ML061640348: Difference between revisions

From kanterella
Jump to navigation Jump to search
Created page by program invented by StriderTol
StriderTol Bot change
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:w%0'En terWg                                                                     Entergy Nuclear Operations, Inc.
{{#Wiki_filter:w%0'En terWg Entergy Nuclear Operations, Inc.
Pilgrim Station 600 Rocky Hill Road Plymouth, MA 02360 Stephen J. Bethay June 5, 2006                                                                  Director, Nuclear Assessment U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
Pilgrim Station 600 Rocky Hill Road Plymouth, MA 02360 June 5, 2006 Stephen J. Bethay Director, Nuclear Assessment U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555


==SUBJECT:==
==SUBJECT:==
Entergy Nuclear Operations, Inc.
Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station Docket 50-293 License No. DPR-35 Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 (TAC No. MD01 78)
Pilgrim Nuclear Power Station Docket 50-293 License No. DPR-35


==REFERENCE:==
==REFERENCE:==
: 1. NRC Letter, 1.06.052, Pilgrim Nuclear Power Station - Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 (TAC No. MD01 78), dated April 24, 2006.
LETTER NUMBER:
LETTER NUMBER:         2.06.046


==Dear Sir or Madam:==
==Dear Sir or Madam:==
 
Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 (TAC No. MD01 78)
By Reference 1, the NRC requested additional information regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003.
: 1.
NRC Letter, 1.06.052, Pilgrim Nuclear Power Station - Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 (TAC No. MD01 78), dated April 24, 2006.
2.06.046 By Reference 1, the NRC requested additional information regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003.
Entergy has evaluated the request and the response is provided in Attachment 1.
Entergy has evaluated the request and the response is provided in Attachment 1.
This letter contains no commitments.
This letter contains no commitments.
If you have any questions or require additional information, please contact Mr. Bryan Ford, Licensing Manager, at (508) 830-8403.
If you have any questions or require additional information, please contact Mr. Bryan Ford, Licensing Manager, at (508) 830-8403.
Sincerely, Stephen J,.Beth~ayt Director, Nuclear Safet Assurance ERS/dm
Sincerely, Stephen J,. Beth~ayt Director, Nuclear Safet Assurance ERS/dm


==Attachment:==
==Attachment:==
1; Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003. (3 pages)
1; Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003. (3 pages)
                                                                                                    .Jruo /
.Jruo /
 
Entergy Nuclear Operations, Inc                          Letter Number 2.06.046 Pilgrim Nuclear Station                                  Page 2 cc:    Mr. James Shea, Project Manager        Mr. Robert Walker, Director Plant Licensing Branch 1-1            Massachusetts Department of Public Division of Operator Reactor Licensing Health Office of Nuclear Reactor Regulation  Radiation Control Program U.S. Nuclear Regulatory Commission    90 Washington Street, 2ndFloor One White Flint North 0-802            Dorchester, MA 02121 11555 Rockville Pike Rockville, MD 20852 Regional Administrator, Region 1      Ms Cristine McCombs, Director U.S. Nuclear Regulator Commission      Mass. Emergency Management Agency 475 Allendale Road                    400 Worcester Road King of Prussia, PA 19406              Framingham, MA 01702 Senior Resident Inspector Pilgrim Nuclear Power Station


