ML20199E913: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 18: Line 18:
=Text=
=Text=
{{#Wiki_filter:_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
{{#Wiki_filter:_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
na a#e                                   UNITEo STATES p       --
na a#e UNITEo STATES p
g                 NUCLEAR REOULATORY COMMISSION
g NUCLEAR REOULATORY COMMISSION
    $                                                . Reason av URANIUM RE VE                             FIELD OFFICE DENVER, COLORADO 88235 OCT 291992 Docket No. WM-64 h- 73 .
. Reason av URANIUM RE VE FIELD OFFICE DENVER, COLORADO 88235 OCT 291992 Docket No. WM-64 h-73.
:U.S. Department of Energy
:U.S. Department of Energy
            - Albuquerque Operations Office ATTN: Albert R. Chernoff Project Manager P.O. Box.5400 Albuquerque, New Mexico 87115 Q            
- Albuquerque Operations Office ATTN: Albert R. Chernoff Project Manager P.O. Box.5400 Albuquerque, New Mexico 87115 Q


==Dear Mr. Chernoff:==
==Dear Mr. Chernoff:==
 
In our review of-the certification data for the uranium mill tallings. site at Lakeview, Oregon, we have identified several requirements that have not been addressed-in the Final-Completion Report. Please respond to the enclosed comments and provide appropriate revisions to the Final Completion Report so that we-may complete our review.
In our review of- the certification data for the uranium mill tallings. site at Lakeview, Oregon, we have identified several requirements that have not been addressed-in the Final-Completion Report. Please respond to the enclosed comments and provide appropriate revisions to the Final Completion Report so that we-may complete our review.                                                                                                 i Although DOE did not provide placement. volume-data, NRC accepts your certification that testing was done proportionally throughout the remedial action. - Though accepted for this project,1you should provide the necessary construction data in future completion reports and not presume _ acceptance based on certification.
i Although DOE did not provide placement. volume-data, NRC accepts your certification that testing was done proportionally throughout the remedial action. - Though accepted for this project,1you should provide the necessary construction data in future completion reports and not presume _ acceptance based on certification.
Several of the issues raised in our review of. the Lakeview Final Completion
Several of the issues raised in our review of. the Lakeview Final Completion
            -Report appear to be generic-in nature since similar issues were identified in
-Report appear to be generic-in nature since similar issues were identified in
-n             our review of the Tuba City Draft Completion Report. W e therefore request
-n our review of the Tuba City Draft Completion Report.
W e therefore request
(_)
(_)
thnt you include volume placement. data summaries when you provide the Tuba City Final Completion Report for our review. In addition, please review the Draft Completion Report- for Durango and revise as necessary. We will suspend our review of the Durango Draft Completion Feport until you have completed any necessary revisions.
thnt you include volume placement. data summaries when you provide the Tuba City Final Completion Report for our review.
If you nave any questions, please contact the NRC Lakeview project manager, Ray Gonzales, at FTS (303) 231-5808.                                                                                       -  -
In addition, please review the Draft Completion Report-for Durango and revise as necessary. We will suspend our review of the Durango Draft Completion Feport until you have completed any necessary revisions.
Sincerely, k124 Ramon E. Hall     N Director
If you nave any questions, please contact the NRC Lakeview project manager, Ray Gonzales, at FTS (303) 231-5808.
Sincerely, k124 Ramon E. Hall N
Director


==Enclosure:==
==Enclosure:==
.As stated l COPY PDR WASTE WPt-73 PDR m


            .As stated
a OCT 291992 U. S. Department of Energy 2
                                                                              .                                                l COPY PDR    WASTE WPt-73            PDR    m
CC:
 
a U. S. Department of Energy                                 2 OCT 291992 CC:
S. Hamp, DOE P. Mann, DOE R. Edge, DOE F. Micra, Oregon D. Stewart-Smith, Oregon n
S. Hamp, DOE P. Mann, DOE R. Edge, DOE F. Micra, Oregon D. Stewart-Smith, Oregon n
v
v


