ML19269F485: Difference between revisions

From kanterella
Jump to navigation Jump to search
StriderTol Bot insert
 
StriderTol Bot change
 
Line 2: Line 2:
| number = ML19269F485
| number = ML19269F485
| issue date = 11/19/1979
| issue date = 11/19/1979
| title = Responds to NRC 791020 Ltr Re Violations Noted in IE Insp Rept 50-346/79-04.Corrective Actions:Prepared Deviation Rept for Violation of Tech Spec 6.8.1
| title = Responds to NRC Re Violations Noted in IE Insp Rept 50-346/79-04.Corrective Actions:Prepared Deviation Rept for Violation of Tech Spec 6.8.1
| author name = Crouse R
| author name = Crouse R
| author affiliation = TOLEDO EDISON CO.
| author affiliation = TOLEDO EDISON CO.
Line 11: Line 11:
| contact person =  
| contact person =  
| document report number = NUDOCS 7912210147
| document report number = NUDOCS 7912210147
| title reference date = 10-20-1979
| package number = ML19269F486
| package number = ML19269F486
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
Line 18: Line 19:
=Text=
=Text=
{{#Wiki_filter:*
{{#Wiki_filter:*
TOLEDO November 19, 1979                                                     !!E)!!$(IId Docket No. 50- 346                                                   naam P Cmust
TOLEDO November 19, 1979
!!E)!!$(IId Docket No. 50- 346 naam P Cmust
: w. p,.*,
: w. p,.*,
License No. NPF-3                                                     h[f$In, Serial No. 1-105 Mr. R. F. Heishman, Chief Reactor Operations and Nuclear Support Branch U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137
h[f$In, License No. NPF-3 Serial No. 1-105 Mr. R. F. Heishman, Chief Reactor Operations and Nuclear Support Branch U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137


==Dear Mr. Heishman:==
==Dear Mr. Heishman:==
Toledo Edison acknowledges receipt of your October 20, 1979 letter and enclosures, Appendix A and Report 79-28, referencing an apparent deviation from Davis-Besse Nuclear Power Station Unit 1 commitments to the NRC listed as an " Infraction" in Appendix A.
Toledo Edison acknowledges receipt of your {{letter dated|date=October 20, 1979|text=October 20, 1979 letter}} and enclosures, Appendix A and Report 79-28, referencing an apparent deviation from Davis-Besse Nuclear Power Station Unit 1 commitments to the NRC listed as an " Infraction" in Appendix A.
Following an examination of the item of concern, Toledo Edison herein offers in-formation regarding the item of non-compliance.
Following an examination of the item of concern, Toledo Edison herein offers in-formation regarding the item of non-compliance.
Infraction: Technical Specification 6.5.1.6.e requires the Station Review Board to investigate all violations of Technical Specifications including preparation and forwarding reports covering evaluation and recommenda-tions to prevent recurrence to the Vice President - Energy Supply and to the Chairman of the Company Nuclear Review Board.
Infraction: Technical Specification 6.5.1.6.e requires the Station Review Board to investigate all violations of Technical Specifications including preparation and forwarding reports covering evaluation and recommenda-tions to prevent recurrence to the Vice President - Energy Supply and to the Chairman of the Company Nuclear Review Board.
Contrarv to the above, the Station Review Board did not investigate the violations of Technical Specification and prepare a report for the items contained in IE Inspecticn Report No. 50-346/79-04 dated March 28, 1979.
Contrarv to the above, the Station Review Board did not investigate the violations of Technical Specification and prepare a report for the items contained in IE Inspecticn Report No. 50-346/79-04 dated March 28, 1979.
Response:      1. The violation of Technical Specification 6.8.1 addressed in NRC Inspection Report 79-04 was not documented nor reviewed by the Station Review Board. A Deviation Report has been prepared to provide the established investigation and review of this event.
 
: 2. Per Station Administrative Procedure AD 1807.00 " Control of Conditions Adverse to Quality" the Technical Engineer has the responsibility to assure that a Deviation Report is initiated for non-periodic reportable events within this context, he has
===Response===
    - NOV 231979                                                         2166 255 THE TOLEDO EDISON COMPANY   EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 7912210             h7
1.
The violation of Technical Specification 6.8.1 addressed in NRC Inspection Report 79-04 was not documented nor reviewed by the Station Review Board. A Deviation Report has been prepared to provide the established investigation and review of this event.
2.
Per Station Administrative Procedure AD 1807.00 " Control of Conditions Adverse to Quality" the Technical Engineer has the responsibility to assure that a Deviation Report is initiated for non-periodic reportable events within this context, he has
- NOV 231979 2166 255 THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 7912210 h7


