Line 3: Line 3:
| issue date = 09/17/1986
| issue date = 09/17/1986
| title = Responds to NRC 860728 & 0808 Ltrs Re Violations Noted in Insp Repts 50-259/86-22,50-260/86-22 & 50-296/86-22. Corrective Actions:Hold Placed on All Cable Pulling Activities Pending Rev to Incorporate Specs G-38 & G-40
| title = Responds to NRC 860728 & 0808 Ltrs Re Violations Noted in Insp Repts 50-259/86-22,50-260/86-22 & 50-296/86-22. Corrective Actions:Hold Placed on All Cable Pulling Activities Pending Rev to Incorporate Specs G-38 & G-40
| author name = GRIDLEY R
| author name = Gridley R
| author affiliation = TENNESSEE VALLEY AUTHORITY
| author affiliation = TENNESSEE VALLEY AUTHORITY
| addressee name = GRACE J N
| addressee name = Grace J
| addressee affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
| addressee affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
| docket = 05000259, 05000260, 05000296
| docket = 05000259, 05000260, 05000296
Line 14: Line 14:
| page count = 8
| page count = 8
}}
}}
See also: [[followed by::IR 05000259/1986022]]


=Text=
=Text=
{{#Wiki_filter:TENNESSEE VALLEY AUTHORITY cHATTANQQGA.
{{#Wiki_filter:TENNESSEE VALLEYAUTHORITY cHATTANQQGA. TENNEssEE 374ot 5B 157B Lookout P1eoe-i Q l7 $86 U.S. Nuclear Regulatory Commission Region II Attn:
TENNEssEE 374ot 5B 157B Lookout P1eoe-i Q l7$86 U.S.Nuclear Regulatory
Dr. J. Nelson Grace, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323
Commission
 
Region II Attn: Dr.J.Nelson Grace, Regional Administrator
==Dear Dr. Grace:==
101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323 Dear Dr.Grace: BROWNS FERRY NUCLEAR PLANT UNITS 1, 2, AND 3-NRC-OIE REGION II INSPECTION
BROWNS FERRY NUCLEAR PLANT UNITS 1, 2, AND 3 NRC-OIE REGION II INSPECTION REPORT 50-259/86-22,
REPORT 50-259/86-22,-260/86-22, 96/86-22-RESPONSE TO VIOLATION Enclosed is our response to G.G.Zech's July 28 and August 8, 1986 letters to S.A.White transmit.ting IE Inspection
-260/86-22, 96/86-22
Report Nos.50-259/86-22,-260/86-22, and-296/86-22
 
for our Browns Ferry Nuclear Plant which cited TVA with one Severity Level IV Violation.
===RESPONSE===
This response was due September 8, 1986.An extension to September 22, 1986 was discussed between M.J.May and Floyd Cantrell of your staff on September 4, 1986.If you have any questions, please get in touch with M.J.May at (205)729-3566.To the best of my knowledge, I declare the statements
TO VIOLATION Enclosed is our response to G.
contained herein are complete and true.Very truly yours, TENNESSEE VALLEY AUTHORITY R.ridley, D'rector'Nuclear Safet and Licensing, Enclosure cc: Mr.James Taylor, Director (Enclosure)
G. Zech's July 28 and {{letter dated|date=August 8, 1986|text=August 8, 1986 letter}}s to S.
Office of Inspection
A. White transmit. ting IE Inspection Report Nos. 50-259/86-22,
and Enforcement
-260/86-22, and -296/86-22 for our Browns Ferry Nuclear Plant which cited TVA with one Severity Level IV Violation.
U.S.Nuclear Regulatory
This response was due September 8,
Commission
1986.
Washington, D.C.20555 8610020087
An extension to September 22, 1986 was discussed between M. J.
860'717 PDR ADOCK 05000259 8'DR An Equal Opportunity
May and Floyd Cantrell of your staff on September 4, 1986.
Employer
If you have any questions, please get in touch with M. J.
rt  
May at (205) 729-3566.
RESPONSE NRC INSPECTION
To the best of my knowledge, I declare the statements contained herein are complete and true.
REPORT NOS.50-259/86-22, 50-260/86-22, AND 50-296/86-22
Very truly yours, TENNESSEE VALLEY AUTHORITY R.
GARY G.ZECH'S LETTERS TO S.A.WHITE DATED JULY 28 AND AUGUST 8, 1986 Item 1 10 CFR 50, Appendix B, Criterion III requires that measures shall be established
ridley, D'rector
to assure applicable
'Nuclear Safet and Licensing, Enclosure cc:
regulatory
Mr. James Taylor, Director (Enclosure)
requirements
Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D.C.
and the design basis are met.These measures shall include provisions
20555 8610020087 860'717 PDR ADOCK 05000259 8'DR An Equal Opportunity Employer
to assure that appropriate
 
