ML041070068: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(4 intermediate revisions by the same user not shown)
Line 3: Line 3:
| issue date = 01/06/2004
| issue date = 01/06/2004
| title = Initial Admin SRO JPM 3821.0102
| title = Initial Admin SRO JPM 3821.0102
| author name = Anderson J, Pickley T, Ryan P K
| author name = Anderson J, Pickley T, Ryan P
| author affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| author affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| addressee name =  
| addressee name =  
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:CLINTON POWER STATIONJob Performance MeasureReview a completed SRV actuation reportJPM Number: 3821.0102Revision Number: 00 Date: 7/28/03Developed By:T. Pickley 7/24/03InstructorDateValidated By:J. Anderson 10/16/03SME or InstructorDateReview By:P. Ryan 8/18/03Operations RepresentativeDate JOB PERFORMANCE MEASURE VALIDATION CHECKLISTNOTE:All steps of this checklist should be performed upon initial validation. Prior to JPM usage, revalidate JPM using steps 8 through 11 below.________1.Task description and number, JPM description and number areidentified.________2.Knowledge and Abilities (K/A) references are included.________3.Performance location specified. (in-plant, control room, orsimulator)________4.Initial setup conditions are identified.
{{#Wiki_filter:CLINTON POWER STATION Job Performance Measure Review a completed SRV actuation report JPM Number: 3821.0102 Revision Number: 00 Date: 7/28/03 Developed By:
________5.Initiating and terminating cues are properly identified.
T. Pickley 7/24/03 Instructor Date Validated By:
________6.Task standards identified and verified by SME review.
J. Anderson 10/16/03 SME or Instructor Date Review By:
________7.Critical steps meet the criteria for critical steps and are identifiedwith an asterisk (*).________8.Verify the procedure referenced by this JPM matches the mostcurrent revision of that procedure:
P. Ryan 8/18/03 Operations Representative Date
Procedure Rev. _____ Date _____________________9.Pilot test the JPM:a. verify cues both verbal and visual are free of conflict, and
 
: b. ensure performance time is accurate.________10.If the JPM cannot be performed as written with properresponses, then revise the JPM.________11.When JPM is revalidated, SME or Instructor sign and date JPMcover page.SME/InstructorDateSME/InstructorDateSME/InstructorDate CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.
3831.0102                                 REVISION: 00Page 3 of 1Revision Record (Summary)1.Revision 00,This is a new JPM CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
Prior to JPM usage, revalidate JPM using steps 8 through 11 below.
3831.0102                                 REVISION: 00Page 4 of 1Operator's Name:SSN:Job Title:   o   NLO   o   RO   o   SRO   o   STA   o   SRO CertJPM Title/Number: 3831.0101, Review a completed SRV actuation report Revision Number:
: 1. Task description and number, JPM description and number are identified.
00 Task Number and Title: 383101.01, Complete Control Room ac tions to document data onfailures and actuation's of the Safety Relief Valves in the Main Steam System and to generate reports required by the Nuclear Regulatory CommissionSuggested Testing Environment:
: 2. Knowledge and Abilities (K/A) references are included.
Any     Actual Testing Environment:
: 3. Performance location specified. (in-plant, control room, or simulator)
n   Simulator   o   Plant   o   Control RoomTesting Method:oSimulateFaulted:oYesnPerformAlternate Path:oNoTime Critical:oNoEstimated Time to Complete:16
: 4. Initial setup conditions are identified.
_minutesActual Time Used:
: 5. Initiating and terminating cues are properly identified.
: 6. Task standards identified and verified by SME review.
: 7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).
: 8. Verify the procedure referenced by this JPM matches the most current revision of that procedure:
Procedure Rev. _____ Date _____________
: 9. Pilot test the JPM:
: a. verify cues both verbal and visual are free of conflict, and
: b. ensure performance time is accurate.
10.If the JPM cannot be performed as written with proper responses, then revise the JPM.
11.When JPM is revalidated, SME or Instructor sign and date JPM cover page.
SME/Instructor Date SME/Instructor Date SME/Instructor Date
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 3 of 1 Revision Record (Summary)
: 1. Revision 00, This is a new JPM  
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 4 of 1 Operators Name:
SSN:
Job
 
