#REDIRECT [[ET 16-0018, Seventh Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events.]]
| number = ML16239A397
| issue date = 08/18/2016
| title = Seventh Six-Month Status Report for the Implementation of Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events.
| author name = Mccoy J
| author affiliation = Wolf Creek Nuclear Operating Corp
| addressee name =
| addressee affiliation = NRC/Document Control Desk, NRC/NRR
| docket = 05000482
| license number =
| contact person =
| case reference number = EA-12-049, ET 16-0018
| document type = Letter, Status Report
| page count = 11
| project =
| stage = Other
}}
 
=Text=
{{#Wiki_filter:~LFCREEK    'NUCLEAR OPERATING CORPORATION August 18, 2016 Jaime H. McCoy Vice President Engineering ET 16-0018 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
 
==References:==
: 1) Letter dated March 12, 2012, from E. J. Leeds and M. R. Johnson, USNRC, to M. W. Sunseri, WCNOC, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
: 2)  NRC Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"
Revision 0, August 29, 2012
: 3)  NEI 12-06, "Diverse and Flexible Coping                        Strategies (FLEX)
Implementation Guide," Revision 0, August 2012
: 4)  Letter ET 12-0029, dated October 29, 2012, from J. P. Broschak, WCNOC, to USNRC
: 5)  Letter WO 13-0014, dated February 28, 2013, from R. A. Smith, WCNOC, to USNRC
: 6)  Letter ET 13-0027, dated August 28, 2013, from J. P. Broschak, WCNOC, to USNRC
: 7)  Letter ET 14-0011, dated February 26, 2014, from J. P. Broschak, WCNOC, to USNRC
: 8)  Letter ET 14-0024, dated August 28, 2014, from C. 0. Reasoner, WCNOC, to USNRC
: 9)  Letter ET 15-0005, dated February 24, 2015, from J. H. McCoy, WCNOC, to USNRC
: 10) Letter ET 15-0020, dated August 25, 2015, from J. H. McCoy, WCNOC, to USNRC
: 11) Letter ET 16-0008, dated February 17, 2016, from J. H. McCoy, WCNOC, to USNRC P.O. Box 411 I Burlington, KS 66839 I Phone: (620) 364-8831 An Equal Opportunity Employer M/F/HCNET
 
ET 16-0018 Page 2 of 3
 
==Subject:==
Docket No. 50-482: Wolf Creek Nuclear Operating Corporation's Seventh Six-Month Status Report for the Implementation of Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" Gentlemen:
On March 12, 2012, the Nuclear Regulatory Commission (NRC) issued Order EA-12-049 (Reference 1) to Wolf Creek Nuclear Operating Corporation (WCNOC). Reference 1 was immediately effective and directs WCNOC to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities in the event of a beyond-design-basis external event. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an Overall Integrated Plan (OIP) pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document Nuclear Energy Institute (NEI) 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide,"
(Reference 3) with clarifications and exceptions identified in Reference 2. Reference 4 provided the WCNOC initial status report regarding mitigation strategies. Reference 5 provided the WCNOC OIP. References 6, 7, 8, 9, 10, and 11 provided the first, second, third, fourth, fifth, and sixth six-month status reports for the implementation of Order EA-12-049, respectively.
Reference 1 requires submission of a status report at six-month intervals following. submittal of the OIP. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the seventh six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The attached report provides an update of milestone accomplishments since submittal of Reference 11, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
This letter contains no commitments. If you have any questions concerning this matter, please contact me at (620) 364-4156, or Cynthia R. Hafenstine (620) 364-4204.
Sincerely, r711&-
Jaime H. McCoy JHM/rlt Attachment cc:    K. M. Kennedy (NRC), w/a C. F. Lyon (NRC), w/a N. H. Taylor (NRC), w/a Senior Resident Inspector (NRC), w/a
 
