{{#Wiki_filter:Vendor Inspection Program Plan Revision 30 July 2024 | {{#Wiki_filter:Vendor Inspection Program Plan Revision 30 July 2024 | ||
Prepared By: | Prepared By: Quality Assurance and Vendor Inspection Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission CONTENTS | ||
1.0 Vendor Inspection Program Overview................................................................................1 | 1.0 Vendor Inspection Program Overview................................................................................1 | ||
Line 57: | Line 57: | ||
Appendix E: Vendor Inspection Program Performance Metrics.........................................E-1 | Appendix E: Vendor Inspection Program Performance Metrics.........................................E-1 | ||
Appendix F: Major Plant Modification Criteria.F-1 1.0 | Appendix F: Major Plant Modification Criteria.F-1 1.0 Vendor Inspection Program Overview | ||
The Vendor Inspection Program (VIP) verifies that reactor applicants and licensees are fulfilling their regulatory obligations with respect to providing effective oversight of the nuclear supply chain. It accomplishes this through limited scope, targeted inspections of vendor quality assurance (QA) programs, communicating relevant vendor information to stakeholders, and supporting allegation response activities. Vendor inspections are planned using a strategy for vendor identification and selection which samples the effectiveness of the domestic and international nuclear supply chains for the current fleet and new reactor construction. To effectively implement vendor inspections, the vendor inspectors maintain the necessary knowledge and skills to perform inspections. Communication of vendor-related information is achieved through interaction with nuclear consensus standards organizations, vendors, industry supply chain organizations, international constituents, and other external stakeholders. The VIP serves as a mechanism to address vendor-related allegations received by the U.S. Nuclear Regulatory Commission (NRC) by providing technical support and/or vendor inspections for such allegations. | The Vendor Inspection Program (VIP) verifies that reactor applicants and licensees are fulfilling their regulatory obligations with respect to providing effective oversight of the nuclear supply chain. It accomplishes this through limited scope, targeted inspections of vendor quality assurance (QA) programs, communicating relevant vendor information to stakeholders, and supporting allegation response activities. Vendor inspections are planned using a strategy for vendor identification and selection which samples the effectiveness of the domestic and international nuclear supply chains for the current fleet and new reactor construction. To effectively implement vendor inspections, the vendor inspectors maintain the necessary knowledge and skills to perform inspections. Communication of vendor-related information is achieved through interaction with nuclear consensus standards organizations, vendors, industry supply chain organizations, international constituents, and other external stakeholders. The VIP serves as a mechanism to address vendor-related allegations received by the U.S. Nuclear Regulatory Commission (NRC) by providing technical support and/or vendor inspections for such allegations. | ||
Line 70: | Line 70: | ||
* Technical and managerial support for vendor-related allegations. | * Technical and managerial support for vendor-related allegations. | ||
2.0 | 2.0 Objectives of the Vendor Inspection Program | ||
The VIP establishes specific objectives derived from six overarching goals that provide a nexus to the NRCs statutory mission of protecting public health and safety, promoting the common defense and security, and protecting the environment. The VIP is communicated both internally within the NRC and externally with industry stakeholders to ensure full integration of the program. Performance metrics have been established for each VIP objective to demonstrate that the following overarching goals are met: | The VIP establishes specific objectives derived from six overarching goals that provide a nexus to the NRCs statutory mission of protecting public health and safety, promoting the common defense and security, and protecting the environment. The VIP is communicated both internally within the NRC and externally with industry stakeholders to ensure full integration of the program. Performance metrics have been established for each VIP objective to demonstrate that the following overarching goals are met: | ||
Line 115: | Line 115: | ||
Section 11.0 of this plan describes these performance metrics. | Section 11.0 of this plan describes these performance metrics. | ||
3.0 | 3.0 Organization | ||
The vendor inspection staff conducts inspections related to the requirements in Appendix B to 10 CFR Part 50 and 10 CFR Part 21 at suppliers that provide design, fabrication, and engineering services (including commercial-grade dedication) for nuclear components. In addition, the vendor inspection staff provides technical support for regional inspections, special projects, programs, and policy activities. The vendor inspection staff coordinates inspection activities and, as necessary, requests additional support from other NRC offices, technical divisions, regions, branches or contractors. | The vendor inspection staff conducts inspections related to the requirements in Appendix B to 10 CFR Part 50 and 10 CFR Part 21 at suppliers that provide design, fabrication, and engineering services (including commercial-grade dedication) for nuclear components. In addition, the vendor inspection staff provides technical support for regional inspections, special projects, programs, and policy activities. The vendor inspection staff coordinates inspection activities and, as necessary, requests additional support from other NRC offices, technical divisions, regions, branches or contractors. | ||
4.0 | 4.0 Scope of Activities | ||
The vendor inspection staff conducts vendor inspections to verify that QA programs at vendor facilities are being effectively implemented and comply with the applicable regulatory requirements, including 10 CFR Part 21 and the licensee-imposed requirements of Appendix B to 10 CFR Part 50. These inspections also verify that component design requirements imposed on the vendors by their customers have been met, including as applicable, requirements associated with the environmental and seismic qualification of equipment. Vendor inspections may also support the Commissions determination that the acceptance criteria in a combined license are met in accordance with 10 CFR 52.99, Inspection During Construction, and 10 CFR 52.103(g). Also, using Inspection Procedure (IP) 37805, Engineering Design Verification Inspections, dated April 8, 2020, the NRC has conducted vendor inspections to review the development of the detailed design for new reactor designs licensed under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants. Vendor inspections follow the procedures given in the table below, as applicable, and are governed by Inspection Manual Chapter (IMC) 2507, Vendor Inspections. | The vendor inspection staff conducts vendor inspections to verify that QA programs at vendor facilities are being effectively implemented and comply with the applicable regulatory requirements, including 10 CFR Part 21 and the licensee-imposed requirements of Appendix B to 10 CFR Part 50. These inspections also verify that component design requirements imposed on the vendors by their customers have been met, including as applicable, requirements associated with the environmental and seismic qualification of equipment. Vendor inspections may also support the Commissions determination that the acceptance criteria in a combined license are met in accordance with 10 CFR 52.99, Inspection During Construction, and 10 CFR 52.103(g). Also, using Inspection Procedure (IP) 37805, Engineering Design Verification Inspections, dated April 8, 2020, the NRC has conducted vendor inspections to review the development of the detailed design for new reactor designs licensed under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants. Vendor inspections follow the procedures given in the table below, as applicable, and are governed by Inspection Manual Chapter (IMC) 2507, Vendor Inspections. | ||
3 Inspection Procedure (IP) | 3 Inspection Procedure (IP) Title IP 35007 Quality Assurance Program Implementation During Construction and Pre-Construction Activities IP 35017 Quality Assurance Implementation Inspection | ||
IP 35034 | IP 35034 Design Certification Testing Inspection | ||
IP 35710 | IP 35710 Quality Assurance Inspection of Software Used in Nuclear Applications IP 36100 Inspection of 10 CFR Parts 21 and Programs for Reporting Defects and Noncompliance IP 36100.01 Inspection of 10 CFR 50.55(e) Programs for Reporting Defects and Noncompliance During Construction IP 37804 Aircraft Impact Assessment IP 37805 Engineering Design Verification Inspections | ||
IP 43002 | IP 43002 Routine Inspections of Nuclear Vendors | ||
IP 43003 | IP 43003 Reactive Inspection of Nuclear Vendors IP 43004 Inspection of Commercial-Grade Dedication Programs IP 43005 NRC Oversight of Third-Party Organizations Implementing Quality Assurance Requirements IP 43006 Inspection of Implementation of Mitigation Strategies Order Regarding the Use of National Safer Response Centers IP 65001 Inspections of Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Related Work IP 81811 Protection of Safeguards Information by Design Certification Applicants and Vendors | ||
5.0 | 5.0 Vendor Inspection Program | ||
The NRC performs routine and reactive vendor inspections and QA implementation inspections for the commercial nuclear power industry including new and operating reactors via the Quality Assurance Vendor and Inspection Branch (IQVB). IQVB also reviews changes to vendor and licensees QA programs pursuant to 10 CFR Part 50.4(b)(7) or 10 CFR Part 50.54(a), | The NRC performs routine and reactive vendor inspections and QA implementation inspections for the commercial nuclear power industry including new and operating reactors via the Quality Assurance Vendor and Inspection Branch (IQVB). IQVB also reviews changes to vendor and licensees QA programs pursuant to 10 CFR Part 50.4(b)(7) or 10 CFR Part 50.54(a), | ||
respectively. IQVB is responsible for performing reactive inspections in response to operating experience, reports of defects and noncompliance made in accordance with 10 CFR Part 21, or allegations, and conducting routine inspections to verify the effective implementation of vendor QA programs in order to assure the quality of materials, equipment, and services supplied to the commercial nuclear power reactor industry. | respectively. IQVB is responsible for performing reactive inspections in response to operating experience, reports of defects and noncompliance made in accordance with 10 CFR Part 21, or allegations, and conducting routine inspections to verify the effective implementation of vendor QA programs in order to assure the quality of materials, equipment, and services supplied to the commercial nuclear power reactor industry. | ||
4 6.0 | 4 6.0 Vendor Identification and Selection Methodology | ||
The identification and selection of vendors for inspection is based on several factors that include: | The identification and selection of vendors for inspection is based on several factors that include: | ||
Line 153: | Line 153: | ||
Appendix B defines the process by which those vendors are prioritized and scheduled for inspection, and Appendix F provides the criteria to determine when a plant change should be considered a major plant modification for enhanced vendor oversight. | Appendix B defines the process by which those vendors are prioritized and scheduled for inspection, and Appendix F provides the criteria to determine when a plant change should be considered a major plant modification for enhanced vendor oversight. | ||
7.0 | 7.0 Types of Inspection | ||
Vendor inspections are classified into two broad categories: routine inspections and reactive inspections. | Vendor inspections are classified into two broad categories: routine inspections and reactive inspections. | ||
Line 184: | Line 184: | ||
Routine and reactive inspections can be announced or unannounced. For announced inspections, the vendor or any member of the vendor organization is notified by the lead inspector or any member of the NRC staff that an inspection is to be conducted. The announcement may be made by a telephone call followed by written communication informing any member of the vendor organization that an inspection may or will take place at a specific time or date. For unannounced inspections, the vendor or any member of the vendor organization is not notified by the inspector or any member of the NRC staff until the inspectors arrive at the vendor's facility or at the site where the inspection is to be conducted. | Routine and reactive inspections can be announced or unannounced. For announced inspections, the vendor or any member of the vendor organization is notified by the lead inspector or any member of the NRC staff that an inspection is to be conducted. The announcement may be made by a telephone call followed by written communication informing any member of the vendor organization that an inspection may or will take place at a specific time or date. For unannounced inspections, the vendor or any member of the vendor organization is not notified by the inspector or any member of the NRC staff until the inspectors arrive at the vendor's facility or at the site where the inspection is to be conducted. | ||
8.0 | 8.0 Enforcement | ||
