      C            pt n Disposal of Plant Systems (continued) 2b.1.1.18 Reactor al859 ealiA                                          72        15        16                  246                      83    432        432                                        -    1,091                                    97,874    2,068 2b.1.1.19 Reacto El 859 AkealB                                      449          29        64        712        344                      317  1,914      1,914                                7,624      1,526                                  440,483    12.740 2b.1.1.20 Reactor a 859 Are2A                                          73        25        26        -        401                      125    650          650                                  -        1,780                                  159,714      2,137 2b.1.1.21 Reactor El 859 Area2B                                        70          3        8          99        40                      44    284          264                                1,055        177                                    58,760    2,009 2b.1.1.22 Reoctor E 59 Area3A                                          48          9        9                  137                      49    252        252                                  -          608                                    54.543    1,356 2b.1.1.23 Reactor El 859 Area3B                                        34          2        3          23        23                      18    103        103                                  249        103                                    19,362      975 2.1,.1.24 Reactor El 859 Area4A                                        51          9        8                    117                      44    229        229                                  -          520                                    48,666    1,416 2b.t.1'25 Reactor El 859 Area48                                        17          1        2          19        14                      11      65            65                                208          82                                    14,010      487 2b.1.1.26 Reactor El 859 Aret5A                                        64        16        17                  252                      86    445          445                                            1.163                                  -14,381      1,839 2b.1.1.27 Reactor El 859 Area5B                                        38          2        3          23        23                      19    107        107                                  242        102                                    18,927    1,114 2b.1.1.28 Reactor El  f83 Area2A                                        4          0        0                      6                        3    14            14                                              26                                    2,372      123 2b.1.1.29 Reactor El 903 Area2B                                        71          5        12        149        51                      55    342        342                                1.594        225                                    84.943    1,983 2b.1.1.30 Reactor EA903 Aroo3A                                          37        10        11        -          167                      54    279        279                                              741                                    66.516    1,109 2b.1.1.31 Reactor EA9D3 Arwe3B                                        25          2        3          37        17                      17    101        101                                  401          77                                    23,200      744 2b.1.1.32 Reactor Ef903 Area4A                                        31          8        9                    136                      44    229        229                                              666                                    54,373      928 2b.1.1.33 Reactor El 083 Area4B                                        24          1        3          38        17                      17    101        101                                  411          75                                    23,408      717 2b.I.1.34 Reactor EI 931 AreslA                                        25          3        3                    52                      20    104          104                                  -          232                                    20,858      681 2b.1.1.35 Reactor El931 ArealB                                      307          22        45        483        256                      222  1,334      1,334                                5,169      1,137                                  311,878    8,640 2b.1.1.36 Reactor El931Area2A                                          31          2        2        -          35                      17    87            87                                            154                                    13,824      881 2b.1.1.37 Reactor El 931 Area2B                                        3          0        0            1        0                        1      5            5                                    7          1                                      380        91 2b.1.1.38 Reactor El 931 Area3A                                      123        23        22                    336                    120    625        625                                            1.651                                  134,007    3,509 2b.1.1.39 Reactor El 931 Are3B                                          3          0        0            1          0                      1      4            4                                    7          0                                      345        85 2b51.1.40 Reactor El 931 Area4C                                        24                                                                    4    28                                    28                                                              -        767 2b.1 .1.41 Reactor El 3l AreasC                                        7                                                                    I      8          -                          8                                                              S
                                                                                                                                                                                                                                                                  -        213 2b.1.1.42 Reactor El S58 ArelA                                        57          9        10                    149                      54    279        279                                    -          662                                    59,432    1,492 2b.1.1.43 Reactor El 958 Areml8                                      171          8        18        209          88                    100    594        594                                2,238        392                                  126.002    4,814 2b.1.1.44 Reactor El 958 A8a2A                                        49        10        10        -          153                      53    276        276                                    -          681                                    61,083    1.425 2b,51145 Reactor Els58 Are2B                                          15          1        1            6        14                        8    46            46                                  66        63                                    8,331      430 2b.511.46 Reactor El8958Ae3A                                          38          4        3        -          48                      22    116        116                                    -          214                                    19,185    1,070 2b.1.1.47 Reactor EA958 Area3B                                        17          1        1            6        12                        8    45            45                                  60        54                                    7,250      491 2b51,1.48 Turbine El 882 ArelA                                        38          3        3        -          50                      23    117          117                                  -          222                                    19,878    1,028 2b.1.1.49 Turbine El 882 ArealB                                      394          40        95      1.101        478                      402  2,515      2,515                                11,784      2.117                                  668,352    11,459 2b51.1.50 Turbine El 852 Area2A                                        22          2        2        -          29                      13    68            68                                  -          129                                    11,556      597 2b.1.1.51 Turbine El 882 Area2B                                      213          10        23        301        89                    125    762        762                                3,227        405                                  166,542    5,929 2b1,
* 32 Turbine El 882 Area3A                                      17          2        1        -          23                      10    53            53                                  -          101                                    9,017      461 2b.1.1.53 Turbine El 882 Area3                                      620          62      156      1,960        633                      637  4,068      4,068                                20,984      2,817                                1,104,460    17,788 2b.1.1.54 Turbine El 903 ArealA                                        9          1        1          -          15                        6    33            33                                  -          68                                    6,127      239 2b.1.1.55 Turbine FJ903 AesIB                                        995        134      271      2.728      1,717                  1,141  6,983      8,993                                29.100      7,631                                1,868,932    28,509 2b51,156 Turbine El 903 Aea2A                                          5          1        1        -            8                      4    20            20                                  -          42                                    3,729      145 2b51.1.57 Turbine El 03 Area2B                                        147          3        8        105        30                      62    355        355                                1,122        133                                    57,476    4,141 2511.58 Turbine El 903 Aa3B                                            3          0        2          33        2                        7    48            48                                357            9                                  15,340        97 2b.1.1.59 Turbine      003 Area3C                                    108                                                                  16    124          -                        124                                                              -      3,412 2b51.1.60 Turbin El 903 Area4B                                        12          0        2          26        3                        8    50            50                                276          11                                  12,251      397 2b51.1.61 YardAreaiC                                                  197                                                                  30    227          -                        227                                                                        ,770
                                                                                                                                                                                                                                                                          .-
2b.1.1      Totals                                                6,646        6893    1,087      8,811      8,996                    5,365  31,398      30,598                      8o0      92,185      41,662                                7,327,776    189,487 2b. 1.2    Scaffolding in support of decommnrissioning            2,588          30        14        210        29                    691  3,560      3,560                                2,028        128                                  102,490    35.115 Decontamination of Site Budings 2b.1.3.1    Reactor                                      2.702    1,457        131      320      4,748      1.116                  2,767  13.241      13,241                                50,830      18.343                                3,680,298    101,984 2b.1,3,2 Augmented Redwaste                                  55        32          7        10          23      119                      71    316        316                                  242      2,189                                  228,383      2,299 2b.1.3.3 Mascelaneous Structures -Contamninated            377      174        is        43        759          74                    372  1,815      1.815                                8.129        679                                  395,527    13,327 2b.1.3.4 Mutj-Purposs Facility                              72        73        11        19        115        172                    118    579        579                                1,234      3,087                                  356.985    3,680 2b.1.3.5 Radwaste                                          167        98        18        26          38      319                      196    850        850                                  404      5,886                                  603,975      6,839 2b.1.3.6 Turbine                                            552      267          70        97          84    1,261                    689  3,001      3,001                                  688      23,302                                2,357,288    21,920 2b.1.3      Totals                                        3,924    2.088        252      515      5.747      3.061                  4.214  19,801      19,801                                61,526      51,485                                7.622,455    150,050 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                      DocumentNI01-1590-002, Rev. I Appendix D, Page 7 of35 DecommissioningCost Analysis Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars) off-sita    LLRW                                          NRC        SpentFuel      Situ    Processed            BurialVolumes              BurialI                Utlty and Activity                                                Decon  Removal    Packaging  Transport  Processing  Disposal    Other        Total        Total  Lic.Term. Management  Restoration  Volume    Class A  Class B  Class C  GTCC Processed        Craft      Contractor Index                    Activio Description            Cost    Cost        Costs      Costs        Costs      Costs      Costs    Contin encv    Costs    Costs        Costs        Costs    Cu. Feel  Cu. Feet  Cu. Feet Cu. Foot Cu. Feet  Wt. Lbs. Manhours    Manhours 3.924  11.322        975      1,616      14,567    12,086          -          10.269  54.759      53,960                        880  155,741    93.273      -                -    15,052.720  374,651            -
2b.1        Subtotal Period 2b Activity Costs Period 2b  Collateral Costs 2b.3.1      Process liquid waste                              184      -            54      283                    323                        211    1,035      1,035                                          1,126                                  67.588        220 2b.3.2      Small teWallowance                                -        195                                                                        29    225        225            -
2b.3.3      Spent Fuel Capital and Transfer                                                                                    15,867          2.380  18,247          -          18,247 2b.3.4      Corporate Overteads                                .        .          .          ..                                5,754            863    6,618      6,618            -
323      21,621          3,483  26.124      7,877        18,247                          1,126                                  67,588        220 2b.3        Subtotal Period 2b Collateral Costs              164      195            54      283 Period 2b  Period-Dependeot Costs 2b.4.1      Decon supplies                                  1,318                                                                  -              330    1,648      1,648 2b.4.2      Insutrance                                        -                                                                1,273            127    1.400      1,400 2b.4.3      Property taxes                                              -                                                            10            1      11          11          -
2b.4.4      Health physics supplies                                  2,257                                                        -              564    2,822      2,822 2b.4.5      Heavy equipment rental                                  4.559                      -          -                -                    684    5,243      5,243 55 835                        218    1,135      1,135                                        17,954                                164,691 2b.4.6      Disposal of DAWgenerated                                    -            53        29                                -
2b.4.7      Plant energy budget                                                                                        -        1,805            271    2.076      2,076 2h.4.8      NRC Fees                                                                                                            1,709            171    1,880      1.880 2b.4.9      Emergency Planning Fees                                                                                              2,190            219    2,409                      2,409 2b.4.10    Spent Fuel Pool O&M                                                                                                  1.936            290    2,227          -          2,227 2b.4.11    Liquid Radwaste Processing Equipment/Services                                                                          487              73    560        560            -
2b.4.12    ISFSI Operating Costs                                                                                                  220              33    254          -            254 2b.4.13    Security Staff Cost                                                                                                12,279          1,842  14,120      14,120            -                                                                                          342,634 29.008          4,351  33,359      33,359                                                                                                        395,491 2b.4.14    DOC Staff Cost 40,864          6,130  46,993      46,993            -                                                                                          734,023 2b.4.15    Ulily Staff Cost 29                    835      91.781        15,324  116,137    111,248          4,889                          17.954                                164.691          55  1.472,109 2b.4        Subtotal Period 2b Period-Dependent Costs      1,318    6,816            53 18.334        1,081      1,928      14,567    13,243    113,402        29,057  197,020    173.085        23.135          800  155,741  112,354                              15,285.000  374,928    1,472.109 2b.0        TOTAL PERIOD 2b COST                            5,407 PERIOD 2c - Decontamination Folosing Wet Fuel Storage Period 2c Direct Decommissioning Actovilaes 2c.1.1      Remove spent fuel racks                          267        33          79        88                  1,348                        500    2,316      2,316                                          5,988                                537,141      1,004 Disposal of Plant Systems 50          7          8                  121                          45    231        231                                    -      537                                  48,175      1,273 2c.1.2.1    Reactor El 1001 ArealA 64          1          4          54        13                        28    164          164                                  578        57                                28,513      1,737 2c.1.2.2    Reactor El 1001 Areal B 2c. 1.2.3 Reactor El 976 AreslA                                          i1          1          1                    16                          7      36          36                                  -        72                                  6,482        324 Reactor El 976 Area lB                                      150          11        27          328      115                        121      752        752                                3,516      511                                188,501    4,017 2c.1.2.4 7          1          1          -          13                          5      26          26                                  -        57                                  5,136        174 2c.1.2.5    Reactor El 976 Aree2A 38          1          3          42        16                        20    121          121                                  449        72                                24,474      1,056 2c.1.2.6    Reactor El 976 Area2B 321          23        44          424      293                        226    1,331      1.331                                4,543    1,305                                301,281    8,561 2c.1.2      Totals Decontamination of Site Buildings 2c.1.3.l    Reactor (post fuel)                              257      510          97      138            163    1,742                        747    3,656      3,658                                1,749  32,119                              3,281,659    18,302 Totals                                            257      510          97      138            163    1.742                        747    3.656      3,658                                1,749  32,119                              3.281,659    18,302 2c.1.3 2c 1.4      Scaffolding in support of decommsuioning                    518            6                      42        6                      138      712          712                                  405        25                                20,498      7,023 1,611  8,014      8.014                                6.697  39,437                              4,140.579    34,890 2c.1        Subtotal Period 2c Actiolty Costs                525    1,382          205        273            630    3,389 Period 2c Additional Costs 2c.2.1      Final Site Survey                                                                                                    1,205          362    1,567      1.567                                                                                        -      -        12,480 12,480 2c.2        Subtotal Period 2c Additional Costs                                                                                  1,205          362    1,567      1,567 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                          Document N01.1590-002, Rev. I DecommissioningCost Analysis                                                                                                                                                                                                                                        Appendix D, Page8 of 35 Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
                                                                                                                  .off-Sit  LLRW                                        NRC        Spent Fuei      Site    Processed            Burial Volumes            Buriall                Utility and Activy                                                  Decon    Removal    Packaging    Transport    Processing  Disposal    Other        Total        Total Lc. Terom    Management    Restoration  Volume    Class A  Class B    Class C  GTCC    Processed    Craft    Contractor index                      Activity Description        Cost    Cost        Costs      Costs        Cost.        Costs      Costs    ContinIen      Cost. Costs          Costs        Costs      Cu. Feet  Cu Feet  Cu. Feet Cu Feet  Cu Feet  WI. Lbs. Manhours    Manhours Period 2c Collateral Costs 2c.3. 1    Process liquid waste                            101                        33        175                      200                        130    639        639                                              696                                41.756        136 2c.3 2      Small tool allowance                              -            22                                                                            3      25          25 2c.3.3      Deconmissionng Equtlment Disposition                                        s8        50          621          84                      130    973        973                                  6.000      373                                303.507          88 2c.3.4      Spent Fuel Capital and Transfer                                                      -        -1,949                                    292  2,242          -            2,242 2c.3        Subtotal Period 2c Collateral Costs              101          22        121        225            621      284      1,949            556  3,879      1,637          2,242                  6.000    1,069                                345.263        224 Period 2c Period-Dependent Costs 2c.4.1      Decon supplies                                    90                                      -                                                23    113        113 2c.4.2      Insurance                                                                                                                  197            20    217        217 2c.4.3      Property taxes                                              -                                                                2            0      2            2 2c.4.4      Health physics supplies                                    256                                                                            64    320        320 2c.4.5      Heavy equipment rental                                      707                                                                            106    813        813 2c.4.6      Disposal of DAWgenerated                                    -              12          6                      184        -              46    250        250                                            3,949                                36,227          12 2c.4.7      Plant energy budget                                                                                            -          149            22    172        172 2c.4.8      NRCFees                                                                                                                    265            27    292        292 2c.4.9      Emergency Planning Fees                                                                                                    340            34    373          -              373 2C.4.10    Liquid Radwaste Processing EquipmentlServices                                                                              151            23    174        174 2C.4.11    ISFSI Operating Costs                                                                                                        34            5      39                          39 2C.4.12      SecurityStaff Cost                                                                                                      1,159            174  1,333      1,333                                                                                                          27.930 2c.4.13    DOC Staff Cost                                                                                                          3,126            469  3,595      3,595                                                                                                          42,000 4,699            705  5.404      5,404                                                                                                            80,220 2C.4.14    Utlity Staff Cost 2c,4        Subtotal Period 2c Peaod-Dependent Costs            90      963            12          6                      184    10,123          1,719  13,096      12,684            413                            3,949                                36,227          12    150,150 2c.0        TOTAL PERIOD 2c COST                            716      2,367          337        504          1,251      3,856    13,277          4,248  26,556      23,902          2,654                  12,697  44.455                              4,522,069    35,126      162,630 PERIOD 2e - License Termination Period 2e Direct Decommissioning Activiats 2e.1.1      ORISE confirmatory survey                                                                                                  147            44    191        191 2e.1.2      Terninate license 2e. 1      Subtotal Period 2e Actuty Costs                                                                                            147            44    191        191 Period 2e Additional Costs 2e.2.1      Final Site Survey                                                                                                                      1,799  7,797      7,797                                                                                            148.435          6,240 2e.2      Subtotal Period 2e Additional Costs                                                                                                    1,799  7,797      7,797                                                                                            148,435          6.240
* 5.912 5718
                                                                                                                                -
* Period 2e Collateral Costs 20.3.1      DOC staff relocation expenses                                      -      . -        .              .          -          912            137  1,049      1,049 2e.3.2      Spent Fuel Capital and Transfer                                    -      . .        -              -          -          571            80    656          -              656 2e.3        Subtotal Period 2e Collateral Costs                              *    ~~  -          -              -          -      1483
                                                                                                                                          ,                222  1,705      1,049            656 Period 2e Period-Dependent Costs 2e.4.1    Insurance                                                                                                                  327            33    360        360 2e.4.2    Property taxes                                                                                                                3            0      3            3 2e.4.3    Health physics supplies                                    737                                                                            184    921        921 3                      1          42                        11      58          58                                            914                                  8,380          3 2e,4.4    Disposal of DAWgenerated 20.4.5      Plant energy budget                                                                                                        139            21    160          160 2e.4.6      NRC Fees                                                                                                                  530            53    583        583 2e.4.7      Emergency Planning Fees                                                                                                    633            63    696          -              696 2.4.8      ISFS1Operatng Costs                                                                                                          64            10      73                          73 2e.4.9      Security Staff Cost                                                                                                    2,125            319  2,444      2,444                                                                                                            50.886 2e.4.10    DOC Staff Cost                                                                                                          4,442            666  5,108      5,108                                                                                                            57,149 2e.4.11    UtifityStaff Cost                                                                                                      5,071            761  5,832      5,832                                                                                                -          80,634 20.4      Subtotal Period 2e Period-Dependent Costs                  737              3          1                        42    13,334          2.121  16.238      15.468            769                              914                                  8,380          3    188,669 2e.0      TOTAL PERIOD 2e COST                                        737              3          I                        42  20,962          4.187  25,931      24,506          1,426                              914                                  8,380  148.438      194.909 TMG Services,Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                          Document N01.1590-002, Rev. I Appendix D, Page9 of 35 Decommissioning Cost Analysis Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sit. LLRW                                        NRC      Spent Fuel      Site      Processed            Burial Volumes                BurialI            Utlity and Activiy                                            Docon  Removal    Packaging Transport Processing Disposal    Other      Total        Total Lic. Term. Management  Restoration    Volume    Class A Class B Class C      GTCC      Processed  Craft    Contractor Index                    Acvity Descriptlon      Cost    Cost      Costs    Costs      Costs    Costs      Costs    Continaenc      Costs    Costs      Costs        Costs        Cu. Feet  Cu. Feat Cu. Feet Cu. Feet  Cu. Feet  WL Lbs. Manhoure Manhours PERIOD 2 TOTALS                                      6,750    39,950    10,481    6,870    30,933  46,723    207,625        72,836  422,169    385,342        35,926        901      319,826  219,601    3,104      1,205          31,151,470  771,150    2.653,551 PERIOD3b - Sit Restoration Period31DirectDecommissioning      Activities Demolition of Remaining Site Buishings 1,473                                                              221    1,694                                1.694                                                                  14,089 3b.1.1.1  Reactor                                                                                                                                                                                                                                        2,119 3b.1.1.2 Augmented Radwaste                                      222                                                                33    255                                  255 32    246                                  246                                                                    1,655 3b.1.1.3  Control                                                214 523                                                                78    602                                  602                                                                    5,621 3b.1.1.4  Intake Structure 145                                                                22      167                                  167                                                                  1,227 31.1.1.5 LLRWStorage Pad                                                                                                                                                                                                                                11,837 3b.1.1.6 Miscellaneous Structures - Clean                      1,196                                                              179    1,375                                1,375 4      30                                    30                                                                    572 3b.1.1.7  Misceaneous Stnrutures - Contaminated                  27 123                                                                1i      141                                  141                                                                  1,982 3b.1.1.8  MuiS-Purpose Facilty 3      20                                    20                                                                    283 3b.1.1.8  OWC Gas Generator                                        18 156                                                                23      179                                  179                                                                  1.920 3b.1.1.10 Office 391                                                                59    449                                  449                                                                    3.229 3b.1.1.11 Radreste 3      20                                    20                                                                    166 3b51.1.12 SealWen                                                  17 4                                                                1        5                                      5                                                                      53 3b 1.1 13 Sewrage Treatment Area 3      24                                    24                                                                    172 3b.1.1.14 Transfonner Yard                                        20 2,596                                                              389    2.985                                  2,985                                                                  40.503 3b.1.1.15 Turbine                                                                                                                                                                                                                                        2.100 3b.1.1.16 Turbine Pedestal                                        277                                                                42    318                                    318
* 18                                                                3      21                                    21                                                                    512 3b.1.1.17 Reactor (post fuel) 7,418                                                              1,113    8.531                                8,531                                                                  88,040 3b.1.1    Totals Site Closeout Ac'invies                                                                                                                                                                                                                                  3,288 3b.1 .2    Remove Rubble                                          424                                                                64    488                                  488 578                                                  -              87    6685                                  686                                                                  1,578 3b. 1.3    Grade & landscape site Final report to NRC                                                                                        156            23      179        179                                                                                                          1.560 3b.1.4 8,421                                                  156        1,286    0,863        179                      9,684                                                                  92,904        1.560 3b. 1      Subtotal Peard 3b ActivityCosos Period 3b Additonal Costs 3b.2.1    Concrete Crushing                                      499                                                    8            76    582                                    582                                                                  3,045 3b.2.2    Cofferdam                                              458                                                  -              69    527                                    527                                                                  5,130 957                                                    8          145    1.109                                1,109                                                                  8,175 3b.2      Subtotal Period 3b Additional Costs Period 3b Collateral Costs 3b.3.1    Small tool alrowance                                    53                                                -              8      61                                    61 3b.3.2    Spent Fuel Capital and Transfer                                                                            758            114    872                      872          -
53                                                758            122    932                      872            61 3b.3      Subtotal Period 3b Collateral Costs Period 3b Period-Dependent Costs 3b54.1    Insurance                                                                                                  751            75    826                      826 3b.4.*    Property toxes                                                                                                7            1        8                        8 3 .4.3    Heavy equapment rental                              4,053                                                              608    4.661                                4,661 160            24      184                                  184 3b.4.4    Plant energy budget 3b.4.5    NRC ISFSI Fees                                                                                            437            44    481                      481 3b.4.8    Emergency Planning Fees                                                                                  1,453            145    1.598                    1,598 3b.4.7    ISFSI Operating Costs                                                                                      148            22      168                      168 4,878          732    5,610                    4,937          673                                                                              116,814 354.8      Security Staff Cost 9,777          1,467  11,244          -                      11,244                                                                              122,206 31.4.9    DOC Staff Cost 5,903          885    6,789          0        1,697        5,091                                                                              97.944 3b.4.10    Utility Staff Cost 4,053                                              23,513        4.003  31.569            0        9.715      21,853                                                                              336,964 3b.4      Subtotal Period 3b Pedod-Oependent Costs 13,483                                              24,435          5,555  43,473        179        10,587      32,707                                                                  101,079      338,524 3b.0      TOTAL PERIOD 3b COST TLG Services, Inc.
 
