ML14107A106: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 1: Line 1:
{{Adams
#REDIRECT [[05000369/LER-2013-001]]
| number = ML14107A106
| issue date = 07/22/2013
| title = LER 13-001-01 for McGuire Nuclear Station, Unit 1, Valid Actuation of Reactor Protection and Auxiliary Feedwater Systems
| author name = Capps S D
| author affiliation = Duke Energy Corp
| addressee name =
| addressee affiliation = NRC/Document Control Desk, NRC/NRR
| docket = 05000369
| license number =
| contact person =
| case reference number = M-13-01728
| document report number = LER 13-001-01
| document type = Letter, Licensee Event Report (LER)
| page count = 8
}}
 
=Text=
{{#Wiki_filter:Steven D. Capps Vice President ENERGY. McGuire Nuclear Station Duke Energy MG01VP 1 12700 Hagers Ferry Road Huntersville, NC 28078 o: 980.875.4805 f: 980.875.4809.Steven.Capps@duke-energy.com July 22, 2013 10 CFR 50.73 U.S. Nuclear Regulatory Commission Washington, D.C. 20555 ATTENTION:
Document Control Desk
 
==Subject:==
Duke Energy Carolinas, LLC McGuire Nuclear Station, Unit 1 Docket No. 50-369 Licensee Event Report 369/2013-01, Revision 1 Problem Investigation Process Number M-13-01728 Pursuant to 10 CFR 50.73 Sections (a) (1) and (d), attached is Licensee Event Report (LER) 369/2013-01, Revision 1, regarding valid actuations of Unit 1 Reactor Protection and Auxiliary Feedwater Systems.This event was originally reported on April 22, 2013. Revision I is being submitted to correct a minor editorial error involving page numbering.
This has been entered into the McGuire Corrective Action Program as PIP M-13-07093.
This report is being submitted for Unit I in accordance with 10 CFR 50.73 (a) (2) (iv) (A),"Any event or condition that resulted in manual or automatic actuation of any of the systems listed in paragraph (a) (2) (iv) (B)." The 10 CFR 50.73 (a) (2) (iv) (B) systems to which the requirements of paragraph (a) (2) (iv) (A) applied was the Reactor Protection System and the Auxiliary Feedwater System.This event is considered to have a low risk impact and no significance with respect to the health and safety of the public. There are no regulatory commitments contained in this LER.If questions arise regarding this LER, contact Lee A Hentz at 980-875-4187.
Sincerely, Steven D. C ps Attachment www.duke-energy.com U.S. Nuclear Regulatory Commission July 22, 2013 Page 2 cc: V. M. McCree Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave.NE Suite 1200, 30303-1257 J. C. Paige Project Manager U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, MD 20852-2738 Mail Stop 0-8 G9A J. Zeiler NRC Senior Resident Inspector McGuire Nuclear Station W. L. Cox III, Section Chief North Carolina Department of Environment and Natural Resources Division of Environmental Health Radiation Protection Section 1645 Mail Service Center Raleigh, NC 27699-1645 NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0104 EXPIRES: 10/31/2013 (10-2010)
Estimated burden per response to comply with this mandatory collection request: 80 hours.Reported lessons learned are incorporated into the licensing process and fed back to industry.Send comments regarding burden estimate to the FOIAPrivacy Section (T-5 F53), U.S. Nuclear Regulatory Commission.
Washington, DC 20555-0001, or by internet e-mail to infocollacts Resource@rrc.gov.