November 19, 1979 Docket No. 50-346 License No. NPF-3 Serial No. 1-105 Page 2 been instructed to review NRC Inspection Reports upon receipt to insure all reported items of non-compliance are assigned a Deviation Report, if such a report has not already been prepared.
November 19, 1979 Docket No. 50-346 License No. NPF-3 Serial No. 1-105 Page 2 been instructed to review NRC Inspection Reports upon receipt to insure all reported items of non-compliance are assigned a Deviation Report, if such a report has not already been prepared.
This will allow a documented investigation of violations of Technical Specifications per existing administrative require-ments. Station Administrative Procedures AD 1804.00 " Reports Management", AD 1807.00 " Control of Conditiens Adverse to Quality", and Davis-Besse, Unit 1, Technical Specifications currently require a Station Review Board investigation of all Technical Specification violations including preparation and forwarding reports covering evalu_ cions and recommendations to prevent recurrince to the Vice President, Energy Supply and to the Chairman of the Company Nuclear Review Board.
This will allow a documented investigation of violations of Technical Specifications per existing administrative require-ments. Station Administrative Procedures AD 1804.00 " Reports Management", AD 1807.00 " Control of Conditiens Adverse to Quality", and Davis-Besse, Unit 1, Technical Specifications currently require a Station Review Board investigation of all Technical Specification violations including preparation and forwarding reports covering evalu_ cions and recommendations to prevent recurrince to the Vice President, Energy Supply and to the Chairman of the Company Nuclear Review Board.
: 3. A review of NRC Inspection Reports for the year 1979 has deter-mined that similar prob'. ems of this nature have occurred. A Deviation Report has been prepared to identify these violations of Technical Specification 6.5.1.6.e so as to permit a Station Review Board examination of these events. Full compliance will be achieved by December 31, 1979.
3.
Your very truly, Richard P. Crouse                                                         4 Vice President, Energy Supply                                             v RPC/TDM/SMQ/ daw
A review of NRC Inspection Reports for the year 1979 has deter-mined that similar prob'. ems of this nature have occurred. A Deviation Report has been prepared to identify these violations of Technical Specification 6.5.1.6.e so as to permit a Station Review Board examination of these events. Full compliance will be achieved by December 31, 1979.
    -}}
Your very truly, Richard P. Crouse 4
Vice President, Energy Supply v
RPC/TDM/SMQ/ daw
-}}

Latest revision as of 06:23, 3 January 2025

Responds to NRC Re Violations Noted in IE Insp Rept 50-346/79-04.Corrective Actions:Prepared Deviation Rept for Violation of Tech Spec 6.8.1
ML19269F485
Person / Time
Site: Davis Besse 
Issue date: 11/19/1979
From: Crouse R
TOLEDO EDISON CO.
To: Heishman R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML19269F486 List:
References
NUDOCS 7912210147
Download: ML19269F485 (2)


Text

TOLEDO November 19, 1979

!!E)!!$(IId Docket No. 50- 346 naam P Cmust

w. p,.*,

h[f$In, License No. NPF-3 Serial No. 1-105 Mr. R. F. Heishman, Chief Reactor Operations and Nuclear Support Branch U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Heishman:

Toledo Edison acknowledges receipt of your October 20, 1979 letter and enclosures, Appendix A and Report 79-28, referencing an apparent deviation from Davis-Besse Nuclear Power Station Unit 1 commitments to the NRC listed as an " Infraction" in Appendix A.

Following an examination of the item of concern, Toledo Edison herein offers in-formation regarding the item of non-compliance.

Infraction: Technical Specification 6.5.1.6.e requires the Station Review Board to investigate all violations of Technical Specifications including preparation and forwarding reports covering evaluation and recommenda-tions to prevent recurrence to the Vice President - Energy Supply and to the Chairman of the Company Nuclear Review Board.

Contrarv to the above, the Station Review Board did not investigate the violations of Technical Specification and prepare a report for the items contained in IE Inspecticn Report No. 50-346/79-04 dated March 28, 1979.

Response

1.

The violation of Technical Specification 6.8.1 addressed in NRC Inspection Report 79-04 was not documented nor reviewed by the Station Review Board. A Deviation Report has been prepared to provide the established investigation and review of this event.

2.

Per Station Administrative Procedure AD 1807.00 " Control of Conditions Adverse to Quality" the Technical Engineer has the responsibility to assure that a Deviation Report is initiated for non-periodic reportable events within this context, he has

- NOV 231979 2166 255 THE TOLEDO EDISON COMPANY EDISON PLAZA 300 MADISON AVENUE TOLEDO, OHIO 43652 7912210 h7

November 19, 1979 Docket No. 50-346 License No. NPF-3 Serial No. 1-105 Page 2 been instructed to review NRC Inspection Reports upon receipt to insure all reported items of non-compliance are assigned a Deviation Report, if such a report has not already been prepared.

This will allow a documented investigation of violations of Technical Specifications per existing administrative require-ments. Station Administrative Procedures AD 1804.00 " Reports Management", AD 1807.00 " Control of Conditiens Adverse to Quality", and Davis-Besse, Unit 1, Technical Specifications currently require a Station Review Board investigation of all Technical Specification violations including preparation and forwarding reports covering evalu_ cions and recommendations to prevent recurrince to the Vice President, Energy Supply and to the Chairman of the Company Nuclear Review Board.

3.

A review of NRC Inspection Reports for the year 1979 has deter-mined that similar prob'. ems of this nature have occurred. A Deviation Report has been prepared to identify these violations of Technical Specification 6.5.1.6.e so as to permit a Station Review Board examination of these events. Full compliance will be achieved by December 31, 1979.

Your very truly, Richard P. Crouse 4

Vice President, Energy Supply v

RPC/TDM/SMQ/ daw

-