DocumentNO.1-1590-002, Rev. I CooperNuclear Station Appendix D, Page 10 of"35 DecommissioningCost Analysis Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sits      LLRW                                          NRC      Spent Fuel        Site    Processed          Burial Volumes              Burial I            Utilityand Activity                                            Decon Removal  Packaging  Transport Processing    Disposal      Other      Total        Total  Lis.Tero. Management      Restoration  Volume  Class A  Class B Class C GTCC Processed        Crft      Contractor Index                    Activ iDescription        Cost  Cost      Costs    Costs      Costs        Costs      Costs    Contlngency    Costs    Costs        Costs          Costs      Cu. Feet Cu.Feet  Cu. Feet Cu. Feet Cu. Feet WI. Lbs. Manhosre    Manhours PERIOD 3c - Fuel Storage Operations/Shlpping Period 3c Collateral Costs 3c.3.1      Spent Fuel Capital and Transfer                                                                            9,855        1.478  11,334                  11,334 3c.3        Subtolal Period 3c Collateral Costs                                                                        9,855        1,478  11,334                  11,334            -                --                        -
Period 3c Period-Dependent Costs 3c.4.1      insurance                                                                                                  8.525          852    9,377                    9,377 3c.42      Property taxes                                                                                                  78                    Be                        86 3c.4.3      Plant energy budget 3c.4.4      NRC ISFSI Fees                                                                                              4,964          496    5,460                    5,460 Emergency Planning Fees                                                                                    16,486        1.649  18,135                    18,135 3c.4.5 3c.4-6      ISFSI Operating Costs                                                                                      1-660          249    1.909                    1,909
* 1,101,291 3c.4.7      Security Staff Cost                                                                                        48,727        7,309  56,036                  56,036 16,889        2.533  10,422                  19,422                                                                                        275,323 3c.4.8      UtilityStaff Coat 3c.4        Subtotal Period 3c Pedrod-Dependent Costs                                                                  97,329        13,097  110,425                  110,425                                                                                      1,376,614 107.184        14,575  121,759                  121,759                                                                                      1,376,614 3c.0      TOTAL PERIOD 3c COST PERIOD 3d - GTCC shipping Period 3d Direct Decommissioning Acivities Nuclear Steam Supply System Removal 3d.1.1.1 Vessel &Intemat GTCC Disposal                                    660                            7,470 S                        1,186    9,316      9,316                                                                      508    89,497 660                                                      1,186    0,310      9,316                                                                      508    89,497 3d,1.1      Totals                                                                                          S 7,470 660
* 7,470                    1,186    9,316      9,316                                                                      508    89,497 3d. I      Subtotal Period 3d Activty Costs Period 3d Collateral Costs 3d.3.1    Spent Fuel Capital and Transfer                                            *-          -          -            76            11      87                        07                                                  -
3d.3      Subtotal Period 3d Collateral Costs                                        --          -79                                  11      87                        87--
Period 3d Period-Dependent Costs 3d.4.1    Insurance                                                                                                      17            2      18                        18 3d.42      Property taxes                                                                                                  0            0      0 3d.4.3    Plant energy budget 3d.4.4    NRC ISFSI Fees                                                                                                  a            1      8                          8 3d.4,5    Emergency Planning Fees                                                                                        32            3      36                        364 3            0      4                          4 3d.4.6    ISFSI Operating Costs                                                                                                                                                                                                                                      -2160 3d.4.7    Security Staff Cost                                                                                            96            14    110                      110 33            5      38                        38                                                                                            540 3d.4.8    UtilityStaff Cost 189          25      214                      214                                                                                          2,700 3d.4      Subtotal Period 3d Period-Dependent Costs 302                                                        508    89,497                    2,700 3d.0      TOTAL PERIOD 3d COST                                            660                            7,470          265        1.223    9,618      9,318 PERIOD 3e - ISFSI Decontamination Period 3e Direct Decommissioning Activities Period 3e Additional Costs 3e.2.1      ISFSI Decontamimation                            1.012          9        24                      60    1,250          460    2,811                    2,811                            1,175                              165.113    26.509          2,560 1,012          6        24                      60    1,250          460    2,811                    2,811                            1,175                              165,113    26,509          2,560 3e.2        Subtotal Period 30 Additional Costs Period 3e Collateral Costs 2      16                        16 3e.3.1      Small tool allowance                                  14 5            1        9                        6 3e.3.2      Spent Fuel Capital and Transfer 14                                                        5            3      22                        22 3e.3        Subtotal Period 3e Cotateral Costs TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                Document NO1.1590-002,Rev. I Deco .un-ioning      Cost Analysis                                                                                                                                                                                                                        Appendix D, Page 1 of"35 Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                        NRC      Spent Fuel      Site    Processed              Burial Volumes              Burial I            Utilty and Activity                                            Decon  Removal    Packaging  Transport  Processing Disposal    Other      Total        Total Li. Term. Management    Restoration  Volume    Ciss A    Class B    Class C  GTCC    Processed    Craft  Contractor Index                    Activity Description      Cost      Cost      Costs      Casts      Costs      Costs      Costs  Contln en      Costs    Costs      Costs        Costs      Cu. Feet  Cu. Feet  Cu. Faet Cu. Feet  Cu. Feet  WL, Lbs. Manhours  Manhours Period 3e Period-Dependent Costs 3e.4.1    Insurance                                                                                                        145            14    159                      109 3e.4.2    Property taxes                                                                                  -    -            1            0      1 3e.4.3    Heavy equipment rental                                  232                                                                    35    267                      267 3e.4.4    Plant energy budget 3e.4.5      Security Staff Cost                                                                                            303            46    349                      349                                                                                            5,013 3e.4.6    UtflityStaff Cost                                                                                                249            37    287                      287                                                                                            38803 3A.4      Subtotal Period 3e Peitod-Dependent Casts                232                                                    699          132  1,063                    1,063                                                                                            6,816 3e.0      TOTAL PERIOD 30 COST                                  1,258            6          24                  60    1,954          595  3,896                    3,896                              1,175                                  165,113    28,509      11,376 PERIOD 3f -ISFSI Site Restoration Period 3f Direct Decornrrissioning Activities Period 3f Additional Costs 3f.2.1      ISFSi Dernolition                                      672                                          -          44          107    824                      824                                                                        -      5,898        160 3W.2        Subtotal Period 3WAdditional Costs                      672                                          -          44          107    824                      824                                                                        -      5,898        160 Period 3f Collateral Costs 31.3.1      Smealtool atowance                                -        3        *          .                    -                        0      4                        4-
* 31.3        Subtotal Period 3f Collateral Costs
* 3        *                                -                        0      4                        4 Period 3f Pedod-Oepenvent Costs 314.1      Insurance 31.4.2      Propedy taxes                                                                                                      1            0      1                        1 3f.4.3      Heavy equipment rental                                    79                                                                  12      91                      91 3A.44      Plant energy budget 3X.4.5      Security Staff Cost                                                                                            155            23    179                      179                                                                                            2,569 3WA.6      UtaityStaff Cost                                        -                                                      110            16    126                      126                                                                                            1,594 31.4        Subtatal Period 3WPeriod-Dependent Costs                  79                                                    266            52    396                      396                                                                                            4,163 31.0      TOTAL PERIOD 3f COST                                    754                                                    310          160  1,224                    1.224                                                                                5,898      4,323 PERIOD 3 TOTALS                                                  15,495        666          24        -      7,530  134,148        22,108 179,970      9,495      137,768        32,707        -      1,175                -        508    254.610  133,486  1,733,537 TOTALCOST TO DECOMMISSION                              9.296    58.392      11,201      7,212      30.933    56,732  437,605      111,599 722,972    506,207      182,368        34,396    319,826  234.031    3,647      1,205      508  31,649,200  915,901  5,434.429 TlG Services, Inc.
 
Coop-rNtudnaStation                                                                                                                                                                                                                                  Document N0I.1590-002,Rev. 1 De~commissioning Coot Analysis                                                                                                                                                                                                                            Appendix D, Page 12 of"35 Table D-1 Cooper Nuclear Station 2034 DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                      NRC    Spent Fuel    Site    Processed            Burial Volumes              Burial I            Utility and i DecO0 Removal Packaging Transport  Processing  Disposal    Other      Total      Total Lic. Term. Management Restoration  Volume  Class A  Class B    Class C  GTCC    Processed  Craft    Contractor ctviy                                                              Cost  Cast    Costs    Casts      Casts      Costs      Costs  Contlaoonnon Casts    Casts      Casts      Costs      Cu. Fant Cu. Fent Cu. Fant Cu. Foot  Cu. Fant  Wit. Lbs. Manhoure  Manhours I
* I I*ez                        A*UV* *rml*n B
ex                                                              cast  Cast    Costs    Costs      Costs      costs      Costs  Contingency  Costs    costs      Costs      coati      Cu. Fast Cu Feel  Cu. Fast Cu. Feet    . Fast            Manhours  Manhours TOTALCOST TO DECOMMISSIONWITH 18.25% CONTINGENCY:                                            $722,972  thousands of 2008 dollars TOTALNRC UCENSE TERMINATIONCOST IS 70.02% OR:                                                $506.207  thousands of 2008 dollars SPENTFUEL MANAGEMENTCOST IS 25.22% OR:                                                      $182.368 thousands of 2008 dollars NON-NUCLEARDEMOLITIONCOST iS 4.76% OR:                                                        024,396 thousands of 2008 dollam TOTALLOW-LEVELRADIOACTIVEWASTE VOLUME BURIED (EXCLUDING GTCC):                                238,883 cubic feet TOTALGREATER THANCLASS C RADWASTE VOLUMEGENERATED:                                                  600 cubic feet TOTALSCRAP METAL REMOVED:                                                                      30.340 tons TOTALCRAFT LABOR REQUIREMENTS:                                                                915,901 man-hours End Notes:
ra - Indicates that his acvity not charged as decommissioning expenrse a - indicates that this activity performed by decommissioning staff.
0 - indicates thra this value is less than 0.5 but is non-zem.
a cell containing" -" indicates a zero value TLG Services,Inc.
 
CooperNuclear Station                                                                                                                                                                                                                        Document N01-1590-002, Rev. 1 DecornmissioningCost Analysis                                                                                                                                                                                                                    Appendix D, Page 13 of 35 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site      LLRW                                    NRC        Spent Fuel      Site    Processed            Burial Volumes            Burial I          Utilityand Activity                                          Decon Removal Packaging      Transport  Processing    Disposal    Other      Total      Total Lic.Term. Management  Restoration  Volume  Class A Class B Close C    GTCC    Processed  Craft  Contractor eIndex                  Activity Description      Cost  Cost      Costs        Costs      Costs        Costs    Costs  Contingency  Costs    Costs        Costs        Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Feet Cu. Feet  WI. Lbs. Manhours  Mahours PERIODis - Shutdown through Transition Periodla DirectDecommissioning      Activities le.1.1      SAFSTOR site characterization survey                                                                          346          104  450        450 lu 1l2      Prepare preliminary decommissioring cost                                                                      130            20  150        150                                                                                                    1,300 1a.1.3      Nctiticaton of Cessation of Operations                                                                                              a rda 10.14      Remove furl & source material
: i. 1.5      Notificaton of Pernranent Defuelrng is. 1.6    Deactivate plant systems &process waste 200            30  230        230                                                                                                      2,000 ta.1.7      Prepare and submit PSDAR u.I .8    Review plant dwgs & specs.                                                                                    130            20  150        150                                                                                                    1,300 10.1.9      Perform detailed red survey 100            15    10        115                                                                                                    1,000 ul.10    Estimate by-product inventory 100            15  115        115                                                                                                    1,0O00 1a.1.11    End product descrrption                                                                                                                                                                                                                                1.500 10.I.12    Detailed by-product inventocy                                                                                  150            23  173        173                                                                                                    1,000 1:.1.13    Def-oe major morksequence                                                                                      100            15  115        115 I0. 1.14    Perform SER and EA                                                                                            310            47  357        357                                                                                                      3,100 1a.1.15    Perform Site-Specific Cost Study                                                                              500            75  575        575                                                                                                      5,000 ActivitySpecifications 18.1.16.1 Prepare plalt and faciities for SAFSTOR                                                                          492            74  566        566                                                                                                    4,920 417            63  479        479                                                                                                      4,167 la.1.6.2 Plant systems 1a.1.15.3Plant structures and butilings                                                                                312            47  359        359                                                                                                    3.120 la.l,16.4 Waste management                                                                                                200            30  230        230                                                                                                      2.000 10.1.16.5 Facility and site dormancy                                                                                      200            30  230        230                                                                                                      2,000 1,621          243  1,864      1.864                                                                                                  16,207 1a.1.16 Total Detailed Work Procedures la.1.17.1 Plant systems                                                                                                                  18  136        138                                                                                                    1,103 18  138        138                                                                                                    1,200 la.t.17.2 Facility closeout &dormancy                              -      . .          -            .          .        120 la.1.17    Total                                                  *      . .          -            .          -        238            36  274        274                                                                                                      2,383 lus1.18    Procure vacuum drying system                                                                                          10      2    12          12                                                                                                    100 la.1.19    Drain/de-energie non-cort. systems a
la.1.20    Drain &dry NSSS la.1.21    Drain/de-energizecontaminated systems la-. 22    Decon/securecontaminated systems 3,930          642 4.577      4,077                                                                                                  35.890 la.1        Subtotal Period 10Activty Costs Penod Ia Collateral Costs la.3.1      Spent Fuel Capital and Transfer                        *        --          -            -          -      2,721          408 3,129                    3,129                    -        .      .
1a,3.2      Corporate Overheads                                    -            .      -            -3,105                            466 3,570      3,570 1l.3      Subtotal Period tu Collateral Costs                    *        ..          .            .          .      5,825          874 6,699      3,570        3,129 Peniod 10Period-Dependent Costa la.4.1      Insurance                                                                                                    1,600          160  1.760      1,760 1:.4.2    Property taxes                                                                                                    4            0      4            4 1.4.3      Health physics supplies                            370                                                                        63  463        463 1:.4.4    Heavy equipment rental                            368          -                                                            55  423        423 1 a.4.5    Disposal of DAW generated                                          5                                  73                    19    100        100                                          1,575                                14,445        5 la.4.6    Plant energy budget                                                                                            927          139  1.066      1,066 1a.4.7    NRC Fees                                                                                                                      71  776        776 1:.4.6    Emergency Planning Fees                                                                                      1,165          11i  1,303                    1,303 1A.4.9    Spent Fuel Pool O&M                                                                                            745          112  857                      857 1a,4.10    ISFSI Operating Costs                                                                                            85          13    68        -              98 6,021          903 6,924      6,924                                                                                                  157.471 1a,4.11 Security Staff Cost TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                    Document N0-1590-002,Rev. 1 DecommissioningCoast Analysis                                                                                                                                                                                                                                Appendix D, Page 14 of 35 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                          NRC      Spent Fuel      Site    Processed            Burial Volumes                Burial I            Utility and I Decon  Removal    Packaging  Transport  Processing Disposal      Other        Total        Total Lic. Term. Management  Restoration  Volume  Class A  Class B    Class C    GTCC    Processed  Craft    Contractor IActivity                  ACBV*
* nD[*g      Cost      Cost      Costs      Costs        Costs    Costs      Costs    Continienon    Costs    Costa        Costs        Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Feat    Cu. Feet  Wt. Lts. Manors    Manhours I II    InnBx n ex                                    ri n Period 1a Period-Dependent Costs (conifnued) la.4.12 Utility  Staff Cost                                                                *              -            23,690          3-403  26,093      26,093                                                                                    -        -      423,400 1..4      Subtotal Period  la Penod-Dependent Costs              738                      3                    73    33,962          5,087  39,867      37,609        2,258                          1,675                                    14,445        5    580,871 la.0      TOTAL PERIOD l a COST                                    738                      3                    73    43,723          6,603  51,144      45,757        5,387                          1,575                                    14,445        5    616,761 PERIOD lb - SAFSTOR Limited DECONActivities Period lb Direct Decormissioning Actvities Decontamination of Site Buildings 1b 1.1.1 Reactor                                      2.929                                                                                1,465  4,394        4,394                                                                                          68,438 lb. 1.1.2 Augmented Radwaste                              52                                                                                  26      78          78                                                                                          1,562 lb.1.1.3 Misceltaneous Sb'uctures - Contaminated        376                                                                                188    565          565                                                                                            6,542 1b.1.1.4 Muli-Purpose Facility                            68                                                                                  34    101          101                                                                                            2,036 1b.1-.15 Radwaste                                        158                                                                                  79    237          237                                                                                            4,761 Ib.1.1.6 Turbine                                        520                                                                                260    780          780                                                                                          15,667 lb.1.I    Totals                                      4,103                                                                              2,052  6,155        6,155                                                                                          101,060 Ib.1      Subtotal  Period 1b Activity Costs          4,103                                                                              2,052  6,155        6,155                                                                                          101,008 Period lbAdditiomal Costs lb.2.1    Spent Fuel Pool Isolation                                            .-        .                                9,407          1,411 10,818      10,818 lb2.2      Asbestos Insulation Disposal                            773            1        65                  558                        265    1,662      1,662                                      10,333                                  134.329    10,002 lb.2      Subtotal Period Ib Additional Costs                      773            1        65                  558      9,407          1,676 12,480      12,480                                      10,333                                  134,329    10.002 Period 1b Collateral Costs 1b.3*1 Decon equipment                                  713                    -          -              -      -                          107    820          820 Ib.3.2    Process liquid waste                          229
* 74        392                  448                        293    1,436      1,436                                        1,561                                    93,644      304 1b.3.3    Small tool allowance                                      70                                -              -                      11      61          81 lb.3.4    Spent Fuel Capital and Transfer                                                                                    930            130    1,069        -          1,009 lb.3.5    Corporate Overheads                            ..-                              -                                  766            115    880          880 lb.3      Subtotal Period lb Cotateral Costs            942          70        74      392                    448        1,695            665  4,286        3,217        1,069                          1,561                                    93,644      304 Period lb Period-Dependent Costs Wb4.1    Decon supplies                              1,156                                      -              -            -            289    1,445      1,445 1h4.2      Insurance                                      -        -121                                                                      12    133        133
                                                                      *    -                                                            1              0      1            1 1b.4.3    Property tavos 1b.4.4    Health physics supples                                  473                                                                      118    592          592 lb.4.5    Heavy equipment rental                              -      01        -          -                      .            -              14    104        104 1b.4.6    Disposal of DAWgenerated                                                5          3                    81        -              21    110        110                                        1,741                                    15.98          5 lb.4.7    Plant energy budget                                                                                                229              34    263          263 lb.4.6    NRC Fees                                                                                                          174              17    191        191 lb.4.9    Emergency Planning Fees                                                                                            292              29    321                      321 1.b4.10    Spent Fuel Pool O&M                                                                                                184              28    211                      211 1b.4.11    ISFS1Operating Costs                                                                                                21              3      24        -              24 lb.4.12    Security Staff Cost                                                                                              1,485            223    1,707      1,707                                                                                                      38,829 1b.4.13 Utiliy Staff Cost                                                                                                  5,595            839  6,434        6,434                                          -                .104,400 lb.4      Subtotal Period 1 b Penod-Dependent Costs  1.156        564            5          3                    81      8,101          1,628 11,538      10,981          557                          1,741                                    15,968        5    143,229 lb.0      TOTAL PERIOD lb COST                        6,201      1,407          so      460                  1,087      19,203          6,020  34,458      32,833        1,626                        13,635                                  243,942  111,318    143,229 TLG Servdveea    Inc.
 