and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-LICENSEE EVENT REPORT (LER) 10202, (3150-0104), Office ot Management and Budget, Washington, DC 20503. If a means used (See reverse for required number of to impose an information collection does not display a currently valid OMB control number, the digitsecharacters for each block) NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
: 1. FACILITY NAME 2. DOCKET NUMBER 3. PAGE McGuire Nuclear Station, Unit 1 05000- 0369 1 OF 6 4. TITLE Valid Actuation of Unit 1 Reactor Protection and Auxiliary Feedwater Systems 5. EVENT DATE 6. LER NUMBER 7. REPORT DATE 8. OTHER FACILITIES INVOLVED SEQUENTIAL I FACILITY NAME DOCKET NUMBER MO DAY YEAR YEAR NUMBER I NO MO DAY YEAR None 05000 FACILITY NAME DOCKET NUMBER 02 21 2013 2013 01 07 22 2013 None 05000 11. THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR §: (Check all that apply)9. OPERATING MODE[1 20.2201(b)
[I 20.2203(a)(3)(i)
C1 50.73(a)(2)(i)(C)
[I 50.73(a)(2)(vii) 1 El 20.2201(d)
El 20.2203(a)(3)(ii)
El 50.73(a)(2)(ii)(A)
[I 50.73(a)(2)(viii)(A) 0 20.2203(a)(1)
[I 20.2203(a)(4)
El 50.73(a)(2)(ii)(B)
[I 50.73(a)(2)(viii)(B)
El 20.2203(a)(2)(i)
El 50.36(c)(1)(i)(A)
Dl 50.73(a)(2)(iii)
El 50.73(a)(2)(ix)(A)
[E 20.2203(a)(2)(ii)
El 50.36(c)(1)(ii)(A) 0 50.73(a)(2)(iv)(A)
[I 50.73(a)(2)(x)
: 10. POWER LEVEL El 20.2203(a)(2)(iii)
[I 50.36(c)(2)
El 50.73(a)(2)(v)(A)
El 73.71(a)(4)
El 20.2203(a)(2)(iv)
EU 50.46(a)(3)(ii)
[I 50.73(a)(2)(v)(B)
El 73.71(a)(5)
[I 20.2203(a)(2)(v)
[I 50.73(a)(2)(i)(A)
[I 50.73(a)(2)(v)(C) 0 OTHER 1 00 El 20.2203(a)(2)(vi)
[E 50.73(a)(2)(i)(B)
El 50.73(a)(2)(v)(D)
E] Specify in Abstract below or in NRC Form 366A 12. LICENSEE CONTACT FOR THIS LER FACILITY NAME TELEPHONE NUMBER (Include Area Code)Lee A Hentz, Regulatory Affairs 1 980-875-4187
: 13. COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT MANU- REPORTABLE I MANU- REPORTABLE CAUSE SYSTEM COMPONENT FACTURER TO EPIX I CAUSE SYSTEM COMPONENT FA CTURER TO EPIX KA PS U075 /A 14. SUPPLEMENTAL REPORT EXPECTED 15. EXPECTED MONTH DAY YEAR SUBMISSION IYES (if yes, complete EXPECTED SUBMISSION DATE) xIxlNODT 16. ABSTRACT On February 21, 2013 Unit 1 tripped (Reactor Protection System actuation) from 100% power as a result of a turbine trip signal initiated after operating main feedwater system (CF) pumps tripped. The CF pumps tripped as a result of the operating Condensate Booster Pumps (CBPs) tripping on emergency low suction pressure following an inadvertent trip of the 1C3 Heater Drain Tank (HDT) Pump. The 1A and Turbine Driven Auxiliary Feedwater System (CA) pumps automatically started (Engineered Safety Feature actuation) as designed following the CF pumps tripping.
The 1 B CA pump was removed from service prior to the event to support maintenance.
The 1 C3 HDT Pump was inadvertently tripped by an operator investigating the cause of an extinguished "on" indicating light bulb which is part of the HDT pump start/stop pushbutton switch. The cause of the HDT pump trip was attributed to an administrative procedure that did not explicitly prohibit intrusive investigation of light bulbs having transient/trip potential.
The HDT pump trip caused a secondary system pressure transient that resulted in premature tripping of the CBPs which ultimately led to the reactor trip and CA pump auto-start.
The CBP trip was caused by inadequate venting of CBP Suction Header Pressure Switches (PS) and an accumulation of air voids in PS process tubing due to an inadequate slope configuration.
Immediate actions were taken to revise an administrative procedure to prevent intrusive investigation of bulbs having transient/trip/
potential.
The slope of process tubing to the CBP suction header PSs was corrected and the PSs were vented, calibrated, and verified functional.
Planned action will be taken to ensure the condensate system (CM) is filled and vented and a hotwell pump is running prior to venting the CBP suction header PSs.
NRC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION (10-2010)LICENSEE EVENT REPORT (LER)1. FACILITY NAME 2. DOCKET 6. LER NUMBER 3. PAGE Y SEQUENTIAL J REVISION YEAR NUMBER NUMBERI McGuire Nuclear Station, Unit 1 05000 369 2013 _ 01 01 2 OF 6 I 17. NARRATIVE BACKGROUND The following information is provided to assist readers in understanding the event described in this LER.Applicable Energy Industry Identification
[EIIS] system and component codes are enclosed within brackets.McGuire Nuclear Station unique system and component identifiers are contained within parentheses.