ET 16-0018 Page 3 of 3 STATE OF KANSAS              )
                            ) SS COUNTY OF COFFEY )
Jaime H. McCoy, of lawful age, being first duly sworn upon oath says that he is Vice President Engineering of Wolf Creek Nuclear Operating Corporation; that he has read the foregoing document and knows the contents thereof; that he has executed the same for and on behalf of said Corporation with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.
                                                    . McCoy resident Engineering SUBSCRIBED and sworn to before me this        I~ day of ~                    , 2016.
GAYLE SHEPHEARD My Appointment Expires July 24, 2019
                                          *~~
Expiration Date    7/d.. Y /d cJ 19
 
Attachment to ET 16-0018 Page 1 of 8 Wolf Creek Nuclear Operating Corporation's (WCNOC) Seventh Six-Month Status Report for the Implementation of Order EA-12-049, "Order to Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
: 1. Introduction WCNOC developed an Overall Integrated Plan (OIP) (Reference 1), documenting the diverse and flexible strategies (FLEX), in response to Reference 2. This attachment provides an update of milestone accomplishments since submittal of the OIP, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
: 2. Milestone Accomplishments As of August 01, 2016, the following milestones have been completed since the submittal of the last six-month status report (Reference 3).
* Submittal of the seventh six-month status report (this submittal)
* Procure On-Site FLEX Equipment.
: 3. Milestone Schedule Status The following provides an update to Attachment 2 of the OIP. It provides the activity status of each item, and whether the expected completion date has changed. The dates are planning dates and are subject to change as design and implementation details are developed.
The revised milestone target completion dates do not impact the order implementation outage.
lt~licized text denotes that a Milestone was updated since the sixth six-month status update.
Revised Target Target Milestone                    Completion        Activity Status Completion Date Date Submit 60-Day Status Report                    Oct 2012          Complete              -
Submit Overall Integrated Plan                Feb 2013          Complete              -
Submit 6-Month Updates:
Update 1                                    Aug 2013          *Complete              -
Update 2                                    Feb 2014          Complete              -
Update 3                                    Aug 2014            Complete              -
Update 4                                    Feb 2015          Complete              -
Update 5                                    Aug 2015            Complete              -
Update f3                                    Feb 2016          Complete              -
Update 7                                    Aug 2016            Complete              -
FLEX Strategy Evaluation                      Apr 2013          Complete              -
Walk- Throughs or Demonstrations              Sep 2014          On-Going          Sep 2016
 
Attachment to ET 16-0018 Page 2 of 8 Revised Target Target Milestone                  Completion      Activity Status Completion Date Date Perform Staffing Analysis                    Dec 2013          Complete              -
Modifications:
Modifications Evaluation                    Apr2013          Complete              -
N-1 Walkdown                                Apr 2014          Complete              -
Design Engineering                          Jan 2014          Complete              -
Condensate Storage Tank (CST)
Oct 2015          On-Going          Oct 2016 Reinforcement - Design Engineering Implementation Outage                      Feb 2015        As Scheduled        Sep 2016 FLEX Equipment:
Procure On-Site Equipment                  Dec 2014          Complete              -
Develop Strategies with Regional Nov 2013          Complete              -
Response Center (RRC)
Install Off-Site Delivery Station (if Sep 2014          On-Going          Nov 2016 necessary)
Procedures:
Pressurized Water Reactor Owners Group (PWROG) issues NSSS-                  Jun 2013          Complete              -
specific guidelines Create WCGS FLEX Support Jun 2014          Complete              -
Guidelines (FSG)
Create Maintenance Procedures              Jul2014            Started          Oct 2016 Training:
Develop Training Plan                      Jul2014          Complete              -
Training Complete                          Feb 2015          On-Going          Sep 2016 Submit Completion Report*                    Mar 2015          Started          Jan 2017
*The report will be submitted 90 days after the completion of Refueling Outage 21.
: 4. Changes to Compliance Method Since the submittal of Reference 3, WCNOC has completed an evaluation for compliance to NEI 12-06, Revision 2 (Reference 18) and will be in compliance upon completion of FLEX implementation activities.
: 5. Need for Relief/Relaxation and Basis for the Relief/Relaxation WCNOC requested (Reference 4) relaxation for the implementation of Order EA-12-049. The Wolf Creek Generating Station (WCGS) FLEX strategies rely on the low leakage Reactor Coolant Pump (RCP) seals and a seismic and missile protected Condensate Storage Tank
 
