{{#Wiki_filter:April 13, 2017 Mr. G. T. Powell | {{#Wiki_filter:April 13, 2017 | ||
Mr. G. T. Powell | |||
Executive Vice President and CNO | Executive Vice President and CNO | ||
STP Nuclear Operating Company | STP Nuclear Operating Company | ||
P.O. Box 289 | P.O. Box 289 | ||
Wadsworth, TX 77483 SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND | Wadsworth, TX 77483 | ||
EXPERIMENTS INSPECTION (05000498/2017007 AND 05000499/2017007) AND REQUEST FOR INFORMATION Dear Mr. Powell: | SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION | ||
- NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND | |||
EXPERIMENTS INSPECTION (05000498/2017007 | |||
AND 05000499/2017007) AND REQUEST FOR INFORMATION | |||
Dear Mr. Powell: | |||
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant | The purpose of this letter is to notify you that | ||
modifications at your South Texas Project Electric Generating Station from May 22-26, 2017. The inspection will consist of three reactor inspectors from the NRC's Region IV office for one week. The inspection will be conducted in accordance with NRC Inspection | U.S. Nuclear Regulatory Commission (NRC) staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant | ||
modifications at your South Texas Project Electric Generating Station | |||
from May 22-26, 2017. The inspection will consist of three reactor inspectors from the NRC's Region IV office for one week. The inspection will be conducted in accordance with NRC Inspection | |||
Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments." | Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments." | ||
Experience has shown that this inspection is resource | Experience has shown that this | ||
inspection is resource intens | |||
ive for both the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection. | |||
Please note that the documents are requested to be provided by May 15, 2017. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. It | Please note that the documents are requested to be provided by May 15, 2017. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. It | ||
is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. | is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. | ||
We have discussed the schedule for these inspection activities with your staff and understand | We have discussed the schedule for these inspection activities with your staff and understand | ||
that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing | that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing | ||
organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at Chris.Smith@nrc.gov. | organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at | ||
Chris.Smith@nrc.gov. | |||
This letter does not contain new or amended information collection requirements subject | This letter does not contain new or amended information collection requirements subject | ||
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to | to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to | ||
respond to, a request for information or an information collection requirement unless the UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 | respond to, a request for information or an information collection requirement unless the | ||
G. Powell 2 requesting document displays a currently valid Office of Management and Budget control number. | UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 | ||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | G. Powell 2 | ||
requesting document displays a currently valid Office of Management and Budget control | |||
number. | |||
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its | |||
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Sincerely, | |||
/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1 | |||
Division of Reactor Safety | Division of Reactor Safety | ||
Docket Nos. 50-498 and 50-499 | Docket Nos. 50-498 and 50-499 | ||
License Nos. NPF-76 and NPF-80 | |||
License Nos. NPF-76 and NPF-80 | |||
Enclosure: | Enclosure: | ||
Evaluations of Changes, Tests, and Experiments Inspection | Evaluations of Changes, Tests, and Experiments Inspection | ||
Request for Information | |||
cc: Electronic Distribution for STP | cc: Electronic Distribution for STP | ||
ML17103A627 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: TFarnholtz Yes No Publicly Available Sensitive NRC-002 OFFICE RI:EB1 C:EB1 NAME CSmith TFarnholtz SIGNATURE /RA/ /RA/ DATE 4/12/17 4/13/17 | ML17103A627 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: TFarnholtz Yes No Publicly Available Sensitive NRC-002 OFFICE RI:EB1 C:EB1 NAME CSmith TFarnholtz SIGNATURE /RA/ /RA/ DATE 4/12/17 4/13/17 | ||
Enclosure Request for Information Evaluations of Changes, Tests, and Experiments Inspection South Texas Project Electric Generating Station, Units 1 and 2 | Enclosure | ||
Request for Information | |||
Evaluations of Changes, Tests, and Experiments Inspection South Texas Project Electric Generating Station, Units 1 and 2 | |||
Inspection Report: 05000498/2017007; 05000499/2017007 | Inspection Report: 05000498/2017007; 05000499/2017007 | ||
Inspection Dates: May 22-26, 2017 | Inspection Dates: May 22-26, 2017 | ||
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments" | |||
Lead Inspector: Chris Smith, Reactor Inspector | Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments" | ||
Lead Inspector: Chris Smith, Reactor Inspector | |||
Information Requested for the In-Office Preparation Week | Information Requested for the In-Office Preparation Week | ||
The following information should be sent to the Region IV office in hard copy or electronic | |||
format (preferred) by May 15, 2017, to the attention of Chris Smith. We request that you | format (preferred) by May 15, 2017, to the attention of Chris Smith. We request that you | ||
categorize the documents in your response with the numbered list below. If only hard copies of the requested documents are available or if the electronic format is too large, please inform the lead inspector and provide the documents on the first day of the on-site inspection. Also, the | categorize the documents in your response with the numbered list below. If only hard copies of the requested documents are available or if the electronic format is too large, please inform the lead inspector and provide the documents on the first day of the on-site inspection. Also, the | ||
inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection weeks. We ask that the specific | inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection weeks. We ask that the specific | ||
items requested be available and ready for review on the first day of inspection. If you have any questions regarding this information request, please contact the lead inspector as soon as possible. 1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations. 2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation. | items requested be available and ready for review on the first day of inspection. If you have any questions regarding this information request, please contact the lead inspector as soon as | ||
did not result in an application for a license amendment. | possible. | ||
5. A list with descriptions of all compensatory actions for degraded or non-conforming conditions implemented since the last triennial 10 CFR 50.59 inspection. | 1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations. | ||