Cooper Nucekar Stai~on                                                                                                                                                                                                                                  Document N01-1590-002, Rev. I DecomomissioninogCost Analysis                                                                                                                                                                                                                                Appendix D, Page 15 of"35 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommnissioning Cost Estimnate (thousands  of'2096 dollars)
Off-Site    LLRW                                        NRC        Spent Fuel      Site    Processed            Burial Volumes              Burial I              Utntyoad n
IActivity                                              Oecon coot Removal Cost Packaging Coots Transport Coots Processing Costs Disposal Costs Other Costs Total Continoorco Total Costs LiO.Term.
Costs Management Cost.
Restoration Ceot.
Volume Cn. Foot Class A Cu. Foet Clans B    Clans C Cu. Feet Cu. Foot GTCC Co. Foot Processed est. Ltt.
Craft Manhon,,
Contractor Masnhour.
I m    Innnx                  A*VZ*    *CMnZ*n n as                  A  v        c      n        Cost    Cast      costs      Costs        Costs      costs      Costs    Cortina""      Costs    Costs        Costs        Costs      Cu Fast  Cu    I Cu Fast Cu. Feet  Cu. Fast  Wt Los    Manhours PERIOD Ic - Preparations for SAFSTOR Dormancy Period lc Direct Decommlssionirg Activities lC.1.1    Prepare support equipmenrt for storage                    387                                                                      58      445        445                                                                                              3.0D0 it. 1.2  Install containment pressure equal. lines                  31                                                                                            36                                                                                              700 5      36 Ic.1.3    Interim surpey prior to dormancy                          -                                                          733          220      953          53                                                                                          15,696 1c.1.4    Secure building accesses Ic.1.5    Prepare &submit ioterim report                                                                                        58            0      67          67                                                                                                -  *583 IC.1      Subtotal Period Ic Activiy Costs                        419                                                        791          291    1,501      1,501                                                                                            19.396          583 Period lc Collateral Costs lc.3.1    Process liquid waste                            235                    76        403                    460                      301    1,475      1,475                                          1,603                                  96,195      313 lc.32    Small tool aliowance                                        3                                                                      0        3            3 lc.3.3    Spent Fuer Capital and Transfer                                                                                      940          141    1,081        -            1,081 lc.3.4    Corporate Overheads                                                                                      -          774          116      890        890 lc.3      Subtotal Period It Coltateral Costs            235          3        76        403                      460      1,714          558    3,449      2.368          1,081                          1,603                                  96,195      313 Period ic Period-Dependent Costs 1cA.1    Insurance                                                                                                            122            12      134        134 IcA4.2    Property loves                                                                                                          1            0        1            1 lc.4.3    Heath physics supplies                                    160                                                        -              40      200        200 1C,4.4    Heavy eqaipment rental                                      92                                            -                        14      105        105 1.4.5    Disposal of DAWgenerated                                                1          I                      s1      -                5      25          25                                            393                                    3,601          1 1c.4.6    Plant energy budget                                                                                                  231            35      266        266 1c.4.7    NRC Fees                                                                                                            176            18      194        194 lc.4.8    Emergency Planning Fees                                                                                              295            30      325                        325 lc,4.9    Spent Fuel Pool O&M                                                                                                  188            28      214                        214 Itil 0    ISFSI Operating Costs                                                                                                  21            3      24        -              24 1c.4.11  Securdy Stafl Cost                                                                                                1,501          225    1,726      1,726                                                                                                          39.260 lc.4.12  Utlity Staff Cost                                                                                                  5.657          849    6,505      6.505                                                                                                -      105,560 1c.4      Subtotal Period Ic Penod-Oependent Costs                  252            1          1                      18    8,191        1,257    9,720      9,157            583                            393                                    3,601          1    144,820 lc.0      TOTALPERIOD Ic COST                            235      673          77        404                    478    10.696        2,107  14.670    13,026          1,644                          1.996                                  99,796    19,710    145.403 PERIOD 1 TOTALS                                          6,437    2.818        162        866                  1.636    73.621        14.730  100,272    91,616          8.657                          17,205                                358,183    131.033    905.393 PERIOD 2a - SAFSTOR Dormancy with Wet Spent Fuel Storage Period 2a Direct Decommissioning Activities 2a.1.1    Quarterly Inspection 2a.1 .2    Semi-annuol environmental survey                                                                                                              a 2a 1.3    Prepare reports 20.1.4    Bitominous roof replacement                                              *        -            .        -            63            9      73          72 2a. 1.5    Maintenance supplies                                                    *      -              .
* 553          126    629        629 20.1      Subtotal Period 2a ActivityCosts                                        *        --            -566                              135      701        701 Pedod 2a Coliateral Costs 2a.3.1    Spent Fuel Capital and Transfer                                                --              -        -      21.155        3,173  24,329        -          24,329 2a.3.2    Corporate Overheads                                                            *.              -        -        4.139          621    4,759      4,759 2a.3      Subtotal Period 2a Collateral Costs                                                                              25.294        3,794  29,069      4,759        24,329 Penod 2a Period-Dependent Costs 2a.4.1    Insurance                                                                                                          1,962          196    2,158                      2,158 2a,4.2    Property laces                                                                                                        16            2      18                          18 2a.4.3    Health physics supplies                                  344                                                                      86    430        430 TLG Services, Inc.
 
0 Document N01.1590-002, Rev. I Cooper Nuclear Station Appendix D, Page 16 of 35 Decommissioning Cost Analysis Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousonds of 2008 dollars)
Off-Site  LLRW                                        NRC        Spent Fuel      Site    Processed            Burial Volumes              Burial I            Utility and I Packaging  Transport  Processing Disposal  Other        Total        Total  Lc. Term. Management  Restoration  Volume  Class A  Class B    Class C  GTCC    Processed  Craft    Contractor Decon Removal I Act.iity m  n ex                                                  Cost  Cost      Costs      Costs      Costs    Costs    Costs    Contingency    Costs    Costs        Costs        Costs      Cu. Feet Cu. Feet Cu. Faet Cu. Feet  Cu. Feet  Wt., Lbs. Manhours  Manhours I Period 2a Period-Dependent Costs (iconnued)                                                                                                                                                                                                    39,139        13 13          7                  198        -              52    270        270            -                            4,267 2a.4.4      Disposal of DAWgeeerated 2a.4.5      Plant energy budget                                                                                        742            111      053          -            853 2a.4.      NRC Fees 007              01    887        887            -
3,374            337    3.712          -          3,712 28.4.7      Emergency Planning Fees 2a.4.8      Spent Fuel Pool O&M                                                                                      2.984            448    3.431                      3,431 340              51    391                        391 2a,4.9      ISFSI Operating Costs                                                                                                                                                                                                                                  444,561 2a.4.10    Security Staff Cost                                                                                      17.728          2,659  20,387                    20,387
                                                                                                                                                                  -          21,639                                                                                      329,769 2a.4.11    Ublity Staff Cost                                                                                        188-816            2,822  21,639 344          13          7                  198    46.768          6,845  54.176      1,587        52.588                          4,267                                  39,139        13    774,330 28.4        Subtotal Period 2a Perod-Deeondent Costs 344        13          7                  198    72.628        10.775  83,965      7T048        76,917                          4,267                                  39.139        13    774.330 20.0        TOTALPERIOD 2a COST PERIOD 2b - SAFSTOR Dormancy with Dry Spent Fuel Storage Pedod 2b  Direct Decommissioning ti Activities 2b.1.1      Quarterly Inspec on 21b.1.2    Semi-annual environmental survey                                                                                                      a 2b.1.3      Prepare reports 2b.1.4      Bituminous roof replacement                                                                                354              53    407        407 2b.1.5      Maintenance supplies                                                                                      2,825            706    3,531      3,531 2b 1        Subtotal Period 2b ActivityCosts                                                                          3.178            759    3,938      3,938 Penod 2b Collateral Costs 2b.3.1      Spent Fuel Capital and Transfer                                                                          13,214          1,982  15,197                    15,197 2b.3        Subtotal Period 2b Collateral Costs                                                                      13,214          1,982  15.197                    15,197 Pedod 2b  Period-Dependent Costs 2b.4.1      Insurance                                                                                                9,796            980  10,775                    10.775 90            9      99          -99" 21.4.2      Property taues 2b.4.3      Health physics supples                              1,620                                        -                      405    2,025      2,025
                                                                          -          66        36                1,037        -            271    1,411      1,411            -                          22,311                                204,651        68 2b.4.4      Disposal of DAW generated 2b.4.5      Plant energy budget                                                                                      2.083            312    2,395          -          2.395 2b.4.e      NRC Fees                                                                                                  4.528            453    4,981      4,981 2b.4.7      Emergency Planning Fees                                                                                  18.944          1,894  20,838          -          20,838 2b.4.      ISFSI Operating Costs                                                                                      1,908            286  2.194                      2,194 57,312          8,597  65,909                    65.909                                                                                    1,265,451 2b.4.9      Security Staff Cost 2b.4.10    UtilityStaff Cost                                                                                        41,970          6,295  48,265                    48,265                                                                                      749,897 1,620        66        36                1.037  136.630        19,503  158.892      8,416        150,476                        22,311                                204.651        68  2,015,349 2b.4      Subtotal Period 2b Period-Oepenrdent Costs 1.620        66        36                1.037  153,023        22,244  178,026      12,354        165,672                        22.311                                204,651        68  2.015.349 2b.0        TOTAL PERIOD 2b COST 78        43                1,236  225,651        33,019  261.991      19,402        242,589                        26,578                                243,790        681  2.789.679 PERIOD 2 TOTALS                                                  1,964 PERIOD 3a - Reactivate Sits Following SAFSTOR Dormancy Period 3a Direct Decorrmmusioning  Actnifies 3a.1.1    Prepare prelminadry decommissioning cost                                                                    130            20    150          150                                                                                                        1.300 3a.1.2      Review plant dwgs & specs.                                                                                  460            69    529          529                                                                                                        4.600 3a.1.3      Perform detailed rod su*rey                                                                                                          a 100            15    11.          115                                                                                                        1,000 3a.1.4    End product description 130            20    150          150                                                                                                        1,300 3a. 1.5    Detailed by-product inventory 3a. 1.6    Defires major work sequence                                                                                  750            113    863        863                                                                                                        7,500 310            47    357          357                                                                                                        3,100 3a.1.7      Perform SER and EA 3a.1.8      Perform Sts-Speciflc Cost Study                                                                            500            75    575          575                                                                                                        5,000 3a. 1.9    Prepare/subrmit License Terninabotn Plan                                                                    410            61    471        471                                                                                                        4.096 3a. 1.10    Receliv NRC approval of termination plan                                                                                              a TLG Services, Inc.
 
DocumentN01.1590-002, Rev. 1 Cooper Nuvkar Station Appendix D, Page17 of 35 Dereoziiaaonig CostA-mlysis Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sita  LLRW                                    NRC      Spent Fuel    Sits      Processed          Burial Volumes          Burial I            Utilityand Activity                                            Decon Removal Packaging Transport  Processing Disposal Other        Total      Total Lic.Tenm. Management  Restoration  Volume  Class A Class B Class C GTCC Processed      Craft    Contractor Index                      Activity Description    Cost  Cost    Costs    Costs      Costs    CostsCosts                                          Costs      Costs      Cu. Fent Co.Fee Cu. Feet Cu. Feet Cu. Feet WI. Lbs. Manhours  Manhours ActivitySpecifications 737          111    848        763                                                                                                7,370 3a.1.11.1  Re-activate plant &temporary focilities 417          63    479      431                                                                                                4,167 3a.1.11.2  Plant systems                                                                                                                                                                                                                            7.100 710          107    817        917 3a.1.11.3  Reactor internals                                                                                                                                                                                                                        6.500 650          98    748        748 3a.1.11,4  Reactor vessel                                                                                                                                                                                                                              500 50          8      58        58 3a.1.11-5  Sacriflcial shield                                                                                                                                                                                                                        1,000 Moisture separators/rerheaters                                                                        100          15    115        115 3a.1.11.6                                                                                                                                                                  92 160          24    184        92                                                                                                11.600 3a.1.11.7  Reinforced concrete 209          31    240        240                                                                                                2,088 3a.1.11 .8  Main Turbine 209          31    240        240                                                                                                2,088 30.1.11.9  Main Condensers 200          30    230        230                                                                                                2,000 3a.1.11.10  Pressure suppression structure 160          24    184        184                                                                                                1,6w0 3a.1.11.11  Drysell 312          47    359        179                                                                                                3,120 3a.1.11.12  Plant structures &buildings 460          69    529        529                    "52                                                                        4,600 3a. 1.11.13 Waste management 90          14    104        52                                                                                                  900 3a.1.11.14  Faciity &site closeout                                                                                                                                        456 4.463          669  5,133      4,677                                                                                              44,633 3a.1.11    Total Planning & Sits Preparations 240          36    276        276                                                                                                2.400 30.1.12    Prepare dismantling sequence 3a.1.13    Plant prep. &temp. svoes                                                                            2,700          405  3,105      3,105 140          21    161        161                                                                                                1,400 3a.1.14    Design "ster clear.up system Rigging/Cont. Cotd Envlps/tooUngletc.                                                                2,100          315  2,415      2,415 3a.1.15                                                                                                                                                                                                                                              1.230 3a.1.16    Procure casistliners &containers                                                                        123          10    141        141 12,556        1,883  14,439    13,983                    456                                                                      77,559 30.1        Subtotal Period 3a ActivityCosts Period 3a  Period-Dependent Costs 420          42    462        462 30.4.1      Insurance 3a.4.2      Property taxes                                                                                            4            0      4          4 324                                                              81    405        405 3a.4.3      Hea*th physics supplies 3a.4.4      Heavy equipment rental                              368                                                              55    423        423 2                  62                    16      84        84                                      1.329                            12,190        4 3a.4.5      Disposal of DAWgenerated 027          130  1.066      1,096 3a.4.6      Plant energy budget 249          25    274        274 3a.4.7      NRC Fees 3a.4.8      Security Staff Cost                                                                                  2,855          428  3,283      3,203                                                                                              65,179 UtitilyStaff Cost                                                                            -      14,190        2.128  16,318    16,318                                                                                        -    258,629 3a.4.9                                                                                                                                                                                                                                      4      323,807 691                  2                  62    18.644        2,915  22,318    22.318                                      1.329                            12.190 3a.4        Subtotal Period 3a Perlod-Depenoent Costs 691                                      62    31.200        4,799  36,758    36,302                    456              1.329                            12,190        4      401,366 3a.0        TOTAL PERIOD 3a COST PERIOD 3b - Decommissioning Preparations Perod 3b Direct Decommissioning Activities Detailed Work Procedures 3b.1.1.1    Plant systems                                                                                          473          71    544        490                      54                                                                        4,733 400          60    460        460                                                                                                4,000 38.1.1.2 Reactor internals 135          20    155        39                    116                                                                        1,350 3b.1.1.3 Remaining buildings                                                                                                                                                                                                                          1,000 310.1.1.4 CRD housings &Nis                                                                                        100          15    115        115 100          15    110        115                                                                                                1.000 3b.1.1.5 Incore instrumentation 200          30    230        230                                                                                                2,000 3b.1.1.6 Removal primary containment 363          54    417        417                                                                                                3,630 3b.1.1.7 Reactor vessel 120          18    138        69                                                                                                1,200 3b.1.1.8 Facility closeout                                                                                                                                                  69 120          18    138        138                                                                                                1,200 3b, 1.1.9 sacrifcial Shield 100          15    115        58                    58                                                                        1,000 3b.1.1.10 Reionorced concrete 208          31    239        239                                                                                                2,080 3b'1.1.11 Main Turbine 209          31    240        240                                                                                                2.088 3b01 1.12 Main Condensers TLG Services, Inc.
 
Cooper Nuclear Sftaton                                                                                                                                                                                                                            DocumentN01-1590-002, Rev. I Decn reiasioning Cost Analoysis                                                                                                                                                                                                                        Appendix D, Page18 of 35 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars) off-Site      LLRW                                        NRC        Spent Fuel    site      Processed            Burial Volumes              Burial I              Utility and Decon  Removal  Packaging  Transport  Processing    Disposal    Other      Total        Total Lie. Term. Management  Restoration  Volume    Clans A  Class B  Clase C  GTCC    Processed    Craft    Contractor I Actity.
m  InlAY                    ACHV* *CN*                Cost    Cost      Costs      Costs      Costs        Costs      Costs  Continnosno    Costs    Costs        Costs      Costs      Cu. Feet  Cu. Feet Cu. Fast Cu. Feet  Cu. Feet  Wt. Lbs. Manhours    MachoursI n ex                        v      c Detailed Work Procedures (continued) 3b*1.1.13 Moisture separalors & reheaters                                                                                    200          30    230          230                                                                                                          2,000 3b1.1.14 Radwastebuilding                                                                                                    273          41    314          283                        31                                                                                2,730 3b 1.1.15 Reactor building                                                                                                  273          41    314          283                        31                                                                                2,730 3.274          491  3,765        3,405                      360                                                                                32.741 3b.1.1    Total 3b,1      Subtotal Period 3b Actvity Costs                                                                                3,274          491  3,765        3,405                      360                                                                                32,741 Period 3b Addtl~onal Costs 3b.2.1    Site Charactetization                                                                                          5,395        1,619  7.014        7,014 3b.2      Subtotal Period 3b Additional Costs                                                                            5.395        1,619  7.014        7,014 Period 3b Collateral Costs 3b.3.1    Decon equipment                              713                                                                  -            107    820          820 3b.3.2    DOC staff relocation expenses                                                                                    912          137  1,049        1.049 3b.3.3    Pipe cutting equipment                      -      1,000                                                        -            150  1,150        1.150 3b.3      Subtotal Period 3b Collateral Costs          713    1.000                                                        912          394  3,019        3.019 Period 3k Period-Dependent Costs 3b.4.1    Decon supplies                                22                                                                                5    27            27 3b.4.2    Insurance                                                                                                        246          25    270          270 3.4.3      Property taxes                                                                                                      2            0      2            2 3b.4,4    Health physics supplies                                179                                                                      45    224          224 3b.4.5    Heavy equipment rental                                184                                                                      28    212          212 3b.4.6    Disposal of DAWgenerated                                                                                35                      9    48            48                                          754                                  6,913          2 3b.4.7    Rant energy budget                                                                                                465          70    534          034 3b.4,8    NRC Fees                                                                                                          125            12    137          137 31.4.9    Security Staff Cost                                                                                            1,431          215  1,646        1,646                                                                                                        32,679 3b.4.10    DOC Staff Cost                                                                                                  4,370          657  5,035        5,035                                                                                                        58,560 3b.4.11    UWllyStaff Cost                                                                                        -        7.114        1,067  8,181        8,151                                                                                              -      129,669 3b.4      Subtotal Period 3b Period-Dependent Costs      22      363                                              35    13,761        2,133  16,317      16,317                                          754                                  6,913          2    220,907 31.0      TOTAL PERIOD 3b COST                        735    1,303                                              35    23,342        4,636  30,115      29,755                      360                  754                                  6.913          2    253,648 2
PERIOD 3 TOTALS                                        735    2,055            6                                  97    54,542        9,435  668,72      66,056                      816                2,083                                  19,104          6    655,014 PERIOD 4a - Large Component Removal Period 4a Direct Decommissioning Actvimies Nuclear Steam Supply System Removal 4a.1.1.1  Recirculation System Piping & Vatnes          16        70          14        14            25      272                      101    512          512                                  100      897                                119,606    2.487            -
4a.1.1.2  Recirculation Pumps &Motors                    6        28          11        28                    321                      95    488          488                                  -    1,188                                132,880    1,125 4a.1.1.3 CROMs &Nis Removal                              24      139        377        68                    317        -            174  1,099        1,099                                        6.935      -        -                126,494    3,972 4a.1.1.4 Reactor Vessel Internals                        86    1,959      3,871        912                  5.607        155        5,535  18,124      18.124                                        1,878    1,252      470      -      359,044    18,900            888 4a. 1.1.5 Vessel & Internals GTCC Disposal                                                                    7,470                    1,120  8.590        8.590                                            -        -                508      89,497 4a.'1.1.6 Reactor Vessel                                        5,054        906        351          -      4,408        155        6.332  17,205      17,205                                        11,247    2,859      -        -    1,447,089    18,900            888 4a. 1.1    Totals                                      132    7.250      5,179      1,371            25  18,395        309      13.357  46,018      46,018                                  100  22,145    4,111      470      508  2.274,610    45.384          1.776 Removal of Major Equipment 4a 1.2    Main TurbinelGenerator                                167        845        372        6,376                              1,138  8,898        8,898                              61,604                                        2,772,179    4,438 4a 1.3    Main Condensers                                        706        588        259        4,439                                940  6,932        6,932                              42,889                                        1,930,000    19.519 Cascading  Costs from Clean Building Demolation 4a.1.4.1  Reactor                                                260          -                                                          39    299          299                                                                                          2,486 4a.1.4.2  Augmented Radwaste                                      25                                                                      4      28          26                                                                                            235 4a.1.4.3  Radwaste                                                43                                                                      7      50          50                                                                                            359 TLG Ser-ices, Ins.
 