Attachment to ET 16-0018 Page 3 of 8.
(CST). Compliance with the original Order EA-12-049 schedule requirement for full completion and implementation of mitigation strategies would have resulted in hardship or unusual difficulty without a compensating increase in the level of safety.
An extension of one additional refueling cycle was requested in Reference 4. Reference 10 approved the relaxation of the order implementation date. This moves the implementation date to completion of the fall 2016 refueling outage, which is still within the maximum allowed timeframe of December 2016.
: 6. Open Items from Overall Integrated Plan and Interim Staff Evaluation The following table provides a summary of the open items documented in the OIP and the status of each item. Italicized text denotes that an Open Item was updated since the sixth six-month status update.
Open Overall Integrated Plan Open Item                          Status Item#
Finalize the location of the FLEX        Closed - The locations of the two FLEX storage building. The deployment          storage buildings have been selected.
routes, distances, and times provided    Construction of both buildings has been in this report are bounded for the        completed and the deployment routes currently proposed locations but will    and distances have been confirmed.
011 be updated as necessary.                The verification and validation process (Milestone: Walk-Throughs or Demonstrations) will confirm that deployment times are consistent with analysis values.
Perform containment evaluation,          Closed - The Generation of Thermal using GOTHIC, based on the                Hydraulic Information for Containment boundary conditions described in        (GOTHIC) analysis has been completed.
Section 2 of NEI 12-06. Based on the    The containment structure and 012    results of this evaluation, required    instrumentation inside containment actions to ensure maintenance of        critical to coping with an Extended Loss containment integrity and required        of ac Power (ELAP) event are shown to instrument function will be developed. be acceptable following a 7-day duration (Reference 5).
 
Attachment to ET 16-0018 Page 4 of 8 Open Overall Integrated Plan Open Item                      Status Item#
The current CST and CST pipe chase    Ongoing - An evaluation was performed are non-seismic. Therefore, WCNOC      to show that the existing CST meets is currently pursuing two options; the current licensing basis for seismic and qualification and hardening of the    tornado missile hazards (References 6, existing CST, or the construction of a 7, 8, and 9).
new 670, 000 gallon seismically Design Change Package (DCP) 14277 is qualified and missile protected CST.
being implemented to harden the CST by One of these options must be welding a layer of plating around the tank completed before the volume of the in order to withstand a Safe Shutdown CST can be credited.
Earthquake. Necessary modification work will be complete by the end of Refuel Outage 21.
013 The CST pipe chase has been evaluated and can withstand the current licensing basis for seismic and tornado missile hazards (Reference 12).
DCP 14864 is being implemented to harden the CST Valve House. The valve house will be replaced with a metal frame steel structure built to withstand missile hazards and Safe Shutdown Earthquake. Necessary modification work will be complete by the end of Refuel Outage 21.
Modify the RWST to protect it from    Closed - Identified an alternate source tornado missiles or identify a borated strategy using the Boric Acid Tanks in source that is protected for tornados  the Auxiliary Building as the primary 014 and can be utilized to provide core    source and Refueling Water Storage cooling when steam generators are      Tank (RWST) as the alternate source.
not available.
For non-Class 1E instrumentation that  Closed - The final plant strategies do not will be repowered using a temporary    rely on any equipment that is not 015    battery, an analysis will need to be  powered by a Class 1E source.
performed to determine battery life and frequency of replacing battery.
 