quality standards are specified and included in design documents and that deviations
rt
from such standards are controlled.
 
Contrary to the above, this requirement
===RESPONSE===
was not met from January 15-June 16, 1986, in that newly implemented
NRC INSPECTION REPORT NOS.
standards for control of installation
50-259/86-22, 50-260/86-22, AND 50-296/86-22 GARY G.
of insulated cables (TVA General Specification
ZECH'S LETTERS TO S. A. WHITE DATED JULY 28 AND AUGUST 8, 1986 Item 1 10 CFR 50, Appendix B, Criterion III requires that measures shall be established to assure applicable regulatory requirements and the design basis are met.
38)were not, specified for use on facility design modifications
These measures shall include provisions to assure that appropriate quality standards are specified and included in design documents and that deviations from such standards are controlled.
in progress prior to January 15, 1986.The TVA Office of Engineering
Contrary to the above, this requirement was not met from January 15 June 16, 1986, in that newly implemented standards for control of installation of insulated cables (TVA General Specification
implemented
: 38) were not, specified for use on facility design modifications in progress prior to January 15, 1986.
the new cable installation
The TVA Office of Engineering implemented the new cable installation criteria of General Specification 38, revision 7, at all TVA facilities with the exception of Browns Ferry (BFN) as of January 15, 1986.
criteria of General Specification
General Specification 38 was issued for all TVA sites to have insulated cable installations done consistently at all TVA nuclear plants and to bring TVA's cable installation practices up to a level consistent with current industry practice.
38, revision 7, at all TVA facilities
General Specification 38, revision 7, was issued on January 15, 1986 to June 16, 1986 (inspection date) the licensee did not implement the cable installation specification G-38 at BFN although this'orrective action was deemed necessary at all other TVA facilities to meet cable installation standards.
with the exception of Browns Ferry (BFN)as of January 15, 1986.General Specification
This is a Severity Level IV violation (Supplement I).
38 was issued for all TVA sites to have insulated cable installations
1.
done consistently
Admission or Denial of the Alle ed Violation We admit that the violation occurred as stated.
at all TVA nuclear plants and to bring TVA's cable installation
2.
practices up to a level consistent
Reasons for the Violation
with current industry practice.General Specification
,All insulated cables installed at BFN before January 15, 1986, were installed to Construction Specification G-4, Cable Installation.
38, revision 7, was issued on January 15, 1986 to June 16, 1986 (inspection
TVA management decided that some modifications in process would be finished under Specifications G-3, Conduit. Instal'lation, and G-4, Cable Installation, instead of using the new Specifications G-38, Cable Installation, and G-40, Conduit, Installation.
date)the licensee did not implement the cable installation
 