The NRCs Enforcement Policy governs the processes and procedures for the initiation and review of nonconformances and/or violations of NRC requirements, and the NRC Enforcement Manual contains implementation guidance. The NRCs OE issues both documents. Potential violations identified through inspection activities are processed in accordance with the NRCs Enforcement Policy. The NRCs Enforcement Policy is located on the NRCs public website at: | The NRCs Enforcement Policy governs the processes and procedures for the initiation and review of nonconformances and/or violations of NRC requirements, and the NRC Enforcement Manual contains implementation guidance. The NRCs OE issues both documents. Potential violations identified through inspection activities are processed in accordance with the NRCs Enforcement Policy. The NRCs Enforcement Policy is located on the NRCs public website at: | ||
Line 217: | Line 217: | ||
10 CFR Part 21). An NON is the official notification to a vendor of a failure to meet contract requirements related to NRC activities (e.g., Appendix B to 10 CFR Part 50) where the NRC has not placed requirements directly on the vendor. For NOVs and NONs, the NRC requests the vendor to respond to the issue and (1) discuss the reason for the noncompliance, or if contested, the basis for disputing the noncompliance; (2) the corrective steps that have been taken and results achieved; (3) the corrective steps that will be taken to avoid further noncompliance; and (4) the date when the corrective actions will be completed. | 10 CFR Part 21). An NON is the official notification to a vendor of a failure to meet contract requirements related to NRC activities (e.g., Appendix B to 10 CFR Part 50) where the NRC has not placed requirements directly on the vendor. For NOVs and NONs, the NRC requests the vendor to respond to the issue and (1) discuss the reason for the noncompliance, or if contested, the basis for disputing the noncompliance; (2) the corrective steps that have been taken and results achieved; (3) the corrective steps that will be taken to avoid further noncompliance; and (4) the date when the corrective actions will be completed. | ||
9.0 | 9.0 Coordination Activities and Industry Interactions | ||
The vendor inspection staff communicates both internally within the NRC and externally with industry stakeholders as described below. | The vendor inspection staff communicates both internally within the NRC and externally with industry stakeholders as described below. | ||
Line 367: | Line 367: | ||
* assumptions for typical vendor inspections (including preparation and documentation): | * assumptions for typical vendor inspections (including preparation and documentation): | ||
- 200 hours for the team leader | |||
- 120 hours per team member | |||
- one team leader and three team members for each inspection | |||
- 560 hours total per inspection | |||
* assumptions for typical engineering design verification inspections (including preparation and documentation): | * assumptions for typical engineering design verification inspections (including preparation and documentation): | ||
- 350 hours for the team leader | |||
- 275 hours per team member | |||
- 2 week inspection | |||
- one team leader and five to eight members for each inspection | |||
- 2,000 hours total per inspection | |||
For the majority of the inspection procedures executed by the vendor inspection branches, the resources related to direct inspection effort for each team member are estimated to be between 40 and 80 hours, depending on the complexity of the activity being inspected and the scope of the inspection. | For the majority of the inspection procedures executed by the vendor inspection branches, the resources related to direct inspection effort for each team member are estimated to be between 40 and 80 hours, depending on the complexity of the activity being inspected and the scope of the inspection. | ||
Line 391: | Line 391: | ||
As described in referenced sections of the VIP Plan, the vendor inspection staff performs the following on-goingongoing actions: | As described in referenced sections of the VIP Plan, the vendor inspection staff performs the following on-goingongoing actions: | ||
Frequency | Frequency Action VIP Plan Section Manage an internal database to store vendor On-going information and to facilitate vendor communication Appendix A and selection | ||
On-going | On-going Maintain a list of vendors Appendices A & C | ||
Quarterly | Quarterly Review vendor selection data and update, as Appendix B necessary VIP Self-Assessment: | ||
* VIP Performance Metrics Annually | * VIP Performance Metrics Annually | ||
* Number of NOVs and NONs | * Number of NOVs and NONs All | ||
* Communication of generic industry issues identified during the assessment with the relevant internal and external stakeholders. | * Communication of generic industry issues identified during the assessment with the relevant internal and external stakeholders. | ||
Annually | Annually Provide an electronic newsletter to be sent to Appendix C interested vendors | ||
Biennially | Biennially Establish workshops on vendor oversight Appendix C | ||
As necessary | As necessary Host town hall meetings with stakeholders Appendix C | ||
16 | 16 | ||
NRR-106 OFFICE | NRR-106 OFFICE NRR/DRO/IQVB NRR/DRO/IQVB NRR/DRO/IQVB NAME ABowie YDiaz-Castillo KKavanagh DATE 2/21/2024 2/21/2024 7/1/2024 APPENDIX A | ||
STRATEGY FOR VENDOR IDENTIFICATION PURPOSE | STRATEGY FOR VENDOR IDENTIFICATION PURPOSE | ||
Line 431: | Line 431: | ||
A-1 | A-1 | ||
- The vendor inspection staff populates the database from the above-mentioned sources. | |||
- The database contains the following information for each vendor (this list may be expanded to support the vendor selection methodology): | |||
name address telephone number point of contact (e.g., Quality Assurance Manager) and email address scope of supply (e.g., Class I piping, electric motors) comments | name address telephone number point of contact (e.g., Quality Assurance Manager) and email address scope of supply (e.g., Class I piping, electric motors) comments | ||
Line 496: | Line 496: | ||
Here is an example of a tabular target research vendor information: | Here is an example of a tabular target research vendor information: | ||
NRC | NRC NUPIC Part 21 Industry Product Vendor Scope Inspection Audit & Reports Issues Impact Recommendation | ||
& Findings Findings ASME QSC manufacturer of ferrous Low ABC and non-comple Company ferrous xity 123 Main welding None None None None Management Street, material Low Discretion Washington including Risk-DC 20012 utilization of signific unqualified ance source materials | |||
Target Research Information: | Target Research Information: | ||
Line 523: | Line 523: | ||
Vendor Strategist | Vendor Strategist | ||
NUPIC | NUPIC ASME TRG Others PEARTS Inspection Leads Leads Leads Leads Team Leads | ||
NEI Leads Allegation Team Leads | NEI Leads Allegation Team Leads | ||
Line 550: | Line 550: | ||
* Public web Site: The vendor inspection public web site (http://www.nrc.gov/reactors/new-reactors/oversight/quality-assurance.html) provides vendors a venue to obtain useful information on many topics, including the following: | * Public web Site: The vendor inspection public web site (http://www.nrc.gov/reactors/new-reactors/oversight/quality-assurance.html) provides vendors a venue to obtain useful information on many topics, including the following: | ||
- key regulations, such as Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of Production and Utilization Facilities, and 10 CFR Part 21, Reporting of Defects and Noncompliance | |||
- inspection procedures | |||
- inspection reports | |||
- information on commercial-grade dedication | |||
- presentations from past NRC workshops and town hall meetings | |||
- NRC presentations at conferences attended by the NRC | |||
* Workshops on Vendor Oversight: The NRC continues to host workshops on vendor oversight. The workshops continue to be successful and are excellent examples of NRC outreach. The workshops are widely attended and always generate significant dialogue with the vendor community about regulatory issues. Feedback through meeting comment forms is positive and stakeholders have requested additional workshops. | * Workshops on Vendor Oversight: The NRC continues to host workshops on vendor oversight. The workshops continue to be successful and are excellent examples of NRC outreach. The workshops are widely attended and always generate significant dialogue with the vendor community about regulatory issues. Feedback through meeting comment forms is positive and stakeholders have requested additional workshops. | ||
Line 562: | Line 562: | ||
* Participation in industry conferences and meetings: The vendor inspection staff continues to participate in related industry conferences and meetings such as the following: | * Participation in industry conferences and meetings: The vendor inspection staff continues to participate in related industry conferences and meetings such as the following: | ||
- American Society of Mechanical Engineers | |||
- Nuclear Procurement Issues Corporation meetings | |||
- NRCs Regulatory Information Conference | |||
- Electric Power Research Institute Procurement Engineering and Related Topics Symposium meetings | |||
- International Laboratory Accreditation Cooperation process activities | |||
- Working Group on Supply Chain meetings, under the auspices of the Committee on Nuclear Regulatory Activities and the Nuclear Energy Agency | |||
- Small Modular Reactors Regulators' Forum | |||
- Nuclear Oversight Conference | |||
KEY IMPROVEMENTS | KEY IMPROVEMENTS | ||
Line 576: | Line 576: | ||
* Improved the accessibility of the portions of the NRCs public web site that are relevant to vendor oversight. | * Improved the accessibility of the portions of the NRCs public web site that are relevant to vendor oversight. | ||
- The NRC created a link within the quick link box on the pages for new reactors and operating reactors. | |||
* Created a page on the public web site that categorizes nonconformances and violations from NRC vendor inspection reports. | * Created a page on the public web site that categorizes nonconformances and violations from NRC vendor inspection reports. | ||
- The NRC added a page with the 18 criteria from Appendix B to 10 CFR Part 50 and 10 CFR Part 21 so that vendors can select one of the criteria or 10 CFR Part 21 requirements and have all applicable inspection reports with nonconformances and violations in those areas listed. | |||
* Created a frequently asked questions (FAQ) page on the public web site that includes questions received at vendor conferences and other NRC outreach meetings. | * Created a frequently asked questions (FAQ) page on the public web site that includes questions received at vendor conferences and other NRC outreach meetings. | ||
- The FAQ provides a quick source of information and serves as a knowledge management tool. | |||
* Provide an annual electronic newsletter for vendors. | * Provide an annual electronic newsletter for vendors. | ||
C-2 | C-2 | ||
- The newsletter includes recent nonconformances and/or violations, potential rulemakings, upcoming conferences, operating experience and other useful information. Stakeholders can sign up for the newsletter through the NRCs web site. | |||
* Continue biennial workshops on vendor oversight. | * Continue biennial workshops on vendor oversight. | ||
- The NRC will continue to host a workshop every 2 years as one key forum for communication and outreach with vendors. The vendor inspection staff will continue to use comment cards to solicit feedback and seek recommendations for improving future workshops. | |||
CONTINUOUS IMPROVEMENT | CONTINUOUS IMPROVEMENT | ||
Line 658: | Line 658: | ||
VENDOR INSPECTION PROGRAM PERFORMANCE METRICS | VENDOR INSPECTION PROGRAM PERFORMANCE METRICS | ||
VIP-O-1 | VIP-O-1 Accomplish DROs (the U.S. Nuclear Regulatory Commissions Office of Nuclear Reactor Regulation, Division of Reactor Oversight) Established Number of Vendor Oversight Activities per Fiscal Year | ||
Definition: | Definition: Accomplish DROs established number of oversight activities per fiscal year to capture a reasonable perspective of industry performance. Oversight activities includes inspections and inspection support, licensing audits, and observations, performed domestically or internationally. | ||
Criteria: Expect DRO to perform the required number of oversight activities established at the beginning of the fiscal year. | Criteria: Expect DRO to perform the required number of oversight activities established at the beginning of the fiscal year. | ||
Line 666: | Line 666: | ||
Goals: Effective, Open | Goals: Effective, Open | ||
VIP-O-2A | VIP-O-2A Obtain Feedback from Vendors After the Vendor Inspection | ||
Definition: | Definition: The Branch Chief will solicit feedback from vendors inspected during the fiscal year on such aspects as the immediate inspection effort, vendor oversight, or NRC requirements and guidance. | ||
Criteria: 1. Expect BC to solicit feedback from 100% of vendors inspected during the fiscal year, | Criteria: 1. Expect BC to solicit feedback from 100% of vendors inspected during the fiscal year, | ||
Line 675: | Line 675: | ||
Goals: Effective, Open, Understandable | Goals: Effective, Open, Understandable | ||
VIP-O-2B | VIP-O-2B Notification of Inspection | ||
Definition: | Definition: Obtain data on the total number of inspections that were notified to the vendor within the timeliness goals stipulated in Section 10 of the Vendor Inspection Program (VIP) plan. | ||
Criteria: Expect 90 percent of inspections to be announced to the vendor within the VIPs timeliness goals. | Criteria: Expect 90 percent of inspections to be announced to the vendor within the VIPs timeliness goals. | ||
Line 683: | Line 683: | ||
Goals: Effective, Open, Predictable | Goals: Effective, Open, Predictable | ||
VIP-O-2C | VIP-O-2C Inspection Plans are Timely | ||
Definition: | Definition: Obtain data on the total number of inspection plans issued within the timeliness goals stipulated in Section 10 of the VIP plan. | ||
Criteria: Expect 90 percent of inspection plans to be issued within the VIPs timeliness goals. | Criteria: Expect 90 percent of inspection plans to be issued within the VIPs timeliness goals. | ||