Attachment to ET 16-0018 Page 5 of 8 The method for isolating              Closed - It was confirmed that the accumulators during Reactor Coolant    accumulator isolation valves are on a System [RCS] inventory control has    bus that is being re-powered for the 016      not been finalized.                    primary electrical FLEX strategy.
For the alternate electrical FLEX strategy, nitrogen injection will be prevented by venting the accumulators.
The method for repowering the SFP      Closed - Powering a Spent Fuel Pool cooling pumps has not been finalized.  (SFP) cooling pump is a Phase 3 017 action. The pump will be re-powered by a 4160V generator provided by the RRC.
The following table provides a summary of the open items documented in the Interim Staff Evaluation Report (Reference 15) and the status of each item. Italicized text denotes that an Open lt~m was updated since the sixth six-month status update.
Open ISE Open Item                                Status Item#
Verify that the potential for          Closed - A recent re-evaluation of the liquefaction considerations to impede  WCNOC seismic Probabilistic Risk
      --    movement of FLEX equipment            Assessment (PRA) analysis has following a severe seismic event at    confirmed that liquefaction is not an 3.1.1.2.A    Wolf Creek are evaluated.              issue on-site (References 16 and. 17).
Thus, there will be no liquefaction concerns for impeding the movement of FLEX equipment on-site following a severe seismic event.
Verify that power that might be        Closed - The deployment of FLEX required to deploy equipment, such    equipment will not require external 3.1.1,2.B    as power to open roll up doors at a    power. Equipment such as roll up doors storage location, is evaluated.        will have provisions to be opened manually.
Verify resolution of the generic      Closed - WCNOC will conform to the concern associated with the modeling  position expressed by the NRC staff in
  \          of the timing and uniformity of the    the letter dated January 8, 2014 to the mixing of a liquid boric acid solution PWROG (Reference 13). The NRC injected into the RCS under natural    letter states that the NRC staff has 3.2.1.8.A conditions potentially involving two-    reviewed the information submitted to
            . phase flow.                            date and concluded that use of the industry approach in PWROG letter OG-13-284 dated August 19, 2013, (Reference 14) is acceptable with clarifications listed in the letter.
 
Attachment to ET 16-0018 Page 6 of 8 Closed - The FLEX 500kW generator Verify that instrumentation that will be used to power 480 Vac Load Centers used to monitor portable/FLEX NG001 and NG002 are provided with electrical power equipment ensures complete protection. The generators that: 1) the electrical equipment built in voltage regulator provides voltage remains protected (from an electrical control and generator protection.
power standpoint- e.g., power Protection consists of but is not limited fluctuations) and, 2) the operator is to: Generator Over and Undervoltage, provided with accurate information to Loss of Excitation, Instantaneous Field maintain core cooling, containment, Overcurrent, Over Excitation and Under and spent fuel cooling strategies.
Frequency.
The FLEX 500kW generator also includes a separate Electronic Modular Control Panel (EMCP) 4.4 Generator Controller. This unit provides additional protection including but not limited to:
Generator phase sequence, Over/Under voltage (27159), Over/Under Frequency (81 O/U), Reverse power (32),
Overcurrent (50151), and Current Balance (46).
The protections from these two (2) mdependent devices are active at all times and prevent the generator set from 3.2.4.8.B                                            generating power that fluctuates in amplitude or is low or high frequency.
The generic FLEX Support Guidelines (FSGs) developed via the PWROG contain sufficient guidance to control the plant using installed and/or portable FLEX equipment based on the requirement to monitor actual plant processes. The DRAFT FSGs conform to the requirements detailed in the generic FSGs by monitoring installed plant instruments required for FLEX coping via Draft EMG C-0, Loss of All AC Power- Attachment H, Assessment Of Vital Instruments.
Additionally, Draft Procedure EMG C-0 Attachment H directs initiation of FSG-l Loss Of Vital Instrumentation Or Controi Power, if minimum plant instruments are not available. Draft FSG-7 provides guidance for plant control when certain instruments are lost. FSG-7 also provides a primary and backup method for obtaining process readings using oortable instruments.
 
