ML17103A627: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(8 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML17103A627
| number = ML17103A627
| issue date = 04/13/2017
| issue date = 04/13/2017
| title = South Texas Project Electric Generating Station- Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000498/2017007 and 05000499/2017007) and Request for Information
| title = Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000498/2017007 and 05000499/2017007) and Request for Information
| author name = Farnholtz T R
| author name = Farnholtz T
| author affiliation = NRC/RGN-IV/DRS/EB-1
| author affiliation = NRC/RGN-IV/DRS/EB-1
| addressee name = Powell G T
| addressee name = Powell G
| addressee affiliation = South Texas Project Nuclear Operating Co
| addressee affiliation = South Texas Project Nuclear Operating Co
| docket = 05000498, 05000499
| docket = 05000498, 05000499
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter: April 13, 2017   Mr. G. T. Powell  
{{#Wiki_filter:April 13, 2017  
Mr. G. T. Powell  
Executive Vice President and CNO  
Executive Vice President and CNO  
STP Nuclear Operating Company  
STP Nuclear Operating Company  
P.O. Box 289  
P.O. Box 289  
Wadsworth, TX 77483 SUBJECT: SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND
Wadsworth, TX 77483  
EXPERIMENTS INSPECTION (05000498/2017007 AND 05000499/2017007) AND REQUEST FOR INFORMATION  Dear Mr. Powell:
   
   
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff will conduct the baseline inspection of changes, tests, experiments, and permanent plant
SUBJECT:
modifications at your South Texas Project Electric Generating Station from May 22-26, 2017.  The inspection will consist of three reactor inspectors from the NRC's Region IV office for one week.  The inspection will be conducted in accordance with NRC Inspection
SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION -  
Procedure 71111.17T, "Evaluations of Changes, Tests, and Experiments." 
NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND
EXPERIMENTS INSPECTION (05000498/2017007 AND 05000499/2017007)
AND REQUEST FOR INFORMATION
   
   
Experience has shown that this inspection is resource intensive for both the NRC inspectors and your staff.  In order to minimize the impact to your on-site resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection.   
Dear Mr. Powell:
Please note that the documents are requested to be provided by May 15, 2017.  Upon review of these documents, the inspectors will select additional documentation for review upon arrival.  It  
is important that all of these documents are up-to-date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.  
The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff
will conduct the baseline inspection of changes, tests, experiments, and permanent plant
modifications at your South Texas Project Electric Generating Station from May 22-26, 2017. 
The inspection will consist of three reactor inspectors from the NRCs Region IV office for
one week.  The inspection will be conducted in accordance with NRC Inspection
Procedure 71111.17T, Evaluations of Changes, Tests, and Experiments. 
Experience has shown that this inspection is resource intensive for both the NRC inspectors  
and your staff.  In order to minimize the impact to your on-site resources and to ensure a  
productive inspection, we have enclosed a request for documents needed for this inspection.   
Please note that the documents are requested to be provided by May 15, 2017.  Upon review of  
these documents, the inspectors will select additional documentation for review upon arrival.  It  
is important that all of these documents are up-to-date and complete in order to minimize the  
number of additional documents requested during the preparation and/or the on-site portions of  
the inspection.  
   
   
We have discussed the schedule for these inspection activities with your staff and understand  
We have discussed the schedule for these inspection activities with your staff and understand  
that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing  
that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing  
organization.  If there are any questions about this inspection or the material requested, please contact the lead inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at Chris.Smith@nrc.gov.   
organization.  If there are any questions about this inspection or the material requested, please  
contact the lead inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at  
Chris.Smith@nrc.gov.   
   
   
This letter does not contain new or amended information collection requirements subject   
This letter does not contain new or amended information collection requirements subject   
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to  
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.).  Existing information  
respond to, a request for information or an information collection requirement unless the  UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511
collection requirements were approved by the Office of Management and Budget, control  
G. Powell 2  requesting document displays a currently valid Office of Management and Budget control number.  
number 3150-0011.  The NRC may not conduct or sponsor, and a person is not required to  
  In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).     Sincerely,   /RA/     Thomas R. Farnholtz, Chief  Engineering Branch 1  
respond to, a request for information or an information collection requirement unless the  
  Division of Reactor Safety  
   
UNITED STATES  
NUCLEAR REGULATORY COMMISSION  
REGION IV  
1600 E. LAMAR BLVD  
ARLINGTON, TX 76011-4511  
 
G. Powell  
2  
   
requesting document displays a currently valid Office of Management and Budget control  
number.  
   