t U. S. Department of Energy                                   3 MT29 R                             ,
t U. S. Department of Energy 3
Casework Nos. 040WM064920E 040WM048050R 040WM073200E bec:
MT29 R Casework Nos.
Docket File WM-64 Occket File WM-48                       ~'
040WM064920E 040WM048050R 040WM073200E bec:
DocketLFilel:WM-73 PDR/DCS URF0 r/f LJCallan, RIV LLUR. Branch, LLWM, SE2 R0Gonzales DLJacoby 0:\ROG\WM6400E. FIN O
Docket File WM-64 Occket File WM-48 DocketLFilel:WM-73
~'
PDR/DCS URF0 r/f LJCallan, RIV LLUR. Branch, LLWM, SE2 R0Gonzales DLJacoby 0:\\ROG\\WM6400E. FIN O
o PM:URF0*eh PM:URF0 k
o PM:URF0*eh PM:URF0 k
* DD:URF0 M, v ..D:URF0:RIk,-
* DD:URF0 M, v..D:URF0:RIk,-
su ROGonzales/lv DLJacobyvb                             EFHawkins REHall % _v 10/22/92       ,10$7/92                             10PM92   10hs@k2
su ROGonzales/lv DLJacobyvb EFHawkins REHall % _v 10/22/92
            *Previously concurred
,10$7/92 10PM92 10hs@k2
*Previously concurred


LAKEVIEW, OREGON REVIEW COMMENTS ON THE FINAL COMPLETION The-following requirements were described in the RAP, RAP addendums, PIDs, or in the RAIP but do not appear to have been addressed in the Final Completion Report. Please revise the Final Completion Report (FCR) as appropriate.
LAKEVIEW, OREGON REVIEW COMMENTS ON THE FINAL COMPLETION The-following requirements were described in the RAP, RAP addendums, PIDs, or in the RAIP but do not appear to have been addressed in the Final Completion Report.
: 1. Design Specification 02200-2,1.C.2.a requires that Radon Barrier Materials be uncontaminated soil whose projected Ra-27.6 content not exceed 5.0 pCi/gm. This requirement has not been addressed in the FCR.
Please revise the Final Completion Report (FCR) as appropriate.
2.-   Design Specification 02200-2,1.C.3 requires that Geochemical Flow
1.
(]            Barrier materials be select, natural, uncontaminated materials similar to the Radon Barrier. Therefore comment I-1 also applies to the Geochemical Flow Barrier.
Design Specification 02200-2,1.C.2.a requires that Radon Barrier Materials be uncontaminated soil whose projected Ra-27.6 content not exceed 5.0 pCi/gm. This requirement has not been addressed in the FCR.
: 3. Design Specification 02200-3.5.B requires that the top 6 inches of the                                                       ,
(]
subgrade of each permanent drainage ditch be compacted to a minimum of 95 percent of maximum density. This requirement has not been addressed in the FCR.
2.-
: 4. Procedure 6.2.1 of the RAIP, Rev. 3, requires, in part, that a minimum of I gradation / classification test per week be performed on Radon Barrier material, when an appreciable amount of material is placed. The same requirement is specifled for the Geochemical Flow Barrier. In a minimum Section 4.per of one test  Volume day was3, performed Appendixwhenever E, of the more FCR,than DOE150states                              yd        tha} of Radon g           Barrier material were placed. The same statement is made for the v           Geochemical Flow Barrier in Section 2 Volume-3, Appendix E, of the FCR.
Design Specification 02200-2,1.C.3 requires that Geochemical Flow Barrier materials be select, natural, uncontaminated materials similar to the Radon Barrier. Therefore comment I-1 also applies to the Geochemical Flow Barrier.
3.
Design Specification 02200-3.5.B requires that the top 6 inches of the subgrade of each permanent drainage ditch be compacted to a minimum of 95 percent of maximum density. This requirement has not been addressed in the FCR.
4.
Procedure 6.2.1 of the RAIP, Rev. 3, requires, in part, that a minimum of I gradation / classification test per week be performed on Radon Barrier material, when an appreciable amount of material is placed. The same requirement is specifled for the Geochemical Flow Barrier.
In Section 4. Volume 3, Appendix E, of the FCR, DOE states tha} of Radon a minimum of one test per day was performed whenever more than 150 yd g
Barrier material were placed. The same statement is made for the v
Geochemical Flow Barrier in Section 2 Volume-3, Appendix E, of the FCR.
NRC agrees that this testing frequency meets the requirement. However, it appears that there may be a typographical error here. Was one test per day performed as stated in the FCR or was one test per week performed?
NRC agrees that this testing frequency meets the requirement. However, it appears that there may be a typographical error here. Was one test per day performed as stated in the FCR or was one test per week performed?
: 5. Design Specifications 02200-1.4.C and 02200-3.4.B.5 require that Type 1 materials be placed in the upper portions of the Disposal Cell. This requirement has not been addressed in the-FCR.
5.
: 6. Design Specifications 02200-1.4.0 and 02200-3.4.B.5 require that Type 2 materials be placed in the lower portions of the Disposal Cell. This requirement-has not been addressed in the FCR.
Design Specifications 02200-1.4.C and 02200-3.4.B.5 require that Type 1 materials be placed in the upper portions of the Disposal Cell. This requirement has not been addressed in the-FCR.
: 7. Design Specification 02200-3.4.B.6 requires that Vicinity Property materials be placed in the Encapsulation Cell. This requirement has not been addressed in the FCR.
6.
Design Specifications 02200-1.4.0 and 02200-3.4.B.5 require that Type 2 materials be placed in the lower portions of the Disposal Cell. This requirement-has not been addressed in the FCR.
7.
Design Specification 02200-3.4.B.6 requires that Vicinity Property materials be placed in the Encapsulation Cell. This requirement has not been addressed in the FCR.


