ML20105A964: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 1: Line 1:
{{Adams
#REDIRECT [[3F0992-04, Requests Concurrence W/Deferral of Elements of Security Upgrade Project Affected by Proposed Changes to Security Requirements Until Changes Are Addressed & Any Revised Requirements Clearly Defined,Per Util ]]
| number = ML20105A964
| issue date = 09/11/1992
| title = Requests Concurrence W/Deferral of Elements of Security Upgrade Project Affected by Proposed Changes to Security Requirements Until Changes Are Addressed & Any Revised Requirements Clearly Defined,Per Util 920120 Ltr
| author name = Beard P
| author affiliation = FLORIDA POWER CORP.
| addressee name = Taylor J
| addressee affiliation = NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
| docket = 05000302
| license number =
| contact person =
| document report number = 3F0992-04, 3F992-4, NUDOCS 9209180073
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE
| page count = 2
}}
 
=Text=
{{#Wiki_filter:.
d Florida Power CORPORATION Crywal Rher Unk 3 Docket No. 4M2 September 11, 1992 3F0992-04 Mr. Jar,es M. Taylor Executive Director for Operations V. S. Nuclear Regulatory Commission Washington, DC 20555
 
==Subject:==
Security Upgrade
 
==References:==
A. FPC to NRC letter, 3F0192-02, dated January 20, 1992 B. NUMARC letter to Brian Grimes, dated June 24, 1992 C. SECY 92-272
 
==Dear Mr. Taylor:==
 
Florida Power Corporation (FPC) has been following the activities of the NRC and NUMARC related to nuclear security. FPC provided the plan and schedule for a major upgrade to our security system in Reference A. The total upgrade program is currently forecast to cost over $14 million. FPC has concluded that elements of this upgrade should be deferred until pending proposed changes in the requirements are dispositioned by the NRC.
NUMARC, in Reference B, documented four areas.where reevaluation of protective measures appears warranted. These include vital area controls, containment access control, vehicle escort, and guard search requirements.      FPC considers this reevaluation to be appropriate and would suggest that even more changes may be warranted as well. It is our understanding that the NRC Staff has forwarded their recommendations on these and related subjects to the Commission in Reference C.
170045                                                                          $
pma mae                                                                                7
 
of
    . Nuclear Regulatory Commission 3F0992-04 Page 2 Changes to current requirements, particularly those for vital areas, would have a significant effect on how we implement our security upgrade project with
* potential to save up to $8 million in revised scope.                        Therefore, FPC requests your concurrence with deferral of the elements of the security upgrade project affected by proposed changes to security requirements until these changes are addressed and any revised requirements are clearly defined.
FPC will closely follow the resolution of the proposed changes to security requiresents and will continue to redefine our project accordingly.                                              Also, we wil's continue to keep the NRC promptly advised of the status of the project.
Sincerely, l
P. M. Beard, Jr.
Senior Vice President Nuclear Operations PMB/RCW. mig cc: Mr. S. D. Ebneter Dr. T. E. Murley