{{Adams
| number = ML090410625
| issue date = 02/09/2009
| title = Reactor and Senior Reactor Operator Initial Examinations - Surry Power Station 05000280/2009301 and 05000281/2009301
| author name = Widmann M
| author affiliation = NRC/RGN-II/DRS/OLB
| addressee name = Christian D
| addressee affiliation = Dominion
| docket = 05000280, 05000281
| license number = DPR-032, DPR-037
| contact person =
| case reference number = 50-280/09-301, 50-281/09-301
| document type = Letter, License-Operator, Part 55 Examination Related Material
| page count = 5
}}
See also: [[see also::IR 05000280/2009301]]
 
=Text=
{{#Wiki_filter:UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
SAM NUNN ATLANTA FEDERAL CENTER 
61 FORSYTH STREET, SW, SUITE 23T85
ATLANTA, GEORGIA  30303-8931
February 9, 2009
Mr. David A. Christian
Senior Vice President and 
  Chief Nuclear Officer
Innsbrook Technical Center
5000 Dominion Boulevard
Glen Allen, VA  23060
SUBJECT:
NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION -
SURRY POWER STATION - 05000280/2009301 AND 05000281/2009301
Dear Mr. Christian:
In a telephone conversation on February 2, 2009, between Mr. David Wilson, Operations
Training Supervisor, and Mr. Mark Bates, Senior Operations Engineer, arrangements were
made for the administration of licensing examinations at the Surry Power Station.  The operating
test is scheduled to be administered the week of July 20, 2009.  The written examination is
scheduled to be administered the week of July 27, 2009.  The on-site preparatory week is
scheduled for the week of June 29, 2009.
As agreed during the telephone conversation, the staff of the U.S. Nuclear Regulatory
Commission (NRC) will prepare the written examination and your staff will prepare the operating
test based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing
Examination Standards for Power Reactors."  Your staff will be given the opportunity to review
the written examination during the week of May 29, 2009.  The NRC regional office will discuss
with your staff any changes to the operating test that might be necessary before the tests are
administered.  Your staff has also agreed to make copies of all examination materials that are
necessary for administering the examination.
To meet the above schedule, it will be necessary for your staff to furnish the reference materials
identified in Attachment 3 to ES-201 by February 6, 2009.  The operating test outline will be due
by April 27, 2009 and the operating tests will be due by June 8, 2009.  Pursuant to Title 10,
Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized
representative of the facility licensee shall approve the outline and test before they are
submitted to the NRC for review and approval.  All materials shall be complete and ready-to-
use. 
We request that any personal, proprietary, sensitive unclassified, or safeguards information in
your response be contained in a separate enclosure and appropriately marked.  Any delay in
receiving the required examination and reference materials, or the submittal of inadequate or
incomplete materials, may cause the examinations to be rescheduled.
 
VEPCO
2
In order to conduct the requested written examinations and operating tests, it will be necessary
for your staff to provide adequate space and accommodations in accordance with ES-402, and
to make the simulation facility available on the dates noted above.  In accordance with ES-302,
your staff should retain the original simulator performance data (e.g., system pressures,
temperatures, and levels) generated during the dynamic operating tests until the examination
results are final.
Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in
effect while the written examinations and operating tests are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor
operator and senior reactor operator license applications (Office of Management and Budget
(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),
and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first
examination date.  If the applications are not received at least 30 days before the examination
date, a postponement may be necessary.  Signed applications certifying that all training has
been completed should be submitted at least 14 days before the first examination date.
This letter contains information collections that are subject to the Paperwork Reduction Act of
1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under
approval number 3150-0018, which expires on June 30, 2009.  The public reporting burden for
this collection of information is estimated to average 500 hours per response, including the time
for reviewing instructions, gathering and maintaining the data needed, writing the examinations,
and completing and reviewing the collection of information.  Send comments on any aspect of
this collection of information, including suggestions for reducing the burden, to the Information
and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov;
and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-
0018), Office of Management and Budget, Washington, DC 20503.
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection
of information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS
is accessible from the NRC Web site at http://www/nrc.gov/readingrm/adams.html (the Public
Electronic Reading Room).
 
VEPCO
3
Thank you for your cooperation in this matter.  Mr. Wilson has been advised of the policies and
guidelines referenced in this letter.  If you have any questions regarding the NRC's examination
procedures and guidelines, please contact Mr. Mark Bates at (404) 562-4612, (Internet E-mail:
Mark.Bates@nrc.gov) or me at (404) 562-4550, (Internet E-mail: Malcolm.Widmann@nrc.gov).
Sincerely,
/RA/
Malcolm T. Widmann, Chief
Operations Branch
Division of Reactor Safety
Docket Nos.:  50-280, 50-281
License Nos.:  DPR-32, DPR-37
(cc see page 4)
 