2
2 8.
: 8. In Section 4. Volume 3 Appendix E, of the FCR, DOE 5;ates that there were 28 passing gradation and classification tests performed on Radon Barrier material. DOE provided a summary table showing the results of gradation, classification and PI tests in a submittal dated July 17, 1992. As the table has 32 entries we 3ssume that some of the samples were re-tests. The following comments concern the summary table.
In Section 4. Volume 3 Appendix E, of the FCR, DOE 5;ates that there were 28 passing gradation and classification tests performed on Radon Barrier material. DOE provided a summary table showing the results of gradation, classification and PI tests in a submittal dated July 17, 1992. As the table has 32 entries we 3ssume that some of the samples were re-tests. The following comments concern the summary table.
a)   Were tests G-RB-04 and G-RB-04-R1 performed on the same soil?     If yes, than why did one sample have a ML classification while the other had a MH classification? Also, if the soil was the same, why did one sample have a PI of 3 while the other had a PI of 11.
a)
Were tests G-RB-04 and G-RB-04-R1 performed on the same soil?
If yes, than why did one sample have a ML classification while the other had a MH classification? Also, if the soil was the same, why did one sample have a PI of 3 while the other had a PI of 11.
If the tests were not run on the same soil, then there were more that 28 samples tested.
If the tests were not run on the same soil, then there were more that 28 samples tested.
b)   Were tests G-RB-015A and G-00-015B performed on the same soil?     If yes, then why did one sample have a ML classification while the O                   other had a MH classification 7 If the tests wer9 not run on the same soll, then there were more that 28 samples tested.
b)
c)   Were tests G-RB-016, G-RB-016-R1, and G-RB-016-R2 performed on the same soll? If yes, then why was the minus 200 fraction almost tw!ce as much for test G-RB-016-R2 et it was for test G-RB-0167 Also, if the soil was the same, why did one sample have a P1 of 10 while the others had Pls of 07 If the tests were not run on the same soll, then there were more that 28 samples tested.
Were tests G-RB-015A and G-00-015B performed on the same soil?
: 9. Design SpActfications 02200-3.5 B and 02200-3.5.C. PID No. 13-S-09, re4uire that subgrade areas be corapacted to 95 percent of maximum dry density. In order to determine the appropriate maximum dry density value, laboratory compaction tests are required. Please discuss the testing frequency that was used for performing laboratory compaction tests or identify the section in the RAIP or other documentation where the laboratory compaction test frequency is described.
If yes, then why did one sample have a ML classification while the O
: 10. PID No. 03-S-29 proposed to substitute B-2 bedding for the apron, key trench, and ditch. However, As-Built Drawing LKV-DS-1321 indicates ". hat-B-1 bedding was used as was originally proposed. Please clarify and revise the Final Completion Report if necessary.
other had a MH classification 7 If the tests wer9 not run on the same soll, then there were more that 28 samples tested.
c)
Were tests G-RB-016, G-RB-016-R1, and G-RB-016-R2 performed on the same soll? If yes, then why was the minus 200 fraction almost tw!ce as much for test G-RB-016-R2 et it was for test G-RB-0167 Also, if the soil was the same, why did one sample have a P1 of 10 while the others had Pls of 07 If the tests were not run on the same soll, then there were more that 28 samples tested.
9.
Design SpActfications 02200-3.5 B and 02200-3.5.C. PID No. 13-S-09, re4uire that subgrade areas be corapacted to 95 percent of maximum dry density.
In order to determine the appropriate maximum dry density value, laboratory compaction tests are required.
Please discuss the testing frequency that was used for performing laboratory compaction tests or identify the section in the RAIP or other documentation where the laboratory compaction test frequency is described.
10.
PID No. 03-S-29 proposed to substitute B-2 bedding for the apron, key trench, and ditch. However, As-Built Drawing LKV-DS-1321 indicates ". hat-B-1 bedding was used as was originally proposed.
Please clarify and revise the Final Completion Report if necessary.
1 J%-}}
1 J%-}}