Line 691: | Line 691: | ||
E-3 Goals: Effective, Open, Predictable | E-3 Goals: Effective, Open, Predictable | ||
VIP-O-2D | VIP-O-2D Inspection Reports are Timely | ||
Definition: | Definition: Obtain data on the total number of inspection reports issued within the timeliness goals stipulated in Section 11 of the VIP plan and Inspection Manual Chapter 0617, Vendor and Quality Assurance Implementation Inspection Reports, dated February 2020. | ||
Criteria: Expect 90 percent of inspection reports to be issued within the VIPs timeliness goals. | Criteria: Expect 90 percent of inspection reports to be issued within the VIPs timeliness goals. | ||
Line 699: | Line 699: | ||
Goals: Effective, Open, Collaborative, Predictable | Goals: Effective, Open, Collaborative, Predictable | ||
VIP-O-2E | VIP-O-2E Acknowledgment Letters Are Timely | ||
Definition: | Definition: Obtain data on the total number of acknowledgment letters issued within the timeliness goals stipulated in Section 11 of the VIP plan. | ||
Criteria: Expect 90 percent of acknowledgment letters to be issued within the VIPs timeliness goals. | Criteria: Expect 90 percent of acknowledgment letters to be issued within the VIPs timeliness goals. | ||
Line 707: | Line 707: | ||
Goals: Effective, Open, Predictable | Goals: Effective, Open, Predictable | ||
VIP-O-2F | VIP-O-2F Inspection Results Accepted by Stakeholders | ||
Definition: | Definition: Track the total number of NOVs and NONs contested by vendors. | ||
Criteria: Retract less than 10 percent of NOVs and NONs because they are successfully contested by the stakeholders. | Criteria: Retract less than 10 percent of NOVs and NONs because they are successfully contested by the stakeholders. | ||
Line 715: | Line 715: | ||
Goals: Effective, Objective, Open, Predictable | Goals: Effective, Objective, Open, Predictable | ||
VIP-O-3 | VIP-O-3 Allegation Support | ||
Definition: | Definition: Achieve the timely submittal of allegation response documents. | ||
Criteria: Conduct all support within the Allegation program timeliness goals. Support includes, but is not limited to, providing input for Allegation Review Board (ARB) materials, attending ARBs, providing input to Requests for Information, participating in phone calls with the Concerned Individual(s), providing input for closure and response after closure letters, etc. | Criteria: Conduct all support within the Allegation program timeliness goals. Support includes, but is not limited to, providing input for Allegation Review Board (ARB) materials, attending ARBs, providing input to Requests for Information, participating in phone calls with the Concerned Individual(s), providing input for closure and response after closure letters, etc. | ||
Line 723: | Line 723: | ||
Goals: Effective, Objective, Risk-Informed | Goals: Effective, Objective, Risk-Informed | ||
VIP-O-4A | VIP-O-4A Assessment of Trainee Qualifications | ||
Definition: | Definition: The Branch Chief assess inspectors-in-training for progress in achieving qualifications at least three times per fiscal year. | ||
F-1 Criteria:Expect 90 percent of trainees to qualify in 2 years from the start date. | F-1 Criteria:Expect 90 percent of trainees to qualify in 2 years from the start date. | ||
Line 731: | Line 731: | ||
Goals: Effective, Predictable, Understandable | Goals: Effective, Predictable, Understandable | ||
VIP-O-4B | VIP-O-4B Assessment of Inspector Proficiency | ||
Definition: | Definition: Maintain proficiency for all qualified inspectors. | ||
Criteria: Maintain annual proficiency for all qualified inspectors in accordance with the guidance set forth by the VIP for refresher and continuing training. | Criteria: Maintain annual proficiency for all qualified inspectors in accordance with the guidance set forth by the VIP for refresher and continuing training. |
Latest revision as of 14:09, 5 October 2024
ML24051A166 | |
Person / Time | |
---|---|
Issue date: | 07/01/2024 |
From: | Dong Park NRC/NRR/DRO/IQVB |
To: | |
References | |
Download: ML24051A166 (1) | |
Text
Vendor Inspection Program Plan Revision 30 July 2024
Prepared By: Quality Assurance and Vendor Inspection Branch Division of Reactor Oversight Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission CONTENTS
1.0 Vendor Inspection Program Overview................................................................................1
2.0 Objectives of the Vendor Inspection Program...................................................................1
3.0 Organization...........................................................................................................................3
4.0 Scope of Activities................................................................................................................3
5.0 Vendor Inspection Program.................................................................................................4
6.0 Vendor Identification and Selection Methodologies..........................................................5
7.0 Types of Inspection...............................................................................................................5
8.0 Enforcement...........................................................................................................................7
9.0 Coordination Activities and Industry Interactions.............................................................8
10.0 Communication and Outreach.........................................................................................11
11.0 Performance Metrics.........................................................................................................12
12.0 Knowledge Management and Training............................................................................13
13.0 Resource Management.....................................................................................................14
14.0 Implementation Schedule and Assessment...................................................................16
Appendix A: Strategy for Vendor Identification....................................................................A-1
Appendix B: Strategy for Vendor Selection..........................................................................B-1
Appendix C: Strategy for Enhanced Vendor Outreach and Communications..................C-1
Appendix D: Strategy for Coordinating Vendor Inspections..D-1
Appendix E: Vendor Inspection Program Performance Metrics.........................................E-1
Appendix F: Major Plant Modification Criteria.F-1 1.0 Vendor Inspection Program Overview
The Vendor Inspection Program (VIP) verifies that reactor applicants and licensees are fulfilling their regulatory obligations with respect to providing effective oversight of the nuclear supply chain. It accomplishes this through limited scope, targeted inspections of vendor quality assurance (QA) programs, communicating relevant vendor information to stakeholders, and supporting allegation response activities. Vendor inspections are planned using a strategy for vendor identification and selection which samples the effectiveness of the domestic and international nuclear supply chains for the current fleet and new reactor construction. To effectively implement vendor inspections, the vendor inspectors maintain the necessary knowledge and skills to perform inspections. Communication of vendor-related information is achieved through interaction with nuclear consensus standards organizations, vendors, industry supply chain organizations, international constituents, and other external stakeholders. The VIP serves as a mechanism to address vendor-related allegations received by the U.S. Nuclear Regulatory Commission (NRC) by providing technical support and/or vendor inspections for such allegations.
The VIP includes objectives and associated performance metrics to demonstrate that overarching goals are being met. These performance metrics are assessed annually to ensure successful implementation and continuous improvement of the VIP.
The purpose of the VIP Plan is to establish an overall approach, including goals, priorities, performance metrics, and resource management strategies for VIP activities. Key parts of the plan include:
- The objectives of the VIP, including its overarching goals that provide a link to the NRCs statutory mission of protecting public health and safety, promoting the common defense and security, and protecting the environment.
- The organization, staffing, training, and qualification of the vendor inspection staff in the NRCs Office of Nuclear Reactor Regulation (NRR) necessary to perform effective oversight of vendors.
- The necessary infrastructure, including inspection and regulatory guidance and tools (e.g., QA website, inspection planning and scheduling, and self-assessments).
- Communication and coordination activities with internal and external stakeholders.
- Technical and managerial support for vendor-related allegations.
2.0 Objectives of the Vendor Inspection Program
The VIP establishes specific objectives derived from six overarching goals that provide a nexus to the NRCs statutory mission of protecting public health and safety, promoting the common defense and security, and protecting the environment. The VIP is communicated both internally within the NRC and externally with industry stakeholders to ensure full integration of the program. Performance metrics have been established for each VIP objective to demonstrate that the following overarching goals are met:
1 (1) Objective - Decisions are based on factual information.
(2) Risk-informed - Risk insights are considered along with other factors (such as engineering judgment and management discretion) to better focus vendor and regulatory attention on issues commensurate with their importance to the NRCs mission.
(3) Understandable - The process and its results are clear and written in plain English.
(4) Predictable - More than one individual can follow the same defined process and arrive at the same conclusion in a consistent manner (e.g., repeatable).
(5) Open - NRC appropriately informs and involves stakeholders in the regulatory process.
(6) Effective - NRCs actions are of high quality, efficient, timely, and realistic, to enable the safe operation and construction of nuclear power plants.
The vendor inspection staff is responsible for implementing the VIP and ensuring that the objectives of the VIP are met. The objectives of the VIP are:
VIP-O-1Verify that applicants and licensees are fulfilling their regulatory obligations with respect to providing effective oversight of the nuclear supply chain for both operating reactors and new reactor design and construction activities through a strategic sample of vendor inspections.
The vendor inspection staff accomplishes this objective by performing various vendor oversight activities (e.g., inspections and inspection support, licensing audits, and observations) intended to verify the effective implementation of a vendors QA program. The oversight activities focus on verifying that basic components and services are supplied in accordance with the requirements of Appendix B, Quality Assurance Program Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of Production and Utilization Facilities, and 10 CFR Part 21, Reporting of Defects and Noncompliance, as passed down by licensees and applicants in the procurement documents to their vendors.
VIP-O-2Effectively communicate with internal and external stakeholders.
The vendor inspection staff accomplishes this objective through confirmation of the following:
- Inspection results provide sufficient detail to communicate whether the vendor is meeting commitments related to NRC-regulated activities and provide a direct link to the requirements that were not met.
- Inspection reports are written in plain language.
- Announcement letters, inspection plans, inspection reports, requests for information, acknowledgment letters, and other correspondence are completed in a timely manner consistent with the VIP metrics.
Inspection nonconformances and/or violations are rarely rescinded if contested.
2
- Communicate Appendix B to 10 CFR Part 50 and 10 CFR Part 21 issues with internal and external stakeholders.
VIP-O-3Perform timely and adequate allegation follow up and closure.
The vendor inspection staff accomplishes this objective by providing the necessary technical support to make sure that allegations are closed in a timely manner consistent with the NRCs metrics, in coordination with the Office of Enforcement (OE), Headquarters Allegation Review Team, as discussed in Appendix E, Vendor Inspection Program Performance Metrics, of this plan.
VIP-O-4Ensure that vendor inspectors have the necessary knowledge and skills to successfully implement the VIP.
The vendor inspection staff accomplishes this objective by verifying that vendor inspections are conducted by qualified inspectors, vendor inspectors-in-training make acceptable progress in their required qualifications, and qualified vendor inspectors maintain their proficiency. In addition, management provides appropriate oversight of on-going inspections and inspection reports.
The vendor inspection staff developed a set of performance metrics associated with each of the objectives of the VIP to assess program performance with respect to the goals listed above.
Section 11.0 of this plan describes these performance metrics.
3.0 Organization
The vendor inspection staff conducts inspections related to the requirements in Appendix B to 10 CFR Part 50 and 10 CFR Part 21 at suppliers that provide design, fabrication, and engineering services (including commercial-grade dedication) for nuclear components. In addition, the vendor inspection staff provides technical support for regional inspections, special projects, programs, and policy activities. The vendor inspection staff coordinates inspection activities and, as necessary, requests additional support from other NRC offices, technical divisions, regions, branches or contractors.