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its  
enclosure will be available electronically for public inspection in the NRC Public Document  
Room or from the Publicly Available Records (PARS) component of NRC's document system  
(ADAMS).  ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).  
Sincerely,  
/RA/  
Thomas R. Farnholtz, Chief  
   
Engineering Branch 1  
   
Division of Reactor Safety  
Docket Nos. 50-498 and 50-499
License Nos. NPF-76 and NPF-80 
   
   
  Docket Nos. 50-498 and 50-499
License Nos. NPF-76 and NPF-80   
Enclosure:   
Enclosure:   
Evaluations of Changes, Tests,   and Experiments Inspection   Request for Information  
Evaluations of Changes, Tests,
  and Experiments Inspection
  Request for Information  
   
   
cc:  Electronic Distribution for STP  
cc:  Electronic Distribution for STP  
   
G. Powell 3  SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION - NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND EXPERIMENTS INSPECTION
(05000498/2017007 AND 05000499/2017007) AND REQUEST FOR INFORMATION -  April 13, 2017  DISTRIBUTION: KKennedy, RA
SMorris, DRA
TPruett, DRP AVegel, DRS JClark, DRS
RLantz, DRP
JBowen, RIV/OEDO
KFuller, RC VDricks, ORA JWeil, OCA
LRenger, NRR
AMoreno, RIV/CAO
BMaier, RSLO THipschman, IPAT EUribe, IPAT
MHerrera, DRMA
RIV ACES 
NTaylor, DRP
DProulx, DRP JMelfi, DRP SJanicki, DRP
FSanchez, DRP
NHernandez, DRP
HWright, DRP 
   
   
   
   
   
   
  ADAMS ACCESSION NUMBER:  ML17103A627  SUNSI Review  ADAMS:   Non-Publicly Available  Non-Sensitive Keyword:  By:  TFarnholtz  Yes    No  Publicly Available  Sensitive  NRC-002 OFFICE RI:EB1 C:EB1     NAME CSmith TFarnholtz    SIGNATURE /RA/ /RA/    DATE 4/12/17 4/13/17    OFFICIAL RECORD COPY 
 
  Enclosure Request for Information Evaluations of Changes, Tests, and Experiments Inspection South Texas Project Electric Generating Station, Units 1 and 2 
 
Inspection Report:  05000498/2017007; 05000499/2017007
  ML17103A627  
  SUNSI Review   
ADAMS:  
Non-Publicly Available  
  Non-Sensitive  
Keyword:   
By:  TFarnholtz  
  Yes    No  
  Publicly Available  
  Sensitive   
NRC-002  
OFFICE  
RI:EB1  
C:EB1  
   
   
   
Inspection Dates:  May 22-26, 2017
Inspection Procedure: IP 71111.17T, "Evaluations of Changes, Tests, and Experiments" 
Lead Inspector:  Chris Smith, Reactor Inspector 
   
   
Information Requested for the In-Office Preparation Week  The following information should be sent to the Region IV office in hard copy or electronic  
NAME
CSmith
TFarnholtz
SIGNATURE
/RA/
/RA/
DATE
4/12/17 
4/13/17
 
Enclosure
Request for Information
Evaluations of Changes, Tests, and Experiments Inspection
South Texas Project Electric Generating Station, Units 1 and 2
Inspection Report: 
05000498/2017007; 05000499/2017007
Inspection Dates:
May 22-26, 2017
Inspection Procedure:
IP 71111.17T, Evaluations of Changes, Tests, and Experiments
Lead Inspector:
Chris Smith, Reactor Inspector
Information Requested for the In-Office Preparation Week  
   
The following information should be sent to the Region IV office in hard copy or electronic  
format (preferred) by May 15, 2017, to the attention of Chris Smith.  We request that you  
format (preferred) by May 15, 2017, to the attention of Chris Smith.  We request that you  
categorize the documents in your response with the numbered list below.  If only hard copies of the requested documents are available or if the electronic format is too large, please inform the lead inspector and provide the documents on the first day of the on-site inspection.  Also, the  
categorize the documents in your response with the numbered list below.  If only hard copies of  
inspectors will select specific items from the information requested below and request from your staff additional documents needed during the on-site inspection weeks.  We ask that the specific  
the requested documents are available or if the electronic format is too large, please inform the  
items requested be available and ready for review on the first day of inspection.  If you have any questions regarding this information request, please contact the lead inspector as soon as possible.  1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.  2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully implemented changes, tests, and experiments performed since the last triennial modification inspection that did not result in an evaluation.   3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes, tests, and experiments performed since the last triennial 10 CFR 50.59 inspection that  
lead inspector and provide the documents on the first day of the on-site inspection.  Also, the  
did not result in an application for a license amendment.   4. A list with descriptions of all temporary plant modifications implemented since the last triennial 10 CFR 50.59 inspection.  
inspectors will select specific items from the information requested below and request from your  
  5. A list with descriptions of all compensatory actions for degraded or non-conforming conditions implemented since the last triennial 10 CFR 50.59 inspection.   6. A list with descriptions of all corrective action documents related to 10 CFR 50.59 screenings and evaluations since the last triennial 10 CFR 50.59 inspection.   7. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations, including qualification dates.  8. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or evaluations, including qualification dates.   
staff additional documents needed during the on-site inspection weeks.  We ask that the specific  
  2  9. Current revisions of the Technical Specifications and Bases and the Updated Final Safety Analysis Report.  10. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59 programs.   11. A copy of the most recent submittal of the report containing a brief description of any changes, tests, and experiments, including a summary of the evaluation of each, required by 10 CFR 50.59(d)(2).   12. A list of systems and system designators and a set of one-line (i.e., simplified) system diagrams.  Note:  Descriptions should be brief but of sufficient detail to ensure that inspectors can determine the safety and/or risk significance of the screenings, evaluations, and modifications.  
items requested be available and ready for review on the first day of inspection.  If you have any  
questions regarding this information request, please contact the lead inspector as soon as  
possible.  
   