Latest revision as of 07:51, 10 December 2024

Requests That Appropriate Revs & Response to Encl Final Completion Rept Be Submitted in Order to Complete Review
ML20199E913
Person / Time
Issue date: 10/29/1992
From: Randy Hall
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Chernoff A
ENERGY, DEPT. OF
References
REF-WM-73, TASK-TF, TASK-URFO NUDOCS 9802030005
Download: ML20199E913 (5)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

na a#e UNITEo STATES p

g NUCLEAR REOULATORY COMMISSION

. Reason av URANIUM RE VE FIELD OFFICE DENVER, COLORADO 88235 OCT 291992 Docket No. WM-64 h-73.

U.S. Department of Energy

- Albuquerque Operations Office ATTN: Albert R. Chernoff Project Manager P.O. Box.5400 Albuquerque, New Mexico 87115 Q

Dear Mr. Chernoff:

In our review of-the certification data for the uranium mill tallings. site at Lakeview, Oregon, we have identified several requirements that have not been addressed-in the Final-Completion Report. Please respond to the enclosed comments and provide appropriate revisions to the Final Completion Report so that we-may complete our review.

i Although DOE did not provide placement. volume-data, NRC accepts your certification that testing was done proportionally throughout the remedial action. - Though accepted for this project,1you should provide the necessary construction data in future completion reports and not presume _ acceptance based on certification.

Several of the issues raised in our review of. the Lakeview Final Completion

-Report appear to be generic-in nature since similar issues were identified in

-n our review of the Tuba City Draft Completion Report.

W e therefore request

(_)

thnt you include volume placement. data summaries when you provide the Tuba City Final Completion Report for our review.

In addition, please review the Draft Completion Report-for Durango and revise as necessary. We will suspend our review of the Durango Draft Completion Feport until you have completed any necessary revisions.

If you nave any questions, please contact the NRC Lakeview project manager, Ray Gonzales, at FTS (303) 231-5808.

Sincerely, k124 Ramon E. Hall N

Director

Enclosure:

.As stated l COPY PDR WASTE WPt-73 PDR m

a OCT 291992 U. S. Department of Energy 2

CC:

S. Hamp, DOE P. Mann, DOE R. Edge, DOE F. Micra, Oregon D. Stewart-Smith, Oregon n

v

t U. S. Department of Energy 3

MT29 R Casework Nos.

040WM064920E 040WM048050R 040WM073200E bec:

Docket File WM-64 Occket File WM-48 DocketLFilel:WM-73

~'

PDR/DCS URF0 r/f LJCallan, RIV LLUR. Branch, LLWM, SE2 R0Gonzales DLJacoby 0:\\ROG\\WM6400E. FIN O

o PM:URF0*eh PM:URF0 k

  • DD:URF0 M, v..D:URF0:RIk,-

su ROGonzales/lv DLJacobyvb EFHawkins REHall % _v 10/22/92

,10$7/92 10PM92 10hs@k2

  • Previously concurred

LAKEVIEW, OREGON REVIEW COMMENTS ON THE FINAL COMPLETION The-following requirements were described in the RAP, RAP addendums, PIDs, or in the RAIP but do not appear to have been addressed in the Final Completion Report.