Cooper Nuclear Station                                                                                                                                                                                                                                          DocumentNO-1590-002, Rev. I Appendix D, Page 19 of 35 Deeommissiaaoning Cosd Analvais Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars) off-Site      LLRW                                      NRC        Spent Fuel    Site      Processed              Burial Volumes              Burial I            Utility and l Decon  Removal  Packaging  Transport  Processing    Disposal    Other      Total        Total Lc. Tens. Management  Restoration    Volume    Class A  class B    Class C  GTCC    Processed    Craft    Contractor Actlnfty                                                    Cost    Cost      Costs      Costs      Costs        Costs    Costs    Contlnoency    Costs  Costs          Costs      Costs        Cu. Feet  Cu. Feet  Cu. Feet Cu. Feet  Cu. Feet  W". Lbs. Manhours  Mantrours I n ex                                  ri In ActiVVl Cascading Costs    from Clean BudildingDemolition (continued) 4a.1.4.4 Turbine                                                          285                                                                      43      328        328                                                                                                4,419 613                                                                      92      705        705                                                                                                7,498 40.1.4      Totals Disposal of Plant Systems 4a.1.5.1    Augmented Radwasts E 877      ArealA                          203          28        28                      432                    166      857        857                                            2,055                                  172.205      5,668 66                                                                      44      228        228                                              469                                    41,606      1,842 4a.1.5.2    Augmented Radwasta El 903    ArealA                                        6          7                      104 52        10          9                      139                      50      260        260                                              765                                    55,345      1,432 4a.1.5.3 Augmented Rrdwasts El 918        ArealA 21          4          5          -          73                      25      127        127                                    -        324                                    28,038        579 4a.1.5.4 Augmented Radmasta El 929        ArealA 3          0          0              4                                  1      8            8                                    38                                              1,529        75 4a.1.5.5 Augmented Radwaste El 929        Aeal B 457                                            1,289                    458    2,373      2,373                                            5.726                                  513,627    12,634 40.1.5.6 DRYWELLArealA                                                                  85        84 112          1          5            75          2                    41      235        235                                    806        10                                  33,576      3,304 4a.1.5.7    DRYWELLArealS 324          16        8s        1.477                                317    2,220      2,220                        -        15.808                                            641,963      9,170 4a.1.5.8    Turbine El 932 Areal B 1      9                                                                                                  *-        237 4a.1.5.9 Turbine El 932 Area2C                                                                                                                                                                      78 10      78                          *78                -                    *        -                    -      2,083 4a.1.5.10 Turbine El 932 Area3C                                              67 518          50        264        4,517                                852    6,201      6,201                                48.365      -                                  1,964,114    14,340 4a1.5.11 Yard ArealB 4a.1.5      Totals                                                      1,831        202        487        6,073      2,040                  1.964  12,597    12,510                        87      65,016    9,348                                3.453,003    51.444 4a.1.6      Scaffoldng in support of decommissioning              -      2,049          24          11          168          23                    547    2,921      2,121                                  1,821      101                                    81,992    27,411 Subtotal Period 4a ActivityCosts                    132    12,616      6,838      2,500        17,081      20.457      309        18,039  77,972    77,885                          87    171,229    31,594    4,111        470      508  10,511,780    155,694        1,776 4a.1 Period 4a Collateral Costs 69      -            24        125                      143                      91      451        451                        -                    498        -                          29,865        97 4a.3.1      Process liquid waste 4a.3.2      Smail tool allowance                                            90                                                                      14      104          94                        10
* 24        125                        143                    105      555        545                          10                  498                                    29,865        97 40.3        Subtotal Period 4a Collateral Costs                    69        90 Period 4a Period-Dependent Costs 4a.4.1    Decon supplies                                        49                                                                                12      61          61 4a.4.2      Insurance                                                                                                                549            55      604        604 4a.4.3      Property taes                                                                                                              4              0      5            4                        0 4a.4.4      Health physics supplies                                        944                                                                      236    1.180      1,180 4a.4.5      Heavy equipment rental                                      1,981                                                                      297    2.278      2,278 26          14                      405                    106      551        551                                            8,708                                    79,878        27 4a.4.6      Disposal of DAW generated                                                                                -
4a.4.7      Flant energy budget                                                                                                      587          148    1,135      1,135 4a.4.8    NRC Fees                                                                                                                  737            74      811        811 4a.4.9      Liquid Radwaste Processing EquipmenteSurvices                                                                            420            63      483        483                                                                                                            73,036 4a.4.10    Security Staff Cost                                                                                                    3,199          480    3.679      3,679 11,638        1,746  13.384    13,384                                                                                                          181,263 4a.4.11    DOC Staff Cost 16,014        2,402  18.416    18,416                                                                                                          292,143 4a.4.12    UtilityStaff Cost 4a.4      Subtotal Period 4a Penod-Dependent Costs              49    2,925          26          14                      405    33.548        5,619  42,586    42,585                            0                8.708        -                          79,878        27    526,441 40.0      TOTALPERIOD 4a COST                                  250    15,631      6,887      2,640        17,081      21,005    33,858        23,762  121,113    121,016                          98    171,229    40,800    4.111        470      508  10,621.530    155,818    528,217 PERIOD 4b -Site Decontamination Peded 4b Direct Decommissioning Activities 79          88                    1,348                    498    2,308      2,308                                            5,986                                  537,141      1,004          -
4b.1.1    Remove spent fuel racks                              262        33 Disposal of Plant Systems 4b.1.2.1    Control El 882ArealB                                          280                                                                      178    1,178      1,178                        -        7.213                                            292,908      7.797 7        39          674                                                                                                                                                        5.155 4b.1.2.2 Control El03ArealC                                              170                                                                      25      195                                  195          -
4b.1.2.3 Control El 818ArnealC                                              66                                                                      10      76                                    76                                                                  -  2,100 22                                                                        3      28                                    26                                                                      702 4b.1.2.4 Control El 932 Areal C 4b.1.2.5 Intake                                                          101                                                                        15    116        -                        116                                                              -      3,136 7        2,558                                            103,862      5,430 4b.1.2.6 Mua-Purpose Faciity                                              198            3        14          239                                  88      541        541 62          -          949                    353    1.836      1,838                        -
* 5,097                                  377,917    10.930 4b.1.2.7 Radwaste El 877 AvealA                                          398          75 TLG Service., Inc.
 
Cooper Nuclearo Station.                                                                                                                                                                                                          Doaeamon,NOI.1590-002. Rev. I Decomissaionig CoastAnalysis                                                                                                                                                                                                            Appenadix D, Page 20 of 35 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sita    LLRW                                    NRC      Spent Fuel    Site    Processed            BurialVolumes            BurialI              Utilityand Activity                                    Cecon Removal  Packaging  Transport  Processing  Disposal  Other      Total      Total Lie.Tenn. Management , Restoration  Volume    Class A Class B Class C  GTCC    Processed    Craft    Contractor lides                  Actviy Description Cost  Cost      Costs      Costs      Costs      Costs    Costs  Contlo encv  Costs  Costs        Costs      Costs      Cu. Feet-  Cu. Fee Cu. Feet Cu. Feet Cu.Feet  WI. Lbs. Manhours  Manhours Disposal of Plant Systems (continued) 4b.1.2.8 Radwaste El 877 Area2A                          43          9          7                    113                    41    213        213                                          613                              44.992      1,189 18          13                    201                    72    372        372                                        1,156                              79.983      1,969 4b.1.2.9 Radwaste El 877 A.ea3A                          71 110            9          10                    153                    68    351        351                                          684                              61.153      3,015 4b.1.2.10 Radaste El 903 AealA                                                                                                                                                                                                  175,093      5,282 188          36        29                    439                    165    856        856                                        1,955 4b.1.2.11 Radwaste El 903 Area2A                                                                                                                                                                                                41,366      1.029 37          6          7                    104                    37    190        190                                          463 40b1.2.12 Radwast El 903 Area3A                                                                                                                                                                                                  12,033        477 18          2          2                    30                    12      64        64                                          135 4b.1.2.13 Radwaste E 918 AnnalA                                                                                                                                                                                                  15,667        448 16          3          3                    39                    15      75        75                                          201 4b.1.2.14 Radwaste El 918 Area2A                                                                                                                                                                                                134,827      5,045 185          23        22                    338                    138    705        705                                        1,690 4b.1.2.15 Radwaste a] 918 Area3A                                                                                                                                                                                                              680 26          3          4                    60                    22    115        115                                          266                              23,735 4b.1.2.16 Radwaste El 934 ArealA 98          11          12                    177                    72    370        370                                          8O8                              70,665      Z663 4b.12.17 Radwaste El 934 Area2A                                                                                                                                                                                                                305 12          I          2                    24                      9      47        47                                          105                                9,381 4b.1.2.18 Radwaste, E 949 ArealA 50          7          8                    121                    45    230        230                                          537                              48,175      1,261 40.1.2.19 Reactor El 1001 ArealA 4            64                              26    157        157                                689                                        27.979      1,681 40t.1.2.20 Reactor E 1001 ArealB                        62          1 15          16                    248                    83    430        430                                -      1,091                              97,874      2,024 4b.1.2.21 Reactor E[8595AealA                            71 440          11          58        994        -                      269  1,771      1,771                              10,641        -                              432,136    12,411 4b.1.2.22 Reactorl  [ 859 ArealB 25        26                    401                    125    648        648                                -      1,780                              159,714      2,094 4b.1.2.23 Reactor El 859 Area2A                          72 1          8        131        -                      38    247        247                              1.406      -                                57,093      1,954 4b.1.2.24 Reactor [] 859 Area2B                          69 9          -        137                    48    251        251                                  S        9608                              54,543      1,321 41b.1.2.25 Reactor El 859 Area3A                        47          9 33          0          2            42      -                      15      93        93                                453                                        18,381        951 4b.1.2.26 Reactor El 859 Area3B 50          g          8                    117                    44    227        227                                  -        520                              46,666      1,374 4b.12.27 Reactor Cl859 Area4A                                                                                                                                                                                                    13,424        476 17          0          2            31                -              9      59        59                                331        -
4b.1.2.28 Reactor C 859 Area4B                                                                                                                                                                                                              1,798 16          17                    262                    85    443        443
* 1,163                              104,381 4b.1.2.29 Reactor El 859 AreaSA                          63 37          0          2            41                              16      98        98                                442              -                        17.982      1,087 4b.1.2.30 Reactor C 859 AreaB5                                                                                                                                                                                                  259.190    10.497 401          56          42                    651                    275  1,424      1.424                                -      2,892 4b.1.2.31 Reactor Ej903 ArealA                                                                                                                                                                                                  239.197    12,496 451            6          32        550                              201  1,240      1,240                              0.890        -
4b.1.2.32 Reactor"[ 903ArealB 4          0          0          -            6                      3    14        14                                            26                              2,372        120 4b.1.2.33 Reactor El 903Area2A                                                                                                                                                                                                              1,915 69          2          11        190                                48    320        320                              2,039        -                                82,815 4b.1.2.34 Reactor El 903 Area2B                                                                                                                                                                                                  68,516        929 32        10          11          -        167                    52    272        272                                          741 40.1,2,35 Reactor El 903 Area3A S21          1          3            52                              14      90        90                                553                                        22,464        618 4b.1.2.36 Reactor El 903 Area3B 27          8          9                    136                    43    223        223                                          606                              54,373        776 4b.1.2.37 Reactor El 903 Area4A                                                                                                                                                                                                                597 21            t          3            52      -        -              14    90        90                                559        -                                22,692 4b0.1.2.38 Reactor E 903 Area4B                                                                                                                                                                                                                670 3          3            2      52                    20    104        104                                          232                              20,858 40.1 2.39 Reactor E]031 ArealA                          25 8        40          692                              186  1,227      1,227                              7,412      .                                301,017      8,410 4b.12.40 Reactor El 931 Areal B                        300 2          2          -          35                    14      74        74                                -        154                              13,824        544 40.1.2.41 Reactor C 931 Area2A                          20 0          0            1        0                      1      3          3                                    9        0                                371          53 4b.1.2.42 Reactor El 931 Area2B                            2 77          23          22                    338                    109    567        567                                        1,651                              134,007      2,165 40.1.2.43 Reactor CJ931 Area3A                                                                                                                                                                                                                  49 0          0                                              1      3          3                                    8                                          340 4b.1.2.44 Reactor El 931 Area3B                            2 4      28                                                                                                      767
      ,40.1.2.45 Reactor CJ931 Area4C                          24 1      8                                                                                            -        213 4b.1.2.46 Reactor El 931 Area5C                            7 9          10                    149                    54    278        278                                          662                              589,432    1,472 4b0.1.2.47 Reactor El 958ArealA                          56 167            3          18        281        -                      87    554        554                              3,009                                        122,212      4,693 4b.1.2.48 Reactor El 958 Areal B                                                                                                                                                                                                              880 31          10          10
* 153                    49    253        253                                  -        681                              61.083 4b.1.2.49 Reactor EC958 Area2A 10          1          1            12        7                    6      37        37                                125        33                              8,024        263 40.1.2.50 Reactor C 958 Area2B                                                                                                                                                                                                                898 4          3                    48                    21    109        109                                -        214                              19.185 4b.1.2.51 Reactor El 958 Area3A                          33 14                                  10        6                      7    39        39                                109        29                              7,011        410 4b.1-2.52 Reactor C 958 Area3B                                        1          1 11          1          1                      16                      7    36        36                                            72                              6,482        298 4b.1.2.53 Reactor C 976 ArealA 147            5          25        422                              104    703        703                              4,521                                        183,615      3.931 4b.1.2.54 Reactor El 976 ArealB 7          1          1                      13                      5    26        29                                            57                              5,138        172 40.1.2.55 Reactor EJ976 Area2A                                                                                                                                                                                                  23,813      1,033 37          1          3            55                              18    114        114                                586 4b.1.2.56 Reactor Cl976 Area2B 37          3          3          -          50                    23    116        116                                          222                              19,878      1,004 4b.1,2.57 Turbine El 882 ArealA 386          16          87        1,490                              335  2,313      2,313                              15,948                                        647,659    11,113 40.1.2.58 Turbine El 882 ArealB                                                                                                                                                                                                                584 21          2          2                    29                    13      67        67                                  -        129                              11,556 4b.1.2.59 Turtbie El 882 Area2A 209            4        22          374                              112    721        721                              4,006                                        162,678      5,781
: 40. 1.2.60 Turbine C 882 Area2B 16          2          1                    23                    10      52        52                                          101                                9,017        451 4b.1.2.61 Turbine C]882 Area3A 27        145        2,478                              548  3,805      3,805                              26,533      -                              1,077.531    17,302 4b.1.2.62 Turbine El 882 Area38                        607 9          1          1          -          15                    6      32        32                                            68                              6,127        232 4b.1,2.63 Turbine EC903 ArealA TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                                                                                                    Document NOI-1590-002, Rev. I Decommissioning Cost Analysis                                                                                                                                                                                                                                  Appendix D, Page 21 of 35 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                        NRC        Spent Fuel      Site      Processed            Burial Volumes              BuriulI              Utilityand Activity                                                Decon    Removal    Packaging    Transport  Processing  Disposal    Other      Total        Total LIc.Term. Management      Restoration  Volume    Class A Class B Class C GTCC        Processed    Craft    Contractor Index                    Activtv Descrlptlon          Cost      Cost        Costs      Costs      Costs      Costst      s sts    Cootlnles        CCosts                          Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Wt. Lbs. Manhours  Manhours Disposal of Plant Systems (continued) 4b. 12.64 Turbine E4 03 AreaIS                                          974          46        241        4,133        -                        904    6,299      6,299                                44,251                                      1,797,054    27,674 4b, 1.2.65 Turbine El 903 Area2A                                            5            1        1                        6                      4      20          20                                            42                                3.729      142 4b.1.2.66 Turbine El 903 Area2B                                          144              1        7          128                                  56      337        337                                  1,375                                          55,851    4.040 4b.1.2.67 Turbine El 903 Area3B                                              3          0          2            35                                  6      47          47                      -          376                                          15,251        97 4b.1.2.68 Turbine El 903 Area3C                                          108                                                                        16    124        -                        124        -                                              -      3,412 4b.1.2.69 Turbine FA903 Aes4B                                              12          0          2            28                                  7      49          49                      -          299                                          12,139      367 30      227        -                        227        -                                                      5,770 4b.1.2.70 Yard AealC                                                    197 4b.1.2      Totals                                                -    7.771          556      1.148      13.202    5,814                    5,535  34,027      33,227                        800    141.342  27,486                              8,056,388  218,627 4b.1.3      Scaffolding in support of deconmnissioning                3,073          36          17          252          34                    821    4,232      4,232                        -        2,431      151                                122,988    41,117 Decontamination of Site Buildings 4b.1.4.1    Reactor                                        2,880      1.820          202        422        4,911    2,376                    3,310  15.922    15,922                                52,579  39,536                              6,069,283  115,053 45.1.42 Augmented Radwaste                                    52          19          4          6            23        60                      51      215        215                                    242    1,099                                119,326    1,978 4b.1.4.3 Miscelaneous Sruturms - Contaminated                368        167          15          42          759          62                    363    1,777      1,777                                  8,129      452                                372.774    12,956 4b,1 .4.4 MulU-Purp*se Facility                              68          55          6        12          115        89                      90      437        437                                  1,234    1,567                                205,068    3,237 4b51.4.5 Radwaste                                            159          50            9        14            38      161                      141      572        572                                    404    2,953                                310,769    5,863 4b51.4.6 Turbine                                            526        142          35          51            64      633                      477    1,928      1.628                                    688  11,664                              1,193,496    18,679 4b5.1A      Totals                                          4,055      2,253          271        547        5,910    3.362                    4,432  20,850      20,850                                63.275  57,271                              8,270.774  157,769 4b.t      Subtotal Period 40 Actvity Costs                4,318    13.131          942    , 1,800      19,364    10,578                    11,285  61,417      60,618                        800    207,048  90,895                            16,987,290  419,513 Period 4b Additional Costs 4b.2.1      ISFSI Decontamination                                    1,012              6        24                      60    1,250          460    2,811        -          2,811                            1,175                                165,113    26,509        2,560 4b.2.2      Final Ste Survey                                                                                                      1,205          362    1,567      1,567                                                                                                      12,460 4b.2        Subtotal Period 40 Additional Costs                      1,012              6        24                      60    2,455          821    4,378      1,567          2.811                            1,175                              165,113    26.509      15,040 Period 4b Coilateral Costs 4b.3.1      Process liquid vaste                            143        -            49        262                    299                      190      944        944                                            1,042                                62,521        203 4b.3.2      Small tooi allowance                                        235                                                                        35    270        270 4b.3.3      Decommissioning Equipment Disposition                                    -6          50          621          84                    130      973        973                                  6,000      373                                303,507        68 45.3        Subtotal Period 45 Colluteral Costs              143        235          137        312          621        363                      356    2,187      2,187                                  6,000    1,415                              368,028        291 Period 4b Period-Dependert Costs 4b.4.1      Deconsupplies                                  1,252                                                                                  313    1,564      1,564 4b.4.2      Insurance                                                                                                              1,192          119    1,312      1,312 45.4.3      Property tanes                                                                                                            10            1      11          11 4b.4.4      Health physics supplies                                  2,404                                                                      601    3,005      3,005 4b.4.5      Heavy equipment rental                                    4,270                                                                      641    4,911      4,911 4b.4.6      Disposal of DAW generated                                                  55        31                    876                      229    1,191      1,191                                          18,832                                172,741        58 4b.4.7      Plant energy budget                                                                                                  1,691          254    1,945      1,945 4b.4.8      NRC Fees                                                                                                              1,601          160    1,761      1,761 4b.4.9      LiquidRadwaste Processing Equipment/Servioes                                                                            913          137    1,049      1,049 4b.4.10    Security Staff Cost                                                                                                  6,945        1,042    7,987      7.987                                                                                                      158,571 4b.4.1I    DOC StaflCost                                                                                                        24,622        3,693  28,315    28,315                                                                                                      339,977 45.4.12    Utiity Staff Cost                                                                                                    33,00          4,962  38,042    38,042                                                                                                      598,766 4b.4        Subtotal Period 4b Pedod-Dependent Costs      1,252      6.674            55        31                    876    70,053        12,151  91,092    91,092                                          18,832                                172,741        58  1,097,314 4b.0        TOTALPERIOD 4        COST                      5,712    21,052        1,140      2,168      19,985    11.897      72,508        24,614  159,074    155,463          2,811          800    213,048  112.318                            17,691,170  445,371  1,112.354 PERIOD 4a - License Termination PeFod 4e  Direct Decommissioning Actvities
: 45. t.1    ORISE confirmatory survey                                                                                              147            44      191        191 4e,1.2    Terminate license 48.1        Subtotal Period 4e ActivityCosts                                                                                        147            44      191        191 TLG Services, Inc.
 
