{{#Wiki_filter:TENNESSEE VALLEY 1\\14 AUTHORITY
{{#Wiki_filter:Post Office Box 2000, Decatur, Alabama 35609-2000 June 23, 2024 10 CFR 21.21 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Unit 3 Renewed Facility Operating License No. DPR-68 NRC Docket No. 50-296  
 
Post Office Box 2000, Decatur, Alabama 35609-2000
 
June 23, 2024
 
10 CFR 21.21
 
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
 
Browns Ferry Nuclear Plant, Unit 3 Renewed Facility Operating License No. DPR-68 NRC Docket No. 50-296


==Subject:==
==Subject:==
Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System
Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 21.21(a)(2), the Tennessee Valley Authority is submitting this interim report for Browns Ferry Nuclear Plant (BFN).
 
In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 21.21(a)(2), the Tennessee Valley Authority is submitting this interim report for Browns Ferry Nuclear Plant (BFN).
 
On March 3, 2024, excessive valve stem rotation was observed while troubleshooting the BFN, Unit 3, High Pressure Coolant Injection (HPCI) outboard steam isolation valve. This issue was promptly entered into the BFN Corrective Action Program (CAP) as Condition Report (CR) 1914295.
On March 3, 2024, excessive valve stem rotation was observed while troubleshooting the BFN, Unit 3, High Pressure Coolant Injection (HPCI) outboard steam isolation valve. This issue was promptly entered into the BFN Corrective Action Program (CAP) as Condition Report (CR) 1914295.
On April 24, 2024, TVA completed its 10 CFR Part 21 discovery process and determined the need to perform a 10 CFR Part 21 Evaluation. This Part 21 Evaluation is being tracked by TVA under CR 1926691. The vendor, Flowserve, was contacted and has assumed responsibility for performing the Part 21 Evaluation for this valve. However, the vendors evaluation is ongoing and will not be completed within 60 days of discovery, prompting BFN to submit this interim report.
On April 24, 2024, TVA completed its 10 CFR Part 21 discovery process and determined the need to perform a 10 CFR Part 21 Evaluation. This Part 21 Evaluation is being tracked by TVA under CR 1926691. The vendor, Flowserve, was contacted and has assumed responsibility for performing the Part 21 Evaluation for this valve. However, the vendors evaluation is ongoing and will not be completed within 60 days of discovery, prompting BFN to submit this interim report.
There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact David Renn, Site Licensing Manager, at (256) 729-2636.
There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact David Renn, Site Licensing Manager, at (256) 729-2636.
Respectfully, Manu Sivaraman Site Vice President 1\14 TENNESSEE VALLEY AUTHORITY


Respectfully,
U.S. Nuclear Regulatory Commission Page 2 June 23, 2024 cc:
 
Manu Sivaraman Site Vice President U.S. Nuclear Regulatory Commission Page 2 June 23, 2024
 
cc:
 
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant}}
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant}}

Latest revision as of 04:19, 21 February 2026

Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System
ML24175A004
Person / Time
Site: Browns Ferry 
Issue date: 06/23/2024
From: Sivaraman M
Tennessee Valley Authority
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
Download: ML24175A004 (1)


Text

Post Office Box 2000, Decatur, Alabama 35609-2000 June 23, 2024 10 CFR 21.21 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Browns Ferry Nuclear Plant, Unit 3 Renewed Facility Operating License No. DPR-68 NRC Docket No. 50-296

Subject:

Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System In accordance with the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 21.21(a)(2), the Tennessee Valley Authority is submitting this interim report for Browns Ferry Nuclear Plant (BFN).

On March 3, 2024, excessive valve stem rotation was observed while troubleshooting the BFN, Unit 3, High Pressure Coolant Injection (HPCI) outboard steam isolation valve. This issue was promptly entered into the BFN Corrective Action Program (CAP) as Condition Report (CR) 1914295.

On April 24, 2024, TVA completed its 10 CFR Part 21 discovery process and determined the need to perform a 10 CFR Part 21 Evaluation. This Part 21 Evaluation is being tracked by TVA under CR 1926691. The vendor, Flowserve, was contacted and has assumed responsibility for performing the Part 21 Evaluation for this valve. However, the vendors evaluation is ongoing and will not be completed within 60 days of discovery, prompting BFN to submit this interim report.

There are no new regulatory commitments contained in this letter. Should you have any questions concerning this submittal, please contact David Renn, Site Licensing Manager, at (256) 729-2636.

Respectfully, Manu Sivaraman Site Vice President 1\14 TENNESSEE VALLEY AUTHORITY

U.S. Nuclear Regulatory Commission Page 2 June 23, 2024 cc:

NRC Regional Administrator - Region II NRC Senior Resident Inspector - Browns Ferry Nuclear Plant NRC Project Manager - Browns Ferry Nuclear Plant