Attachment 1 to Letter 2.06.046Pae1o3                                     Page I of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRIC Integrated Inspection Report 05000293/2005003 NRC RAI #1 The Pilgrim FSAR Section 8.5.5 states that "Readiness can best be demonstrated by periodic testing, which insofar as practical, simulates actual emergency conditions. NA)
Entergy Nuclear Operations, Inc Pilgrim Nuclear Station cc:
Mr. James Shea, Project Manager Plant Licensing Branch 1-1 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North 0-802 11555 Rockville Pike Rockville, MD 20852 Regional Administrator, Region 1 U.S. Nuclear Regulator Commission 475 Allendale Road King of Prussia, PA 19406 Letter Number 2.06.046 Page 2 Mr. Robert Walker, Director Massachusetts Department of Public Health Radiation Control Program 90 Washington Street, 2ndFloor Dorchester, MA 02121 Ms Cristine McCombs, Director Mass. Emergency Management Agency 400 Worcester Road Framingham, MA 01702 Senior Resident Inspector Pilgrim Nuclear Power Station to Letter 2.06.046Pae1o3 Page I of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRIC Integrated Inspection Report 05000293/2005003 NRC RAI #1 The Pilgrim FSAR Section 8.5.5 states that "Readiness can best be demonstrated by periodic testing, which insofar as practical, simulates actual emergency conditions. N A)
What was your basis for determining that it was not practical to sequence load one RBCCW Pump and one SSW Pumps on the Emergency Diesel Generator (EDG) during surveillance testing (TS SR 4.9.A. 1.b and SR 4.9.A. 1.c)?
What was your basis for determining that it was not practical to sequence load one RBCCW Pump and one SSW Pumps on the Emergency Diesel Generator (EDG) during surveillance testing (TS SR 4.9.A. 1.b and SR 4.9.A. 1.c)?
B) Also, explain why equivalent loads in lieu of RBCCW and SSW pumps were not added in order to have required DG Loading.
B) Also, explain why equivalent loads in lieu of RBCCW and SSW pumps were not added in order to have required DG Loading.
Entercav Response A)The "B"trains of RBCCW and SSW were not available during the surveillance test of the "B"EDG conducted during RFO 15. Procedure 8.M.3-1 "SPECIAL TEST FOR AUTOMATIC ECCS LOAD SEQUENCING OF DIESELS AND SHUTDOWN TRANSFORMER WITH SIMULATED LOSS OF OFF-SITE POWER AND SPECIAL SHUTDOWN TRANSFORMER LOAD TEST" was performed while the RBCCW & SSW systems were out of service. The RBCCW heat exchanger was out of service for channel repairs and eddy current testing. When the RBCCW heat exchanger is out of service, both of the associated trains RBCCW & SSW must be isolated. Procedure 8.M.3-1 was actually performed on April 28, 2005 from 0000 to 0600. The RBCCW &
Entercav Response A) The "B" trains of RBCCW and SSW were not available during the surveillance test of the "B" EDG conducted during RFO 15. Procedure 8.M.3-1 "SPECIAL TEST FOR AUTOMATIC ECCS LOAD SEQUENCING OF DIESELS AND SHUTDOWN TRANSFORMER WITH SIMULATED LOSS OF OFF-SITE POWER AND SPECIAL SHUTDOWN TRANSFORMER LOAD TEST" was performed while the RBCCW & SSW systems were out of service. The RBCCW heat exchanger was out of service for channel repairs and eddy current testing. When the RBCCW heat exchanger is out of service, both of the associated trains RBCCW & SSW must be isolated. Procedure 8.M.3-1 was actually performed on April 28, 2005 from 0000 to 0600. The RBCCW &
SSW systems were returned to service as follows:
SSW systems were returned to service as follows:
        *SSW returned April 29,2005 @1200
*SSW returned April 29,2005 @ 1200
        *RBCCW Heat exchanger PWT April 29,2005 @ 1200
*RBCCW Heat exchanger PWT April 29,2005 @ 1200
        *RBCCW returned April 30, 2005 @0400 The "A"trains of RBCCW and SSW were available and were included in the surveillance test of the "AK EDG.
*RBCCW returned April 30, 2005 @ 0400 The "A" trains of RBCCW and SSW were available and were included in the surveillance test of the "AK EDG.
B) Since this test does not prove the load capability of the EDG, additional load was not added to simulate the RBCCW and SSW pumps. The load capacity of the EDG is proven monthly by performance of procedure 8.9.1.
B) Since this test does not prove the load capability of the EDG, additional load was not added to simulate the RBCCW and SSW pumps. The load capacity of the EDG is proven monthly by performance of procedure 8.9.1.
NRC RAI #2 Explain why starting the last sequenced load(s) RBCCW & SSW will not adversely affect the performance of the EDG. Specifically, address KW and KVAR requirements and available DG margin in KW and KVAR.
NRC RAI #2 Explain why starting the last sequenced load(s) RBCCW & SSW will not adversely affect the performance of the EDG. Specifically, address KW and KVAR requirements and available DG margin in KW and KVAR.
Entergy Response In this test, the RHR and CS pumps are run at minimum flow. Actual loading on the EDG at the point when all three of these pumps are running (which includes all other loads normally powered in this configuration) is:
Entergy Response In this test, the RHR and CS pumps are run at minimum flow. Actual loading on the EDG at the point when all three of these pumps are running (which includes all other loads normally powered in this configuration) is:
Current = 1.5 A (recorded CT current) x 600/5 CT ratio = 180 A Voltage = 120.64 V (recorded PT voltage) x 4200/120 PT ratio = 4222 V to Letter 2.06.046                                           Page2of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 Enterciv Response to NRC RAI #2 (continued)
Current = 1.5 A (recorded CT current) x 600/5 CT ratio = 180 A Voltage = 120.64 V (recorded PT voltage) x 4200/120 PT ratio = 4222 V to Letter 2.06.046 Page 2of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 Enterciv Response to NRC RAI #2 (continued)
Apparent power (MV) = 4.222 kV x 180 A x 4I3 = 1316 kVA Real power (kW) (assuming 80% power factor) = 1316 x 0.8 = 1053 kW The capability of the EDG is 2600 kW (continuous rating). The power available is 2600
Apparent power (MV) = 4.222 kV x 180 A x 4I3 = 1316 kVA Real power (kW) (assuming 80% power factor) = 1316 x 0.8 = 1053 kW The capability of the EDG is 2600 kW (continuous rating). The power available is 2600
- 1053 = 1547 kW The additional power to start a 100 HP SSW pump is approximately 560 kW and to start an RBCCW pump approximately 336 kW determined as follows:
- 1053 = 1547 kW The additional power to start a 100 HP SSW pump is approximately 560 kW and to start an RBCCW pump approximately 336 kW determined as follows:
SSW pump is 100OHP x 0.746 kW/HP x 6 (inrush) / 0.8 efficiency = 560 kW Steady state = 100 HP x 0. 746 kW/H P/ 0.8 efficiency = 93.25 kW RBCCW pump is 60HP x 0.746 kW/HP x 6 (inrush) /0.8 efficiency = 336 kW Steady-state = 60 HP xO.746 kW/HP /0.8 efficiency = 55.95 kW With 1547 kW available, there is sufficient capacity on the EDG to start the SSW pump, which develops 560 kW during inrush, then 93.25 kW during steady state. After the SSW pump is started, the available margin is 1453.75 kW (1547 - 93.25) to start the RBCCW pump load of 336 kW during inrush, then 55.95 kW during steady state.
SSW pump is 100OHP x 0.746 kW/HP x 6 (inrush) / 0.8 efficiency = 560 kW Steady state = 100 H P x 0. 746 kW/H P / 0.8 efficiency = 93.25 kW RBCCW pump is 60HP x 0.746 kW/HP x 6 (inrush) /0.8 efficiency = 336 kW Steady-state = 60 HP xO.746 kW/HP /0.8 efficiency = 55.95 kW With 1547 kW available, there is sufficient capacity on the EDG to start the SSW pump, which develops 560 kW during inrush, then 93.25 kW during steady state. After the SSW pump is started, the available margin is 1453.75 kW (1547 - 93.25) to start the RBCCW pump load of 336 kW during inrush, then 55.95 kW during steady state.
Interms of KVA:
In terms of KVA:
At the point where all three CSCS pumps are running, EDG kVA is 1316 kVA (4.222 kV xl18OA x 3).
At the point where all three CSCS pumps are running, EDG kVA is 1316 kVA (4.222 kV xl18OA x 3).
EDG capacity is 3250 MV,Therefore, the available margin is 1934 kVA (3250     - 1316 kVA) for starting the SSW and RBCCW pumps.
EDG capacity is 3250 MV, Therefore, the available margin is 1934 kVA (3250 - 1316 kVA) for starting the SSW and RBCCW pumps.
The inrush and running KVA of each of these pumps is:
The inrush and running KVA of each of these pumps is:
SSW nameplate kVA code = F = 5.59 kVA /HP (from National Electric Code)
SSW nameplate kVA code = F = 5.59 kVA /HP (from National Electric Code)
Line 68: Line 68:
Running kVA: 480 V x74.5 A x43= 62kVA.
Running kVA: 480 V x74.5 A x43= 62kVA.
The EDG's remaining available margin of 1934 kVA is sufficient to start and run both the RBCCW and SSW pumps.
The EDG's remaining available margin of 1934 kVA is sufficient to start and run both the RBCCW and SSW pumps.
to Letter 2 .06.046                                         Pg~f Page3 of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 NRC RAI #3 A) What does Entergy consider a 'small"y EDG load?
to Letter 2.06.046 Pg~f Page 3 of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 NRC RAI #3 A) What does Entergy consider a 'small"y EDG load?
B) Would this include the RBCCW and SSW pumps?
B) Would this include the RBCCW and SSW pumps?
C)Explain why these loads would not impact EDG performance when taken in total during the sequence load of the emergency diesel.
C) Explain why these loads would not impact EDG performance when taken in total during the sequence load of the emergency diesel.
Enterpy Response A) Loads less than or equal to 5%of the EDG capacity. 2600 x 0.05 = 130 kW (175 HP)
Enterpy Response A) Loads less than or equal to 5% of the EDG capacity. 2600 x 0.05 = 130 kW (175 HP)
B) Yes.
B) Yes.
C) After starting the EDG and loading it with the normal loads for a simulated LOCA w/LOOP, and after all three CSCS pumps have started, the total load on the EDG as measured is 1053 kW At this point in the test, when the SSW and RBCCW pumps would sequence on, the EDG load is 1053 kRW. This leaves (2600 - 1053) = 1547 kW available on the EDG which is more than adequate to start the SSW and RBCCW pumps in sequence}}
C) After starting the EDG and loading it with the normal loads for a simulated LOCA w/LOOP, and after all three CSCS pumps have started, the total load on the EDG as measured is 1053 kW At this point in the test, when the SSW and RBCCW pumps would sequence on, the EDG load is 1053 kRW. This leaves (2600 - 1053) = 1547 kW available on the EDG which is more than adequate to start the SSW and RBCCW pumps in sequence}}

