{{#Wiki_filter:I l
{{#Wiki_filter:2 NRC-3-016 (412)787 - 5141 (412)923 - 1960 Telecopy (412) 787-2629 Nuclear Construction Division Nbinson Plaza, Building 2, Suite 210 April 6, 1983 Pittaburgh, PA 15205 Mr. Harold R. Denton, Director Division of Project Management U. S. Nuclear Regulatory Commission Washington, D. C. 20555
l 2 NRC-3-016 (412)787 - 5141 (412)923 - 1960 Telecopy (412) 787-2629 Nuclear Construction Division Nbinson Plaza, Building 2, Suite 210                                   April 6, 1983 Pittaburgh, PA 15205 Mr. Harold R. Denton, Director Division of Project Management U. S. Nuclear Regulatory Commission Washington, D. C. 20555


==Subject:==
==Subject:==
Line 23: Line 24:


==Dear Mr. Denton:==
==Dear Mr. Denton:==
Please be advised that Mr. R. J. Washabaugh, Project Manager BVPS-2, Duquesne Light Co., is authorized to review, approve and affix his signature on my behalf to documents submitted to your office which directly relate to the Duquesne Light Co. licensing application for the Beaver Valley Power Station, Unit 2 at such times when I am not available.
Please be advised that Mr. R. J. Washabaugh, Project Manager BVPS-2, Duquesne Light Co., is authorized to review, approve and affix his signature on my behalf to documents submitted to your office which directly relate to the Duquesne Light Co. licensing application for the Beaver Valley Power Station, Unit 2 at such times when I am not available.
Very truly yours, E.   . Woolever Vice President JAH:aev CC:     L. Lazzo G. Knighton G. Walton NCD File DO 8304120389 830406 PDR ADDCK 05000412 H                       pga}}
Very truly yours, E.
. Woolever Vice President JAH:aev CC:
L. Lazzo G. Knighton G. Walton NCD File DO 8304120389 830406 PDR ADDCK 05000412 H
pga}}

Latest revision as of 10:42, 16 December 2024

Informs of Authorization for R Washabaugh to Review, Approve & Affix Signature on Behalf of Authors to Documents Re Licensing Application
ML20069H940
Person / Time
Site: Beaver Valley
Issue date: 04/06/1983
From: Woolever E
DUQUESNE LIGHT CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
2-NRC-3-016, 2-NRC-3-16, NUDOCS 8304120389
Download: ML20069H940 (1)


Text

2 NRC-3-016 (412)787 - 5141 (412)923 - 1960 Telecopy (412) 787-2629 Nuclear Construction Division Nbinson Plaza, Building 2, Suite 210 April 6, 1983 Pittaburgh, PA 15205 Mr. Harold R. Denton, Director Division of Project Management U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Subject:

Beaver Valley Power Station - Unit 2 USNRC Docket No. 50-412 Authority to Sign Official Correspondence

Dear Mr. Denton:

Please be advised that Mr. R. J. Washabaugh, Project Manager BVPS-2, Duquesne Light Co., is authorized to review, approve and affix his signature on my behalf to documents submitted to your office which directly relate to the Duquesne Light Co. licensing application for the Beaver Valley Power Station, Unit 2 at such times when I am not available.

Very truly yours, E.

. Woolever Vice President JAH:aev CC:

L. Lazzo G. Knighton G. Walton NCD File DO 8304120389 830406 PDR ADDCK 05000412 H