(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 08/28/2003 07:50 CDT
| event date = 08/28/2003 07:50 CDT
| last update date = 09/02/2003
| last update date = 09/02/2003
| title = Loss Of Power To Emergency Operations Facility
| title = Loss of Power to Emergency Operations Facility
| event text = The Emergency Operations Facility (EOF) for Grand Gulf was lost when power was removed from the facility and the EOF diesel generator failed to start.  Power had to be removed due to the loss of one phase of the local power supply.  Actual plant operations are not affected.  The power phase problem and failure of the EOF diesel generator to start are being investigated at this time.  The Backup EOF is available if needed.
| event text = The Emergency Operations Facility (EOF) for Grand Gulf was lost when power was removed from the facility and the EOF diesel generator failed to start.  Power had to be removed due to the loss of one phase of the local power supply.  Actual plant operations are not affected.  The power phase problem and failure of the EOF diesel generator to start are being investigated at this time.  The Backup EOF is available if needed.
The licensee notified the NRC Resident Inspector.
The licensee notified the NRC Resident Inspector.

Latest revision as of 21:25, 1 March 2018

ENS 40110 +/-
Where
Grand Gulf Entergy icon.png
Mississippi (NRC Region 4)
Reporting
10 CFR 50.72(b)(3)(xiii), Loss of Emergency Preparedness
Time - Person (Reporting Time:+3.62 h0.151 days <br />0.0215 weeks <br />0.00496 months <br />)
Opened: Mike Beard
16:27 Aug 28, 2003
NRC Officer: Bill Gott
Last Updated: Sep 2, 2003
40110 - NRC Website