4.0 Scope of Activities
The vendor inspection staff conducts vendor inspections to verify that QA programs at vendor facilities are being effectively implemented and comply with the applicable regulatory requirements, including 10 CFR Part 21 and the licensee-imposed requirements of Appendix B to 10 CFR Part 50. These inspections also verify that component design requirements imposed on the vendors by their customers have been met, including as applicable, requirements associated with the environmental and seismic qualification of equipment. Vendor inspections may also support the Commissions determination that the acceptance criteria in a combined license are met in accordance with 10 CFR 52.99, Inspection During Construction, and 10 CFR 52.103(g). Also, using Inspection Procedure (IP) 37805, Engineering Design Verification Inspections, dated April 8, 2020, the NRC has conducted vendor inspections to review the development of the detailed design for new reactor designs licensed under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants. Vendor inspections follow the procedures given in the table below, as applicable, and are governed by Inspection Manual Chapter (IMC) 2507, Vendor Inspections.
3 Inspection Procedure (IP) Title IP 35007 Quality Assurance Program Implementation During Construction and Pre-Construction Activities IP 35017 Quality Assurance Implementation Inspection
IP 35034 Design Certification Testing Inspection
IP 35710 Quality Assurance Inspection of Software Used in Nuclear Applications IP 36100 Inspection of 10 CFR Parts 21 and Programs for Reporting Defects and Noncompliance IP 36100.01 Inspection of 10 CFR 50.55(e) Programs for Reporting Defects and Noncompliance During Construction IP 37804 Aircraft Impact Assessment IP 37805 Engineering Design Verification Inspections
IP 43002 Routine Inspections of Nuclear Vendors
IP 43003 Reactive Inspection of Nuclear Vendors IP 43004 Inspection of Commercial-Grade Dedication Programs IP 43005 NRC Oversight of Third-Party Organizations Implementing Quality Assurance Requirements IP 43006 Inspection of Implementation of Mitigation Strategies Order Regarding the Use of National Safer Response Centers IP 65001 Inspections of Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Related Work IP 81811 Protection of Safeguards Information by Design Certification Applicants and Vendors
5.0 Vendor Inspection Program
The NRC performs routine and reactive vendor inspections and QA implementation inspections for the commercial nuclear power industry including new and operating reactors via the Quality Assurance Vendor and Inspection Branch (IQVB). IQVB also reviews changes to vendor and licensees QA programs pursuant to 10 CFR Part 50.4(b)(7) or 10 CFR Part 50.54(a),
respectively. IQVB is responsible for performing reactive inspections in response to operating experience, reports of defects and noncompliance made in accordance with 10 CFR Part 21, or allegations, and conducting routine inspections to verify the effective implementation of vendor QA programs in order to assure the quality of materials, equipment, and services supplied to the commercial nuclear power reactor industry.
4 6.0 Vendor Identification and Selection Methodology
The identification and selection of vendors for inspection is based on several factors that include:
- The significance to safety of the equipment or service provided.
- Vendors manufacturing major plant modifications (i.e., replacement steam generators and reactor vessel heads, new fuel design, etc.).
- Verification of ITAAC in support of onsite construction activities.
- Input from the technical staff necessary to support completion of design certification and combined license (COL) reviews.
- The frequency and significance to safety of problems identified with vendor-supplied materials, equipment, or services, including third-party auditing organizations.
- The number of licensees affected by the problem identified, the performance history of a vendor.
- Other information received by IQVB from allegations, 10 CFR Part 21 reports, 10 CFR 50.55(e), Evaluation of Defects and Failures to Comply Associated with a Substantial Safety Hazard reports, Licensee Event Reports, and other NRC organizations.
- Significance, type, and duration of previously opened findings during previous inpection activities.
The methodology for the identification and selection of vendors for inspection is considered an essential element of the VIP. More detailed information on how IQVB identifies and selects vendors for inspection can be found in Appendix A, Strategy for Vendor Identification, Appendix B, Strategy for Vendor Selection, and Appendix F, Major Plant Modification Criteria, to this plan. Specifcally, Appendix A describes the strategy used to identify vendors supplying safety-related material, equipment, and services to the nuclear power industry.
Appendix B defines the process by which those vendors are prioritized and scheduled for inspection, and Appendix F provides the criteria to determine when a plant change should be considered a major plant modification for enhanced vendor oversight.
7.0 Types of Inspection
Vendor inspections are classified into two broad categories: routine inspections and reactive inspections.
Routine Inspections
Routine inspections verify that vendors supplying basic components in accordance with the requirements in Appendix B to 10 CFR Part 50 and 10 CFR Part 21 provide a product meeting the technical and quality requirements in the procurement documents, including industry codes, standards, and applicable regulatory requirements. Routine inspections focus on observing the vendors activities during the design, fabrication, and testing of basic components. In addition,
5 the inspection verifies that the vendor implements controls for reporting defects and noncompliance in accordance with 10 CFR Part 21 requirements. For vendors performing dedication of commercial-grade items, the inspections also verify the effectiveness of the commercial-grade dedication program. Furthermore, the vendor inspection staff performs QA implementation and engineering design verification inspections to verify that the translation of high-level design information and performance requirements into procedures, specifications, calculations, drawings, procurement, and construction documents is consistent with the applicable regulatory requirements. For vendors that hold safeguards information (SGI),
including applicants for design certification, the vendor inspection staff performs triennial inspections of SGI information protection per IP 81811 in accordance with 10 CFR 73.22, Protection of Safeguards Information: Specific Requirements.
Reactive inspections are conducted in response to allegations, previous inspection nonconformances and/or violations, reports submitted in accordance with 10 CFR Part 21 or 10 CFR 50.55(e), or other information indicating the possibility that vendors are not meeting regulatory requirements. Reactive inspections verify that vendors of basic components have developed and implemented adequate procedures and controls to evaluate and correct conditions adverse to quality. In response to allegations, the vendor inspection staff conducts reactive inspections to verify the validity of any declaration, statement, or assertion of impropriety or inadequacy associated with NRC-regulated activities involving a vendor-supplied product or service. During these inspections, the vendor inspection staff evaluates the effectiveness of the vendors QA program and procedures, as it relates to the reported problem.
The vendor inspection staff also supports regional requests in response to events at licensee facilities. Inspections of vendors have been conducted in support of regional reactive inspections where the focus has been on the failure of safety-related systems, structures, or components.
When the vendor inspection staff receives information that questions a vendors ability to provide quality components, the following criteria are used to determine the need to perform a reactive versus a routine inspection:
- Involved loss of a safety function at an operating reactor site where a vendor issue was identified as a root cause.
- Involved a major deficiency in design or dedication involving potential generic safety implications.
- Led to a significant issue that affected/could affect closure of ITAAC.
- Involved counterfeit, fraudulent, or suspect items that caused or could have caused a failure of a safety system.
- Involved a fabrication or construction deficiency involving potential generic implications.
- Involved a major deficiency in the design, function, or traceability of a critical digital asset.
6
- Involved repetitive and frequent failures of components provided by a specific vendor (i.e. as evident by regulatory notifications).
- Involved a reported defect that failed to provide an appropriate technical evaluation to address the scope of the identified concern.
Routine and reactive inspections can be announced or unannounced. For announced inspections, the vendor or any member of the vendor organization is notified by the lead inspector or any member of the NRC staff that an inspection is to be conducted. The announcement may be made by a telephone call followed by written communication informing any member of the vendor organization that an inspection may or will take place at a specific time or date. For unannounced inspections, the vendor or any member of the vendor organization is not notified by the inspector or any member of the NRC staff until the inspectors arrive at the vendor's facility or at the site where the inspection is to be conducted.
8.0 Enforcement
The NRCs Enforcement Policy governs the processes and procedures for the initiation and review of nonconformances and/or violations of NRC requirements, and the NRC Enforcement Manual contains implementation guidance. The NRCs OE issues both documents. Potential violations identified through inspection activities are processed in accordance with the NRCs Enforcement Policy. The NRCs Enforcement Policy is located on the NRCs public website at:
https://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html. The NRCs NRRs Office Instruction NRR COM-104, Revision 3, NRR Interfaces with the Office of Enforcement, provides information on the interface between NRR and OE. OE.
Vendors supplying basic components to the nuclear power industry are subject to the following regulations:
- 10 CFR 50.5 and 10 CFR 52.4, Deliberate Misconduct
- 10 CFR 50.7 and 10 CFR 52.5, Employee Protection
In addition, applicants and licensees contractually impose the following regulations, as applicable, on their vendors:
- Appendix B to 10 CFR Part 50
- 10 CFR 50.55a, Codes and Standards
- 10 CFR 73.54, Protection of Digital Computer and Communication Systems and Networks
For vendors that hold SGI, the following apply:
- 10 CFR 73.21, Protection of Safeguards Information: Performance Requirements
- 10 CFR 73.22, Protection of Safeguards Information: Specific Requirements
- NRC Order No. EA-07-231, Order Imposing Safeguards Information Protection Requirements and Fingerprinting and Criminal History Records Check Requirements for Access to Safeguards Information, dated September 12, 2007 (applicable to addressed design certification applicants)
7 A vendor that fails to comply with the above regulations is subject to the following enforcement actions:
- notices of violation (NOVs)
- notices of nonconformance (NONs)
The NRC issues NONs and NOVs to vendors for failures to meet the requirements of Appendix B to 10 CFR Part 50 or 10 CFR Part 21, respectively. Failure to meet an NRC Order, applicable to that vendor, would also be an NOV. When applicable, the NRC may also issue an Unresolved Item (URI). URIs are for issues which more information is required to determine if it is acceptable, if it is a finding, or if it constitutes a deviation or violation. These issues may require additional information from the vendor or cannot be resolved without additional guidance, clarification, or interpretation of the existing guidance.
Vendors NONs and NOVs are assessed annually to identify industry weaknesses and are communicated through the VIPs Strategy for Enhanced Vendor Outreach and Communications.
The target audience for this strategy includes licensees, license or design certification applicants, and vendors. The strategy also includes hosting workshops on vendor oversight every two years, which are widely attended and generate significant dialogue with the vendor community about technical and regulatory issues. Additionally, the vendor inspection staff will hold virtual town hall meetings as necessary to engage with external stakeholders to discuss any current issues of importance to the nuclear industry, and to provide guidance and clarification, as necessary. The goal of the virtual town hall meeting is to keep the external stakeholders informed on activities related to vendor inspection, quality assurance, etc. The number of virtual town hall meetings will depend on the number of significant topics or issues as well as the availability of NRC resources.
An NOV is the official notification of a failure to meet the NRCs regulatory requirements (e.g.,
10 CFR Part 21). An NON is the official notification to a vendor of a failure to meet contract requirements related to NRC activities (e.g., Appendix B to 10 CFR Part 50) where the NRC has not placed requirements directly on the vendor. For NOVs and NONs, the NRC requests the vendor to respond to the issue and (1) discuss the reason for the noncompliance, or if contested, the basis for disputing the noncompliance; (2) the corrective steps that have been taken and results achieved; (3) the corrective steps that will be taken to avoid further noncompliance; and (4) the date when the corrective actions will be completed.
9.0 Coordination Activities and Industry Interactions
The vendor inspection staff communicates both internally within the NRC and externally with industry stakeholders as described below.
Communication within the NRC on Vendor Inspection Activities
The vendor inspection staff interacts with the technical branches within NRR divisions that provide technical expertise in civil, mechanical, electrical, instrumentation and control, geotechnical, and chemical and materials engineering for all structures, systems, and components (SSCs) for new and operating nuclear power reactors manufactured and procured through licensee engineering procurement contracts. These technical experts participate in vendor inspections with qualified vendor inspectors to ensure that the quality of safety-related
8 SSCs is such that there is reasonable assurance that the SSCs will perform their intended safety function when installed in nuclear power plants.