Reactor Protection System [JC] (IPE): The Reactor Protection System keeps the Reactor operating within a safe operating range by automatically shutting down the Reactor whenever the limits of the operating range are approached by monitoring process variables.
Whenever a direct or calculated process variable exceeds a setpoint the Reactor is automatically tripped to protect against fuel cladding damage or loss of Reactor Coolant System (NC)integrity.
Station operators may elect to manually actuate the reactor trip switchgear (manual reactor trip)using either of two control board switches.Condensate
[KA] (CM): The Condensate System (CM) takes condensate from the hotwell, purifies it to meet water chemistry specifications, heats it to improve the thermal cycle efficiency, and delivers it to the Feedwater System for makeup to the steam generators.
Feedwater System ISJI (CF): The CF System takes treated Condensate (QM) System water, heats it further to improve the plant's thermal cycle efficiency, and delivers it at the required flow rate, pressure and temperature to the steam generators.
The CF System is designed to maintain proper vessel water levels with respect to reactor power output and turbine steam requirements.
Auxiliary Feedwater System [BA] (CA): The CA System automatically supplies feedwater to the steam generators to remove decay heat from the NC System upon the loss of normal feedwater supply. The CA System mitigates the consequences of any event with loss of normal feedwater.
The design basis of the CA System is to supply water to the S/Gs to remove decay heat and other residual heat by delivering at least the minimum required flow rate to the steam generators.
The CA system is designed to start automatically for any event requiring emergency feedwater.
The CA System will automatically provide feedwater via the Motor Driven Pumps when initiated on any of the following conditions:
: 1. Loss of both main feedwater pumps 2. AMSAC Actuation 3. Two out of four (2/4) low-low level alarms in any one steam generator 4. Initiation of a safety injection signal 5. Loss of power to the 4160V essential bus (Blackout)
NRC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION (10-2010)LICENSEE EVENT REPORT (LER)1. FACILITY NAME 2. DOCKET 6. LER NUMBER 3. PAGE f SEQUENTIAL REVISION YEAR NUMBER NUMBER McGuire Nuclear Station, Unit 1 05000 369 2013 01 01 3 OF 6 I 17. NARRATIVE EVENT DESCRIPTION On February 21, 2013, while in Mode 1, an Operator performing rounds was investigating the cause of an extinguished light bulb indication on the heater drain tank (HDT) panel. In the course of the investigation the operator inadvertently tripped the 1C3 HDT pump.A single C HDT pump provides approximately 10% of total CF system flow at 100% power. Therefore, when the 1C3 HDT pump was tripped, the rest of the CM system and CF system had to respond to maintain final CF flow.This forced the hotwell pumps (HWPs) and CBPs to provide more flow, which resulted in lower pressures.
The decrease in pressure ultimately caused premature actuation of the CBP suction PSs, as sensed by at least two of three PSs (1CMPS5552, 1CMPS5553 and 1CMPS5554) and operating CBPs (1A and 1B) tripped. The trip of all operating CBPs resulted in a trip signal to both CF pumps, which in turn led to a turbine and reactor trip. The auxiliary feedwater system (CA) automatically started as a result of the CF pumps tripping (Engineered Safety Feature actuation).
The 1 B Motor-Driven CA pump was not available at the time of the event because it was removed from service to facilitate maintenance.
Control power fuses were removed to prevent the 1 B Motor-Driven CA pump from automatically starting.