Cooper Nuclear Stations                                                                                                                                                                                                                                Document N01-1590-002, Rev. I Derooomia.ionaing Coast    Anaolysi                                                                                                                                                                                                                        Appendix D, Page 22 of 35 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars) 1o1.S110LLRW                                              NRC      Spo.lFuel      Site      Processed            50.i1,Volms                Burial I              Uility    *sd Activity                                            DOcon    Removal  Packaging  Transport    Processing Disposal    Other        Total          Total  Lin. Trom. Management  Restoration  Volume    Class A  Class B  Class C  GTCC    Processed    Craft      Contractor Index                    Activity Description      Cost      Cast      Costs    Costs        Costs    Costs      Costs    Continaencs      Costs    Costs        Costs        Casts      Cu. Feet  Cu. Feet Cu. Feet Cu. Fast Cu. Fest  Wt Lbs. Manhours    Manhouos Perod 4a Additonal Costs 4e.2.1      Final Sits Survey                                                                                              5.99S          1.799    7,797        7,797                                                                                        148,435        6,240 5.998          1,799    7,797        7,797                                                                                        148.435        6,240 4e.2        Subtotal Period 4e Additienal Costa Peiod 4e Collateral Costs 4e.3.1      DOC staff relocation expenses                                                                                    912            137    1.049        1.049 48.3        Subtotal Period 4e Collateral Costs                                                                              912            137    1,049        1.049 Poed 4e  Period-Dependent Costs 4e.4.1      Insurance 4e.4.2      Property tales                                                                                                      3              0        3            3 4e.4.3      Healthphysics supplies                                  736                                                                    184      920          920 4e.4.4      Disposalof DAWgenerated                                                            1                    42        -                11        57          57                                          907                                  8,324            3 4e.4.5      Plant energy budget                                                                                              140              21      161          161 4e.4.6      NRC Fees                                                                                                        532              53      585          585 4e.4.7      Security Staff Cost                                                                                            1,012            152    1,164        1,164                                                                                                        18,857 4e.4.8    DOC Staff Cost                                                                                                4,458            669    5.126        5,126                                                                                                        57,357 4e.4.9      UtilityStaff Cost                                                              -                      -      4,695            704    5,399        5,399                                            -                                          -
* 74,643 4e.4      Subtotal Period 4e Petiod-Dependent Costs                736          3          1                    42    10,839          1,794    13,418      13,416                                            907                                  8,324            3    150,857 4e.0      TOTALPERIOD 4e COST                                      736          3          1                    42    17,897          3,774    22,453      22,453                                            907                                  8,324  148.438      157,097 PERIOD 4 TOTALS                                        5,962    37.419      8.030    4,807        37,066  32.944    124,262          52,151  302,640    298,932        2,811          897    384,277  154.025    4.111      470      508  28,321.020  749,627    1,797.609 PERIOD Sb - Site Restaraton Period 5b Direct Decommissioning Activites Demolition of Remaining Site Buildings 5b.1.1.1  Reactor                                                1,491                                                                    224    1,715                                  1.715                                                                14.601 55.1.1.2  Augmented Radwasta                                      222                                                                      33      255                                    255                                                                2,119 5b.1,1.3 Control                                                    214                                                                      32      246                                    246                                                                1,655 523                                                                      78      602                                    6D2                                                                5,621 5b.1..4 Intake Structue 5b.1.1.5 LLRWStorage Pad                                            145                                                                      22      167                                  167                                                                1,227 5b.1.1.6 Miscellaneous Structures- Clen
* 1,199                                                                      179    1,375                                  1,375                                                                11,837 5b.1.1.7 Misceltaneous Structues - Contaminated                      27                                                                      4        30                                    30                                                                    572 5b.1.1.8 Mutb-Puroses Facility                                      123                                                                      18      141                                  141                                                                1,982 5b.1.1.9 OWC Gas Generator                                            18                                                                      3        20                                    20                                                                    283 5b,1.1.10 Office                                                    156                                                                      23      179                                  179                                                                1.920 5b.1,1.11 Radwaste                                                  391                                                                      59      449                                    449                                                                3.229 5b51.1.12 Seal Well                                                  "17                                                                      3        20                                    20                                                                    166 5b.1.1.1 3 Sewage Treatment Area                                      4                                                                        1        5                                      5                                                                      53 5b.1.1.14 Transformer Yard                                            20                                                                        3      24                                    24                                                                    172 5b.51.115 Turbine                                                2,596                                                                    389    2,985                                  2,985                                                                40,503 5.1.1.16 Tubine Pedestal                                            277                                                                      42      318                                  318                                                                2,100 55.1.1    Totals                                                7,418                                                                    1,113    8.531                                  8,531                                                                86,040 Site Closeout Activties 424                                                                      64      488                                  488                                                                3,286 5b.1.2    Reovne Rubble 5b. 1.3    Grade & landscape site                                    578                                                                      87      665          -                        665                                                                  1,578
: 55. 1.4    Final report to NRC                                                                                              156              23      179          179                                                                                              -          1.560 5,421                    *-            -        -          158          1,286    9.863          179                    9.684                                                                92,904          1,560 5b.1      Subtotal Period 5b Acivity Costs Period SbAdditional Costs 5b.2.1    ISFSI Demolition                                        672                                                        44            107      824                      824                                                                            5,898            160 499                                                                      76      582                      -          582                                                                3,045 5b.2.2    Concrete Crushing 5b.2.3    Cofferdam                                                458                                                                      69      527                                  527                                                                5,130 TLG Services, Inc.
 
CaaperA'odriw slolat-                                                                                                                                                                                                                                                Documsent NO -1,590-002, Rev. I Deeomaisioneing CoadAnealysis                                                                                                                                                                                                                                            Appensdix D, Page 23 of 55 Table D-2 Cooper Nuclear Station 2034 Delayed DECON Decommissioning Cost Estimate (thousands of 2008 dollars) m Decon  Removal  Packaging  Transport    aot-Ste Processing    i Li.W Disposal    Other*    Total        Total Ic.JcTrm.
Teom. MSpent guem Management        siou Restoration    Vrole Volume  Ca A Class  A      urClas Class  B Volumes Class CC    C GTCC      uril I Processed    Craft    UCilt anat CoratI IAdtivity I    In*=v                      Artiw*  *r*nt*n ACtIVITY Until  tion                Cost    Cast      cost.      Costs      Costs      Costs      Costs  Contingency    Costs    Costs      costs          Costs    CuFeet  Cu Feet    Cu Fast    Cu Feet  Cu Feet  WL Lbs    Manhoum 5b.2        Subtotal Period 5b Additional Costs                                1,629                                                    52          252    1.933                      824        1.109-                    .                                            14,073          160 Period 5b Collatertl Costs 5b.3.1      Smal tool allowance                                                    56                                                                    8      64                            -        64 5b.3        Subtotal Period 5b Colateral Costs                                    56                                                                    8      64                            -        64        -
Penod 5b Period-Dependent Costs 5b.4.1      Insurance 5b.4.2      Property tawas                                                                                                                  7            1        8                                      8 5b.4.3      Heavy equipment rental                                              4.233                                                                  635-  4.869                          -      4,869                            -          .      -
5b.4.4      Plant energy budget                                                                                                          167            25      192
* 192        -        .          .          -
5b.4.5      Security Staff Cost                                                                                                        2,419          363    2,782
* 2,7a2        .      -          .                  -                              45,051 Sb4.6      DOC Staff Cost                                                                                                            10,212        1.532  11,744
* 11,744        -                    .          -      -                            127,646 5b.4.7      Utlity Staff Cost                                                                                                          4,507          676    5,183                          -      5,183.                                                                              73,209 5b.4        Subtotal Period 5b Pedod-Dependent Costs                            4,233                                                17.312        3.232  24,777                                24.777-                          -          -      -                            245,906 5b.O        TOTAL PERIOD 5b COST                                              14,339                                                17,520        4,779  36,638        179          824        235,634      -                    -          -                        106.977    247.626 PERIOD 6 TOTALS                                                                14,339                                                17,520        4,779  36,638        179          824        35,634                                                                  106,977    247.626 TOTAL COST TO DECOMMISSION                                          13,133  58,595      8,276    5,720        37,066    35,914  495,597      114.112  768,414    476,185      254.881        37,348  384.277  199,891      4,111        470      508  28,942,100  987,724  6,395.380 TOTALCOST TO DECOMMISSION WITH17.44% CONTINGENCY:                                                $768,414 thousands of 2008 dollars TOTALNRC LICENSE TERMINATIONCOST IS 61.97% OR:                                                  $476,185 thousands of 2008 do6am SPENT FUEL MANAGEMENTCOST IS 33.17% OR:                                                          $264,881  thousands of 2008 dollars NON-NUCLEARDEMOLITIONCOST IS 4.86% OR:                                                            $37,348 thousands of 2008 dolam TOTALLOW-LEVELRADIOACTIVEWASTE VOLUME BURIED (EXCLUDING GTCC):                                    204,472 cubic feet TOTALGREATER THAN CLASS C RADWASTE VOLUMEGENERATED:                                                    W08 cubic eset TOTALSCRAP METALREMOVED:                                                                            30.276 tons TOTALCRAFT LABOR REQUIREMENTS:                                                                    987,724 man-hours End Notes:
n/a - indicates that this actvity not charged as decommissioning expense.
a - indicates that this activity performed by decommissioning staff.
0 - indicates that this vatue is less than 0.5 but is ion-zeso.
a cell containing" - "indicates a zer value TLG Services, Inc.
 
CooperNuclear Station                                                                                                                                                                                                                    Docueanet NOI.1590.OOZ,  Rev. I De-om.issioning Cost Analysia                                                                                                                                                                                                                AppendixD, Page 24 of 35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
SOff-Site  LLRW                                      NRC        Spent Fuel      Site    Processed            BurialVolumes            BurialI              Utilityand Activity                                          Decon Removal  Packaging    Transport Processing Disposal  Other      Total      Total  LIO.Term,    Management    Restoration  Volume  Clasw A  Clans B  Class C GTCC    P      acessed Croft  Contractor Index                    ActivityDescription    Cost    Cost    Costs      Costs      Costs    Costs    Costs    Contanheac'  Costs    Costs        Costa        Costs      Cu. Feet          C.Ft Cu.'Feet C.        .Feet      Lbs. ManWouL    Manhours PERIOD la - Shutdown through Transition Period 1a Direct Decommissioning Activities 1a.1.1      SAFSTOR site characterizotion survey                                                                    346            104    450        450 130            20    150        150                                                                                                        1,300 1a.1.2      Prepare preliminary decommissioning cost la.1.3      Ncotificationof Cessation of Operations                                                                                          a tria
      .a.1.4    Remove fuel &source material la.1.5      Notifcation of Permanent Defueling 1.-1.6      Deactivate plant systems & process waste 200            30    230        230                                                                                                          2,000 18.1.7      Prepare and subirt PSDAR 130            20    150        150                                                                                                        1,300 Ia.1.,8    Re.ie plant dgs & specs.
10.1.9      Performrdetailed lad survey 100            15    115        115                                                                                                        1.000 1a.1.10    Estimate by-product inventory 1a.1,11    End product description                                                                                100            15    115        115                                                                                                        1.000 150            23    173        173                                                                                                        1,500 10.1.12    Detailed by-product inventory 100            15    115        115                                                                                                        1,000 10.1.13    Defre major work sectuence 10.1.14    Perform SER and EA                                                                                      310            47    357        357                                                                                                          3,100 10.1.15    Perform Smie-SpecificCost Study                                                                        500            75    575        575                                                                                                          5,000 Activity Specrfications 492            74    566        566                                                                                                          4,920 1:.1.16.1 Prepare piant and tacilies for SAFSTOR 417            63    479        479                                                                                                          4,167 1a.1.18.2 Plant systems 312            47    359        359                                                                                                          3.120 la.1.16.3 Plant structures and buildngs 200            30    230        230                                                                                                          2,000 a.1.16,4 Wasts management 1a.1.16.5 Facilty and site dormancy                                                                                200            30    230        230                                                                                                          2.000 1a.1.16 Total                                                                                                    1.621            243  1 864      1.864                                                                                                      16,207 Detailed Work Procedures 118            18    136        136                                                                                                        1,183 10.1.17.1 Plant systems 120            18    138        138                                                                                                        1,200 1a.1.17.2 Facilitycloseout &dorrnancy 10.1.17 Total                                                                                                      238            36    274        274                                                                                                          2.383 1.1.16      Procure vacuum drying system                                                                              10            2    12            12 1a.1.18    Orairlde-energize non-cont. sypstes
          .1.20  Drain &dry NSSS 0.1.21    Drainde-energize contaminated systems 1:.1.22    Deconlsecure contaminated system 10.1        Subtotal Period 1 a ActivityCosts                                                                    3,935            642  4,577        4,577                                                                                                      35,690 Period Ia Collateral Costs la.3.1      Spent Fuel Capital and Transfer                        -      --        -          -      -      2,721            408  3,129        -            3,129 la.3.2      Corporate Overheads                                    -      --        -            -      -      3,105            468  3,570      3,570 10.3        Subtotal Period 10 Collateral Costs                    -      --        -            -      -      5.825          874  6.699        3,570          3,129 Period 10 Period-Dependent Costs la.4.1      Insurance                                                                                              1,600          160  1,760      1,760 la.4.2      Properly loves                                                                                              4            0      4            4 1.4.3      Health physics supplies                            370                                                                93    463        463 1:.4.4      Heavy equipment rental                              368                                                                55    423        423 1 .4.5      Diaposal of DAW generated                                          5                            73      -              15    100        100                                          1,575                              14,445            5 10.4.6      Plant energy budget                                                                                    927            139  1,066      1,060 1a.4.7      NRC Fees                                                                                                706            71    778        776 tl.4.8    Emergency Planning Fees                                                                                1 1.85          110  1,303                      1,303 10.49      Spent Fuel Pool O&M                                                                                    745            112    857                        857 1:.4.10    ISFSI Operating costs                                                                                      85          13      98          -              98 0.4.11 Security Stafl Cost                                                                                      6&021            903  6.924      6,924                                                                                                      157,471 TLG Services, Inc.
 
Cooper NuclearStation                                                                                                                                                                                                                                    DocumentN01.1590-002, Rev. I DecommissioningCoast Analysis                                                                                                                                                                                                                                  Appendix D, Page25 of 35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Sits  LLRW                                          NRC        Spent Fuel      Sits    Processed              Burial Volunses              Burial              Utilty and Activity                                            escon  Removal    Packaging    Transport  Processing Disposal    Other        Total      Total  Lic. Teom. Management    Restoration  Volume  Class A      Class B    Class C  GTCC    Processed    Craft    Contantor Index                    Activity Description      Cost      Cost        Costs      Costs      Costs    Costs      Costs    Contingency  Costs      Costs          Costs        Costs      Cu. Feet Cu. Foat    Cu. Feet Cu. Feet  Cu. Feet  W.L Lbs. Manhours  Manhours Period ia Period-Dependent Costs (conornued) la.4.12    UtilityStaff Cost                                                                                          - 22,690          3.403  26,093      26,093                                                                                          -        -      423,400 738                                            73    33.962          5,087  39,867      37,609            2,258                          1,575                                      14.445          5    580,871 la.4      Subtotal Period Ia Period-Dependent Costs 738                                            73    43,723          6,603  51,144      45,757            5.387                          1,575                                      14,445          5    616,761 la.0      TOTAL PERIOD Io COST PERIOD lb - SAFSTOR Limited DECON Activities Period lb Direct Decommnssioning Activities Decontamination of Site Buildings lb.1.1.1  Reactor                                    2.929                                                                            1,465  4,394        4.394                                                                                              68,438 52                                                                              26      78            78                                                                                              1,562 lb.1.1.2 Augmrnted Radwasts lb.1.1.3 Mscellaneous Sructures . Contaminated          376                                                                              188    565          565                                                                                                8,542 lb.1.1.4 Muot-Purpose FaCiitty                            68                                                                              34    101          101                                                                                                2.036 79    237          237                                                                                                4,761 lb 1.1.5 Radwaste                                        158 1.1.6      Turbine                                      520                                                                              260    780          780                                                                                              15,667 1I1      Totals                                      4,103                                                                            2,052  6,155        6,155                                                                                              101,006 Subtotal Period I b Actvity Costs          4,103                                                                            2,052  6,155        6,155                                                                                              101,006 lb.1 Period 1b Additional Costs lb.2.1    Spent Fuel Pool Isolation                      -                      -                              -        9.407          1,411  10,818        10,818 lb.2.2    Asbestos Insulation Disposal                            773              1        65                558                      265  1,662        1,662                                        10,333                                    134,329    10,002 lb.2      Subtotal Period l b Additional Costs                    773              1        65                558      9.407          1,676  12,480        12.480                                        10.333                                    134,329    10,002 Period 1b Collateral Costs lb.3.1    Decor equlpment                              713        -            -          -                                              107    820          820 Process lquid waste                          229        -              74      392                448                        293  1,436        1,436                                          1.561                                      93,644      304 lb.3.2 lb.3.3    Small tooi allowance                          -          70                                                                      11      81            81 lb.3.4    Spent Fuel Capital andTransfer                                                                                  930            139  1,069            -            1,069 lb,3.5    Ccrportte Overheads                            .        .    ...                                              766            115    880          880 392                448      1,695            665  4,286        3,217          1,669                          1.561                                      93,644      304 lb.3      Subtotal Period I b Collateral Costs          942        70            74 Period lb Period-Dependent Costs 1A4.1      Decon supplies                              1,156                                                                -            289    1,445        1,445 10.4.2    Insurance                                                                                                        121              12    133          133 lb.4.3    Property taxes                                          -                                                          I              0        1            1 1b.4.4    Health physics supplies                                473                                                                    118    592          592 1b.4.5      Heavy equipment rental                                    91        -          -                    -                          14    104            104 lb.4.6      Disposal of DAWgenerated                                                5          3                  8151                    21    110            110                                        1,741                                      15,968          5 S0.47      Plant energy budget                                                                                            229              34    263          263 1b.4.8    NRC Fees                                                                                                        174              17    191            191 10'4.9      Emergency Planning Fees                                                                                        292            29    321            -              321 1b.4.10    Spent Fuel POolO&M                                                                                              184            28    211                          211 1b.4.11    ISFSlOperaing Costs                                                                                              21              3      24          -              24 lb.4.12    Security Staff Cost                                                                                            1.485            223    1,707        1,707                                                                                                            38,829 lb.4.13    Uilty Staff Cost                                                                                              5,595            839  6.434        6,434                                            -.104,400 Subtotal Period lb Period-Dependent Costs  1,156      564              5          3                  81    8,101          1,628  11,538        10,981            557 2                          1,741                                      15,.68          5    143,229 1b.4 6,020  34,458        32,833          1,626                        13,635                                    243,942  111,318      143,229 lb.0      TOTAL PERIOD lb COST                        6.201    1.407            80      460                1.087    19,203 TLG Serviese, Inc.
 
CooperNuolear Station                                                                                                                                                                                                                                  Document N01-1590-002, Rev. I DecommissioningCost Analysis                                                                                                                                                                                                                                  Appendix D, Page 26 of 35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
I Activity                                              Decon  Removal    Packaging  Transport  off-Sita Processing  LLRI Disposal    Other        Total        Total  Lic.NRC Ten. Spent Fuel Management      site Restoration Processed Volume  Class A    Burial Class B Volumes Class C  GTCC      Burial I Processed    Craft    Utility and Contractor  I Icnde                    Activity Description      Cast      Cost      Costs      Casts      Costs    Costa      costs      nsts                    Costs        Costs        Costa      Cu. Feet Cu. Feet Cu. Feat Cu. Feet Cu. Feet  Wt,. Lbs. Manhours  Manhours    I PERIOD Ic - Preparations for SAFSTOR Dormancy Period i Direct Decommissioning Actvities 1C.1.1    Prepare support equipment for storage                    387                                                                        85    445          445                                                                                            3,000 Ic.1.2    Install containment pressure equal. lines                  31                                                      -                5      36            36                                                                                            700 Ic.1.3    Interim survey prior to dormancy                                                                                  733            220      953          953                                                                                          15,696 lc.1.4    Secure building accesses ic. 1.5    Prepare &submit interim report                                                                                      58              9      67            67                                                                                            -          0583 419                                                      791            291    1,501        1,601                                                                                          19,396          583 1C.1      Subtotal Period ic Activity Costs Period Ic Collateral Costs lc.3.1    Process iquid waste                            235                      76      403                  460                        301    1,475        1,475                                          1,603                                  96,195      313          -
1c.3.2    Small tool allowance                                          3                                                                      0        3            3                        -
lc.3.3    Spent Fuel Capital and Transfer                                                                                    940            141    1,081          -            1,081 lc.3.4    Corporate Over-eads                            .          .            .        ..                              774            116      890          890 lc.3      Subtotal Period lc Collateral Costs            235          3          76      403                  460      1,714            558    3,449        2,368          1.081                          1,603                                  96,195      313 Period 1cPeriod-Dependent Costs lc.4.1    Insurance                                                                                                          122              12      134          134 lc.4.2    Propertytaxs                                                                                                          1            0        1            1 1c.4.3    Health physics supplies                                    160                                                      -              40      200          200 ic,4.4    Heavy equipment rental                                      92        -                              -                          14      105          105
                                                                      *    -1                        1                  18        -                5      25            25                                          393                                  3,601        1 lc.4.5    Disposal of DAW generated 1c.4.6    Plant energy budget                                                                                                231              35      266          266 1c.4.7    NRC Fees                                                                                                          176              18      194          194 ic.4.8    Emergency Planning Fees                                                                                            295              30      325          -            325 1c.4.9    Spent Fuel Pool O&M                                                                                                186              28      214                        214 Ic.4,l0    ISFSI Operating Costs                                                                                                21            3      24          -              24 lc.4.11    Security Staff Cost                                                                                              1,501            225    1.726        1,726            -                                                                                          39,260 1c.4.12    UtilityStaff Cost                                                                                                5 057            849    6.505        6,505                                                                                                    105,560 lc.4      Subtotal Period ic Period-Dependent Costs                252            1          1                    18    80,191        1,257    6,720        90157            563                            393                                  3,601        1    144,820 lc.0      TOTALPERIOD ic COST                            235      673            77      404                  478      10.696          2,107    14,670      13,026          1.644                          1.996                                  99,796    19,710    145,403 PERIOD I TOTALS                                          6,437    2.818          162        866                1,638      73.621        14,730  100,272      91,616          8.657                          17,205                                358,183    131,033    905,393 PERIOD 2a - SAFSTOR Dormancy with Wet Spent Fuel Storage Period 2a Direct Decommissionlng Acivitles 2a.i.1    Quarterly Inspection 2a.1.2    Semi-annual environmental survey                                                                                                              a
: 2. 1.3    Prepare reports 2a.1.4    Bituminous roof replacement                                                                                          63              9      72            72 2a.1.5    Maintenance supplies                                                                                              503            126      629          629 20.1      Subtotal Period 2a ActivityCosts                                                                                  566            135      701          701 Perod 2a Collateral Costs 2a.3.1    Spent Fuel Capital and Transfer                                                                                21.155          3.173    24,329          -          24,329 2a.3.2    Corporate Ocerheads                                                                                              4.139            621    4,759        4,759 2a.3      Subtotal Period 2a Collateral Costs                                                                            25.294          3,794    29,088        4.759        24,329 Period 2a Period-Dependent Costs 2a.4.1    Insurance                                                                                                        1,962            196    2.158        1,848            310                    --                        -      -
16 20.4.2    Property taces                                                                                                                      2      18            18 2a.4.3    Health physics supples                                    344                                                                      88      430          430 TLo Serices, Ine.
 