The vendor inspection staff also interacts with OE with coordination and support to Office of Investigations (OI) on vendor-related issues associated with allegations and with the NRCs Region II staff to coordinate the agencys resources necessary to support inspections of targeted and non-targeted ITAAC-related activities at vendors manufacturing safety-related components and modular assemblies for new reactor construction. Coordination includes effectively communicating any nonconformances and/or violations identified at the vendor facility. Inspection samples of ITAAC-related activities, as well as any relevant inspection results, are documented in the inspection reports. Appendix D of this plan provides the strategy used by the vendor inspection staff for coordinating vendor inspections with the appropriate Region II staff.
In addition, as part of the vendor inspection staffs effort to enhance communications, when potential nonconformances and/or violations at vendor inspections affect an operating reactor(s), the vendor inspection staff will include the applicable NRR Project Managers on the inspection report distribution.
Furthermore, the vendor inspection staff participates in activities associated with the following organizations:
- American Nuclear Society (ANS)
- American Society of Mechanical Engineers (ASME)
- Institute of Electrical and Electronics Engineers (IEEE)
Communication and Engagement with Stakeholders on Vendor Inspection Activities
The vendor inspection staff interacts with the following external organizations:
- Electric Power Research Institute (EPRI)
- Committee on Nuclear Regulatory Activities (CNRA)
- Nuclear Energy Institute (NEI)
- Nuclear Procurement Issues Corporation (NUPIC)
Electric Power Research Institute - Procurement Engineering and Related Topics Symposium
The vendor inspection staff interacts with EPRI by participating the EPRI Procurement Engineering and Related Topics Symposium (PEARTS) procurement forum. During these meetings, the vendor inspection staff presents on NRC perspectives on vendor performance issues. The EPRI PEARTS provides a forum for utility procurement personnel to candidly exchange information and to work together to address common industry issues related to the procurement of materials and services.
Committee on Nuclear Regulatory Activities
CNRA is an international committee made up of senior representatives from regulatory bodies.
It was created in 1989 to guide the NEA program concerning the regulation, licensing and inspection of nuclear installations with regard to safety. The CNRA's main tasks are to: (1) exchange information and experience among regulatory organizations; (2) review developments
9 which could affect regulatory requirements; and (3) review current practices and operating experiences.
The Working Group on Supply Chain (WGSUP) provides a mechanism for nuclear safety regulators and technical support organizations to share their knowledge in making policy and licensing decisions related to the supply chain. The WGSUP seeks to facilitate an active and timely exchange of commendable practices as well as lessons learned to help regulators perform these functions more effectively and efficiently. Although the focus of the group is on those portions of the supply chain used to support the construction and operation of power reactors, the WGSUP may draw on lessons learned from other areas if they are relevant to safety.
The vendor inspection staff participates in vendor inspections led by foreign regulatory authorities to provide additional insights relative to the effectiveness of licensee (both foreign and domestic) oversight of these international vendors. The vendor inspection staff has led several multinational vendor inspections, observed other regulators vendor inspection activities in the US, and supported other regulators observe NRC inspections outside the US.
Nuclear Energy Institute
The vendor inspection staff occasionally interfaces with NEI to discuss mutual items of interest (i.e., commercial-grade dedication, 10 CFR Part 21 implementation, procurement, software dedication, and vendor oversight). These interactions ensure that the agency and industry concerns are both addressed during the development of vendor and supplier guidance documents. In addition, the staff has endorsed several NEI documents related to quality and vendor oversight which can be found on the NRCs QA web site.
Nuclear Procurement Issues Corporation
The vendor inspection staff routinely observes NUPIC joint utility audits in order to verify the effectiveness of the NUPIC audit.
The typical NUPIC audit scope is to determine the overall acceptability and verify the effective implementation of a vendors QA requirements through use of the NUPIC audit checklist, which is structured in accordance with the requirements of Appendix B to 10 CFR Part 50, ASME NQA-1, Quality Assurance Requirements for Nuclear Facility Applications, and 10 CFR Part
- 21. While observing the audit, the NRC Inspectors sample and review audit checklist evaluation areas, observe NUPICs review of the implementation of the vendors QA program, and evaluate the adequacy of NUPICs process for documenting audit findings in the associated trip report. The vendor inspection staff continuously interacts with NUPIC auditors during the NUPIC audit observation. If the vendor inspection staff observes any potential violations of regulations during the audit and the NUPIC auditors fail to act on the issue, the vendor inspection staff will bring the issue to the attention of the NUPIC utility lead auditor for resolution. If the staff disagrees with the audit teams assessment of issues, the staff will have a debrief meeting with the audit team lead after the exit meeting. The staff will wait to get the audit report before issuing the NRC trip report (within 30 days of getting the audit report) and the staff will include the disagreements discussed with the audit team lead in the trip report. The results of the NUPIC observation are documented in a publicly available trip report.
The vendor inspection staff observes approximately two NUPIC audits a year. The vendor inspection staff evaluates NUPIC to make sure the audits meet current regulatory standards,
10 and the process is appropriately holding licensees accountable for their oversight of vendors.
The goal of the evaluation is to conclude that the vendor inspection staffs current interactions with NUPIC (1) are effectively communicating regulatory concerns/initiatives and industry issues between organizations and has served as a catalyst for several NUPIC process improvements, and (2) provide valuable insights into vendor performance issues used as a key parameter in the NRCs criteria for selecting vendors for inspection. However, in order to improve the NRCs oversight of the NUPIC audits, the vendor inspection staff will supplement the current biannual observations of NUPIC audits with observations of limited scope audits (LSAs). An LSA is a supplemental audit scheduled outside the normal NUPIC audit frequency focused on specific performance deficiencies.
Up to three times per year, the vendor inspection staff participates in NUPIC meetings during which the vendor inspection staff provides an update on on-going NRC vendor inspection activities and shares the results of recent NRR NUPIC audit observations. The NRC plans to continue its oversight of the NUPIC process in order to further enhance the NUPIC joint utility audit program and increase the alignment between NUPIC and the agency regarding the conduct of vendor inspections.
NUPIC, in conjunction with NEI, formed an industry team, consisting of licensees and suppliers, to monitor activities by the International Laboratory Accreditation Cooperation (ILAC) as they relate to industrys use of the ILAC accreditation process in lieu of performing a commercial-grade survey as part of commercial-grade dedication process. NUPIC plays a central role in the continued oversight activities, and a NUPIC member leads or participates in the observations of peer evaluations of an Accrediting Body and the associated assessments of calibration and testing laboratories to verify that the ILAC accreditation process continues to be implemented consistent with ILACs requirements and procedures.
10.0 Communication and Outreach
Licensees and applicants are ultimately responsible for the safety of the facilities licensed by the NRC. As such, they must ensure that their vendors understand and effectively implement the applicable regulations. The vendor inspection staffs efforts to improve communication and outreach with these stakeholders enhances the NRCs commitment to openness, efficiency, and clarity. The vendor inspection staff developed the Strategy for Enhanced Vendor Outreach and Communications (see Appendix C to this plan). The purpose of this strategy is to establish and communicate the NRCs plan to enhance outreach and communications with vendors supplying materials, equipment and services for both operating and new reactors. The vendor inspection staff will update this strategy as necessary as part of the annual VIP self-assessment process.
Additionally, in order to better facilitate communication and outreach activities with stakeholders, the NRC established the following goals for announcement letters, inspection plans, inspection reports, and acknowledgment letters:
(1) Notification of Inspection: 30 calendar days before the start of the inspection unless the inspection is unannounced. Notification can be made either by email, phone, or in person. In cases where the need for the inspection arises (i.e., allegation, testing schedule, and/or specific vendor activity) less than 35 days before the inspection start date, issue the Announcement Letter within five calendar days of being notified of the need for the inspection. In cases where the need for the inspection arises less than five calendar days, issue the Announcement Letter prior to inspection.
11 Applicants, and/or vendors should not be notified of the NRCs plans to perform an inspection at the applicant, and/or vendors facility prior to 60 days before the start date of the inspection, except in limited cases (e.g., international inspections, etc.) as previously discussed with and approved by the IQVB Branch Chief.
(2) Inspection Plans: Seven calendar days before the start of the inspection. In cases where the need for the inspection arises (i.e., allegation, testing schedule, and/or specific vendor activity) less than seven calendar days before the inspection start date, issue the inspection plan prior to the inspection. Inspections plans are for the inspection team only and are not made public or shared with the vendors being inspected (Note: inspection plans are non-public).
(3) Inspection Reports: 45 calendar days after the exit meeting, extended until the next business day if the 45 days end on a weekend or holiday.
(4) Acknowledgment Letters: 30 calendar days after the vendors last communication is entered into Agencywide Documents Access Management System (ADAMS).
Additional Methods of Communication Regarding Vendor Issues
When issues are identified regarding materials or services supplied by a vendor to a specific licensee, the vendor inspection staff should consider adding the appropriate NRR Project Manager, Resident Inspectors, and/or licensee contacts to the inspection report distribution list.
Additionally, the vendor inspection staff may notify licensees about specific vendor-related issues via direct written correspondence or generic communications. If significant weaknesses in oversight are observed, the NRC staff may choose to engage directly with the lead licensee on a case-by-case basis.
11.0 Performance Metrics
The vendor inspection staff uses performance metrics to evaluate the success of the VIP.
Measurement of these metrics allows the vendor inspection staff to do the following:
- Identify performance issues and determine their significance
- Adjust resources to focus on significant performance issues
- Take necessary regulatory actions for significant performance issues
- Effectively communicate inspection results to stakeholders
- Make program improvements based on stakeholder feedback and lessons learned
Appendix E, attached to this document, provides a detailed description of the performance metrics associated with the goals described in Section 2.0 of this plan.
Each metric in Appendix E includes its definition, the criteria to determine whether it is met, and a cross-reference to the VIP goals that the metric is intended to support.
12.0 Knowledge Management & Training
Knowledge Management
12 Knowledge management and vendor inspector training are critical for effectiveness of the VIP.
The NRCs knowledge management process includes several training documents (that are defined by community of practice) and SharePoint sites dedicated to vendor inspector qualification and continuing training.
To support the continuing development of the VIP, the vendor inspection staff also maintains a SharePoint site to share information on the various activities performed in the VIP, including 10 CFR Part 21 issues, the issues of other organizations (e.g., NUPIC, ASME), and unique or complex inspection findings. The vendor inspection staff uses these knowledge management systems to ensure the availability of information related to vendor inspections. The IQVB Branch Chief and senior staff actively participate in the mentoring of new staff in support of the vendor inspection and technical reviewer qualification programs.
Vendor Inspector Training and Qualification Activities
As a part of the overall VIP, active involvement by vendor inspection staff members at all experience levels is critical. Specifically, training and qualification monitoring by senior staff, combined with a cohesive system of knowledge transfer from experienced vendor inspection staff to trainees, ensures a continual cadre of knowledgeable, well-trained, and fully qualified vendor inspectors. Appendix C-8, Vendor Inspector Technical Proficiency Training and Qualification Journal, of NRCs IMC 1245, Qualification Program for New and Operating Reactor Programs, contains the training and qualification requirements for NRR vendor inspection staff performing inspection activities.
Competency Areas
Vendor inspector qualification requires the completion of numerous activities. Each activity is designed for the inspector to learn information or a skill that will be important to performing as a vendor inspector. Completion of all qualification training and activities (including those for basic-level general proficiency, and technical proficiency-level) demonstrates that an individual possesses the knowledge necessary to become a successful vendor inspector. Full vendor inspector qualification indicates that the individual has completed all required training and qualification activities. Vendor inspector qualification allows an individual to independently perform the full scope of inspection-related activities with routine oversight and supervision.