VEPCO
4
cc:  Gerald T. Bischof
Site Vice President
Surry Power Station
Virginia Electric and Power Company
Electronic Mail Distribution
Sonny Stanley
Director, Nuclear  Safety and Licensing
Virginia Electric and Power Company
Electronic Mail Distribution
Lillian M. Cuoco, Esq.
Senior Counsel
Dominion Resources Services, Inc.
Electronic Mail Distribution
Chris L. Funderburk
Director, Nuclear Licensing &
Operations Support
Virginia Electric and Power Company
Electronic Mail Distribution
Virginia State Corporation Commission
Division of Energy Regulation
P.O. Box 1197
Richmond, VA  23209
Attorney General
Supreme Court Building
900 East Main Street
Richmond, VA  23219
Senior Resident Inspector
Surry Power Station
U.S. Nuclear Regulatory Commission
5850 Hog Island Rd
Surry, VA  23883
Michael M. Cline
Director
Virginia Department of Emergency
Services Management
Electronic Mail Distribution
Virginia Electric and Power Company
ATTN:  Mr. Andy T. Barbee
Manager of Nuclear Training
Surry power Station
5570 Hog Island road
Surry, VA  23883
 
VEPCO
5
Letter to David A. Christian from Malcolm T. Widmann dated February 9, 2009.
SUBJECT:
REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATIONS -
SURRY POWER STATION - 05000280/2009301 AND 05000281/2009301
Distribution:
RIDSNRRDIRS
PUBLIC
S. P. Lingam, NRR (PM:  NA, SUR)
XG  PUBLICLY AVAILABLE
G  NON-PUBLICLY AVAILABLE
G  SENSITIVE
        XG  NON-SENSITIVE
ADAMS:  XG Yes
ACCESSION NUMBER:_________________________
XG  SUNSI REVIEW COMPLETE
OFFICE
RII:DRS
RII:DRS
RII:DRP
SIGNATURE
NAME
MBates
GMcCoy
MWidmann
DATE
02/6/2009
02/6/2009
02/9/2009
E-MAIL COPY?
    YES
NO    YES
NO    YES
NO    YES
NO    YES
NO    YES
NO    YES
NO
OFFICIAL
RECORD
COPY          DOCUMENT
NAME:
O:\\SURRY
EXAMINATIONS\\INITIAL
EXAM
2009-
301\\CORRESPONDENCE\\2009 -301 SURRY CORPORATE NOTIFICATION LETTER (MAB) REV 0.DOC
}}

Latest revision as of 13:17, 14 January 2025

Reactor and Senior Reactor Operator Initial Examinations - Surry Power Station 05000280/2009301 and 05000281/2009301
ML090410625
Person / Time
Site: Surry  Dominion icon.png
Issue date: 02/09/2009
From: Widmann M
NRC/RGN-II/DRS/OLB
To: Christian D
Dominion
References
50-280/09-301, 50-281/09-301
Download: ML090410625 (5)


See also: IR 05000280/2009301

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET, SW, SUITE 23T85

ATLANTA, GEORGIA 30303-8931

February 9, 2009

Mr. David A. Christian

Senior Vice President and

Chief Nuclear Officer

Innsbrook Technical Center

5000 Dominion Boulevard

Glen Allen, VA 23060

SUBJECT:

NOTIFICATION OF LICENSED OPERATOR INITIAL EXAMINATION -

SURRY POWER STATION - 05000280/2009301 AND 05000281/2009301

Dear Mr. Christian:

In a telephone conversation on February 2, 2009, between Mr. David Wilson, Operations

Training Supervisor, and Mr. Mark Bates, Senior Operations Engineer, arrangements were

made for the administration of licensing examinations at the Surry Power Station. The operating

test is scheduled to be administered the week of July 20, 2009. The written examination is

scheduled to be administered the week of July 27, 2009. The on-site preparatory week is

scheduled for the week of June 29, 2009.

As agreed during the telephone conversation, the staff of the U.S. Nuclear Regulatory

Commission (NRC) will prepare the written examination and your staff will prepare the operating

test based on the guidelines in Revision 9, Supplement 1, of NUREG-1021, "Operator Licensing

Examination Standards for Power Reactors." Your staff will be given the opportunity to review

the written examination during the week of May 29, 2009. The NRC regional office will discuss

with your staff any changes to the operating test that might be necessary before the tests are

administered. Your staff has also agreed to make copies of all examination materials that are

necessary for administering the examination.

To meet the above schedule, it will be necessary for your staff to furnish the reference materials

identified in Attachment 3 to ES-201 by February 6, 2009. The operating test outline will be due

by April 27, 2009 and the operating tests will be due by June 8, 2009. Pursuant to Title 10,

Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized

representative of the facility licensee shall approve the outline and test before they are

submitted to the NRC for review and approval. All materials shall be complete and ready-to-

use.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in

your response be contained in a separate enclosure and appropriately marked. Any delay in

receiving the required examination and reference materials, or the submittal of inadequate or

incomplete materials, may cause the examinations to be rescheduled.