CooperNuclear Station                                                                                                                                                                                                                                      Document N01-1590-002, Rev. I Appendix D, Page 27 of 35 Deom.missioning Cost Analysis Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommnissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                            NRC        Spent Fuel      Site    Processed            Burial Volumes              Burial I            Utility and Total  LIc. Term. Management    Restoration  Volume  Clas A  Class 8    Clans C  GTCC    Processed  Craft    Contractor  I IlActivity-I  Ind*v                    ArH*
Ci6u.&#xfd;
* r*nf*n Decon cost, Removal t'
Packaging Costs Transport costs Processing costs Disposal costs Other Costs Total Continmenca    Costs    Costs          Costs        Costs      Cu. Feet Cu. FPst Cu. Feet Cu. Feet  Cu. Feat  Wt. Lbs. Manhours  ManhoursI
                                                                                                                    -
Period 2a Period-Dependent Costs (continued) 2a.4.4    Disposal of DAWgenerated                                                13          7                  198          -              52    270          270            -                            4,267                                  39,139        13 2a.4.5    Plant energy budget                                                                                      -          742            111    853          427            427 2a.4.6    NRC Fees                                                                                                              807            81    887          887            -
2a.4.7    Emergency Planning Fees                                                                                            3,374          337    3,712          -            3,712 2a.4.8    Spent Fuel Pool O&M                                                                                                - ,984          448    3,431                        3,431 2a.4.9    ISFSI Operating Costs                                                                                                340            51    391          -              391 2a.4.10    Security Staff Cost                                                                                              17,728          2,659  20,387        7,788        12.599                                                                                      444,561 18-816          2,822  21,639        4,426        17,213                              --                                      -              329.769 2a.4.11    Utiity Staff Cost 344          13          7                  198      46,768          6,845  54,176      16,092        382.63                          4.267                                  39,139        13    774,330 2a.4      Subtotal Period 2a Periad-Dependent Costs 344          13          7                  198      72,628        10,775  83.965      21,553          62,412                          4.267                                  39,139        13    774,330 2a.0      TOTALPERIOD 2a COST PERIOD 2b - SAFSTOR Dormancy with Dry Spent Fuel Storage Period 2b Direct Decommitssioning Activities 2b.1-1    Quad"y Inspection 2b. 1.2    Semi-ennual environmental survey 2b.1.3    Prepare reports 2b. 1A    Bituminous roof replacement                                                                                          354            53    407          407 21.1.5    Maintenance supplies                                                                                              -2, 52          706    3,531        3,531 2b. 1      Subtotal Period 2b ActivityCosts                                                                                    3,178          759    3,938        3,938 Period 2b Coulateral Costs 2b.3.1    Spent Fuel Capital and Transfer                                                                                  13,214          1,982  15,197                      16,197 2b.3      Subtotal Period 2b Collateral Costs                                                                              13214          1,982  15.197                      15,197 Period 2b Period-Dependent Costs 2b.4.1    Insurance                                                                                                          9,796          980  10.775      10,373            402 2b.4.2    Property taxes                                                                                                          90            9      99            99            -
2b.4.3    Health physics supplies                                  1.620                                                -                    405    2,025        2,025 66          36                1.037          -            271    1,411        1.411                                        22,311                                204.651        68 2h.4A      Disposal of DAWgenerated 2b.4.5    Plant energy budget                                                                                      -        2.083            312  2.390        2,395 2b.4.6    NRC Fees                                                                                                          4.528            453    4,981        4,981              -
2b.4.7    Emergency Planning Fees                                                                                          18,944          1,894  20,838          -          20,838 2b.4.8    ISFSI Operating Costs                                                                                              1,908          266    2,194          -            2.194 2b.4.9    Security Stuff Cost                                                                                              67,312          8,597  65,909      43,719          22.190                                                                                    1.265,451 2b.4.10    UtilityStaff Cost                                                                                                41,970          6,295  48,265      24,845          23,420                                                                                      749,897 2b.4      Subtotal Period 2b Period-Dependent Costs                1,620        66          36                1,037    136.630        19.503  156,892      89,847          69,045                          22,311                                204.651        68  2,015,349 20.0      TOTAL PERIOD 2b COST                                      1,620          66        36                1,037    153,023        22,244  178,026      93,785        84,241                          22,311                                204.651        68  2,015,349 PERIOD 2oc- SAFSTOR Dormancy wvithout Spent Fuel Storage Penod 2c  Direct Decommissioning Activities 2c. 1.1    Quarterly Inspection                                                                                                                          a 2c. 1.2    Semi-annud envronnmental survey 20c1.3    Prepare reports 2c.1.4    Bituminous roof replacement                                                                                          414            62    476          476 2c.1.5    Maintenance supplies                                                                                                3,306            82e  4,132        4,132 2c.1      Subtotal Period 2c ActivityCosts                                                                                    3,720            889  4,608        4,608 Period 2c Period-Dependent Costs 2C04.1    Insurance                                                                                                        11,037          1,104  12,140      12,140 2C.4.2    Property taxes                                              -                                                        105            11    116          110 2C.4.3    Health physics supplies                                  1.783        -              -                -                        446    2,229        2,229 2c.4.4    Dispoe atof DAWgenerated                                    -          75        42                1,186                        310    1,613      1,613                                        25,518                                234,065        78 TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                                                                                        Document N01-1590-002, Rev. I Decommissioning Cast Analysis                                                                                                                                                                                                                      Appendix D, Page 28 of35 Table D1-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site  LLRW                                          NRC        Spent Fuel    Site      Processed            Burial Volumes              Burial              Utlity 0and I Ac t io y                                            Decon Removal  Packaging  Transport Processing Disposal      Other      Total        Total  Lit. Term. Management  Restoration  Volume  Class A  Class B    Class C  GTCC    Processed  Craft    Conetrsrta Cost  Cost    Costs    Costs      Costs    Costs        Costs  Continsency    Costs    Costs        Costs      Costs      Cu. Feet Cu. FePt Cu. Fast Cu. Feet  Cu. Fast  WLt.Lbs. Manhours    Manbosra I n ex                    --              l-Period 2c Peaiod-Dependunt Costs (contnued) 2c.4.5      Flant energy budget                                                                                      2.437          366    2,803        2,803 2c.4.6      NRC Fees                                                                                                4,799          480    5,279        5,279 2c.4.7      Security Staff Cost                                                                                    44,492        6,674  51,165      51,165                                                                                                      822,771 2c.4.8      UtilityStff Cost                                                                              -      25,284        3,793  29,076      29,076                                                                                    -        -      479,950 2c.d        Subtotal Period 2c Period-Dependent Costs          1,783        75      42                1,186      88,153        13,182  104,422    104,422                                        25.51      -                        234,065        78  1,302.721 2c.0        TOTALPERIOD 2c COST                                1,783        75      42                1,186      91,873        14,071  109,030    109,030                                        25,518                                234,065          78  1,302,721 PERIOD 2 TOTALS                                                3,748      153        85                2,422    317,524        47,090  371,021    224.368        146,654                          52,095                                477,855      160    4,092.400 PERIOD 3a - Reactivate Site Following SAFSTOR Dormancy Period 3a  Direot DecommissioningActivities 3s.1.1      Prepare prelimonary decovnossiorrng cost                                                                  130            20    150          150                                                                                                        1,300 3a. 12      Review piant dwgs &specs.                                                                                460            69    529          529                                                                                                        4.600 3a. 1.3      Perform detailed rod survey 3a. 1.4      End product description                                                                                    100            15    115          115                                                                                                        1,000 3a.1.5      Detaiste by-product inventory                                                                              130            20    150          10                                                                                                        1,300 3,a.16      Defrae major work sequence                                                                                750            113    863          863                                                                                                        7.500 3a. 1.7      Perform SER and EA                                                                                        310            47    357          357                                                                                                        3,100 3a.1,8      Perform Site-Specific Cost Stuly                                                                          500            75    575          575                                                                                                        5.000 3a.1.      Preparepsoubit Lcense Teorination Plan                                                                    410            61    471          471                                                                                                        4.096 3a.1.10      Receive NRC approval of termination plan                                                                                          a Activity Specifications 3a.1.11.1 Re-actvate plant &temporary facilities                                                                        737          111    848          763                        85                                                                            7,370 3a.1.11.2 Plant systema                                                                                                417            63    479          431                        468                                                                            4,167 3a1.11.3 Reactor internans                                                                                            710          107    817          817                                                                                                        7,100 3a.1.11.4 Reactor vessel                                                                                              65O            98    748          748                                                                                                        6,500 3a1.11.5 Sacritfcial shaid                                                                                              50            6      58          58                                                                                                          500 3a.1.11.6 Moisture Separ atorstrheatars                                                                                100            15    115          115                                                                                                        - .000 3a.I.1.7 Reinforced concreta                                                                                          160            24    184          92                        692                                                                            1,600 3a.1,11.8 Main Turbine                                                                                                209            31    240          240                                                                                                        2.088 3a01.11.9 Main Condensers                                                                                              209            31    240          240                                                                                                        2,088 3a.1.11.10 Pressure suppression structure                                                                              200            30    230          230                                                                                                        2.000 3a.1.11.11 Drywel                                                                                                      160            24    184          184                                                                                                        1,600 3a.1.11.12 Plant structures &buildings                                                                                312            47    359          179                      179                                                                              3,120 3a.1.11,.13 Waste management                                                                                          460            69    529          529                                                                                                        4,600 3a.1.11.14 Facility & sits closeout                                                                                    90            14    104          52                        52                                                                              900 3a.1.11      Total                                                                                                    4,463          669    5,133        4,677                      456                                                                            44,633 Planning & Site Preparations 30.1.12    Prepare disaotnrrng sequence                                                                              240            36    276          276                                                                                                        2,400 3a.1.13    Plant prep. & itmp. svcs                                                                                2,700          405    3,105        3.105 3a01.14 Design wtar clsaa-up system                                                                                    140            21    161          161                                                                                                        1,400 3a01.15 Rigging/Coat, Cntt Eovlpsitoolingletc,                                                                      2,100          315  2,415        2,415 3a. 1.16    Procure csktliners & containers                                                                            123            16    141          141                                                                                                        1,230 3a.1        Subtotal Period 3a Activity Costs                                                                      12,556        1,883  14,439      13,983                      456        -                                                                  77,559 Period 3a Period-Dependent Costs 3a04.1      ilasurone                                                                                                420            42    462          462 3a.4.2      Property taxes                                                                                              4            0        4            4 30.43        Healit phrysics suppies                              324                                                                  81    405          405 3a.4.4      Heavy equipment rental                              368                                                                  55    423          423 3a.4.5      Disposal of DAWgenerated                                                                        62                      16      84          84                                        1,329                                12,190 TLG Services, Inc.
 
0 Cooper NuclearStation                                                                                                                                                                                                                        Document N01.1590-002,Rev. 1 DecommissioningCoast Analysis                                                                                                                                                                                                                    Appendix D, Page29 of"35 Table Dl-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thouesansds of 2008 dollars)
Off-Site  LLRW                                        NRC      Spent Fuel    Site      Processed            Burial Volumes              Burial I            Utility and I Decon  Removal  Packaging  Transport  Processing Disposal    Other      Total      Total LIc. Term. Management Restoration    Volume    Class A  Class B  Class C  GTCC    Processed    Craft  Contractor IActsity                                              Cont    Cost      Cosnt    costs      Costs    Costs      Cat      Cuntinnenev  Costs    Cnsts        Costs      Costs        Cu. Feet  Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Wt. Lbs. Manhours  Manhoursre n ex                      Q6ail.iiiu v    n                                                                                                                                                  -
Period 3a Period-Dependent Costs (coninued) 3a.4.6    Plant energy budget                                                                                          927          139  1,066        1,066 3a.4.7    NRC Fees                                                                                                    249            25    274          274
                                                                                                                        -  2,800          428  3,283        3,283                                                                                                      65,179 3a.4.8    Security Staff Cost 3a.4,9    UtilityStaff Cost                                                                                -        14,190        2,128 16,318      16,318                                                                                    -        -      258,629 3a.4      Subtotal Period 30 Period-Dependent Costs            691          4          2                  62    18,644        2,915 22.318      22,318                                          1,329                                12,190        4    323,807 691          4          2                  62    31,200          4,799 36,758      36,302                                          1,329                                12,190        4    401,366 3a.0      TOTAL PERIOD 3a COST PERIOD 3b - Decommissioning Preparations Period 3b Direct Decommissioning Activities Detailed Work Procedures 3b.1.1.1 Plant systems                                                                                                  473            71    544          490                      54                                                                              4.733 400            60    460          460                                                                                                        4,000 3b.1.1.2 Reactor internals 135            20    155          39                      1186                                                                              1,350 3b.1.1.3 Remaining buildings 100            15    115          115                                                                                                        1,000 3b,.1.1.4 CRD housings & Nis 3b.1.1.5 Incore instrumentation                                                                                        100            15    115          115                                                                                                        1,000 3b.I.1.6 Removal primaty containment                                                                                    200            30    230          230                                                                                                        2,000 363            54    417          417                                                                                                        3,630 3b.1.1.7 Reactor vessel 120            18    138          89                      69                                                                              1,200 3b 1.1.8 Facliity closeout 120            18    138          139                                                                                                        1,200 3b.1.1.9 Sacrificial shield 3b.11.10 Reinforced concrete                                                                                            100            15    115          58                      58                                                                              1,000 208            31    239          239                                                                                                        2,080 3b. 11 .1 Maji Turbine 209            31    240          240                                                                                                        2,088 3b0.1.1.12 Muin Condensers 200            30    230          230                                                                                                        2,000 3b.1.113 Moisture seperators &reheaters X01.1.14 Radwaste building                                                                                            273            41    314          283                      31                                                                              2,730 3b01.115 Reactor building                                                                                              273            41    314          283                      31                                                                              2,730 301.1      Total                                                                                                      3.274          491  3.765        3,405                      360                                                                              32,741 3b.1      Subtotal Period 3b Activity Costs                                                                          3,274          491  3,765        3,4058                    360                                                                              32,741 Period 3b Additional Costs 31,2.1    Site Characterzation                                                      - -            -      -        5.395        1,819  7,014        7,014 3b.2      Subtotal Period 3b Additional Costs                                        *-            -      -        5,395        1,618  7,014        7,014 Penod 3b Coliateral Costs 3b.1      Decon equipment                              713                                                              -            107    820          820 303.2      DOC staff relocaion0 expenses                                                                                912          137  1,049      1,049 3b.3.3    Pipe cutting equipment                              1,000                                                    -            150  1,150      1,150 30.3      Subtotal Period 3b Collateral Costs          713    1,000                                                  912          394  3,019        3,019 Perod 3b Period-Dependent Costs 3b.4.1    Decon supplies                                22                                                                            5      27          27 3b.4.2    Insurance                                                                                                    246            25    270          270 3b0.4.3    Property taues                                                                                                  2            0      2          2 3b.4.4    Hoalth physics supplies                              179                                                                  45    224          224 3b.4..5    Heavy equipment rental                                184                                                                  28    212          212 3b.4.6    Disposal of DAW generated                                                                          35        -              9      48          48                                            754                                  6,913        2 2
3b.4.7    Plant energy budget                                                                                          465            70    534          534 3b.4.8    NRC Fees                                                                                                    125            12    137          137 3b.4.9      Security Staff Cost                                                                                      1,431          215  1,646      1,848                                                                                                      32,678 3b.4.10    DOC Staff Cost                                                                                            4,378          657  5,035        5,035                                                                                                      58,560 3b.4.11    UtilityStaff Cost                                                                                -        7,114        1,067  8.181        8,181                                                                                            -      129,669 30.4      Subtotal Period 3b Period-DependentCosts      22      363                                          35    13,761        2,133 16,317      16,317                                            754                                  8,913        2    220.907 2
TLG Services, Inc.
 
Cooper Nuclear Statione                                                                                                                                                                                                                                        DocumentNOI-1590-002, Rev. I Decoo~rmissioreirg CoastAmalyais                                                                                                                                                                                                                                    Appendix:D, Page30 of 35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site      LLRW                                        NRC        Spent Fuel      Site      Processed                Burial Volumes                Burial/              Utility and Activity                                            Decon  Removal    Packaging    Transport    Processing    Disposal    Other      Total      Total  Lic.Tenm. Management  Restoration    Volume    Class A    Class B    Class C  GTCC      Processed    Craft    Contractor Index                    Activit Description        Cost    Cost        Costs        Costs        Costs        Costs      Costs  Continuenev  Costs    Costs          Costs        Costs      Cu. Feet  Cu. Feet  Cu. Feet  Cu. Feet Cu. Feet  WI. Lbs. Manhours  Manhours 3b.0      TOTALPERIOD 3b COST                          735    1,363              2            1                      35    23.342        4,636  30,115    29,755                          360                  754                                        6,913          2    253,646 PERIOD 3 TOTALS                                        735    2,055              6            3                      97    54,542        9,435  66,872    66.056                          616                2,083                                      19.104          6    655,014 PERIOD 4a - Large Component Removal Period 4a D~rectDecommnissioningActivities Nuclear Steam Supply System Removan 4a.1.1.1  Recirculation System Piping &Valves          16        70            14          13          127      151                        86    477        477                                    499      499 1,188                                    115,643      2,487 4a.1.1.2 Recirculation Pumps & Motors                      6        28            11        26            -        321                        95    488        498                                                                                      132,880      1,125 4a.1.1.3 CRDMs &Nis Remonal                              24      139          377          68                      317                      174  1 099      1,099                                            6,935        -                            126,494      3,972 4a. 1.1.4 Reactor Vessel Internals                      86    1,959        3,871        912                    5,169        155        5,314  17,462      17,462                                            1,878      1,252        470              359,044    18,900          888 4a.1.1.5 Vessel & Internals GTCC Disposal                          -            -          -                      7,470        -          1,120  8,590      8,590                                                                              508      89,497 4a.1.1.6 Reactor Vessel                                        5.054          906        351                    3,006        155        5.631  15,103      15,103                                            14,106                                  1,447.089    18,900          888 4a.1.1    Totals                                      132    7,250        5,179      1,370            127    16,431        309      12,420  43,219    43,219                                      499    24,605      1,252        470      508    2,270.647    45,384        1,776 Removal of MajorEquipment 4a. 1.2    Main Turbine/Generator                                167          945        372          6,376                              1,138  8,898      8,898                                  61,604                                            2,772,179      4,438 709          588        259          4,439                                940  6,932      6,932                                  42,889                                            1,930,000    19,519 4a.1.3    Main Condensers Cascading  Costs from Clean Building Demolition 4a. 1.4.1  Reactor                                                260                                                                          39    299        299                                                                                            -      2,486 4a.1.4.2  Augmented Radwaste                                      25                                                                          4      28          28                                                                                                    235 43                                                                          7      50          50                                                                                                    359 4a.1.4.3  Radwaste 40.1.4.4  Turbine                                                285                                                                          43    328        328                                                                                                    4,419
: 40. 1.4    Totals                                                613                                                                            92    705        705                                                                                                    7,498 Disposal of Plant Systems 166    857        857                                            2,055                                    172,205      5,688 4a.1.5.1  Augmented Radwaste El 877    AreslA                  203            28          23                      432 44    228        228                                              469                                      41,606      1.842 4a.1.5.2 Augmented Radwaste EA903        ArealA                    66            6            7                    104 4a.1.5.3 Augmented Radwuast El 918      ArealA                    52            10            9                    139                      50    260        260                                              765                                      55,345      1,432 4a. 1.5.4 Augmented Radtasts El 929      ArealA                    21            4            5          -          73                      25    127        127                    *                -        324                                      29,038        579 4a.1.5.5 Augmented Radwaste El 929      Areal B                      3            0            0            4      -                          1      a            8                                    "38      -32                                      1,529        75 4a.1.5.6 DRYWELLArealA                                            457            85          84            -      1,289                      458  2,373      2.373                                            5,726                                    513,627    12,634 4a.1.5.7 DRYVWELL      ArealB                                    112              1            5            75          2                      41    235        235                                    806          10                                    33,576      3,384 324            16          86        1,477                                317  2,220      2,220                        "        15.808                                              641,963      9,170 4a.1.0.8 Turbine El 932 AnealB 4a.1.5.9 Turbine El 932 Area2C                                        8                                                                          1      9
* 9                                                                          237 4a.1.5.10 Turbine El 932 Area3C                                    67                        -          -          -                          10      78        -                          78                                                                -      2,083
                                                                                                                                                                                                                  -        -
4a.1.5.11 YardAuealB                                              518            50      264          4,517                                852  6,201      6,201                          76      48,365                                            1,964,114    14,340 4a.1.5    Totals                                              1,831          202        487          6,073      2.040                    1.964  12,597      12,510                        "87      65,016    9,348                                  3,453.003    51.444 4a. 1.6    Scaffolding in support of decommissioning            2,049            24          11          168          23                    047  2,821      2,821                                  1,921      101                                      81,992    27.411 4a. I      Subtotal Period 4a Acivity Costs            132    12,616        6,838      2,499        17,183    18,493        309      17,102  75,172      75,085                          87    171.628    34,065      1,252        470      5068  10.507.820    155,694        1.776 Period 4a Collateral Costs 4a.3.1    Process liquie masne                          36        -              14          76                        87                      54    270        270                          "10                  304                            -          18,226        59 40a3.2    Small tool allowance                                      90                                                                        14    104            94                        10                    -
4a.3      Subtotal Period 4ACotlateral Costs            38        90            14          76                        87                      67    374        363                -        0                  304        -                            18,226        59 Period 4a Period-Dependent Costs 4a.4.1    Decon sewpiLes                                47                                                                                    12      59          59 4a.4.2    Insurance                                                                                                            529            53    579        579 4a.4.3    Property taxes                                                                                                          4            0      5            4                        0 4a.4.4    Health physics supplies                                927                                                                          232  1,159      1,159 4a.4.5    Heavy equipnent rental                              1,899                                                                          285  2,183      2,183 TLG Services, Inc.
 