==Title:==
o NLO o RO o SRO o STA o SRO Cert JPM Title/Number: 3831.0101, Review a completed SRV actuation report Revision Number: 00 Task Number and
 
==Title:==
383101.01, Complete Control Room actions to document data on failures and actuation's of the Safety Relief Valves in the Main Steam System and to generate reports required by the Nuclear Regulatory Commission Suggested Testing Environment: Any Actual Testing Environment: n Simulator o Plant o Control Room Testing Method: o Simulate Faulted: o Yes n Perform Alternate Path: o No Time Critical: o No Estimated Time to Complete: 16 _minutes Actual Time Used:
minutes
minutes


Line 35: Line 58:


==SUMMARY==
==SUMMARY==
:Were all the Critical Elements performed satisfactorily?oYesoNoThe operator's performance was evaluated against the standards contained in this JPM, and has been determined to be:oSatisfactoryoUnsatisfactoryComments: Evaluator's Name: __________________________
Were all the Critical Elements performed satisfactorily?
CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
o Yes o
3831.0102                                 REVISION: 00Page 5 of 1Evaluator's Signature:
No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be:
o Satisfactory o
Unsatisfactory Comments:
Evaluators Name: __________________________
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 5 of 1 Evaluators Signature:
Date:
Date:
CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
3831.0102                                  REVISION: 00Page 6 of 1READ TO THE OPERATORI will explain the initial conditions, which step(s) to s imulate or discuss, and provide the initiating cues. When you complete the task successfully, the objective of this Job Performance Measure will be satisfied.SIMULATOR SET-UP CONDITIONS
: NoneTASK STANDARDS
:The SRV has been identified as leaking and the failure mode is coded incorrectly.TOOLS, EQUIPMENT, OTHER SPECIAL REQUIREMENTS
: NonePROCEDURAL/REFERENCES
:CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TESTCPS 3831.01, SAFETY RELIEF VALVE REPORTEVALUATOR INSTRUCTIONS
:Amplifying cues are provided within the JPM steps. Provide the operator with the following:CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TESTCPS 9056.02C001, SAFETY/RELIEF VALVE MANUAL ACTUATION CHECKLISTCPS 3831.01, SAFETY RELIEF VALVE REPORTCPS 3831.01D002, ACTUATION LOGDCS Display 6D-04DCS Display D05AD1DCS Display DD5BD3SRV Tailpipe temperature graphINITIAL CONDITIONS AND INITIATING CUE
: CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST and CPS 3831.01, SAFETYRELIEF VALVE REPORT have been complete
: d. You are to review and approve them.START TIME:
CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
3821.0102REVISION: 00Page 7 of 1 CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
3821.0102REVISION: 00Page 8 of 1
==========================================================================PERFORMANCE INFORMATIONCritical steps are denoted with an asterisk (*)
to the left of the step number and appear in BOLDEDletters. Failure to meet the standards for a critical step constitutes failure of the Job Performance


Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM.
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 6 of 1 READ TO THE OPERATOR I will explain the initial conditions, which step(s) to simulate or discuss, and provide the initiating cues.
==========================================================================PERFORMANCE STEPS*1Reviews through block 309StandardDetermines that block 309 is incorrect, the tail pipe has not returned tonormal and that the SRV is leaking.CUEComments SAT       UNSAT     Comment Number2Reviews blocks 310 through 314StandardDetermines block 314 is coded incorrectly and s hould be coded as an "A"and/or "E" at this time.CUEComments SAT       UNSAT     Comment Number CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
When you complete the task successfully, the objective of this Job Performance Measure will be satisfied.
3821.0102REVISION: 00Page 9 of 1 CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
SIMULATOR SET-UP CONDITIONS:
3821.0102REVISION: 00Page 10 of 1STOP TIME:_____________TERMINATING CUES:The SRV actuation log has been reviewed.K/A REFERENCE NUMBERSImportance RatingK/A SYSTEM NUMBERK/A NUMBER ROSRO2.1.323.43.82.1.252.83.1 CLINTON POWER STATIONSYSTEM JPMJPM NUMBER:
None TASK STANDARDS:
3821.0102REVISION: 00Page 11 of 1INITIATING CUECPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST and CPS 3831.01, SAFETY RELIEFVALVE REPORT have been completed.
The SRV has been identified as leaking and the failure mode is coded incorrectly.
You are to review and approve them.
TOOLS, EQUIPMENT, OTHER SPECIAL REQUIREMENTS:
AttachmentsPage 12 of 1 AttachmentsPage 13 of 1 AttachmentsPage 14 of 1 AttachmentsPage 15 of 1}}
None PROCEDURAL/
 