1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.  
   
2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully  
implemented changes, tests, and experiments performed since the last triennial  
modification inspection that did not result in an evaluation.
3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,  
tests, and experiments performed since the last triennial 10 CFR 50.59 inspection that  
did not result in an application for a license amendment.  
4. A list with descriptions of all temporary plant modifications implemented since the last  
triennial 10 CFR 50.59 inspection.  
   
5. A list with descriptions of all compensatory actions for degraded or non-conforming  
conditions implemented since the last triennial 10 CFR 50.59 inspection.
6. A list with descriptions of all corrective action documents related to 10 CFR 50.59  
screenings and evaluations since the last triennial 10 CFR 50.59 inspection.  
7. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,  
including qualification dates.  
   
8. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or  
evaluations, including qualification dates.  
 
   
2  
   
9. Current revisions of the Technical Specifications and Bases and the Updated Final  
Safety Analysis Report.  
   
10. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59  
programs.  
11. A copy of the most recent submittal of the report containing a brief description of any  
changes, tests, and experiments, including a summary of the evaluation of each,  
required by 10 CFR 50.59(d)(2).  
12. A list of systems and system designators and a set of one-line (i.e., simplified) system  
diagrams.  
   
Note:  Descriptions should be brief but of sufficient detail to ensure that inspectors can  
determine the safety and/or risk significance of the screenings, evaluations, and modifications.  
   
   
Inspector Contact Information:  
Inspector Contact Information:  
  Chris Smith Reactor Inspector  
   
Chris Smith  
Reactor Inspector  
817-200-1095  
817-200-1095  
Chris.Smith@nrc.gov   
Chris.Smith@nrc.gov   
  Wes Cullum Reactor Inspector  
   
Wes Cullum  
Reactor Inspector  
817-200-1563  
817-200-1563  
Wes.Cullum@nrc.gov  
Wes.Cullum@nrc.gov  
  Nnaerika Okonkwo Reactor Inspector  
Nnaerika Okonkwo  
Reactor Inspector  
817-200-1114  
817-200-1114  
Nnaerika.Okonkwo@nrc.gov
Nnaerika.Okonkwo@nrc.gov
  Mailing Address:   
 
Mailing Address:  
   
U.S. NRC, Region IV  
U.S. NRC, Region IV  
Attn:  Chris Smith  
Attn:  Chris Smith  
1600 East Lamar Blvd. Arlington, TX 76011-4125  
1600 East Lamar Blvd.  
 
Arlington, TX 76011-4125
}}
}}

Latest revision as of 10:27, 9 January 2025

Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000498/2017007 and 05000499/2017007) and Request for Information
ML17103A627
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 04/13/2017
From: Thomas Farnholtz
Region 4 Engineering Branch 1
To: Gerry Powell
South Texas
References
IR 2017007
Download: ML17103A627 (5)


See also: IR 05000498/2017007

Text

April 13, 2017

Mr. G. T. Powell

Executive Vice President and CNO

STP Nuclear Operating Company

P.O. Box 289

Wadsworth, TX 77483

SUBJECT:

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION -

NOTIFICATION OF EVALUATIONS OF CHANGES, TESTS, AND

EXPERIMENTS INSPECTION (05000498/2017007 AND 05000499/2017007)

AND REQUEST FOR INFORMATION

Dear Mr. Powell:

The purpose of this letter is to notify you that U.S. Nuclear Regulatory Commission (NRC) staff

will conduct the baseline inspection of changes, tests, experiments, and permanent plant

modifications at your South Texas Project Electric Generating Station from May 22-26, 2017.