specification
The use of G-38 cable installation often requires the use of its companion specification for conduit installation, G-40.
G-38 at BFN although this'orrective
Many modifications in progress for unit 2 would have to be redesigned and/or reconstructed in accordance with G-40 in order for a successful G-38 installation to proceed.
action was deemed necessary at all other TVA facilities
Since the G-38 terminology, "future modifications," was subject to interpretation, it was decided that certain modifications in process would be finished under the old specification.
to meet cable installation
Therefore, the following implementation strategy for the orderly transition to the G-38 and G-40 specifications at, BFN was chosen:
standards.
a.
This is a Severity Level IV violation (Supplement
Utilize G-3 and G-4 to complete remaining unit 2 outage work Eor which designs had been issued before January 15, 1986.
I).1.Admission or Denial of the Alle ed Violation We admit that the violation occurred as stated.2.Reasons for the Violation ,All insulated cables installed at BFN before January 15, 1986, were installed to Construction
b.
Specification
Incorporate G-38 and G-40 requ3.rements into unit 2 outage work for which designs had been issued on or after January 15, 1986.
G-4, Cable Installation.
c.
TVA management
G-38 and G-40 would be utilized Eor the unit 2 cable replacement activities in the drywell.
decided that some modifications
d.
in process would be finished under Specifications
G-38 and G-40 would be used for the future modification activities on units 1 and 3 when work resumed.
G-3, Conduit.Instal'lation, and G-4, Cable Installation, instead of using the new Specifications
3.
G-38, Cable Installation, and G-40, Conduit, Installation.  
Corrective Ste s Which Have Been Taken and Results Achieved On June 18, 1986 TVA placed a hold on all cable pulling at BFN.
The order stated that the hold would be lifted for each applicable section when the following conditions were met:
The use of G-38 cable installation
a.
often requires the use of its companion specification
Site instructions associated with cabl'e pulling activities must be revised or new procedures written to incorporate the requirements set forth in Specifications G-38 and G-40.
for conduit installation, G-40.Many modifications
b.
in progress for unit 2 would have to be redesigned
Site personnel involved in cable pulling activities must receive documented training in the revised site instructions.
and/or reconstructed
Quality Assurance verified compliance with the hold order through the surveillance process.
in accordance
4.
with G-40 in order for a successful
'Corrective Ste s Which Will Be Taken to Avoid Further Violations We will imp'lement standards G-38 and G-40 Eor new cable installation.
G-38 installation
However, both modification and maintenance personnel have requested numerous engineering interpretations in applying all the requirements of" G-38 and G-40 to restoration of existing cable/conduit installations.
to proceed.Since the G-38 terminology,"future modifications," was subject to interpretation, it was decided that certain modifications
Therefore, our Division of Nuclear Engineering is performing an evaluation
in process would be finished under the old specification.
 
Therefore, the following implementation
j
strategy for the orderly transition
 
to the G-38 and G-40 specifications
to determine the appropriate application of G-38 and G-40 to maintenance and modification routine restoration work, in order that we may continue activities without unnecessary documentation and replacement of existing cable and conduit installations.
at, BFN was chosen: a.Utilize G-3 and G-4 to complete remaining unit 2 outage work Eor which designs had been issued before January 15, 1986.b.Incorporate
The evaluation will take into account the necessary installation and inspection controls.
G-38 and G-40 requ3.rements
Until'hat evaluation is complete and appropriate procedural controls are in place, any maintenance or modification restoration activity deviating from G-38 or G-40 will be justified and documented before the work being performed.
into unit 2 outage work for which designs had been issued on or after January 15, 1986.c.G-38 and G-40 would be utilized Eor the unit 2 cable replacement
A status report will be submitted to the NRC by October 30, 1986.
activities
Several technical integrity verification programs are presently underway at BFN to demonstrate the integrity of cable installed under G-3 and G-4.
in the drywell.d.G-38 and G-40 would be used for the future modification
These are scheduled to be completed in the coming months.
activities
Preliminary results indicate that the installed cable is capable of reliable operation at several times the sidewall pressure and at lesser minimum bend radius than specified by the cable suppliers.
on units 1 and 3 when work resumed.3.Corrective
If any of the programs should indicate cases of inadequate cable conditions, new cable will b'e installed using the G-38 and G-40 revised installation instructions.
Ste s Which Have Been Taken and Results Achieved On June 18, 1986 TVA placed a hold on all cable pulling at BFN.The order stated that the hold would be lifted for each applicable
5.
section when the following conditions
Date When Full Com liance Mill Be Achieved 0
were met: a.Site instructions
Our integrity verification programs will be complete before restart of unit 2 at BFN.}}
associated
with cabl'e pulling activities
must be revised or new procedures
written to incorporate
the requirements
set forth in Specifications
G-38 and G-40.b.Site personnel involved in cable pulling activities
must receive documented
training in the revised site instructions.
Quality Assurance verified compliance
with the hold order through the surveillance
process.4.'Corrective
Ste s Which Will Be Taken to Avoid Further Violations
We will imp'lement
standards G-38 and G-40 Eor new cable installation.
However, both modification
and maintenance
personnel have requested numerous engineering
interpretations
in applying all the requirements
of" G-38 and G-40 to restoration
of existing cable/conduit
installations.
Therefore, our Division of Nuclear Engineering
is performing
an evaluation  
j  
to determine the appropriate
application
of G-38 and G-40 to maintenance
and modification
routine restoration
work, in order that we may continue activities
without unnecessary
documentation
and replacement
of existing cable and conduit installations.
The evaluation
will take into account the necessary installation
and inspection
controls.Until'hat evaluation
is complete and appropriate
procedural
controls are in place, any maintenance
or modification
restoration
activity deviating from G-38 or G-40 will be justified and documented
before the work being performed.
A status report will be submitted to the NRC by October 30, 1986.Several technical integrity verification
programs are presently underway at BFN to demonstrate
the integrity of cable installed under G-3 and G-4.These are scheduled to be completed in the coming months.Preliminary
results indicate that the installed cable is capable of reliable operation at several times the sidewall pressure and at lesser minimum bend radius than specified by the cable suppliers.
If any of the programs should indicate cases of inadequate
cable conditions, new cable will b'e installed using the G-38 and G-40 revised installation
instructions.
5.Date When Full Com liance Mill Be Achieved 0 Our integrity verification
programs will be complete before restart of unit 2 at BFN.
}}