Attachment to ET 16-0018 Page 7 of 8 Verify the licensee has fully          Closed - Our National SAFER Response addressed considerations (2) through  Center (NSRC) playbook is complete (10) of NEI 12-06, Section 12.2,      and was loaded onto the STARS E-Minimum Capability of Off-Site        portal.
3.4.A      Resources, which requires each site to establish a means to ensure the necessary resources will be available from off-site.
References
: 1. WCNOC Letter WO 13-0014, "Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," February 28, 2013. ADAMS Accession No. ML13070A026.
: 2. Letter from E. J. Leeds and M. R. Johnson, USNRC, to M. W. Sunseri, WCNOC, "Issuance of Order to Modify Licenses with Regard to Requirements For Mitigation Strategies for Beyond-Design-Basis External Events," March 12, 2012.          ADAMS Accession No. ML12054A735.
: 3. WCNOC Letter ET 16-0008, "Wolf Creek Nuclear Operating Corporation's Sixth Six-Month .
Status Report for the Implementation of Order EA-12-049, 'Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events'," February 17, 2016. ADAMS Accession No. ML16055A113.
: 4. WCNOC Letter WO 14-0023, "Request for Schedule Relaxation of NRC Order EA-12-049, Requirement IV.A.2, at Wolf Creek Generating Station," March 31, 2014. ADAMS Accession No. ML14097A072.
: 5. CN-OA-13-7, Revision 1, "Wolf Creek ELAP Containment Heat-Up," June 16, 2014.
: 6. 020542.13.01-C-001, Revision 0, "Condensate Storage Tank and Refueling Water Storage Tanks Tornado Missile Impact Analy~es," November 2013.
: 7. 020542.13.01-C-002, Revision 0, "Structural Analysis of Condensate Storage Tank,"
November 2013.
: 8. 020542.13.01-C-003, Revision 0, "Condensate Storage Tank Valve House and Refueling Water Storage Tank Valve House Missile Impact and Seismic Analysis," December 2013.
: 9. 020542.13.01-C-004, Revision 0, "Condensate Storage Tank Pipe Stress Analysis,"
December 2013.
 
Attachment to ET 16-0018 Page 8 of 8
*
: 10. Letter from E. J. Leeds, USN RC, to A. C. Heflin, WCNOC, "Wolf Creek Generating Station, Unit 1 - Relaxation of the Schedule Requirements for Order EA-12-049 'Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events'," May 20,
* 2014.            ADAMS Accession No.
ML14104A029.
: 11. 020542.13.01-C-008, Revision 0, "Refueling Water Storage Tank Pipe Stress Analysis,"
December 2013.
: 12. 020542.13.01-C-009, Revision 0, "Condensate Storage Tank Pipe Tunnel Evaluation,"
December 2013.
: 13. Letter from J. Davis, USNRC, to N. J. Stringfellow, PWROG, January 8, 2013. ADAMS Accession No. ML13276A183.
: 14. PWROG Letter OG 13-284, "Submittal of LTR-FSE-13-46, Revision 0, P-Attachment, "Westinghouse Response to NRC Generic Request for Additional Information (RAI) on Boron Mixing in Support of the Pressurized Water Reactor Owners Group (PWROG)"
(Proprietary) (PA-ASC-1184)," August 19, 2013.
: 15. Letter from J. S. Bowen, USNRC, to A. C.- Heflin, WCNOC 1 "Wolf Creek Generating Station, Unit 1 - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies)(TAC NO. MF0788)," February 6, 2014.
ADAMS Accession No. ML14002A190.
: 16. GEi Consultants for Stevenson & Associates, "Liquefaction Evaluation - Power Block Structures Wolf Creek Nuclear Generating Station," July 9, 2015.
: 17. GEi Consultants for Stevenson & Associates, "Liquefaction Evaluation - ESW Pumphouse and Marine Discharge Structure Wolf Creek Nuclear Generating Station," July 15, 2015.
: 18. NEI 12-06, Revision 2, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," December 2015.}}