The inspection will consist of three reactor inspectors from the NRCs Region IV office for

one week. The inspection will be conducted in accordance with NRC Inspection

Procedure 71111.17T, Evaluations of Changes, Tests, and Experiments.

Experience has shown that this inspection is resource intensive for both the NRC inspectors

and your staff. In order to minimize the impact to your on-site resources and to ensure a

productive inspection, we have enclosed a request for documents needed for this inspection.

Please note that the documents are requested to be provided by May 15, 2017. Upon review of

these documents, the inspectors will select additional documentation for review upon arrival. It

is important that all of these documents are up-to-date and complete in order to minimize the

number of additional documents requested during the preparation and/or the on-site portions of

the inspection.

We have discussed the schedule for these inspection activities with your staff and understand

that our regulatory contact for this inspection will be Rafael Gonzalez of your licensing

organization. If there are any questions about this inspection or the material requested, please

contact the lead inspector, Chris Smith, by telephone at 817-200-1095 or by e-mail at

Chris.Smith@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, control

number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD

ARLINGTON, TX 76011-4511

G. Powell

2

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC's document system

(ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Thomas R. Farnholtz, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-498 and 50-499

License Nos. NPF-76 and NPF-80

Enclosure:

Evaluations of Changes, Tests,

and Experiments Inspection

Request for Information

cc: Electronic Distribution for STP

ML17103A627

SUNSI Review

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: TFarnholtz

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

RI:EB1

C:EB1

NAME

CSmith

TFarnholtz

SIGNATURE

/RA/

/RA/

DATE

4/12/17

4/13/17

Enclosure

Request for Information

Evaluations of Changes, Tests, and Experiments Inspection

South Texas Project Electric Generating Station, Units 1 and 2

Inspection Report: 05000498/2017007; 05000499/2017007

Inspection Dates:

May 22-26, 2017

Inspection Procedure:

IP 71111.17T, Evaluations of Changes, Tests, and Experiments

Lead Inspector:

Chris Smith, Reactor Inspector

Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (preferred) by May 15, 2017, to the attention of Chris Smith. We request that you

categorize the documents in your response with the numbered list below. If only hard copies of

the requested documents are available or if the electronic format is too large, please inform the

lead inspector and provide the documents on the first day of the on-site inspection. Also, the

inspectors will select specific items from the information requested below and request from your

staff additional documents needed during the on-site inspection weeks. We ask that the specific

items requested be available and ready for review on the first day of inspection. If you have any

questions regarding this information request, please contact the lead inspector as soon as

possible.

1. Procedure(s) for conducting 10 CFR 50.59 screenings and evaluations.

2. A list with descriptions of all 10 CFR 50.59 screenings (or equivalent) of fully

implemented changes, tests, and experiments performed since the last triennial

modification inspection that did not result in an evaluation.

3. A list with descriptions of all 10 CFR 50.59 evaluations of fully implemented changes,

tests, and experiments performed since the last triennial 10 CFR 50.59 inspection that

did not result in an application for a license amendment.

4. A list with descriptions of all temporary plant modifications implemented since the last

triennial 10 CFR 50.59 inspection.

5. A list with descriptions of all compensatory actions for degraded or non-conforming

conditions implemented since the last triennial 10 CFR 50.59 inspection.

6. A list with descriptions of all corrective action documents related to 10 CFR 50.59

screenings and evaluations since the last triennial 10 CFR 50.59 inspection.

7. A list of personnel qualified to prepare 10 CFR 50.59 screenings and/or evaluations,

including qualification dates.

8. A list of personnel qualified to review and approve 10 CFR 50.59 screenings and/or

evaluations, including qualification dates.

2

9. Current revisions of the Technical Specifications and Bases and the Updated Final

Safety Analysis Report.

10. A copy of the most recent audits/self-assessments performed of the 10 CFR 50.59

programs.

11. A copy of the most recent submittal of the report containing a brief description of any

changes, tests, and experiments, including a summary of the evaluation of each,

required by 10 CFR 50.59(d)(2).

12. A list of systems and system designators and a set of one-line (i.e., simplified) system

diagrams.

Note: Descriptions should be brief but of sufficient detail to ensure that inspectors can

determine the safety and/or risk significance of the screenings, evaluations, and modifications.

Inspector Contact Information:

Chris Smith

Reactor Inspector

817-200-1095

Chris.Smith@nrc.gov

Wes Cullum

Reactor Inspector

817-200-1563

Wes.Cullum@nrc.gov

Nnaerika Okonkwo

Reactor Inspector

817-200-1114

Nnaerika.Okonkwo@nrc.gov

Mailing Address:

U.S. NRC, Region IV

Attn: Chris Smith

1600 East Lamar Blvd.

Arlington, TX 76011-4125