In general, nonqualified inspectors will receive specific tasks to accomplish during these activities, but they will have an experienced inspector assigned as a mentor to provide guidance on the necessary tasks as well as to assist with any questions or concerns related to the activity. In this manner, junior inspectors will gain knowledge from senior staff, meaningfully participate in the VIP, and fulfill their on-the-job training requirements.
Methods for Completing Qualification
In accordance with IMC 1245, previous work experience and training may be accepted as evidence that an individual already possesses the required knowledge or skills achieved by completing parts of the vendor inspection qualification program. The Division of Reactor Oversight (DRO) Director has the authority to accept previous experience and training as an alternate method for meeting the requirements. Justification for accepting previous experience and training to meet program requirements must be determined by the IQVB Branch Chief and documented in the individual's qualification journal. In accordance with IMC 1245, an individual who was previously qualified as an NRC inspector must complete the additional specific training
13 and qualification requirements for vendor inspection specified in Appendix C-8 to IMC 1245.
Inspectors need not repeat previous equivalent training requirements, and the qualification journal will indicate credit for previous similar training. A fully qualified inspector is not required to complete another qualification board for vendor inspector qualification.
The IQVB Branch Chief has the flexibility to determine when an employee is ready for an oral qualification board. For example, this determination can be done by conducting a mock oral qualification examination or by an interview. The IQVB Branch Chief will confirm that all qualification requirements have been met and will convene a qualification board to examine the employees regulatory knowledge, skills, and ability to perform the functions independently. If an employee passes a board and then completes a different position-specific qualification, that employee shall only be tested on the requirements of the subsequent position-specific qualification program. Successfully completing a qualification board will ensure that the inspector understands the role of the agency, the inspection program, and the inspectors responsibilities. Final vendor inspector qualification is provided through certification by the NRR Office Director.
Post-qualification Activities
Qualified vendor inspectors maintain their qualification as required in Appendix D-1 to IMC 1245. Appendix D-1 defines the requirements for post-qualification and refresher training for qualified vendor inspectors.
Post-qualification training is defined as the training received after qualification to supplement or enhance the professional development of the vendor inspection staff. All qualified vendor inspectors are required to participate in on-going post-qualification training to maintain and enhance their knowledge and skills. This training includes elements of both continuing and refresher training as defined in IMC 1245-03. Continuing training includes Vendor Inspector group training conducted at least three times per fiscal year that concentrates on core competencies and lessons learned.
The IQVB Branch Chief and other office management will evaluate the need for additional continuing and refresher training necessary to meet the requirements of Appendix D-1 to IMC 1245, as necessary. Additionally, the IQVB Branch Chief will monitor inspector performance through periodic observations of inspections.
13.0 Resource Management
As a result of the development of the enhanced VIP in 2007, and within the framework of IMC 2507, the vendor inspection staff conducts vendor inspections to a level commensurate with the number of routine and reactive inspections specified in the NRR operating plan on a yearly basis. The VIP continues to use the NRR operating plan, in conjunction with any additional SRMs, or other form of Commission or NRR management direction, to plan and manage resources for the conduct of vendor inspection activities.
In terms of resource management, the objective of the VIP is to ensure that the NRC has an adequate number of knowledgeable, well-trained, and qualified vendor inspectors to meet the forecasted workload of vendor inspections. The vendor inspection staff supports this objective by:
- providing timely training and qualification for vendor inspectors;
14
- periodically looking ahead to anticipate the upcoming workload in terms of planned and potential unplanned or reactive inspections;
- routinely assessing policy and key technical issues that may have an impact on the VIP;
- establishing relationships between the vendor inspection staff and various outside organizations (e.g., NUPIC, ASME, NEI) such that routine interactions can be undertaken as efficiently as possible with maximum results; and
- ensuring that the composition of the vendor inspection team represents the best combination of senior vendor inspectors, technical experts, and vendor inspectors-in-training available, given the nature of the vendor to be inspected, including the leverage of contract resources and technical expertise from other divisions, as necessary.
In addition, the vendor inspection staff gains insights from inspections performed by peer regulators (e.g., CNRA) and industry auditors (e.g., NUPIC) to help inform the prioritization of vendor inspection resources. These insights are another input into the selection process for vendor inspections which also considers other items, including but not limited to the safety significance of the component or service, operational and construction experience (domestic and foreign), construction inspection program insights, and licensee and applicant procurement plans.
NRR currently makes the following resource assumptions about vendor inspection activities in order to support appropriate resource loading for the VIP:
- assumptions for typical vendor inspections (including preparation and documentation):
- 200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> for the team leader
- 120 hours0.00139 days <br />0.0333 hours <br />1.984127e-4 weeks <br />4.566e-5 months <br /> per team member
- one team leader and three team members for each inspection
- 560 hours0.00648 days <br />0.156 hours <br />9.259259e-4 weeks <br />2.1308e-4 months <br /> total per inspection
- assumptions for typical engineering design verification inspections (including preparation and documentation):
- 350 hours0.00405 days <br />0.0972 hours <br />5.787037e-4 weeks <br />1.33175e-4 months <br /> for the team leader
- 275 hours0.00318 days <br />0.0764 hours <br />4.546958e-4 weeks <br />1.046375e-4 months <br /> per team member
- 2 week inspection
- one team leader and five to eight members for each inspection
- 2,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> total per inspection
For the majority of the inspection procedures executed by the vendor inspection branches, the resources related to direct inspection effort for each team member are estimated to be between 40 and 80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br />, depending on the complexity of the activity being inspected and the scope of the inspection.
The vendor inspection staff assembles inspection teams based on: (1) the estimated complexity and associated level of effort for each inspection; (2) the knowledge level and current workload of each member of the inspection team; (3) the need for technical expertise from contract or
15 technical division sources, or both; (4) the usefulness of the inspection as a training activity for junior inspectors; and (5) the potential burden placed upon the vendor from having a larger inspection team. When scope of the inspection is limited, the normal size of the inspection team and the duration of the inspection may be reduced based on the inspection requirements. By taking all of these factors into consideration, the vendor inspection branches are able to assemble the most effective teams available, while also providing for training opportunities and continued learning.
The vendor inspection staffs workload is periodically assessed to ensure that the appropriate level of resource loading is being applied to each vendor inspector, commensurate with his or her experience level, special interests, unique qualifications, and other factors. This ensures that vendor inspection resources are used as efficiently and effectively as possible.
14.0 Implementation Schedule and Assessment
As described in referenced sections of the VIP Plan, the vendor inspection staff performs the following on-goingongoing actions:
Frequency Action VIP Plan Section Manage an internal database to store vendor On-going information and to facilitate vendor communication Appendix A and selection
On-going Maintain a list of vendors Appendices A & C
Quarterly Review vendor selection data and update, as Appendix B necessary VIP Self-Assessment:
- VIP Performance Metrics Annually
- Number of NOVs and NONs All
- Communication of generic industry issues identified during the assessment with the relevant internal and external stakeholders.
Annually Provide an electronic newsletter to be sent to Appendix C interested vendors
Biennially Establish workshops on vendor oversight Appendix C
As necessary Host town hall meetings with stakeholders Appendix C
16
NRR-106 OFFICE NRR/DRO/IQVB NRR/DRO/IQVB NRR/DRO/IQVB NAME ABowie YDiaz-Castillo KKavanagh DATE 2/21/2024 2/21/2024 7/1/2024 APPENDIX A
STRATEGY FOR VENDOR IDENTIFICATION PURPOSE
The purpose of this document is to establish and communicate the U.S. Nuclear Regulatory Commissions (NRCs) strategy for identifying vendors of safety-related parts and services for new and operating nuclear power plants. Application of the strategy will result in a listing of vendors that will enable the NRC to identify and plan its inspection and outreach activities.
BACKGROUND
Licensees and applicants are responsible for the safety of facilities licensed by the NRC. As such, they are responsible for ensuring that their vendors meet applicable regulations and requirements (both technical and quality) in purchase documents. In order to ensure that licensees are meeting the regulatory requirements in this area, the NRC inspects vendors to evaluate their conformance with technical and quality requirements. The NRC also performs direct oversight of licensees by observing Nuclear Procurement Issues Corporation (NUPIC) audits.
To ensure the efficient and effective use of NRC resources, the NRC has developed a methodology to select vendors for inspection and a strategy to enhance outreach and communications with vendors (see Appendix B, Strategy for Vendor Selection, and Appendix C, Strategy for Enhanced Vendor Outreach and Communications, to this document). This vendor identification strategy will support those efforts.
VENDOR IDENTIFICATION STRATEGY
Currently, the NRC obtains information about vendors from the following sources:
- reports under Title 10 of the Code of Federal Regulations (10 CFR) 21.21, Notification of Failure to Comply or Existence of a Defect and Its Evaluation 10 CFR 50.72, Immediate Notification Requirements for Operating Nuclear Power Reactors; and 10 CFR 50.73 reports, Licensee Event Report System
- interaction with industry and standards organizations such as NUPIC, the Nuclear Industry Assessment Committee, and the ASME
- formal and informal communication with licensees, applicants, and engineering, procurement, and construction contractors
- allegations
- approved supplier lists of licensees and vendors
The vendor inspection staff manages an internal database to store vendor information and facilitate vendor communication and selection.
A-1
- The vendor inspection staff populates the database from the above-mentioned sources.
- The database contains the following information for each vendor (this list may be expanded to support the vendor selection methodology):
name address telephone number point of contact (e.g., Quality Assurance Manager) and email address scope of supply (e.g., Class I piping, electric motors) comments
CONTINUOUS IMPROVEMENT
The vendor inspection staff tracks the effectiveness of its vendor identification and outreach activities by considering the usefulness of the information gathered. The vendor inspection staff will consider the strategys effect on inspection planning and vendor outreach and revisit and revise this strategy, as necessary. This strategy is a living document and as such the vendor inspection staff will update and modify it to suit the changing needs of the NRC and at a minimum, it will be reviewed on an annual basis.
A-2 APPENDIX B
STRATEGY FOR VENDOR SELECTION PURPOSE
The purpose of this document is to describe the risk-informed Vendor Inspection Program (VIP) strategy that the Quality Assurance and Vendor Inspection Branch (IQVB) uses to help prioritize vendors for inspection by the U.S. Nuclear Regulatory Commission (NRC) staff. This strategy is applicable to vendors that are currently supplying safety-related material, equipment, and services to the U.S. nuclear power industry. The strategy is a program assessment tool that establishes the basis for the vendor selection process and ensures the integrity of the nuclear supply chain for basic components.
BACKGROUND
Inspection Manual Chapter (IMC) 2507, Vendor Inspections, contains general staff guidance on selecting vendors that are supplying safety-related material, equipment, and services for NRC inspection. The strategy contained in this document expands upon the guidance in the IMC and helps to ensure an efficient and effective use of NRC resources allocated for vendor inspection.
VENDOR SELECTION STRATEGY
As described in the Strategy for Vendor Identification, (Appendix A of the VIP Plan), the vendor inspection staff maintains an internal database to store vendor information and facilitate vendor communication to assist with the vendor selection strategy. The VIP provides guidance for effective oversight of the nuclear supply chain by way of fixed and qualitative factors. Fixed factors are the objectives of the VIP activities which dictate the overarching goals of the NRCs statutory mission of protecting public health and safety, promoting the common defense and security, and protecting the environment. Qualitative factors are those elements related to VIP activities which verify that reactor applicants and licensees are fulfilling their regulatory obligations with respect to ensuring the integrity of the supply chain. The qualitative factors are administered and evaluated by the Vendor Strategists. The Vendor Strategists collect data, detailed below, and present the findings to IQVB management for making a final determination on vendor inspection selection. Management discretion will be responsible for the majority of the vendors selected (about 75%), while the remaining (about 25%) will be based on the Vendor Strategists recommendations.