Cooper Nuclear Station.                                                                                                                                                                                                                                Document NO0-1590-002, Rev. 1 Decuonami-laonitig Coot Analysis                                                                                                                                                                                                                            AppendiarD,Page 31 of 35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    LLRW                                          NRC        Spent Fuel    Site      Processed            Burial Volumes            Burial I              Utility and Activity                                                Decon Removal    Packaging  Transport    Processing  Disposal    Other      Total        Total  Lic.Tens. Management  Restoration  Volume    Class A Class B Class C GTCC        Processed    Craft    Contractor Index                    Activit Descrilption          Cost    Cost      Costs      Costs        Costs      Costs      Costs    Contlingenc    Costs    Costs        Costs      Costs      Cu. Feet  Cu. Feet Cu.Feet Cu. Feet Cu. Feel  W.LLbs. Manhours  Manhours Period 40 Period-Dependent Costs (continued) 25          14                    401        -            105      546        548                                        8,638                                79,217          28 4a.4.6    Disposal of DAWgemerated 4a.4.7    Plant energy budget                                                                                                  946            142    1.087      1,087 4a.4.8    NRC Fees                                                                                                              707            71      778        778 4a.4.9    Liquid Radwaste Processing EquipnrentlServices                                                                        403            60      463        463 4a.4.10    Security Staff Cost                                                                                                3,066            460    3,526      3,528                                                                                                      70,000 11,154          1,073  12,828      12,828                                                                                                    154,560 4a.4.11    DOC Staff Cost UtilityStaff Cost                                                                                                  15,348          2,302  17,650      17,650                                                                                                    280,000 4a.4.12 4a.4      Subtotal Peniod4a Period-Dependent Costs          47    2.825          25          14                    401    32.154          5,394  40.882    40.861                          0              8,636                                79,217          28    504,560 6,878      2,590        17,183    18,982    32.463        22,564  116,408    116,310                        98    171,628  42.995    1,252      470    508  10,605,260    155,780    506.336 4a.0      TOTAL PERIOD 4a COST                            217    15.531 PERIOD4b - Site Decontamination Period 4b Direct Decommissioning Activitias 4b.1.1    Reerove spent Wuel  racks                      262        33          79          88                                              498    2,308      2,308                                        5,986                              537,141      1,004 Disposal of Plant System 4b.1.2.1  Contro El 882 ArealB                                      280                      39          674                                178    1,178      1,178                                7,213                                        292.908      7.797 4b.1.2.2  Controd El 903 A*a1C                                      170                                                                        25      195                                                                                              -      5,155 4b.1.2.3 Control E 918 Area1C                                          66                                                                        10        76                                  78                                                                2,100 4b.1.2.4  Control El 932 AreslC                                      22                                                                          3      26                                  20                                                                  702 4b. .2.5 Intake                                                      101                                                                        15    116                                  118                                                        -      3,136 4b.1.2.6 Multi-Purpose Facility                                      198            3        14          239      -                          88      541        541                                2,558                                        103,862      5,430 398          75          62                    949                      353    1,836      1.836                                  -    5,097                              377,917    10,930 4b.1.2.7 Radwaste El 877 ArealA 40.11.8    Radwaste El 877 Area2A                                      43          9          7                    113                        41      213        213                                          613                                44,992      1,189 4b.1.2.9 Redwaste El 877 Area3A                                        71          16          13                    201                        72      372        372                                        1,156                                79,963      1,969 110          9          10                    153                        68      351        351                                          684                                61,153      3,015 4b.1.2.10 Radwasta El 903 AreslA 4b,1.2.11 Radwaste El 903 Ara2A                                      188          36          29                    439                      165      858        856                                          1.955                              175,093      5,282 37          6          7                    104                        37      190        190                                          463                                41,366      1,029 4b.1.2.12 Radwaste El 903 Area3A 4b.1.2.13 Radwaste El 918 ArealA                                      18          2          2                      30                        12      64          64                                          135                                12,033      477 4b.1.2.14 Radwaste El 918 Area2A                                      16          3          3                      39                        15      75          75                                          201                                15,667      448 4b.1.2.15 Radwaste El 918 Arne3A                                      185          23          22                    338                      136      705        705                                          1,690                              134,827      5,045 26            3          4                      60                      22      115          115                                          268                                23,735        680 4b.1.2.16 Radwasta El 934 ArealA 4b.1.2.17 Radwaste El 934 Area2A                                      98          11          12                    177                        72      370        370                                          808                                70,605      2.663 4b.1.2.18 Radwaste El 949 ArealA                                      12                      2                      24                        9      47          47                                          105                                  9,381      305 1
4b.1.2.19 Reactor    al 1001 ArealA                                    50            7          8                    121                        45      230        230                                          537                                48,175 27,979 1,261 1,681 4b.1.2.20 Reactor El 1001 Areal*                                      62            1          4            64                                26      157          157                                689 4b.1.2.21 Reactor El 859 ArealA                                        71          is          16                    246                        83      430        430                                  -      1,091                              97,874      2,024 4b.1.2.22 Reactor E 859 ArealB                                        440          11          58          994                  -            289    1,771      1,771                              10,641                                        432,136    12,411 4b.1.2.23 Reactor aJ    859 Area2A                                    72          25          26          -        401                      125      648        648                                          1,780                              159,714      2,094 4b.1.2.24 Reactor 8l 859 Ares2B                                        69            1            0        131      -                          38      247        247                                1,406                                        57,093      1.954 4b.1.2.25 Reactor 8l859 Area3A                                        47            9            9                  137                        48      251        251                                  -      608                                54,543    1,321 4b. 1.2.26 Reactor El 859Area3B                                        33            0          2            42                                  15      93          93                                453                                          18,381      951 4b.1,2.27 Reactor El g59    Are4A                                      50            9          8                    117                        44      227        227                                          520                                46,666      1,374 40.,1.2,20 Reactor E[]588Area4B                                        17            0          2            31                                  9      59          59                                331                                          13.424      476 4b0.1.2.29 Reactor El 5' AreasA                                                                                                                                                                                  1,163                              104,381      1,798 63          16          17                    282                        85      443        443 4b.1.2.30 Reactor 81855A8es5                                                                                                                                                                              442                                          17,962    1,087 37            0          2            41      -                          16      98          98 4          Reactor s.1.2.31El 9OAreslA                                                                                                                                                                          -    2,892                              259.190    10,497 401          56          42                    651                      275    1,424      1,424 40.1.2.32 Reaor [903 AeslB                                                                                                                                                                                                                          239,197    12,496 451            6        32          550        -                        201    1,240      1.240                                5,890 4b.1.2.33 Reactor El903 ArealA                                          4                                                                                                                                                                              2,372        120 0          0                        0                        3      14          14                                            26 401.12.34 Reactor El 903 Area2B                                        69                                                                                                                                                                            82,815      1,915 2        11          190                                  48      320          320                              2,039 4b1.2.35 Reactor El 903 Area3A                                                                                                                                                                            -      741                                66,516        929 32          10          II            -        167                        52    272        272 4b.1.2.35  Reactor El Qb.1.236 Reactor    El 903 Area3 903 .*ea3B                                    21                        3          52      -                          14      90          90                                553        ,                                22,464        618 4b. 1.2.37 Reactor El 903 Ares4A                                      27            8            9                  136                        43      223        223                                          606                                54,373      776 4b.1.2.38 Reactor El 903 Area4B                                        21                        3          52                                  14      90          s0                                559                                        22,692        597 4b.1 .2.39 Reactor El 931 AreaIA                                      25                        3                    52                      20      104        104                                  -      232                                20,858        670 TLG Services, Inc.
 
Cooper' Nuclerar Stationa                                                                                                                                                                                                                                  Document N01-1590-002, Rec. I Dneo-aaairrrirag Coat Anaalysis                                                                                                                                                                                                                                  Appendix D, Page 32 of 35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars) off-Site      LLRW                                    NRC        Spent Fuel      Sits      Processed                    BurialVolumes            Burial I            Utilityand ActUvty                                          Decon  Removal      Packaging  Transport  Processing    Disposal    Other    Total      Total Lc. Tenm. Management      Restoration  Volume          ClasnA    Class B Class C GTCC Processed        Craft    Contractor Index                    Activit Description      Cast      Coast      Costs      Costs        Costs        Costs. Costs  Contn enc    Costs  Costs        Costs        Costs      Cu. Feet      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet WL9Lbs. Manhours  Manhours Disposal of Plant Systems (continued) 4b.1.2.40 Reactor El 931 ArealB                                    300              8        40        692                                186  1,227      1,227                                  7.412                                              301,017    8,410 4b.1.2.41 Reactor El 931 Area2A                                        20          2          2        -            35                    14    74          74                                  -      -154                                      13,824      544 41.1.2.42 Reactor El 931 Area2B                                        2          0          0            1          0                    1      3            3                                      9            0                                  371        53 4b.1.2.43 Reactor El 931 Area3A                                        77          23        22          -          336                    109    567        567                                    -          1,651                                134,007    2,165 4b.1,2.44 Reactor Ea 931 Area3B                                        2          0          0                                              1      3            3                                      8                                                340        49 4b.1 .2.45 Reactor El 931 Area4C                                      24                                                                      4    28                                    28                                                                        767 4b.1.2.46 Reactor El 931 Anea5C                                        7                                                                      1      a          -                                                                                          -        213 56          9          10                    149                      54    278        278                                                  662                                  59,432    1,472 4b.1.2.47 Reactor El 9589 ealA                                                                                                                                                                      3,009            .
4b.1.2.48 Reactor El 958 Aeal B                                    167            3          19        281                                  87    554        554                                                                                    122,212    4,693 31          10        10                      153                      49    253        253                                                  681                                  61,083      880 4b. 1.2.49 Reactor El 958 Area2A 4b9.12.50 Reactor El 958 Area2B                                        10          1          1            12          7                    a    37          37                                  125            33                                8,024      263 4b).1.2.51 Reactor El 958 Area3A                                      33          4          3                      48                    21    109        109                                    S-          214                                  19,185      898 4b.1.2.52 Reactor El 958 Area3B                                        14          1          1            10          6                    7    39          39                                  109            29                                7,011      410 4b.1.2.53 Reactor Ea e76    AealA                                      11          1          1              -        16                    7    39          36                                  S-              72                                6.482      298 4b.1.2.54 Reactor El 976 AeaIB                                      147            5        25        422          -                    104    703        703                                4.521                                              183,615    3,931 4b. 1 2.55 Reactor E9 976 Area2A                                        7          1          1                      13                      5    26          26                                  -      -57                                        5,136      172 4b.1.2.56 Reactor El 976 Area2B                                        37          1          3          51                                18    114        114                                                                                      23,813    1,033 4b.21.57 Turbine El 882 krMIA                                          37          3          3          -            50                    23    116        116                                    .-          222                                  19,878    1,004 4b.1.2.58 Turbine El 882 ArealB                                    386            16        87        1,490                                335  2.313      2,313                                15,948                                              647,659    11.113 4b.12.59 Turbine El 882 Area2A                                        21          2          2                      29                    13    67          67                                    .  -        129                                11,556      584 209              4        22          374                                112    721        721                                  4,006                                              162,678    5,78t 4b.1.2.60 Turbine El 882 Area2B 4b.1.2.61 Turbine El 882 Area3A                                        16          2          1        -            23                    10    52          52                                    - -          101                                  9,017      451 4b.1.2.62 Turbine E9882 Aee3B                                      607            27      145        2,478                                548  3,605      3,805                                26,533                                            1,077,531    17.302
                                                                    -        9          1          1        -            15                      6    32          32                                    -      .68                                        6,127      232 4b.1.2.63 Turbine El 903 ArealA 4b.1.2.64 Turbine E9903 ArealB                                      974            46      241        4,133                                904  6.299      6,299                                44,251                                            1,797.054    27.674 4b91.2.65 Trmbine E 903 Area2A                                          5          1          1                        9                    4    20          20                                                  42                                3,729      142
                                                                                                                -128                                56    337        337                                1,375                                                55,851    4,040 4b.1.2966 Turbim El903 Area2B                                      1144            1          7 4b.1.2.67 Turbine El 903 Area3B                              -        3          0          2          35                                  6    47          47                                  376                                                15,251        97 4b.1.2.68 Turbine El 903 Area3C                            -        1012                                                                      16    124        -                        124                                                                -      3,412 4b.1.2.69 Turbine E9903 Area4B                                        12          O                      28                                  7    49          49                                  299                                                12,139      367 4b.1.2.70 Yard ArealC                                                197                                                                      30    227        -                        227                                                                -      5,770
                                                                                                                                                                                                                -
4b.1.2    Totals                                                7.771          556      1,148      13,202        5.814                  5,535  34,027    33,227                        &0      141,342        27,486                              8,056,388  218,627 4b.1.3      Scaffolding In support  decomeissoning              3.073            36          17          252          34                  821  4,232      4,232                                  2,431            151                                122,968    41,117 Decontaminaton of Site Buildings 4b.1.4.1    Reactor                                  2.880      1,820          202      422          4,911      2,376                  3,310  15.922    15,922                                  52,579        39,536                              6,069,283  115,053 4b.1.4.2 Augmented Radwaste                              52            19          4          6          23          60                    51    215        215                                  242          1,099                                119.386    1.978 4b.1.4.3 Miscellaneous Stuctures -Contaminated          368          167          15        42          759          62                  363  1,777      1,777                                  8,t29          452                                372.774    12,956 4b.1.A.4 MuS-Pulpose Facility                            68            55          6          12          115          89                    90    437        437                                  1,234          1,567                                205.066    3,237 4b.1.4.5 Radwaste                                      159            50          9          14          38        161                    141    572        572                                  404          2,953                                310,769    5.863 4b.1.4.6 Turbine                                        526          142          35        51            64        633                    477  1.928      1 ,98                                    688        11,664                              1,193,496    18,679 4b.1.4    Totals                                    4.055      2,253          27t        547        5,910      3.382                  4,432  20,850    20,850                                  63,275        57,271                              8,270,774  157,766 4b91        Subtotal Period 4b Activity Costs        4,318      13,131          942      1,800        19,364      10,578                11,285  61,417    60.618                        8o0o    207,048        90,895                              16,987,290  418,513 Period 4b AdditionalCosts 4b.2.1      ISFSI Decontamination                                1.012            6        24                        so    1,250        460  2,811          -          2,811                                  1,175                                165.113    26,509        2,560 4b.2.2      Final Site Survey                                        .          .          ..                                1,205        362  1,567      1,597                                                                                                            12,480 4b.2        Subtotal Period 4b Additional Costs                  1,012            6        24                        s0    2.455          921  4,378      1,567          2,811                                  1,175                                165.113    26.509      15.040 Period 4b Collateral Costs 4b.3.1      Process liquid waste                        79          -            30      161                        183                    113    566        566                                                  639                                38,338      125 4b.3.2      Smua tool allowance                                      235                                                                      35    270        270 4b.3.3      Decommissioning Equipment Disposition                                  88        50          621          84                    130    973        973                                6,000            373                                303,507        88 4b.3        Subtotal Period 4b Coltaterol Costs          79          235        118      210            621        267                    278  1,810      1,810                                  6,000          1.012                                341,844      213 TLG Service&, Inc.
 
Coope, Nucka-Statio.n                                                                                                                                                                                                                                              DoeumentN01-1590-002, Rev. I Appendix D, Page 33 of 35 DecomoaniaaioningCost Analysis Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars) 2034 SAFSTOR      Cooper (thousands    Nuclear Decommissioning Table    D-3Station of 2008            Cost Estimate Spent Fuel dollars)                                Sits      Processed              Burial Volumes              Burial I              Uility and  I Activity                                                Decon  Removal    Packaging  Transport    Processing  Disposal      Other        Total          Total  Lin.Term. Management  Restoration  Volume    Class A  Class 8  Class C  GTCC    Processed    Craft    Contractor  I Index                    Activity Description          Cost    Cost      Costs        Costa Off*'-Site Costs LIL Costa        Costs      Contlnoency      Costs NRC.
Costs      Costa      Costs      Cu. Feet  Cua Feet  Cu. Feet  Cu. Feet Cu. Feet  WI. Lbs. Manhouro    Manhours    I Period 4b Period-Dependent Costs 4b.4.1    Decon supplies                                  1.252                                                                    -              313      1.565        1,565 4b.4.2    Insurance                                                                                                              1,199              120      1,319        1,319 4b.4.3    Property taxes                                        -                                                                    10                1      1-t          11 4b.4.4    Healtl physics supples                                    2.409                                                          -              602      3.011        3.011 4b.4.5    Heavy equipment rental                                    4,294                      -                      -                            6 644      4,938        4.938 876          -              229      1,192        1,192                                        18,853                                  172.932          58 4b.4.8      Disposal of DAWgenerated                                                  55          31 4b.4.7    Plantenergy budget                                                                                                    1,751              255      1.950        1,958 4b.4.8    NRC Fees                                                                                                              1.610              161      1.771        1,771 45.4.9    Liquid Radwaste Processing Equipment/Services                                                                            918              138      1,055        1.055 6,984            1.048      8,032        8,032                                                                                                        159,464 4b.4.10    Security Staff Cost 4b.4.11    DOC Staff Cost                                                                                                      24,760            3,714    28,474      28.474                                                                                                        341,891 4b.4.12    Utiity Staff Cost                                                                                                    33,266            4,990    38,256      38,256                                                                                                        602,137 1,252    6,703          55          31                  876      70.448          12,215    91,580      91,580                                        18,853                                  172,932          58  1,103,493 4b.4      Subtotal Period 4b Period-Dependent Costs 24,600    159,185      155,574        2,811        800    213.048  111,935                              17,667,180  445,292    1,119,533 4b.0      TOTAL PERIOD 4b COST                            5,649    21,081      1,121      2,065        19,985    11.782      72,902 PERIOD 4o - License Termination Period 4e Direct Decommissioning Activities 48.1.1    ORISE confrmatory survey                                                      -            -                            147                44      191          191 4e.1.2    Terminate license                                                                                                                                      a 4e.1      Subtotal Period 4e Actvity Costs                                                                                        147                44      191          191 Period 4e Additonal Costs 4e.2.1    Final Site Survey                                                                                                      5,998            1,799      7.797        7,797                                                                                          148.435        6.240 5.998            1,799      7.797        7,797                                                                                          148,435        6,240 4e.2      Subtotal Period 4e Addritonal Costs Period 4e Collateral Costs 4e.3.1    DOC staff relocaton expenses                                                                                            912              137    1,049        1,049 4e.3      Subtotal Period 4e Collateral Coals                                                                                      912              137    1,049        1.049 Period 4e Period-Dependent Costs 4 0.4.1    Insurance                                                                                                                                  -.-
4e.4.2    Properytayes-h                                                                                                                  3                0        3            3 4e.4.3    Health physics supplies                                    735          -                        -                -                      184      919          919 3            1                    42                            11        57          57                                            904                                  8,294          3 4e.4.4    Dlsposal of DAW generated 4e.4.5    Plant energy budget                                                                                                      139                21      160          160 48.4.6    NRC Fees                                                                                                                530                53      583          583 4e.4.7    Security Staff Cost                                                                                                    1.009              151    1.160        1,160                                                                                                          18,789 44.4.0    DOC StaffCost                                                                                                          4,442              666      5,108        5,108                                                                                                          57,149
                                                                                                                                                                                                                                  -                          .            -          -        74,371 4e.4.9    Ul1ityStaff Cost                                                            -            -                -        4,678              702      5,379        5,379 735            3            1                    42      10,800            1,788    13,369      13,369                                            904                                  8,294          3    150,309 48.4      Subtotal Period 4e Period-Dependent Costs 22,407                                  -          904                                  8,294  148,438      156,549 4e.0      TOTALPERIOD 4e COST                                        735            3            1                    42      17,857            3,768    22,407 PERIOD 4 TOTALS                                            5,8a8    37,348      8,001      4,658        37.168    30,806      123,223          50,932    297,999      294,291        2,811          897    384,676  155,834    1,252      470      508  29,280,740  749,510    1,781,417 PERIOD 8b - Site Restoration Period 5b Direct Decommissioning Acbvites Demoliton  of Remainig Site Buildings 5b.1.1.1  Reactor                                                  1.491          -            -                                                  224      1,715                                  1,715            -                -        -        -            -      14.601 5b.1.1.2  Augmented Radwaste                                          222                                                                            33      255                                    255                                                                    2,119 5b.11.3    Control                                                    214                                                                              32      246                                    248                                                                    1.655 5b81 1.4  Intake Structore                                            523                                                                            78      602                                    602                                                                    5,621 TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                                                                                            Document N01.1590.002, Rev. I DecommissioniogCost Analysis                                                                                                                                                                                                                            Appendix D, Page 34 of 35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars) m                                                                                              Off-Sit. LLRW                                          NRC      Spent Fuel    Sits      Processed            Burial Volumes                Burial I            Ulity and IActiy                                                Decon  Removal    Packaging  Transport Processing  Disposal    Other        Total        Total UC. Term. Management  Restoration  Volume    Class A  Class 8    Class C  GTCC    Processed    Craft    Contractor I H  [*BX                    A*UV*V*    CrlU[*        Cost    Cost        Costs    Costs      Costs      Costs      Costs      ontinenc      Costs  Costs      Costs      Costs      Cu. Feet  Cu. Feet Cu. Feet Cu. Feet  Cu. Feet  Wt. Lbs. Manhours    Manhour    I n ex                                -    1-Demo5l5oeof Remaining Site Buildings (continued) 5b.1.1.5 LLRWStorage Pad                                          145                                                                      22      167                                167                                                                  1.227 5b.1.1.6 Miscellaneous Siructures - Clean                      1,196                                                                    179    1,375                              1,375                                                                11,837 5b.1.1.7 Miscellaneous Structures - Contarminated                  27                                                                      4      30                                  30                                                                    572 S1t 10.8 MulS-Purpose Facility                                    123                                                                      18      141                                141                                                                  1,982 3      20                                  20                                                                    283 5b 1.1-9 OVWCGas Generator                                        158                                                                                                                                                                                        1,920 5b.1.1.10 Office                                            -    156                                                                    23      179                                179 Sb.1.I.11 Radwasle                                                391                                                                      59    449                                449                                                                    3,229 17                                                                      3      20                                  20                                                                    166 5b.1.1.12 Seal Well St.1.1,13 Sewage TreatmentArea                                      4                                                                      1        5                                  5                                                                      53 5b.1.1.14 Transornier Yard                                          20                                                                      3      24                                  24                                                                    172 St..1.,15 Turbine                                              2,596                                                                    389    2.985                              2,985                                                                  40,503 5b.1.t.16 Turbine Pedestal                                        277                                                                      42      310                                  318                                                                  2.100 5b.1.t    Totals                                              7,418                                                                  1,113    8,531                              8,531                                                                  88.040 Site Closeout Activities 5b.1-      Remove Rubble                                          424                                                                      64      488                                488                                                                    3,286 5b, 1.3    Grade &landscape site                                  578                                                      -              807    665                                665                                                                    1,578 5b. 1.4    Final report to NRC                                                                                            156            23      179        179                                                                                              S-        1,560 5b. I      Subtotal Period 5b Activity Costs                    8,421                                                      156          1,286    9.063        179                  9.684                                                                  92.904        1,560 Peniod5b Additional Costs 5b.2.1    ISFSI Demolition                                      672                                                        44          107      824                    824                                                                                5,8980        16 5b2.2      Cocrete Crushing                                      499                                                              8        76    582                                582                                                                    3.045 W0.2.3 Cofferdam                                                458                                                      -              69      527                                527                                                                    5.130 5b.2      Subtotal Period SbAdditional Costs                  1,629                                                        52          252    1.933                    824        1,100                                                                  14.073        160 Period 5b Collateral Costs 5b.3.1    Small tool allowance                                    560.                                                                    a      64                                  64 8      64                                  64 5b.3      Subtotal Period 5b Cotateral Costs                      560-Period 5b Period-Dependent Costs 5b.4.1    Insurance 5b.4.2    Property tanes                                                                                                      7            1        8 5b.4.3    Heavy equipment rental                              4,233                                                                    635    4.869                              4,869 5b.4.4    Plant energy budget
* 167              25      192                                192 50,4.5    Security Staff Cost                                                                                          2,419            363    2,782                              2,782                                                                              45,051 5b.4.6    DOC Staff Cost                                                                                              10.212          1,532  11,744                              11,744                                                                              127.64" 5b.4.7    U lity Staff Cost                                                                                            4,507            676    5.183                                                                                                                  73,209 104        Subtotal Period So Period-Dependent Costs            4,233                                                  17,312          3.232  24.777                              24,7877                                                                            245.906 5b.0      TOTAL PERIOD SbCOST                                14,339                                                  17,520          4,779  36,638        179        824      35,634                                                                106.977    247,626 824      35.634 PERIOD 5 TOTALS                                          -    14,339                                                  17,520          4,779  36,638        179                                                                                        106.977    247,626 TOTALCOST TO DECOMMISSION                            13,038  60,307        8,323    5.611      37,168  34,963    580.430        126,964  872.803    676.510      158,945      37,348    384.676  227,217    1.252        470      508  29,135,880  987.685    7,681.850 TLG Services, Inc.
 