Latest revision as of 08:30, 15 January 2025

Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293-05-003
ML061640348
Person / Time
Site: Pilgrim
Issue date: 06/05/2006
From: Bethay S
Entergy Nuclear Operations
To:
Document Control Desk, NRC Region 1
References
IR-05-003, TAC MD0178
Download: ML061640348 (5)


Text

w%0'En terWg Entergy Nuclear Operations, Inc.

Pilgrim Station 600 Rocky Hill Road Plymouth, MA 02360 June 5, 2006 Stephen J. Bethay Director, Nuclear Assessment U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

SUBJECT:

Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station Docket 50-293 License No. DPR-35

REFERENCE:

LETTER NUMBER:

Dear Sir or Madam:

Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 (TAC No. MD01 78)

1.

NRC Letter, 1.06.052, Pilgrim Nuclear Power Station - Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 (TAC No. MD01 78), dated April 24, 2006.

2.06.046 By Reference 1, the NRC requested additional information regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003.

Entergy has evaluated the request and the response is provided in Attachment 1.

This letter contains no commitments.

If you have any questions or require additional information, please contact Mr. Bryan Ford, Licensing Manager, at (508) 830-8403.

Sincerely, Stephen J,. Beth~ayt Director, Nuclear Safet Assurance ERS/dm

Attachment:

1; Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003. (3 pages)

.Jruo /

Entergy Nuclear Operations, Inc Pilgrim Nuclear Station cc:

Mr. James Shea, Project Manager Plant Licensing Branch 1-1 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission One White Flint North 0-802 11555 Rockville Pike Rockville, MD 20852 Regional Administrator, Region 1 U.S. Nuclear Regulator Commission 475 Allendale Road King of Prussia, PA 19406 Letter Number 2.06.046 Page 2 Mr. Robert Walker, Director Massachusetts Department of Public Health Radiation Control Program 90 Washington Street, 2ndFloor Dorchester, MA 02121 Ms Cristine McCombs, Director Mass. Emergency Management Agency 400 Worcester Road Framingham, MA 01702 Senior Resident Inspector Pilgrim Nuclear Power Station to Letter 2.06.046Pae1o3 Page I of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRIC Integrated Inspection Report 05000293/2005003 NRC RAI #1 The Pilgrim FSAR Section 8.5.5 states that "Readiness can best be demonstrated by periodic testing, which insofar as practical, simulates actual emergency conditions. N A)

What was your basis for determining that it was not practical to sequence load one RBCCW Pump and one SSW Pumps on the Emergency Diesel Generator (EDG) during surveillance testing (TS SR 4.9.A. 1.b and SR 4.9.A. 1.c)?

B) Also, explain why equivalent loads in lieu of RBCCW and SSW pumps were not added in order to have required DG Loading.

Entercav Response A) The "B" trains of RBCCW and SSW were not available during the surveillance test of the "B" EDG conducted during RFO 15. Procedure 8.M.3-1 "SPECIAL TEST FOR AUTOMATIC ECCS LOAD SEQUENCING OF DIESELS AND SHUTDOWN TRANSFORMER WITH SIMULATED LOSS OF OFF-SITE POWER AND SPECIAL SHUTDOWN TRANSFORMER LOAD TEST" was performed while the RBCCW & SSW systems were out of service. The RBCCW heat exchanger was out of service for channel repairs and eddy current testing. When the RBCCW heat exchanger is out of service, both of the associated trains RBCCW & SSW must be isolated. Procedure 8.M.3-1 was actually performed on April 28, 2005 from 0000 to 0600. The RBCCW &

SSW systems were returned to service as follows:

  • SSW returned April 29,2005 @ 1200
  • RBCCW Heat exchanger PWT April 29,2005 @ 1200
  • RBCCW returned April 30, 2005 @ 0400 The "A" trains of RBCCW and SSW were available and were included in the surveillance test of the "AK EDG.