==REFERENCES:==
CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST CPS 3831.01, SAFETY RELIEF VALVE REPORT EVALUATOR INSTRUCTIONS:
Amplifying cues are provided within the JPM steps.
Provide the operator with the following:

CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST

CPS 9056.02C001, SAFETY/RELIEF VALVE MANUAL ACTUATION CHECKLIST

CPS 3831.01, SAFETY RELIEF VALVE REPORT

CPS 3831.01D002, ACTUATION LOG

DCS Display 6D-04

DCS Display D05AD1

DCS Display DD5BD3

SRV Tailpipe temperature graph INITIAL CONDITIONS AND INITIATING CUE:
CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST and CPS 3831.01, SAFETY RELIEF VALVE REPORT have been completed. You are to review and approve them.
START TIME:
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 7 of 1
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 8 of 1
 
==========================================================================
PERFORMANCE INFORMATION Critical steps are denoted with an asterisk (*) to the left of the step number and appear in BOLDED letters. Failure to meet the standards for a critical step constitutes failure of the Job Performance Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM.
 
==========================================================================
PERFORMANCE STEPS
*1 Reviews through block 309 Standard Determines that block 309 is incorrect, the tail pipe has not returned to normal and that the SRV is leaking.
CUE Comments SAT UNSAT Comment Number 2
Reviews blocks 310 through 314 Standard Determines block 314 is coded incorrectly and should be coded as an A and/or E at this time.
CUE Comments SAT UNSAT Comment Number
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 9 of 1
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 10 of 1 STOP TIME:
TERMINATING CUES:
The SRV actuation log has been reviewed.
K/A REFERENCE NUMBERS Importance Rating K/A SYSTEM NUMBER K/A NUMBER RO SRO 2.1.32 3.4 3.8 2.1.25 2.8 3.1
 
CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 11 of 1 INITIATING CUE CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST and CPS 3831.01, SAFETY RELIEF VALVE REPORT have been completed. You are to review and approve them.
 
Attachments Page 12 of 1
 
Attachments Page 13 of 1
 
Attachments Page 14 of 1
 
Attachments Page 15 of 1}}

Latest revision as of 03:34, 16 January 2025

Initial Admin SRO JPM 3821.0102
ML041070068
Person / Time
Site: Clinton Constellation icon.png
Issue date: 01/06/2004
From: James Anderson, Pickley T, Ryan P
Exelon Generation Co, Exelon Nuclear
To:
Office of Nuclear Reactor Regulation
References
-RFPFR, 50-461/04-301, JPM 3821.0102, Rev 00 50-461/04-301
Download: ML041070068 (15)


Text

CLINTON POWER STATION Job Performance Measure Review a completed SRV actuation report JPM Number: 3821.0102 Revision Number: 00 Date: 7/28/03 Developed By:

T. Pickley 7/24/03 Instructor Date Validated By:

J. Anderson 10/16/03 SME or Instructor Date Review By:

P. Ryan 8/18/03 Operations Representative Date

JOB PERFORMANCE MEASURE VALIDATION CHECKLIST NOTE: All steps of this checklist should be performed upon initial validation.

Prior to JPM usage, revalidate JPM using steps 8 through 11 below.

1. Task description and number, JPM description and number are identified.
2. Knowledge and Abilities (K/A) references are included.
3. Performance location specified. (in-plant, control room, or simulator)
4. Initial setup conditions are identified.
5. Initiating and terminating cues are properly identified.
6. Task standards identified and verified by SME review.
7. Critical steps meet the criteria for critical steps and are identified with an asterisk (*).
8. Verify the procedure referenced by this JPM matches the most current revision of that procedure:

Procedure Rev. _____ Date _____________

9. Pilot test the JPM:
a. verify cues both verbal and visual are free of conflict, and
b. ensure performance time is accurate.