2 9. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report. 10. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 programs. | 2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation. | ||
3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes, tests, and experiments performed since the last triennial 10 CFR 50.59 inspection that | |||
did not result in an application for a license amendment. | |||
4. A list with descriptions of all temporary plant modifications implemented since the last triennial 10 CFR 50.59 inspection. | |||
5. A list with descriptions of all compensatory actions for degraded or non-conforming conditions implemented since the last triennial 10 CFR 50.59 inspection. | |||
6. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial 10 CFR 50.59 inspection. | |||
7. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates. | |||
8. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates. | |||
2 9. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report. | |||
10. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 | |||
programs. | |||
11. A copy of the most recent submittal of the report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each, | |||
required by 10 CFR 50.59(d)(2). | |||
12. A list of systems and system designators and a set of one-line (i.e., simplified) system | |||
diagrams. | |||
Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can determine the safety and/or risk significance of the screenings, evaluations, and modifications. | |||
Inspector Contact Information: | Inspector Contact Information: | ||
Chris Smith Reactor Inspector | |||
Chris Smith | |||
Reactor Inspector | |||
817-200-1095 | 817-200-1095 | ||
Chris.Smith@nrc.gov | Chris.Smith@nrc.gov | ||
Wes Cullum Reactor Inspector | |||
Wes Cullum | |||
Reactor Inspector | |||
817-200-1563 | 817-200-1563 | ||
Wes.Cullum@nrc.gov | Wes.Cullum@nrc.gov | ||
Nnaerika Okonkwo Reactor Inspector | |||
Nnaerika Okonkwo | |||
Reactor Inspector | |||
817-200-1114 | 817-200-1114 | ||
Nnaerika.Okonkwo@nrc.gov | Nnaerika.Okonkwo@nrc.gov | ||
Mailing Address: | |||
Mailing Address: | |||
U.S. NRC, Region IV | U.S. NRC, Region IV | ||
Attn: Chris Smith | Attn: Chris Smith | ||
1600 East Lamar Blvd. Arlington, TX 76011-4125 | 1600 East Lamar Blvd. Arlington, TX 76011-4125 | ||
}} | }} | ||
Revision as of 20:33, 29 June 2018
| ML17103A627 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 04/13/2017 |
| From: | Thomas Farnholtz Region 4 Engineering Branch 1 |
| To: | Powell G T South Texas |
| References | |
| IR 2017007 | |
| Download: ML17103A627 (5) | |
See also: IR 05000498/2017007
Text
April 13, 2017
Mr. G. T. Powell
Executive Vice President and CNO
STP Nuclear Operating Company
P.O. Box 289
Wadsworth, TX 77483
SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION
- NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND
EXPERIMENTS INSPECTION (05000498/2017007
AND 05000499/2017007) AND REQUEST FOR INFORMATION
Dear Mr. Powell:
The purpose of this letter is to notify you that
U.S. Nuclear Regulatory Commission (NRC) staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant
modifications at your South Texas Project Electric Generating Station
from May 22-26, 2017. The inspection will consist of three reactor inspectors from the NRC's Region IV office for one week. The inspection will be conducted in accordance with NRC Inspection
Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments."
Experience has shown that this
inspection is resource intens
ive for both the NRC inspectors and your staff. In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection.
Please note that the documents are requested to be provided by May 15, 2017. Upon review of these documents, the inspectors will select additional documentation for review upon arrival. It
is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand
that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing
organization. If there are any questions about this inspection or the material requested, please contact the lead inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at
Chris.Smith@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511
G. Powell 2
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-498 and 50-499
License Nos. NPF-76 and NPF-80
Enclosure:
Evaluations of Changes, Tests, and Experiments Inspection
Request for Information
cc: Electronic Distribution for STP
ML17103A627 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: TFarnholtz Yes No Publicly Available Sensitive NRC-002 OFFICE RI:EB1 C:EB1 NAME CSmith TFarnholtz SIGNATURE /RA/ /RA/ DATE 4/12/17 4/13/17
Enclosure
Request for Information
Evaluations of Changes, Tests, and Experiments Inspection South Texas Project Electric Generating Station, Units 1 and 2
Inspection Report: 05000498/2017007; 05000499/2017007
Inspection Dates: May 22-26, 2017
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments"
Lead Inspector: Chris Smith, Reactor Inspector
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic
format (preferred) by May 15, 2017, to the attention of Chris Smith. We request that you
categorize the documents in your response with the numbered list below. If only hard copies of the requested documents are available or if the electronic format is too large, please inform the lead inspector and provide the documents on the first day of the on-site inspection. Also, the
inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection weeks. We ask that the specific
items requested be available and ready for review on the first day of inspection. If you have any questions regarding this information request, please contact the lead inspector as soon as
possible.
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.
2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation.
3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes, tests, and experiments performed since the last triennial 10 CFR 50.59 inspection that
did not result in an application for a license amendment.
4. A list with descriptions of all temporary plant modifications implemented since the last triennial 10 CFR 50.59 inspection.
5. A list with descriptions of all compensatory actions for degraded or non-conforming conditions implemented since the last triennial 10 CFR 50.59 inspection.
6. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial 10 CFR 50.59 inspection.
7. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates.
8. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates.
2 9. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report.
10. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59
programs.
11. A copy of the most recent submittal of the report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each,
required by 10 CFR 50.59(d)(2).
12. A list of systems and system designators and a set of one-line (i.e., simplified) system
diagrams.
Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can determine the safety and/or risk significance of the screenings, evaluations, and modifications.
Inspector Contact Information:
Reactor Inspector
817-200-1095
Chris.Smith@nrc.gov
Reactor Inspector
817-200-1563
Wes.Cullum@nrc.gov
Reactor Inspector
817-200-1114
Nnaerika.Okonkwo@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Chris Smith
1600 East Lamar Blvd. Arlington, TX 76011-4125