MANAGEMENT DISCRETION
Management discretion considerations in selecting the vendors to be inspected include, but are not limited to safety culture issues, susceptibility to counterfeiting or cybersecurity issues, targeted reviews of inspections, tests, analyses, and acceptance criteria (ITAAC), fabrication of major plant modifications, Regional management input on potential vendor issues, and risk insights to the extent practicable.
Management discretion considerations also include reactive inspections. Reactive inspections are conducted in response to allegations, previous inspection findings, reports in accordance with 10 CFR Part 21, Reporting of Defects and Noncompliance and/or 10 CFR 50.55(e), and other information sources potentially indicating that NRC requirements are not being met. The need to perform reactive vendor inspections is determined outside the scope of this strategy.
B-1 Fixed factors that the Vendor Strategists prepare for management review when applying discretion include, but are not limited to:
- Inadequate/questionable response to previous NRC inspection findings in the response letter
- Susceptibility to counterfeiting or cybersecurity issues
- Reviews of targeted ITAAC*
- Current or past allegations
- Safety Conscious Work Environment (SCWE), safety culture issues, open chilling effect letters
- Confirmatory orders
- Major plant modifications, input and request from regional management
- Issues with 10 CFR Part 21
- International interest - Committee on Nuclear Regulatory Activities/Working Group on Supply Chain (CNRA/WGSUP)
- Industry supplier oversight activities and feedback
- Targeted ITAAC represent those that provide the highest value of inspection optimization of NRC resource and inspection planning, while providing reasonable assurance that a significant construction flaw will not go undetected.
VENDOR STRATEGISTS
The IQVB Branch Chief assigns Vendor Strategists to conduct on-going VIP Plan activities to assess vendors for proposed selection. The Vendor Strategists are responsible for management of the internal database (Appendix A of the VIP Plan) and the use of qualitative risk-informed research to assess and select vendors for potential vendor inspection. Before the vendor evaluation and selection process, the Vendor Strategists will gather information related to vendors from various sources which include but are not limited to: (1) representative leads from technical review groups (TRGs), Allegations Team, the Electric Power Research Institute (EPRI)
Procurement Engineering and Related Topics Symposium (PEARTS), the American Society of Mechanical Engineers (ASME), Nuclear Procurement Issues Corporation (NUPIC), the Nuclear Energy Institute (NEI) and others (See Figure 1 below, Organization Chart); (2) list of non-selected vendors from previous vendor planning meetings; and (3) findings review panel (FRP) recommendations made by vendor inspection team leads. As part of the research targeting process, the Vendor Strategists will review and evaluate qualitative factors that include, but are not limited to:
- Safety significance of the item/component/service
- Frequency of safety significance of problems identified (number of licensees affected/performance history of vendor)
- Results from past inspections
- Information received from TRGs, Licensee Event Reports and other NRC organizations
- Information received from NUPIC, PEARTS and/or other exterior organizations
- Vendor Quality Assurance (QA) Program Strength:
- a. History (vendor inspection findings, Notice of Violations (NOVs) and Notice of Nonconformances (NONs), corrective action response history, 10 CFR Part 21 notifications, NUPIC findings, Operational Experience (OpE) e-mails, industry issues, etc.)
B-2
- b. Production Dynamics Indicators (QA program changes, first time nuclear supplier, ASME Certificate Holder, foreign supplier, etc.)
- Product Impact:
- a. Level of Technology (Complexity of manufacturing process, reverse engineering, new products (e.g., first-of-a-kind), new manufacturing process (example - additive manufacturing), new/emerging technology)
- b. Component System Criticality (ranking of safety-related and ASME pressure retaining/safety-related and non-ASME components, risk-significance, etc.)
The Vendor Strategists will document the researched vendor information for each vendor assessed in a tabular format to support inspection significance and associated risk (high probability and high consequence).
Here is an example of a tabular target research vendor information:
NRC NUPIC Part 21 Industry Product Vendor Scope Inspection Audit & Reports Issues Impact Recommendation
& Findings Findings ASME QSC manufacturer of ferrous Low ABC and non-comple Company ferrous xity 123 Main welding None None None None Management Street, material Low Discretion Washington including Risk-DC 20012 utilization of signific unqualified ance source materials
Target Research Information:
- 1. ABC Company is an Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, supplier with an ASME Quality System Certificate supplying safety-related and ASME certified welding materials throughout the commercial nuclear industry
- 2. No prior NRC inspection, hence, no history of previous NONs or NOVs
- 3. Since no prior NRC inspection, no history of corrective action response history
- 4. No 10 CFR Part 21 issued by the vendor nor by a licensee
- 5. No NUPIC audits have been conducted at either of the above locations, since ABC Company is not listed on NUPICs database as an approved vendor
- 6. No industry issues
- 7. Low complexity of manufacturing process
- 8. Safety-related and ASME product that may be used for fabrication of pressure retaining components
- 9. Risk-significance of weld wires and electrodes is very low (safety-related low safety significant) 10.ABC Company may have been independently audited by utilities or by ASME Certificate Holders.
B-3 VENDOR SELECTION DETERMINATION
During the vendor inspection planning meeting, the Vendor Strategists will present to the IQVB Branch Chief the researched vendor information and provide justification as to why a particular vendor is selected and proposed for vendor inspection. The IQVB Branch Chief will use the Vendor Strategists information and apply management discretion to make an informed decision as to which vendors will be selected and assigned to the vendor inspection master schedule.
The non-selected vendors will be documented and maintained by the Vendor Strategists for potential future selection and recommendations.
Organization Chart
Branch Chief
Management Discretion
Vendor Strategist
NUPIC ASME TRG Others PEARTS Inspection Leads Leads Leads Leads Team Leads
NEI Leads Allegation Team Leads
FIGURE 1
CONTINUOUS IMPROVEMENT
The vendor inspection staff continually evaluates this strategy to assess whether changes need to be made to the decision factors. The vendor selection strategy will be reviewed on an annual basis prior to a vendor inspection planning meeting and updated in accordance with Appendix A, Strategy for Vendor Identification. This strategy was last updated in May 2020.
B-4 APPENDIX C STRATEGY FOR ENHANCED VENDOR OUTREACH AND COMMUNICATIONS PURPOSE
The purpose of this document is to establish and communicate the U.S. Nuclear Regulatory Commissions (NRCs) strategy to enhance outreach and communications with vendors supplying safety-related parts and services.
AUDIENCE
The target audience for this strategy includes licensees, license or design certification applicants, and vendors. Licensees and applicants are ultimately responsible for the safety of the facilities licensed by the NRC. As such, they must ensure that their vendors understand and implement applicable regulations. The vendor inspection staffs efforts to improve outreach and communications with these stakeholders serves to enhance the NRCs commitment to openness, efficiency, and clarity.
BACKGROUND
This strategy lists key areas of improvement that enhance current vendor inspection staff efforts in communication and outreach and identifies key trending data to be collected to measure the effectiveness of these enhancements. The preparation of a formal plan also provided the staff an opportunity for more strategic focus and coordination.
CURRENT COMMUNICATIONS AND OUTREACH TOOLS
The NRC currently uses the following communications and outreach tools:
- Public web Site: The vendor inspection public web site (http://www.nrc.gov/reactors/new-reactors/oversight/quality-assurance.html) provides vendors a venue to obtain useful information on many topics, including the following:
- key regulations, such as Appendix B, Quality Assurance Criteria for Nuclear Power Plants and Fuel Reprocessing Plants, to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of Production and Utilization Facilities, and 10 CFR Part 21, Reporting of Defects and Noncompliance
- inspection procedures
- inspection reports
- information on commercial-grade dedication
- presentations from past NRC workshops and town hall meetings
- NRC presentations at conferences attended by the NRC
- Workshops on Vendor Oversight: The NRC continues to host workshops on vendor oversight. The workshops continue to be successful and are excellent examples of NRC outreach. The workshops are widely attended and always generate significant dialogue with the vendor community about regulatory issues. Feedback through meeting comment forms is positive and stakeholders have requested additional workshops.
C-1
- Virtual Town Hall Meetings: The NRC will hold virtual town hall meetings as necessary to engage with external stakeholders to discuss any current issues of importance to the nuclear industry, and to provide guidance and clarification, as necessary. The goal of the virtual town hall meeting is to keep the external stakeholders informed on activities related to vendor inspection, quality assurance, etc. The number of virtual town hall meetings will depend on the number of significant topics or issues as well as the availability of NRC resources.
- Participation in industry conferences and meetings: The vendor inspection staff continues to participate in related industry conferences and meetings such as the following:
- American Society of Mechanical Engineers
- Nuclear Procurement Issues Corporation meetings
- NRCs Regulatory Information Conference
- Electric Power Research Institute Procurement Engineering and Related Topics Symposium meetings
- International Laboratory Accreditation Cooperation process activities
- Working Group on Supply Chain meetings, under the auspices of the Committee on Nuclear Regulatory Activities and the Nuclear Energy Agency
- Small Modular Reactors Regulators' Forum
- Nuclear Oversight Conference
KEY IMPROVEMENTS
The NRC implemented the following key improvements in outreach and communications:
- Improved the accessibility of the portions of the NRCs public web site that are relevant to vendor oversight.
- The NRC created a link within the quick link box on the pages for new reactors and operating reactors.
- Created a page on the public web site that categorizes nonconformances and violations from NRC vendor inspection reports.
- The NRC added a page with the 18 criteria from Appendix B to 10 CFR Part 50 and 10 CFR Part 21 so that vendors can select one of the criteria or 10 CFR Part 21 requirements and have all applicable inspection reports with nonconformances and violations in those areas listed.
- Created a frequently asked questions (FAQ) page on the public web site that includes questions received at vendor conferences and other NRC outreach meetings.
- The FAQ provides a quick source of information and serves as a knowledge management tool.
- Provide an annual electronic newsletter for vendors.
C-2
- The newsletter includes recent nonconformances and/or violations, potential rulemakings, upcoming conferences, operating experience and other useful information. Stakeholders can sign up for the newsletter through the NRCs web site.
- Continue biennial workshops on vendor oversight.
- The NRC will continue to host a workshop every 2 years as one key forum for communication and outreach with vendors. The vendor inspection staff will continue to use comment cards to solicit feedback and seek recommendations for improving future workshops.
CONTINUOUS IMPROVEMENT
The vendor inspection staff will track the improved efficiency and effectiveness of its outreach and communications activities by assessing the usefulness of the information shared. Feedback forms from vendor workshops will include specific questions to obtain feedback on the usefulness of information shared. The vendor inspection staff will use the feedback to enhance future workshops.
To evaluate stakeholder interest and participation, the vendor inspection staff will use the number of attendees at the conferences to measure the level of interest and success of the conference. The vendor inspection staff will use feedback forms from vendor workshops to gauge stakeholder interest.
The vendor inspection staff will revisit and revise this strategy as necessary, and at a minimum, it will be reviewed on an annual basis. This strategy is a living document, and the staff will update and modify it to suit the changing needs of the NRC.
STRATEGY QUESTIONS AND ANSWERS
Q. How can I access the NRCs web page for quality assurance and vendor oversight?
A. You can access the vendor web page on NRCs public web site by going to http://www.nrc.gov and then clicking on New Reactors under the Nuclear Reactors tab. Scroll down the page and click on How we Regulate New Reactors. On the right side of the page under Key Topics, click on the link to Quality Assurance for New Reactors.
Q. What kind of questions will I see on the FAQ web page?
A. The FAQ section on the vendor web page lists common questions and answers that presented at NRC conferences and workshops. It also lists questions and answers about relevant NRC regulations and inspections pertaining to vendors.
Q. How do vendors sign up for the newsletter?
A. To sign up to receive the vendor newsletter or to suggest future topics, please visit our Vendor Newsletter public web page.
