| issue date = 06/24/1982
| issue date = 06/24/1982
| title = Submits New Requalification Training Schedule for Approval
| title = Submits New Requalification Training Schedule for Approval
| author name = UDERITZ R A
| author name = Uderitz R
| author affiliation = PUBLIC SERVICE ELECTRIC & GAS CO. OF NEW JERSEY
| author affiliation = PUBLIC SERVICE ELECTRIC & GAS CO. OF NEW JERSEY
| addressee name = VARGA S A
| addressee name = Varga S
| addressee affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR)
| addressee affiliation = NRC OFFICE OF NUCLEAR REACTOR REGULATION (NRR)
| docket = 05000272, 05000311
| docket = 05000272, 05000311
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:Richard A. Uderitz Vice President  
{{#Wiki_filter:Richard A. Uderitz Vice President -
-Nuclear Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609 935-6010 June 24, 1982 Mr. Steven A. Varga Chief Operating Reactor Branch #1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555 REQUALIFICATION TRAINING SCHEDULE FOR LICENSED OPERATORS SALEM GENERATING STATION  
Nuclear Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609 935-6010 June 24, 1982 Mr. Steven A. Varga Chief Operating Reactor Branch #1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.
20555 REQUALIFICATION TRAINING SCHEDULE FOR LICENSED OPERATORS SALEM GENERATING STATION  


==Dear Mr. Varga:==
==Dear Mr. Varga:==
In a letter signed for you by Mr. J. D. Neighbors and dated November 30, 1981, you approved our proposal to change-the annual requalification training cycle for licensed operators, such that it would begin on approximately September 1st of each year. This change gave our program better continuity and facilitated easier scheduling of licensed personnel during the active vacation period. On May 1st of this year PSE&G employees represented by the IBEW went on strike. The strike interrupted the last group in requalification training for the 1981-82 cycle. The strike ended as the active vacation period was starting.
In a letter signed for you by Mr. J. D. Neighbors and dated November 30, 1981, you approved our proposal to change-the annual requalification training cycle for licensed operators, such that it would begin on approximately September 1st of each year.
Due to vacations and the phasing back in of IBEW personnel, we were unable to reassemble the group of individuals whose cation training was interrupted.
This change gave our program better continuity and facilitated easier scheduling of licensed personnel during the active vacation period.
That group has been rescheduled to complete the 1981-82 cycle from August 30 through October 15, 1982. The 1982-83 cycle would then begin on October 18, 1982, and run through July 1, 1983. This change does not decrease the scope of the requalification program. It is our intention to return' to the September 1st annual cycle start date in 1983. cc: Mr. Lief Norroholm, Senior Resident Inspector}}
On May 1st of this year PSE&G employees represented by the IBEW went on strike.
The strike interrupted the last group in requalification training for the 1981-82 cycle.
The strike ended as the active vacation period was starting.
Due to vacations and the phasing back in of IBEW personnel, we were unable to reassemble the group of individuals whose requalifi-cation training was interrupted.
That group has been rescheduled to complete the 1981-82 cycle from August 30 through October 15, 1982.
The 1982-83 cycle would then begin on October 18, 1982, and run through July 1, 1983.
This change does not decrease the scope of the requalification program.
It is our intention to return' to the September 1st annual cycle start date in 1983.
cc:
Mr. Lief Norroholm, Senior Resident Inspector}}

Latest revision as of 04:54, 6 January 2025

Submits New Requalification Training Schedule for Approval
ML18086B534
Person / Time
Site: Salem  PSEG icon.png
Issue date: 06/24/1982
From: Uderitz R
Public Service Enterprise Group
To: Varga S
Office of Nuclear Reactor Regulation
References
NUDOCS 8206290147
Download: ML18086B534 (1)


Text

Richard A. Uderitz Vice President -

Nuclear Public Service Electric and Gas Company P.O. Box 236, Hancocks Bridge, NJ 08038 609 935-6010 June 24, 1982 Mr. Steven A. Varga Chief Operating Reactor Branch #1 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C.

20555 REQUALIFICATION TRAINING SCHEDULE FOR LICENSED OPERATORS SALEM GENERATING STATION

Dear Mr. Varga:

In a letter signed for you by Mr. J. D. Neighbors and dated November 30, 1981, you approved our proposal to change-the annual requalification training cycle for licensed operators, such that it would begin on approximately September 1st of each year.

This change gave our program better continuity and facilitated easier scheduling of licensed personnel during the active vacation period.

On May 1st of this year PSE&G employees represented by the IBEW went on strike.

The strike interrupted the last group in requalification training for the 1981-82 cycle.

The strike ended as the active vacation period was starting.

Due to vacations and the phasing back in of IBEW personnel, we were unable to reassemble the group of individuals whose requalifi-cation training was interrupted.

That group has been rescheduled to complete the 1981-82 cycle from August 30 through October 15, 1982.

The 1982-83 cycle would then begin on October 18, 1982, and run through July 1, 1983.

This change does not decrease the scope of the requalification program.

It is our intention to return' to the September 1st annual cycle start date in 1983.

cc:

Mr. Lief Norroholm, Senior Resident Inspector