The 1 B Motor-Driven CA pump could have been restored if it had been needed following the reactor trip.In addition, the trip of the first Main Feedwater Pump Turbine (CFPT) trip caused a load rejection signal. This load rejection signal resulted in starting the standby HWP (1A), the start/restart of all three CBPs and also caused the Unit 1 Generator Load Rejection Bypass Control Valve (1CM-420) to open.The relevant sequence of events is as follows (all times approximate, where time is the same the event or action is occurring within fractions of seconds): 09:55:44 1C3 HDT pump tripped 09:56:14 1CM-420 should have begun to modulate open at 100 psig decreasing 09:57:07 1A/1B CBP tripped 09:57:07 Unit 1 CBP Suction Press Emergency Low Alarm Cleared 09:57:07 1B CFPT tripped 09:57:07 Load Rejection Signal Generated 09:57:07 1A CFPT tripped 09:57:07 1A CA Pump Starts 09:57:07 Turbine trip 09:57:07 Reactor trip (Turbine Trip above P-8)09:57:07 Unit 1 CF Pump Suction Pressure Low Alarm 09:57:07 1A HWP Auto-starts on Load Rejection Signal (All 3 HWPs Running)09:57:07 1C CBP Auto-starts on Load Rejection Signal 09:57:08 1 CM-420 opened on Load Rejection Signal 09:57:21 1 B CBP Restarts on Load Rejection Signal 09:57:22 1A CBP Restarts on Load Rejection Signal 09:59:27 Unit 1 TDCA Pump Starts (1 SA-49AB Opens)
NRC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION (10-2010)LICENSEE EVENT REPORT (LER)1. FACILITY NAME 2. DOCKET 6. LER NUMBER 3. PAGE SEQUENTIAL REVISION YEAR NUMBER NUMBER McGuire Nuclear Station, Unit 1 105000 369 2013 _ 01 _ 01 4 OF 6 17. NARRATIVE REPORTABILITY DETERMINATION The Unit 1 automatic reactor trip and CA pump start were valid actuations and initially reported, as required, under 50.72 (b)(2)(iv)(B), "Any event or condition that results in actuation of the Reactor Protection System (RPS)when the reactor is critical except when the actuation results from and is part of a pre-planned sequence during testing or reactor operation." The event was also initially reported under 10 CFR 50.72 (b) (3) (iv) (A) and this LER will satisfy the corresponding reporting criteria 10 CFR 50.73 (a)(2)(iv)(A), "Any event or condition that resulted in manual or automatic actuation of any of the systems listed in paragraph (a)(2)(iv)(B)." The applicable 10 CFR 50.73 (a)(2)(iv)(B) systems include the Reactor Protection System (RPS) and the Auxiliary Feedwater System (CA).CAUSAL FACTORS The transient was initiated due to an inadvertent trip of the HDT pump. The HDT pump was inadvertently tripped by an operator investigating the cause for an indicating light bulb out that is part of the HDT pump start/stop pushbutton switch. Although the HDT panel was procedurally identified as having Transient/Trip potential, procedure guidance did not explicitly prohibit intrusive investigation at or near applicable components and applicable components were not uniquely identified.
This developed into a practice whereby operators investigated the cause for the extinguished light bulbs first and consulted the procedure later to determine if the bulb could be replaced.A "C" HDT pump trip is expected to cause a secondary system pressure transient (perturbation) but typically does not result in a unit reactor trip. The unit 1 reactor trip was ultimately caused by the CBPs tripping on an emergency low suction pressure signal. Investigation determined actual CBP suction pressure did not reach the emergency low trip set point (60 psig) and the CBP suction pressure switches (PS) had actuated prematurely.
Analysis of data indicated significant air voids in the common impulse line and vertical impulse line shared by all PSs (1CMPS5552, 1CMPS5553 and 1CMPS5554) in instrument loop (1CMLP5550).
Significant air voiding was caused by inadequate venting of CBP suction PSs. The CBP suction header pressure switches were vented prior to filling the CM system and starting a HWP; therefore, the only pressure in the instrument line was due to static head. The static head in the instrument line provided approximately 5 psig at the pressure switches when they were vented. Venting when the system is fully pressurized improves air removal. It was determined that process tubing configuration contributed to inadequate venting. The tubing from the process tap was vertically routed instrument loop and then routed in a sinusoidal wave pattern to each pressure switch. This resulted in three local high points for potential air entrainment and resulted in the instrument lines being much more susceptible to air remaining in the line (especially when vented at static head pressures versus system pressurized).
Finally, it was determined that sluggish response of the Generator Load Rejection Bypass Control Valve (1CM-420) contributed to the pressure transient.
1 CM-420 is designed to ensure that the CF Pumps have sufficient suction pressure by ensuring that the CBPs have sufficient suction pressure.
This is accomplished by bypassing flow from the Hotwell Pump [HWP] discharge directly to the CBP suction. ICM-420 did not open as expected on low CBP suction pressure.