Latest revision as of 02:53, 7 January 2025

Responds to NRC 860728 & 0808 Ltrs Re Violations Noted in Insp Repts 50-259/86-22,50-260/86-22 & 50-296/86-22. Corrective Actions:Hold Placed on All Cable Pulling Activities Pending Rev to Incorporate Specs G-38 & G-40
ML18031A844
Person / Time
Site: Browns Ferry  
Issue date: 09/17/1986
From: Gridley R
TENNESSEE VALLEY AUTHORITY
To: Grace J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
NUDOCS 8610020087
Download: ML18031A844 (8)


Text

TENNESSEE VALLEYAUTHORITY cHATTANQQGA. TENNEssEE 374ot 5B 157B Lookout P1eoe-i Q l7 $86 U.S. Nuclear Regulatory Commission Region II Attn:

Dr. J. Nelson Grace, Regional Administrator 101 Marietta Street, NW, Suite 2900 Atlanta, Georgia 30323

Dear Dr. Grace:

BROWNS FERRY NUCLEAR PLANT UNITS 1, 2, AND 3 NRC-OIE REGION II INSPECTION REPORT 50-259/86-22,

-260/86-22, 96/86-22

RESPONSE

TO VIOLATION Enclosed is our response to G.

G. Zech's July 28 and August 8, 1986 letters to S.

A. White transmit. ting IE Inspection Report Nos. 50-259/86-22,

-260/86-22, and -296/86-22 for our Browns Ferry Nuclear Plant which cited TVA with one Severity Level IV Violation.

This response was due September 8,

1986.

An extension to September 22, 1986 was discussed between M. J.

May and Floyd Cantrell of your staff on September 4, 1986.

If you have any questions, please get in touch with M. J.

May at (205) 729-3566.

To the best of my knowledge, I declare the statements contained herein are complete and true.

Very truly yours, TENNESSEE VALLEY AUTHORITY R.

ridley, D'rector

'Nuclear Safet and Licensing, Enclosure cc:

Mr. James Taylor, Director (Enclosure)

Office of Inspection and Enforcement U. S. Nuclear Regulatory Commission Washington, D.C.

20555 8610020087 860'717 PDR ADOCK 05000259 8'DR An Equal Opportunity Employer

rt

RESPONSE

NRC INSPECTION REPORT NOS.

50-259/86-22, 50-260/86-22, AND 50-296/86-22 GARY G.

ZECH'S LETTERS TO S. A. WHITE DATED JULY 28 AND AUGUST 8, 1986 Item 1 10 CFR 50, Appendix B, Criterion III requires that measures shall be established to assure applicable regulatory requirements and the design basis are met.

These measures shall include provisions to assure that appropriate quality standards are specified and included in design documents and that deviations from such standards are controlled.