B) Since this test does not prove the load capability of the EDG, additional load was not added to simulate the RBCCW and SSW pumps. The load capacity of the EDG is proven monthly by performance of procedure 8.9.1.

NRC RAI #2 Explain why starting the last sequenced load(s) RBCCW & SSW will not adversely affect the performance of the EDG. Specifically, address KW and KVAR requirements and available DG margin in KW and KVAR.

Entergy Response In this test, the RHR and CS pumps are run at minimum flow. Actual loading on the EDG at the point when all three of these pumps are running (which includes all other loads normally powered in this configuration) is:

Current = 1.5 A (recorded CT current) x 600/5 CT ratio = 180 A Voltage = 120.64 V (recorded PT voltage) x 4200/120 PT ratio = 4222 V to Letter 2.06.046 Page 2of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 Enterciv Response to NRC RAI #2 (continued)

Apparent power (MV) = 4.222 kV x 180 A x 4I3 = 1316 kVA Real power (kW) (assuming 80% power factor) = 1316 x 0.8 = 1053 kW The capability of the EDG is 2600 kW (continuous rating). The power available is 2600

- 1053 = 1547 kW The additional power to start a 100 HP SSW pump is approximately 560 kW and to start an RBCCW pump approximately 336 kW determined as follows:

SSW pump is 100OHP x 0.746 kW/HP x 6 (inrush) / 0.8 efficiency = 560 kW Steady state = 100 H P x 0. 746 kW/H P / 0.8 efficiency = 93.25 kW RBCCW pump is 60HP x 0.746 kW/HP x 6 (inrush) /0.8 efficiency = 336 kW Steady-state = 60 HP xO.746 kW/HP /0.8 efficiency = 55.95 kW With 1547 kW available, there is sufficient capacity on the EDG to start the SSW pump, which develops 560 kW during inrush, then 93.25 kW during steady state. After the SSW pump is started, the available margin is 1453.75 kW (1547 - 93.25) to start the RBCCW pump load of 336 kW during inrush, then 55.95 kW during steady state.

In terms of KVA:

At the point where all three CSCS pumps are running, EDG kVA is 1316 kVA (4.222 kV xl18OA x 3).

EDG capacity is 3250 MV, Therefore, the available margin is 1934 kVA (3250 - 1316 kVA) for starting the SSW and RBCCW pumps.

The inrush and running KVA of each of these pumps is:

SSW nameplate kVA code = F = 5.59 kVA /HP (from National Electric Code)

Starting inrush kVA: 100 HP x5.59kVA/IHP =559 kVA.

Running kVA: 480 V x 113.4 A x 4/3 = 94.3 kVA RBCCW nameplate kVA code = G = 6.29 kVA / HP (National Electric Code)

Starting inrush kVA: 60 HP x 6.29 kVA / HP = 337 kV.

Running kVA: 480 V x74.5 A x43= 62kVA.

The EDG's remaining available margin of 1934 kVA is sufficient to start and run both the RBCCW and SSW pumps.

to Letter 2.06.046 Pg~f Page 3 of 3 Entergy Response to NRC Request for Additional Information Regarding Unresolved Inspection Item 05000293/2005003-01 from NRC Integrated Inspection Report 05000293/2005003 NRC RAI #3 A) What does Entergy consider a 'small"y EDG load?

B) Would this include the RBCCW and SSW pumps?

C) Explain why these loads would not impact EDG performance when taken in total during the sequence load of the emergency diesel.

Enterpy Response A) Loads less than or equal to 5% of the EDG capacity. 2600 x 0.05 = 130 kW (175 HP)

B) Yes.

C) After starting the EDG and loading it with the normal loads for a simulated LOCA w/LOOP, and after all three CSCS pumps have started, the total load on the EDG as measured is 1053 kW At this point in the test, when the SSW and RBCCW pumps would sequence on, the EDG load is 1053 kRW. This leaves (2600 - 1053) = 1547 kW available on the EDG which is more than adequate to start the SSW and RBCCW pumps in sequence