Please revise the Final Completion Report (FCR) as appropriate.

1.

Design Specification 02200-2,1.C.2.a requires that Radon Barrier Materials be uncontaminated soil whose projected Ra-27.6 content not exceed 5.0 pCi/gm. This requirement has not been addressed in the FCR.

(]

2.-

Design Specification 02200-2,1.C.3 requires that Geochemical Flow Barrier materials be select, natural, uncontaminated materials similar to the Radon Barrier. Therefore comment I-1 also applies to the Geochemical Flow Barrier.

3.

Design Specification 02200-3.5.B requires that the top 6 inches of the subgrade of each permanent drainage ditch be compacted to a minimum of 95 percent of maximum density. This requirement has not been addressed in the FCR.

4.

Procedure 6.2.1 of the RAIP, Rev. 3, requires, in part, that a minimum of I gradation / classification test per week be performed on Radon Barrier material, when an appreciable amount of material is placed. The same requirement is specifled for the Geochemical Flow Barrier.

In Section 4. Volume 3, Appendix E, of the FCR, DOE states tha} of Radon a minimum of one test per day was performed whenever more than 150 yd g

Barrier material were placed. The same statement is made for the v

Geochemical Flow Barrier in Section 2 Volume-3, Appendix E, of the FCR.

NRC agrees that this testing frequency meets the requirement. However, it appears that there may be a typographical error here. Was one test per day performed as stated in the FCR or was one test per week performed?

5.

Design Specifications 02200-1.4.C and 02200-3.4.B.5 require that Type 1 materials be placed in the upper portions of the Disposal Cell. This requirement has not been addressed in the-FCR.

6.

Design Specifications 02200-1.4.0 and 02200-3.4.B.5 require that Type 2 materials be placed in the lower portions of the Disposal Cell. This requirement-has not been addressed in the FCR.

7.

Design Specification 02200-3.4.B.6 requires that Vicinity Property materials be placed in the Encapsulation Cell. This requirement has not been addressed in the FCR.

2 8.

In Section 4. Volume 3 Appendix E, of the FCR, DOE 5;ates that there were 28 passing gradation and classification tests performed on Radon Barrier material. DOE provided a summary table showing the results of gradation, classification and PI tests in a submittal dated July 17, 1992. As the table has 32 entries we 3ssume that some of the samples were re-tests. The following comments concern the summary table.

a)

Were tests G-RB-04 and G-RB-04-R1 performed on the same soil?

If yes, than why did one sample have a ML classification while the other had a MH classification? Also, if the soil was the same, why did one sample have a PI of 3 while the other had a PI of 11.

If the tests were not run on the same soil, then there were more that 28 samples tested.

b)

Were tests G-RB-015A and G-00-015B performed on the same soil?

If yes, then why did one sample have a ML classification while the O

other had a MH classification 7 If the tests wer9 not run on the same soll, then there were more that 28 samples tested.

c)

Were tests G-RB-016, G-RB-016-R1, and G-RB-016-R2 performed on the same soll? If yes, then why was the minus 200 fraction almost tw!ce as much for test G-RB-016-R2 et it was for test G-RB-0167 Also, if the soil was the same, why did one sample have a P1 of 10 while the others had Pls of 07 If the tests were not run on the same soll, then there were more that 28 samples tested.

9.

Design SpActfications 02200-3.5 B and 02200-3.5.C. PID No. 13-S-09, re4uire that subgrade areas be corapacted to 95 percent of maximum dry density.

In order to determine the appropriate maximum dry density value, laboratory compaction tests are required.

Please discuss the testing frequency that was used for performing laboratory compaction tests or identify the section in the RAIP or other documentation where the laboratory compaction test frequency is described.

10.

PID No. 03-S-29 proposed to substitute B-2 bedding for the apron, key trench, and ditch. However, As-Built Drawing LKV-DS-1321 indicates ". hat-B-1 bedding was used as was originally proposed.

Please clarify and revise the Final Completion Report if necessary.

1 J%-