Q. Will there be any additional burden on the industry?
A. No. The NRCs goal is to provide additional tools for the industry to be more cognizant of current NRC regulations. Vendors will be able to use the agencys public web site more efficiently to learn about current events and upcoming conferences and NRC workshops.
C-3 Q. Will the NRC consider other options for outreach and communications that may be proposed by the industry and the public?
A. The NRC constantly looks for ways to improve its communications with the public and will consider other options that will be beneficial.
Q. How does the NRC plan to improve tracking and trending?
A. The NRC plans to track and trend the questions received at its conferences and through its FAQs page to gauge the most common issues and concerns that vendors have. The vendor inspection staff will use this information to concentrate its efforts in identifying those issues that are hot topics. The vendor inspection staff plans to track and trend the vendors that attend NRC conferences and workshops. This will help the agency track industry interest in the topics being presented and inform its planning for future activities.
C-4 APPENDIX D
STRATEGY FOR COORDINATING VENDOR INSPECTIONS PURPOSE
The purpose of this Appendix is to document how the U.S. Nuclear Regulatory Commissions (NRCs) strategy for coordinating resources between the Office of Nuclear Reactor Regulation (NRR) and the Regional Offices to support NRCs Regional staff to support the (1) inspections, testing, analyses, and acceptance criteria (ITAAC) - related inspections of vendors manufacturing safety-related components and modular assemblies for new reactor construction, and (2) major digital instrumentation and controls (I&C) modifications approved under the Digital I&C Interim Staff Guidance (ISG)-06, Revision 2, Alternate Review Process (ARP). Application of the strategy will result in the effective and efficient coordination of the agencys inspection resources allocated in the ITAAC and major digital I&C modification oversight process that will enable the NRC to facilitate the ITAAC closure process and development activities for safety-related digital I&C systems, respectively.
BACKGROUND
The NRC staff conducts inspections to review the licensees construction activities as the licensee completes the applicable ITAACs. Guidance for these inspections is contained in Inspection Manual Chapter (IMC) 2503, Construction Inspection Program: Inspections of Inspections, Tests, Analyses and Acceptance Criteria (ITAAC) Related Work. The Region II staff is primarily responsible for implementing the ITAAC inspection program. For major safety-related digital I&C system modifications reviewed under the digital I&C ISG-06, ARP, the NRC staff conducts inspections to verify licensee oversight of vendor development activities for safety-related digital I&C systems in accordance with the activities described in the licensees vendor oversight plan (VOP). Guidance for these inspections is contained in IMC 2515, Light Water Reactor Inspection Program Operations Phase, Appendix C, Special and Infrequently Performed Inspections, which identifies Inspection Procedure (IP) 52003, Digital Instrumentation and Control Modification Inspection. Staff from the NRC Region responsible for the plant undergoing the major digital I&C system modification leads these VOP implementation inspections with support from NRC Headquarter technical staff.
Currently, IMC 2507 contains general guidance for conducting NRC inspections of vendors supplying safety-related components and modular assemblies. The strategy contained in this Appendix expands upon the guidance in IMC 2507 and should help ensure the most efficient and effective coordination of NRCs resources.
VENDOR INSPECTION COORDINATION STRATEGY
The following steps will be implemented to ensure that vendor inspections associated with (1) new reactor construction are properly coordinated with appropriate Region II staff and (2) major safety-related digital I&C system modifications are properly coordinated with appropriate Regional and Headquarter staff:
- a. The vendor inspection staff consistently updates its vendor inspection schedule based on the information collected through communications with:
D-1
- i. new reactor licensees and their engineering and procurement contractors; as well as the review of a list of recommended inspections of ITAAC-related safety-related components including modular assemblies fabricated at vendor sites provided by Region II staff; and ii. operating reactor licensees who have or intend to submit license amendment requests for safety-related digital I&C systems and their vendors responsible for developing these systems.
- b. When a vendors scope of supply includes ITAAC-related items, the vendor inspection staff will coordinate the inspection plan and request inspection support from Region II staff.
- c. When planning for a vendor inspection of a safety-related digital I&C system that has been or is in the process of being reviewed under the ISG-06, ARP, the vendor inspection staff will coordinate the inspection plan and request inspection support from NRR I&C staff, and as applicable, inform the appropriate regional staff to provide the opportunity to observe or participate on the vendor inspection.
- d. The NRR vendor inspection schedule is currently published on the vendor inspection SharePoint site.
- e. ITAAC-related inspections at facilities that are not controlled by the licensee shall be planned in coordination with the vendor inspection staff to ensure that the inspection is properly staffed and includes at least one qualified vendor inspector. These inspections will be licensee inspections, will be led by Region II, and will be conducted in accordance with IMC 2503. Enforcement actions will be taken against the specific licensee as applicable.
Sample-based ITAAC Inspection
- f. While the scope of the NRCs inspection program is comprehensive, 100% inspection is neither necessary nor efficient when evaluating a vendors performance. For this reason, NRC historically has relied on a sample-based inspection program.
For the AP1000 reactor design, between 10-15% of vendor-related ITAACs were verified at the vendor facilities. The vendor inspection and Region II staff interacted with licensees and their agent(s) as applicable to determine which type test or qualification ITAAC would be inspected based upon testing at a vendor location. The vendor inspection staff, in coordination with Region II staff, inspected a representative sample of these testing activities at a broad range of test vendor locations to verify programmatic quality controls associated with key test or qualification attributes were adequately implemented, the methodology used was sound, and that the same methodology was implemented for other ITAAC-related structures, systems, and components. The results of the vendor inspection, as described in the inspection report, supported closure verification of ITAAC.
- g. Inspection Consolidation of Safety-Related Digital I&C System Development Activities:
The inspections of safety-related digital I&C system development activities will be consolidated based on the development phase. The vendor inspection staff should coordinate with NRR I&C technical staff to identify the appropriate vendor inspection
D-2 timeline for the various phases of safety-related digital I&C development phases.
Consideration should be given to which vendor activities require direct observation versus those that are documentation reviews. In general, an inspection should be conducted for earlier phases of the system development lifecycle (e.g., requirements and design phase) and one conducted for vendor testing activities (i.e., factory acceptance tests). The results of the vendor inspection, as described in the inspection report will support regional inspection activities conducted using IP 52003.
D-2 APPENDIX E
VENDOR INSPECTION PROGRAM PERFORMANCE METRICS
VIP-O-1 Accomplish DROs (the U.S. Nuclear Regulatory Commissions Office of Nuclear Reactor Regulation, Division of Reactor Oversight) Established Number of Vendor Oversight Activities per Fiscal Year
Definition: Accomplish DROs established number of oversight activities per fiscal year to capture a reasonable perspective of industry performance. Oversight activities includes inspections and inspection support, licensing audits, and observations, performed domestically or internationally.
Criteria: Expect DRO to perform the required number of oversight activities established at the beginning of the fiscal year.
Goals: Effective, Open
VIP-O-2A Obtain Feedback from Vendors After the Vendor Inspection
Definition: The Branch Chief will solicit feedback from vendors inspected during the fiscal year on such aspects as the immediate inspection effort, vendor oversight, or NRC requirements and guidance.
Criteria: 1. Expect BC to solicit feedback from 100% of vendors inspected during the fiscal year,
- 2. Expect that feedback received is indicative of a stable or increasingly positive perception of the VIPP.
Goals: Effective, Open, Understandable
VIP-O-2B Notification of Inspection
Definition: Obtain data on the total number of inspections that were notified to the vendor within the timeliness goals stipulated in Section 10 of the Vendor Inspection Program (VIP) plan.
Criteria: Expect 90 percent of inspections to be announced to the vendor within the VIPs timeliness goals.
Goals: Effective, Open, Predictable
VIP-O-2C Inspection Plans are Timely
Definition: Obtain data on the total number of inspection plans issued within the timeliness goals stipulated in Section 10 of the VIP plan.
Criteria: Expect 90 percent of inspection plans to be issued within the VIPs timeliness goals.
E-3 Goals: Effective, Open, Predictable
VIP-O-2D Inspection Reports are Timely
Definition: Obtain data on the total number of inspection reports issued within the timeliness goals stipulated in Section 11 of the VIP plan and Inspection Manual Chapter 0617, Vendor and Quality Assurance Implementation Inspection Reports, dated February 2020.
Criteria: Expect 90 percent of inspection reports to be issued within the VIPs timeliness goals.
Goals: Effective, Open, Collaborative, Predictable
VIP-O-2E Acknowledgment Letters Are Timely
Definition: Obtain data on the total number of acknowledgment letters issued within the timeliness goals stipulated in Section 11 of the VIP plan.
Criteria: Expect 90 percent of acknowledgment letters to be issued within the VIPs timeliness goals.
Goals: Effective, Open, Predictable
VIP-O-2F Inspection Results Accepted by Stakeholders
Definition: Track the total number of NOVs and NONs contested by vendors.
Criteria: Retract less than 10 percent of NOVs and NONs because they are successfully contested by the stakeholders.
Goals: Effective, Objective, Open, Predictable
VIP-O-3 Allegation Support
Definition: Achieve the timely submittal of allegation response documents.
Criteria: Conduct all support within the Allegation program timeliness goals. Support includes, but is not limited to, providing input for Allegation Review Board (ARB) materials, attending ARBs, providing input to Requests for Information, participating in phone calls with the Concerned Individual(s), providing input for closure and response after closure letters, etc.
Goals: Effective, Objective, Risk-Informed
VIP-O-4A Assessment of Trainee Qualifications
Definition: The Branch Chief assess inspectors-in-training for progress in achieving qualifications at least three times per fiscal year.
F-1 Criteria:Expect 90 percent of trainees to qualify in 2 years from the start date.
Goals: Effective, Predictable, Understandable
VIP-O-4B Assessment of Inspector Proficiency
Definition: Maintain proficiency for all qualified inspectors.
Criteria: Maintain annual proficiency for all qualified inspectors in accordance with the guidance set forth by the VIP for refresher and continuing training.
Goals: Effective, Predictable, Understandable
F-1 APPENDIX F
MAJOR PLANT MODIFICATIONS CRITERIA
Quality Assurance Vendor Inspection Branch (IQVB) staff worked with staff from the Division of Reactor Oversight and Division of Engineering from the Office of Nuclear Reactor Regulation (NRR), and the Regions to develop criteria to determine when a proposed plant modification in operating reactors should be considered a major modification for enhanced supplier oversight.
The criteria encompass licensees plant modifications regardless of the outcome of the 10 CFR 50.59, Changes, Tests, and Experiments, analysis which include:
- 1. Modifications for the installation of replacement steam generators, reactor vessel heads, control rod drive mechanisms, etc.
- 2. Modifications for the implementation of non-measurement uncertainty recapture power uprates;
- 3. Modifications to install digital instrumentation and control systems, devices, or features in accordance with an NRC-approved topical report;
- 4. Modifications to install a component, device, or design feature pursuant to an NRC Order or compliance backfit;
- 5. Implementation of new fuel design campaigns at operating reactors; or
- 6. Modifications to install a component, device, or design feature to perform a function whose degradation or loss could result in a significant adverse effect on defense-in-depth, safety margin, or risk.
In accordance with Section 07.03, End-of-Cycle Reviews, of Inspection Manual Chapter 0305, Operating Reactor Assessment Program, dated May 4, 2023, the DRO observer should complete Exhibit 10, DRO End-of-Cycle Observation Form, during the meetings to gather lessons learned. The DRO End-of-Cycle Observation Form contains a section for Major Plant Modifications that states, If any major plant modifications are discussed (e.g., S/G replacement, digital I&C, etc.), notify IQVB as a potential vendor inspection sample.
F-1