CooperNuarka, Statio~n                                                                                                                                                                                                                            DocumentN01-1590-002, Rev. I Decovaajarnsionirg Cost Anaalysis                                                                                                                                                                                                                      Appendix D, Page 35 of35 Table D-3 Cooper Nuclear Station 2034 SAFSTOR Decommissioning Cost Estimate (thousands of 2008 dollars)
Off-Site    I.RW                                    NRC    Spent Fuel    Site    Processed            Burial Volumes              BurialI            Utility and Activity                                                            Decon Removal Packaging Transport  Processing  Disposal    Other    Total    Total Lic. Term. Management Restoration  Volume  Class A  Class B    Class C  GTCC    Processed  Craft  Contractor Index                      Activity Description                  Cost  Cost    Costs    Costs      Costs      Costs      Costs  Continefc  Casts    Costs      Costs      Costs      Cu. Feet Cu. Feet Cu. Feet Cu. Feet  Cu. Feet  Wt. Lbs. Manhours  Manhours TOTALCOST TO DECOMMISSION WITH17.02% CONTINGENCY:                                            $872,803  thousands of 2008 dollars TOTALNRC LICENSE TERMINATIONCOST IS 77.51% OR:                                              $676,510  thousands of 2008 dollars SPENT FUEL MANAGEMENTCOST IS 18.21% OR:                                                      $158,945  thousands of 2008 dollars NON-NUCLEARDEMOLITIONCOST IS 4.28% OR:                                                        $37.348  thousands of 2008 dtolars TOTALLOW-LEVELRADIOACTIVEWASTE VOLUME BURIED (EXCLUDING GTCC):                                228.939 cubic feet TOTALGREATER THAN CLASS C RADWASTE VOLUME GENERATED:                                              008 cubic feet TOTALSCRAP METALREMOVED:                                                                        30,276 tons TOTALCRAFT LABOR REQUIREMENTS:                                                                987,686 man-hours End Notes:
nca- indicates that this activity not charged as decommissioning expense.
a - indicates that this activity performed by decommissioning staff.
0 - indicates that this value is less than 0.5 but is nos-zero.
a cll containing - "indicates a zero value TLG Services, Inc.
 
Cooper Nuclear Station                      Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                    Appendix E, Page 1 of 8 APPENDIX E WORK DIFFICULTY ADJUSTMENT FACTORS TLG Services, Inc.
 
CooperNuclear Station                                        Document N01-1590.002, Rev. 1 DecommissioningCost Analysis                                      Appendix E, Page 2 of 8 APPENDIX E WORK DIFFICULTY ADJUSTMENT FACTORS TLG has historically applied work difficulty adjustment factors in determining Unit Cost Factors to account for working in a radiological controlled environment. In performing an area-by-area decommissioning cost/schedule estimate the work difficulty factors are to be applied on an "area" basis, based on the nominal area conditions. Where practical, areas are established based on similar working conditions.
The intent of the use of these factors is to provide the estimator an appropriate means to achieve an additional element of consistency within the estimate.
Access Factor:
ControllingVariables:
* Height of the component above the working floor
* Difficulty in working around the component (restricted access)
Source of Variable Information:
* Estimators observation or judgment
* Plant drawings Range of Access FactorAdjustments:
0%    Components are accessible and located near a working level floor or platform 10%    Scaffolding (component less than <12 feet above floor) is required to access the majority of the components or the area around the components is congested.
20%    Scaffolding (component less than <12 feet above floor) is required to access the majority of the components and the area around the components is congested.
30%    Scaffolding (component between 12 - 20 feet above floor) is required to access the majority of the components or the areas around the components are extremely congested.
TLG Services, Inc.
 
CooperNuclearStation                                  Document NO1-1590-002, Rev. 1 Decommissioning Cost Analysis                                Appendix E, Page 3 of 8 40%    Scaffolding (component between 20 - 45 feet above floor) is required to access the majority of the components).
50%    Scaffolding (component greater than 45 feet above floor) is required to access the majority of the components).
Respiratory Protection Factor:
Controlling Variables:
    " Component surface contamination levels (internal or external)
* Type of work (potential to create an airborne problem)
* General area surface contamination levels
* Site-specific requirements for maintaining respirator qualifications (initial qualification, requalification, etc.)
* Personal air sampler requirements Sources of Variable Information:
* Radiation Work Permit Requirements
* Area Survey Maps
* Site Radiation Protection Program Manual Range of Respiratory Pr-otectionFactorAdjustments:
0%    Respiratory protection is not required (clean system or loose surface contamination has been removed).
25%    Respiratory protection is only required during limited segments of the work (i.e. physical cutting).
50%    Respiratory protection is continuously required while working on the component.
Radiation/ALARA Factor:
Controlling Variables:
* Component contact dose rate
* General area dose rate TLG Services, Inc.
 
CooperNuclear Station                                    Document NO1-1590-002, Rev. 1 DecommissioningCost Analysis                                  Appendix E, Page 4 of 8 o  Site-specific requirements for maintaining radiation worker qualification (initial qualification, requalification, etc.)
* Dosimetry requirements I
Sources of VariableInformation:
* Area Survey Maps
* Site Radiation Protection Program Manual
* Radiation Work Permit Requirements Range of Radiation/ALARA FactorAdjustments:
(Note surface contamination levels are principally accounted for in protective clothing requirements and respiratory protection requirements) 0%      Component is clean and is not located in a radiological controlled area.
10%    Component is located in a radiological controlled area (General Area Radiation field < 2.5 mrem/hr).
20%    Component is located in a radiological controlled area (General Area Radiation field between 2. 5 to 15 mrem/hr).
40%    Component is located in a radiological controlled area (General Area Radiation field between 16 and 99 mrem/hr).
100% Component is located in a radiological controlled area (General Area Radiation field > 100 mrem/hr).
Protective Clothing Factor:
Controlling Variables:
* Component surface contamination levels (internal or external)
    " General area surface contamination levels
* Type of activity (wet/dry work, potential to create a surface contamination problem)
* Site specific work schedule arrangements TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002,Rev. 1 DecommissioningCost Analysis                                  Appendix E, Page 5 of 8 Sources of VariableInformation:
    " Radiation Work Permit Requirements
    " Area Survey Maps
* Site Radiation Protection Program Manual Range of Protective Clothing Factor Adjustments (alternate site-specific schedules may dictate alternateadjustments):
0%    Component is clean and is not located in a radiological controlled area.
30%    Component is clean or contaminated and is located in a surface contamination controlled area. Work is to be completed in accordance with the requirements of an RWP, which specifies a single or double set of "PC's", or "PC's" with plastics.
50%    Components is located in a surface contamination controlled area. Work is to be completed in accordance with the requirements of an RWP, which specifies "plastics" in addition to double PC's for protective clothing.
100% Component is located in a surface contamination controlled area. Work is to be completed in accordance with the requirements of an RWP, which specifies double "PC's" and double "plastics" (extremely wet or humid working environment).
Work Break Factor:
Controlling Variables:
* Site specific work schedule arrangements Sources of VariableInformation:
* Typical site work schedule Range of Work Break FactorAdjustments:
8.33% Workday schedule outlined in AIF/NESP-036 (alternate site-specific schedules may dictate alternate adjustments).
TLG Services, Inc.
 
Cooper NuclearStation                                  DocumentN01-1590-002, Rev. 1 DecommissioningCost Analysis                                Appendix E, Page 6 of 8 TABLE E-1 WORK DIFFICULTY ADJUSTMENT FACTORS Work Difficulty Factors Area Identification      Area Description  Access  Respirator    ALARA    Clothing Reactor El 1001 Area 1 Refuel floor            14%      25%          14%      30%
Reactor El 859 Area 1  Torus                    14%      25%          14%      30%
HPCI Room, B&D RHR Reactor El 859 Area 2  Room                    14%      25%          14%      30%
Reactor El 859 Area 3  B Core Spray Pump Room  14%      25%          14%      30%
Reactor El 859 Area 4  RCIC Pump Room          14%      25%          14%      30%
Reactor El 859 Area 5  A&C RHR Pump Room        14%      25%          14%      30%
CRD Hyd Control Units, Reactor El 903 Area 1  TIP Room                14%      25%          14%      30%
Reactor El 903 Area 2  Steam Tunnel            14%      25%          14%      30%
Reactor El 903 Area 3  A RHR Room              22%      25%          40%      30%
Reactor El 903 Area 4  B RHR Room              22%      25%          40%      30%
RBCCW pumps & heat Reactor El 931 Area 1  exchangers              14%      25%          14%      30%
Reactor El 931 Area 2  RWCU Recirc pump room    10%      25%          100%      30%
Reactor El 931 Area 3  RWCU heat exchangers    10%      25%          100%      30%
Reactor El 931 Area 4  4 KV Switchgear          16%        0%          0%        0%
Reactor El 931 Area 5  Roof Area                16%        0%          0%        0%
Reactor El 958 Area 1  General Area            14%      25%          14%      30%
Reactor El 958 Area 2  Fuel Pool Cooling room  10%      25%          100%      30%
Reactor El 958 Area 3  RWCU piping              22%      25%          40%      30%
Reactor El 976 Area 1  Rx Recirc MG Sets        14%      25%          14%      30%
TLG Services, Inc.
 
CooperNuclear Station                                    Document N01-1590-002, Rev. 1 DecommissioningCost Analysis                                  Appendix E, Page 7 of 8 TABLE E-1 (continued)
WORK DIFFICULTY ADJUSTMENT FACTORS Work Difficulty Factors Area Identification      Area Description    Access  Respirator    ALARA    Clothing Reactor El 976 Area 2  Standby Liquid Control    14%      25%          14%      30%
DRYWELL                Drywell                    22%      25%          40%      30%
Emergency CST's, RHR Control El 882 Area 1  service water pumps        14%      25%          14%      30%
Control El 903 Area 1  Switchgear                16%        0%          0%      0%
Control El 918 Area 1  Battery Rooms              16%        0%          0%        0%
Control Room, Computer Control El 932 Area 1  Room                      14%        0%          0%        0%
Turbine El 882 Area 1  Condenser                  14%      25%          14%      30%
Turbine El 882 Area 2  Diesel / Boiler Room roof  14%      25%          14%      30%
Condensate & FW Pumps Turbine El 882 Area 3  SJAE Room                  14%      25%          14%      30%
Turbine El 903 Area 1  FW heaters, condenser      14%      25%          14%      30%
Turbine El 903 Area 2  Generator Bus Duct        14%      25%          14%      30%
Diesels/Boilers/Water Turbine El 903 Area 3  Treatment                  10%        0%          0%        0%
Turbine El 903 Area 4  Machine Shop              16%        0%          0%        0%
Turbine El 932 Area 1  Turbine operating floor    14%      25%          14%      30%
Maintenance Office I Turbine El 932 Area 2  Storage Area              10%        0%          0%        0%
Turbine El 932 Area 3  Switchgear room            10%        0%          0%        0%
Augmented Radwaste El 877 Area 1          Waste Concentrator        14%      25%          14%      30%
Augmented Radwaste El 903 Area 1          Cask Shipping              14%      25%          14%      30%
Augmented Radwaste    Concentrator heat El 918 Area 1          exchangers                14%      25%          14%      30%
Augmented Radwaste El 929 Area 1          Roof above charcoal tanks  14%      25%          14%      30%
TLG Services, Inc.
 
CooperNuclear Station                                  Document N01-1590-002, Rev. 1 Decommissioning Cost Analysis                                Appendix E, Page 8 of 8 TABLE E-1 (continued)
WORK DIFFICULTY ADJUSTMENT FACTORS Work Difficulty Factors Area Identification      Area Description    Access  Respirator    ALARA    Clothing Radwaste El 877 Area 1  General Basement area    14%      25%          14%      30%
Spent Resin & Backwash Radwaste El 877 Area 2 Separator Tanks          14%      25%          14%      30%
Sludge & Phase Separator Radwaste El 877 Area 3 Tanks                    22%      25%          40%      30%
Drum Capping Handling Radwaste El 903 Area 1 Area                      14%      25%          14%      30%
Resin Loading Station &
Radwaste El 903 Area 2 Control Room              14%      25%          14%      30%
Radwaste El 903 Area 3 Corridor                  14%      25%          14%      30%
Radwaste El 918 Area 1 Resin Hoppers            22%      25%          40%      30%
Condensate Filter Radwaste El 918 Area 2 Demineralizer            14%      25%          14%      30%
Offices, Rad Chem Lab, Radwaste El 918 Area 3 Drum loading area        14%      25%          14%      30%
Radwaste El 934 Area 1 Resin Centrifuges        14%      25%          14%      30%
Demin removal area, Radwaste El 934 Area 2 Laundry, filter units    14%      25%          14%      30%
Radwaste El 949 Area 1 Radwaste Roof            14%      25%          14%      30%
Multi-Purpose Facility Multi-Purpose Facility    14%      25%          14%      30%
Intake                Intake                    10%        0%          0%        0%
Elevated release point, Yard Area 1            tanks                    10%        0%          0%        0%
TLG Services, Inc.
 
CooperNuclear Station                  Document N01-1590-O02,Rev. 1 DecommissioningCost Analysis                Appendix F, Page 1 of 14 APPENDIX F AREA MAPS
 
CooperNuclearStation                                                                                                          Document NO1-1590-002, Rev. I Decommissioning Cost Analysis                                                                                                      Appendix F, Page2 of 14 REACTOR BUILDING o                            @'
                              .  ....                                          I
* II_IC4              V.
I .
                              -L
* L iT ii        *.  .*,.*t.            *              /
L____ __-___.                    ___ - -- _    ............. ....
__D                        ---
41,'*
TLG Services, Inc.
 
CooperNuclear Station                                                DocumentN01-1590-002, Rev. I Appendix F, Page3 of 14 Decommissioning Cost Analysis REACTOR BUILDING
                                          %U w T-11&#xfd;1 F.I. QWQ H
                                                  ~~-976-1
                              -9 7 6  -  V-TLG Services, Inc.
 
CooperNuclear Station                                                                                              DocumentN01-1590-002, Rev. I Decommissioning Cost Analysis                                                                                          Appendix F, Page4 of 14 REACTOR BUILDING
                                                              -Al:
                                              ... . . . . .                .. . . . - - ........              _
                              -. u 4MI R-958-1 "Ti S
A Kc'~~JtF'.
_                    ,~1 -
1~
                                                                                &#xa3;~95 -1 I  -
7-,~7I                                I A:
01              C&#xfd;    S TLG Services, Inc.
 
CooperNuclear Station                        Document NO1.1590-002, Rev. 1 Appendix F, Page 5 of 14 DecommissioningCost Analysis REACTOR BUILDING TLG Services, Inc.
 
Cooper NuclearStation                            Document N01-1590-002, Rev. I DecommissioningCost Analysis                          Appendix F, Page 6 of 14 REACTOR BUILDING
                                              ~'1 TLG Services, Inc.
 
0 CooperNuclear Station                            Document N01-1590-002, Rev. I Decommissioning Cost Analysis                        Appendix F, Page 7 of 14 REACTOR BUILDING (elevation 881)
TLG Services, Inc.
 
Cooper Nuclear Station                        Document N01-1590-002,Rev. 1 Appendix F, Page 8 of 14 Decommissioning Cost Analysis REACTOR BUILDING TLG Services, Inc.
 
Cooper Nuclear Station                                                                                    Document N01.1590-002, Rev. I DecommissioningCost Analysis                                                                                  Appendix F, Page9 of 14 CONTROL AND TURBINE BUILDINGS
__                      ~              U      P~
L1J~~.
T-93,4..-
lY"    IM -  -
                                                                                  ,  %0--s I'
                                                                                    -'-    -4
                                                              -  9-31  1 T-932                                          f.SftV~
I I      g2~          M ITh I
I 0
1        ~IvfI L
TLG Services, Inc.
 
Cooper Nuclear Station                                      Document N01-1590-002,Rev. I Decommissioning Cost Analysis                                  Appendix F, Page10 of 14 CONTROL AND TURBINE BUILDINGS TLG Services, Inc.
 
CooperNuclear Station                                      Document N01-1590-002,Rev. I DecommissioningCost Analysis                                  Appendix F, Page 11 of 14 CONTROL AND TURBINE BUILDINGS TLG Services, Inc.
 
Cooper Nuclear Station                                                                                                                                                      DocumentN01-1590-002, Rev. I Appendix F, Page 12 of 14 Decommissioning Cost Analysis RADWASTE 4;A 9'n
                                    -4          --    --
Z.-~
7--
K ti T~I 7                                  ~2Th        ~
r-  ii    k
* n
                              .4 C'C
                                                    "-'-~~2            j
                                                                            -Jc-,- cL~
[B
[I--I-A...
4 ELEV 534 Or FIRY51    FLOOIR D t
                                      '55" 4
A                c L                          ILL P!A'    "C' 1q'Y -,
AR    &#xfd;-929&#xfd;W1-I]
_iE ROOF    PLAN                                                                  -      INFORMATIONONLY    454,003664
                                                                                                                                                                    *    .'
S      -*    a............    ..        ..    . ...  .    -.*
TLG Services, Inc.
 
CooperNuclear Station                                                                                                                                            Document NOI-1590-002, Rev. 1 Appendix F, Page 13 of 14 Decommissioning CostAnalysis RADWASTE N -- 4--
FA r                      Th-7                      A4__        _
                                                                -~-----I
                                                                      *r I- --11    Affi&#xfd; -
dial w
                                                                      *E *EI J!
4 Fi    'r# ~
r                                                          R ii  &#xa3; W/-0          p 4
A
                                                          -Nt:-                                          I I*l
* I*tl I:III:ITII                      I A
                                                                                  ~
 
i                                                                                          K7 J
1
                                              -  EUEVM~OeJ 4"._              1i %                  i            se-ORU*SON A                  . 4 FRtm-- EMS -it
                          -                                      ----          --                                    - "----.,-  -    -~~-  I-;-.~fL'*~z~aIm~.t-q TLG Services, Inc.
 
CooperNuclearStation              DocumentNOI-1590-002, Rev. I Decommissioning Cost Analysis        Appendix F, Page 14 of 14 YARD TLG Service4 Inc.}}

Latest revision as of 13:52, 14 January 2025

Decommissioning Cost Analysis
ML083580119
Person / Time
Site: Cooper Entergy icon.png
Issue date: 12/15/2008
From: Vanderkamp D
Nebraska Public Power District (NPPD)
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NLS2008098
Download: ML083580119 (212)


Text