Contrary to the above, this requirement was not met from January 15 June 16, 1986, in that newly implemented standards for control of installation of insulated cables (TVA General Specification

38) were not, specified for use on facility design modifications in progress prior to January 15, 1986.

The TVA Office of Engineering implemented the new cable installation criteria of General Specification 38, revision 7, at all TVA facilities with the exception of Browns Ferry (BFN) as of January 15, 1986.

General Specification 38 was issued for all TVA sites to have insulated cable installations done consistently at all TVA nuclear plants and to bring TVA's cable installation practices up to a level consistent with current industry practice.

General Specification 38, revision 7, was issued on January 15, 1986 to June 16, 1986 (inspection date) the licensee did not implement the cable installation specification G-38 at BFN although this'orrective action was deemed necessary at all other TVA facilities to meet cable installation standards.

This is a Severity Level IV violation (Supplement I).

1.

Admission or Denial of the Alle ed Violation We admit that the violation occurred as stated.

2.

Reasons for the Violation

,All insulated cables installed at BFN before January 15, 1986, were installed to Construction Specification G-4, Cable Installation.

TVA management decided that some modifications in process would be finished under Specifications G-3, Conduit. Instal'lation, and G-4, Cable Installation, instead of using the new Specifications G-38, Cable Installation, and G-40, Conduit, Installation.

The use of G-38 cable installation often requires the use of its companion specification for conduit installation, G-40.

Many modifications in progress for unit 2 would have to be redesigned and/or reconstructed in accordance with G-40 in order for a successful G-38 installation to proceed.

Since the G-38 terminology, "future modifications," was subject to interpretation, it was decided that certain modifications in process would be finished under the old specification.

Therefore, the following implementation strategy for the orderly transition to the G-38 and G-40 specifications at, BFN was chosen:

a.

Utilize G-3 and G-4 to complete remaining unit 2 outage work Eor which designs had been issued before January 15, 1986.

b.

Incorporate G-38 and G-40 requ3.rements into unit 2 outage work for which designs had been issued on or after January 15, 1986.

c.

G-38 and G-40 would be utilized Eor the unit 2 cable replacement activities in the drywell.

d.

G-38 and G-40 would be used for the future modification activities on units 1 and 3 when work resumed.

3.

Corrective Ste s Which Have Been Taken and Results Achieved On June 18, 1986 TVA placed a hold on all cable pulling at BFN.

The order stated that the hold would be lifted for each applicable section when the following conditions were met:

a.

Site instructions associated with cabl'e pulling activities must be revised or new procedures written to incorporate the requirements set forth in Specifications G-38 and G-40.

b.

Site personnel involved in cable pulling activities must receive documented training in the revised site instructions.

Quality Assurance verified compliance with the hold order through the surveillance process.

4.

'Corrective Ste s Which Will Be Taken to Avoid Further Violations We will imp'lement standards G-38 and G-40 Eor new cable installation.

However, both modification and maintenance personnel have requested numerous engineering interpretations in applying all the requirements of" G-38 and G-40 to restoration of existing cable/conduit installations.

Therefore, our Division of Nuclear Engineering is performing an evaluation

j

to determine the appropriate application of G-38 and G-40 to maintenance and modification routine restoration work, in order that we may continue activities without unnecessary documentation and replacement of existing cable and conduit installations.

The evaluation will take into account the necessary installation and inspection controls.

Until'hat evaluation is complete and appropriate procedural controls are in place, any maintenance or modification restoration activity deviating from G-38 or G-40 will be justified and documented before the work being performed.

A status report will be submitted to the NRC by October 30, 1986.

Several technical integrity verification programs are presently underway at BFN to demonstrate the integrity of cable installed under G-3 and G-4.

These are scheduled to be completed in the coming months.

Preliminary results indicate that the installed cable is capable of reliable operation at several times the sidewall pressure and at lesser minimum bend radius than specified by the cable suppliers.

If any of the programs should indicate cases of inadequate cable conditions, new cable will b'e installed using the G-38 and G-40 revised installation instructions.

5.

Date When Full Com liance Mill Be Achieved 0

Our integrity verification programs will be complete before restart of unit 2 at BFN.