10.If the JPM cannot be performed as written with proper responses, then revise the JPM.

11.When JPM is revalidated, SME or Instructor sign and date JPM cover page.

SME/Instructor Date SME/Instructor Date SME/Instructor Date

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 3 of 1 Revision Record (Summary)

1. Revision 00, This is a new JPM

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 4 of 1 Operators Name:

SSN:

Job

Title:

o NLO o RO o SRO o STA o SRO Cert JPM Title/Number: 3831.0101, Review a completed SRV actuation report Revision Number: 00 Task Number and

Title:

383101.01, Complete Control Room actions to document data on failures and actuation's of the Safety Relief Valves in the Main Steam System and to generate reports required by the Nuclear Regulatory Commission Suggested Testing Environment: Any Actual Testing Environment: n Simulator o Plant o Control Room Testing Method: o Simulate Faulted: o Yes n Perform Alternate Path: o No Time Critical: o No Estimated Time to Complete: 16 _minutes Actual Time Used:

minutes

References:

EVALUATION

SUMMARY

Were all the Critical Elements performed satisfactorily?

o Yes o

No The operators performance was evaluated against the standards contained in this JPM, and has been determined to be:

o Satisfactory o

Unsatisfactory Comments:

Evaluators Name: __________________________

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 5 of 1 Evaluators Signature:

Date:

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3831.0102 REVISION: 00 Page 6 of 1 READ TO THE OPERATOR I will explain the initial conditions, which step(s) to simulate or discuss, and provide the initiating cues.

When you complete the task successfully, the objective of this Job Performance Measure will be satisfied.

SIMULATOR SET-UP CONDITIONS:

None TASK STANDARDS:

The SRV has been identified as leaking and the failure mode is coded incorrectly.

TOOLS, EQUIPMENT, OTHER SPECIAL REQUIREMENTS:

None PROCEDURAL/

REFERENCES:

CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST CPS 3831.01, SAFETY RELIEF VALVE REPORT EVALUATOR INSTRUCTIONS:

Amplifying cues are provided within the JPM steps.

Provide the operator with the following:



CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST



CPS 9056.02C001, SAFETY/RELIEF VALVE MANUAL ACTUATION CHECKLIST



CPS 3831.01, SAFETY RELIEF VALVE REPORT



CPS 3831.01D002, ACTUATION LOG



DCS Display 6D-04



DCS Display D05AD1



DCS Display DD5BD3



SRV Tailpipe temperature graph INITIAL CONDITIONS AND INITIATING CUE:

CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST and CPS 3831.01, SAFETY RELIEF VALVE REPORT have been completed. You are to review and approve them.

START TIME:

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 7 of 1

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 8 of 1

==============================================================

PERFORMANCE INFORMATION Critical steps are denoted with an asterisk (*) to the left of the step number and appear in BOLDED letters. Failure to meet the standards for a critical step constitutes failure of the Job Performance Measure. The sequence of steps is assumed unless denoted in the comments section of the JPM.

==============================================================

PERFORMANCE STEPS

  • 1 Reviews through block 309 Standard Determines that block 309 is incorrect, the tail pipe has not returned to normal and that the SRV is leaking.

CUE Comments SAT UNSAT Comment Number 2

Reviews blocks 310 through 314 Standard Determines block 314 is coded incorrectly and should be coded as an A and/or E at this time.

CUE Comments SAT UNSAT Comment Number

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 9 of 1

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 10 of 1 STOP TIME:

TERMINATING CUES:

The SRV actuation log has been reviewed.

K/A REFERENCE NUMBERS Importance Rating K/A SYSTEM NUMBER K/A NUMBER RO SRO 2.1.32 3.4 3.8 2.1.25 2.8 3.1

CLINTON POWER STATION SYSTEM JPM JPM NUMBER: 3821.0102 REVISION: 00 Page 11 of 1 INITIATING CUE CPS 9056.02, SAFETY/RELIEF VALVE ACTUATION TEST and CPS 3831.01, SAFETY RELIEF VALVE REPORT have been completed. You are to review and approve them.

Attachments Page 12 of 1

Attachments Page 13 of 1

Attachments Page 14 of 1

Attachments Page 15 of 1