VEPCO

2

In order to conduct the requested written examinations and operating tests, it will be necessary

for your staff to provide adequate space and accommodations in accordance with ES-402, and

to make the simulation facility available on the dates noted above. In accordance with ES-302,

your staff should retain the original simulator performance data (e.g., system pressures,

temperatures, and levels) generated during the dynamic operating tests until the examination

results are final.

Appendix E of NUREG-1021 contains a number of NRC policies and guidelines that will be in

effect while the written examinations and operating tests are being administered.

To permit timely NRC review and evaluation, your staff should submit preliminary reactor

operator and senior reactor operator license applications (Office of Management and Budget

(OMB) approval number 3150-0090), medical certifications (OMB approval number 3150-0024),

and waiver requests (if any)(OMB approval number 3150-0090) at least 30 days before the first

examination date. If the applications are not received at least 30 days before the examination

date, a postponement may be necessary. Signed applications certifying that all training has

been completed should be submitted at least 14 days before the first examination date.

This letter contains information collections that are subject to the Paperwork Reduction Act of

1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under

approval number 3150-0018, which expires on June 30, 2009. The public reporting burden for

this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time

for reviewing instructions, gathering and maintaining the data needed, writing the examinations,

and completing and reviewing the collection of information. Send comments on any aspect of

this collection of information, including suggestions for reducing the burden, to the Information

and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission,

Washington, DC 20555-0001, or by Internet electronic mail at infocollectsresource@nrc.gov;

and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-

0018), Office of Management and Budget, Washington, DC 20503.

The NRC may not conduct or sponsor, and a person is not required to respond to, a collection

of information unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS

is accessible from the NRC Web site at http://www/nrc.gov/readingrm/adams.html (the Public

Electronic Reading Room).

VEPCO

3

Thank you for your cooperation in this matter. Mr. Wilson has been advised of the policies and

guidelines referenced in this letter. If you have any questions regarding the NRC's examination

procedures and guidelines, please contact Mr. Mark Bates at (404) 562-4612, (Internet E-mail:

Mark.Bates@nrc.gov) or me at (404) 562-4550, (Internet E-mail: Malcolm.Widmann@nrc.gov).

Sincerely,

/RA/

Malcolm T. Widmann, Chief

Operations Branch

Division of Reactor Safety

Docket Nos.: 50-280, 50-281

License Nos.: DPR-32, DPR-37

(cc see page 4)

VEPCO

4

cc: Gerald T. Bischof

Site Vice President

Surry Power Station

Virginia Electric and Power Company

Electronic Mail Distribution

Sonny Stanley

Director, Nuclear Safety and Licensing

Virginia Electric and Power Company

Electronic Mail Distribution

Lillian M. Cuoco, Esq.

Senior Counsel

Dominion Resources Services, Inc.

Electronic Mail Distribution

Chris L. Funderburk

Director, Nuclear Licensing &

Operations Support

Virginia Electric and Power Company

Electronic Mail Distribution

Virginia State Corporation Commission

Division of Energy Regulation

P.O. Box 1197

Richmond, VA 23209

Attorney General

Supreme Court Building

900 East Main Street

Richmond, VA 23219

Senior Resident Inspector

Surry Power Station

U.S. Nuclear Regulatory Commission

5850 Hog Island Rd

Surry, VA 23883

Michael M. Cline

Director

Virginia Department of Emergency

Services Management

Electronic Mail Distribution

Virginia Electric and Power Company

ATTN: Mr. Andy T. Barbee

Manager of Nuclear Training

Surry power Station

5570 Hog Island road

Surry, VA 23883

VEPCO

5

Letter to David A. Christian from Malcolm T. Widmann dated February 9, 2009.

SUBJECT:

REACTOR AND SENIOR REACTOR OPERATOR INITIAL EXAMINATIONS -

SURRY POWER STATION - 05000280/2009301 AND 05000281/2009301

Distribution:

RIDSNRRDIRS

PUBLIC

S. P. Lingam, NRR (PM: NA, SUR)

XG PUBLICLY AVAILABLE

G NON-PUBLICLY AVAILABLE

G SENSITIVE

XG NON-SENSITIVE

ADAMS: XG Yes

ACCESSION NUMBER:_________________________

XG SUNSI REVIEW COMPLETE

OFFICE

RII:DRS

RII:DRS

RII:DRP

SIGNATURE

NAME

MBates

GMcCoy

MWidmann

DATE

02/6/2009

02/6/2009

02/9/2009

E-MAIL COPY?

YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO YES

NO

OFFICIAL

RECORD

COPY DOCUMENT

NAME:

O:\\SURRY

EXAMINATIONS\\INITIAL

EXAM

2009-

301\\CORRESPONDENCE\\2009 -301 SURRY CORPORATE NOTIFICATION LETTER (MAB) REV 0.DOC