This valve should have begun to modulate open when CBP suction pressure reached 100 psig decreasing but did not. It was determined that 1 CM-420 failure to modulate open in time was due to NRC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION (10-2010)LICENSEE EVENT REPORT (LER)1. FACILITY NAME 2. DOCKET 6. LER NUMBER 3. PAGE I SEQUENTIAL I REVISION YEAR NUMBER I NUMBER McGuire Nuclear Station, Unit 1 05000 369 2013 _ 01 -01 5 OF 6 I 17. NARRATIVE inadequate tuning of the controller (1 CMPR4200) and equipment malfunction associated with the valve positioner (1CMVP4200).
CORRECTIVE ACTIONS Immediate:
: 1. Instrument lines and PSs associated with CBP Suction Header instrument loop were replaced, flushed, calibrated and functionally verified.2. Components of 1CM-420 were replaced, calibrated and functionally verified.Subsequent:
: 1. Action was taken to limit operator interactions with light bulbs having transient/trip potential and added unique identification of these components.
: 2. The slope of the shared impulse line of the unit 1 CBP suction header PSs was corrected.
Planned: 1. Guidance will be developed to ensure CM system is in service prior to venting CBP suction header PSs.2. The method for testing and verifying ICM-420 for proper operation (i.e., within the operating pressure band) will be incorporated into applicable operating and surveillance guidance.3. Operator guidance will be revised to prevent hands-on verification of light bulbs associated with equipment/components having transient/trip potential.
SAFETY ANALYSIS The risk significance of this reactor trip event due to a loss of Main Feedwater has been evaluated both quantitatively and qualitatively.
The quantitative portion of the analysis considers the following:
0 0 A loss of main feedwater initiating event Actual plant configuration and maintenance activities at the time of the trip Core Damage Frequency (CDF) is the bounding risk metric because there is nothing inherent in a loss of Main Feedwater that is unique to a large early release.
NRC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION (1o-2010)LICENSEE EVENT REPORT (LER)1. FACILITY NAME 2. DOCKET 6. LER NUMBER 3. PAGE SEQUENTIAL I REVISION YEAR NUMBER NUMBER McGuire Nuclear Station, Unit 1 05000 369 2013 .01 01 6 OF 6 I 17. NARRATIVE Qualitatively, there are two dominant core damage accident sequences of importance.
The first type involves the loss of Main Feedwater initiator, failure of operators to restart Main Feedwater, failures of the Turbine-Driven Auxiliary Feedwater Pump and the 1A Motor-Driven Auxiliary Feedwater Pump, the 1B Motor-Driven Auxiliary Feedwater Pump is out of service to support maintenance, and a failure of the operators to initiate feed and bleed cooling.The second sequence type involves the loss of Main Feedwater initiator followed by an Anticipated Transient Without Scram (ATWS), a failure of the Reactor Protection System and a failure of the operators to manually initiate emergency boration for ATWS mitigation.
The end state for this sequence is actually stable, but since the reactor is never fully shut down, core damage is conservatively assumed to occur.This event had a low risk impact due to the redundant mitigating components that were available such as the Turbine-Driven Auxiliary Feedwater Pump and one Motor-Driven Auxiliary Feedwater Pump for feeding the Steam Generators.
A favorable moderator temperature coefficient contributed to the low risk impact by making several ATWS sequences less important.
Additionally, main feedwater pumps were available following the reactor trip and the 1 B motor-driven Auxiliary Feedwater Pump could have been restored if it had been needed.Therefore, this event is considered to have a low risk impact and no significance with respect to the health and safety of the public.ADDITIONAL INFORMATION A search of the McGuire Problem Identification Process (PIP) database was conducted to determine if this event was recurring.
The search identified PIP M-1 1-00389 which documented LER 369-11-02.
LER 369-11-02, January 20, 2011, while shutting down Unit 1 and Unit 2, operators experienced a loss of feed water (CF) to the Unit 1 Steam Generators.
The root cause for the CF pump trip is the use of equipment for a purpose it was not designed.
Transferring steam supplies to the 1 B CFPT uses a gate valve (1 HM-95) which is not designed for throttling.
Actions will be taken to discontinue the use of 1 HM-95 as a throttle valve and utilize the new CFPT governor steam supply controls for governor modulation.
Based on the information reviewed, this is not considered a recurring event.}}

Latest revision as of 14:41, 13 July 2018