ML21110A095: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot insert) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| Line 1: | Line 1: | ||
{{Adams | |||
| number = ML21110A095 | |||
| issue date = 04/19/2021 | |||
| title = GE Hitachi Nuclear Energy - Requesting to Extend Request for Additional Information Response Due Date to July 28, 2021 | |||
| author name = Feyrer M | |||
| author affiliation = GE Hitachi Nuclear Energy | |||
| addressee name = | |||
| addressee affiliation = NRC/Document Control Desk, NRC/NRR | |||
| docket = 05000018 | |||
| license number = DPR-001 | |||
| contact person = | |||
| case reference number = M210053 | |||
| document type = Letter | |||
| page count = 1 | |||
| project = | |||
| stage = Request | |||
}} | |||
=Text= | |||
{{#Wiki_filter:RR3 x;ny | |||
) GEHitachi Nuclear Energy MattJ. Feyrer Site Manager, Vallecitos Nuclear Center 6705Vallecitos Rd M210053 Sunol, CA94586 USA April 19,2021 T 9259186018 U.S. Nuclear Matt.feyrer@ge.com Regulatory Commission Attn: Document Control Desk Washington, D.C.20555-001 | |||
==Subject:== | |||
GEHRequest to Extend Request for Additional Information (RAI) Response DueDate to July 28,2021 | |||
==References:== | |||
1)NRCLicenseDPR-1, Docket 50-18 2)Letter GEHVallecitos Nuclear Center (VNC) Request for Alternate Decommissioning Schedules for DPR-1, DR-10, and TR-1Licenses, 7/10/2015 3)Letter, J.D. Parrot (NRC) to M.F. Feyrer, GEHitachi Request for Alternate Decommissioning Schedule for VBWR atVNC Request - | |||
for Additional Information, (EPID L-2017-LLA-0052), 7/15/2020 4)Letter, M.F. Feyrer Requestingto Extend Requestfor Additional information Due Date toApril 28,2021, 8/14/2020 5)MSTEAMS meeting between GEHand NRC presenting supplemental information regarding thestatus ofVBWRsamplingand analysis, 3/18/2021 6)Letter, M.F. Feyrer Supplemental Information for Request for Additional information Response dueApril 28,2021, 3/22/2021 GEHitachi Nuclear Energy, LLC(GEH) isrequesting toextend theresponse duedate for theNRC's request foradditional information (RAI) related tothealternate decommissioning schedule for theVBWR. | |||
Theinitial request for analternate decommissioning schedule wasmade7/10/2015 (Ref 2)andproposed a VBWRdecommissioning date ofApril 2041tofacilitate a single holistic decommissioning oftheentire VNCsite. | |||
inletter (Ref3)dated 7/15/2020, theNRCrequested GEHprovide additional information related tothe structural integrity ofthe VBWRtoenable anindependent assessment todetermine ifthe requested exemption to10CFR50.82(a)(3) would present anundue risk topublic health andsafetyunder @ | |||
50.12(a). Upon reviewing the n ine R Alsi n that letter,GEH requested (Ref and | |||
: 4) wasauthorized until 4/28/2021 torespond toallowtime for extensive concrete structure coresampling, analysis, and evaluation. GEHupdated theNRConthe status ofthat effort andprovided a detailed plan on3/18/2021 (Ref 4 & 5).Sampling wascompleted on4/8/2021 A response duedate of7/28/2021 isbeing requested inthis communication toallow time toanalyze andevaluate the sample results andtocompose afinal response tothe RAls. | |||
If youhaveanyquestions regarding thismatter, please contact meat(925) 918-6018. | |||
Sincerely, , / | |||
g p4- -- ~- | |||
/M V | |||
(/ | |||
Matt Feyrer,Site Manager Vallecitos Nuclear Center cc:NRCRegion IVAdministrator S.Anderson, NRCRIV J.D. Parrott,NMSS/DUWP/RDB MJF21-006}} | |||
Revision as of 00:25, 3 March 2022
| ML21110A095 | |
| Person / Time | |
|---|---|
| Site: | Vallecitos Nuclear Center |
| Issue date: | 04/19/2021 |
| From: | Feyrer M GE Hitachi Nuclear Energy |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| M210053 | |
| Download: ML21110A095 (1) | |
Text
RR3 x;ny
) GEHitachi Nuclear Energy MattJ. Feyrer Site Manager, Vallecitos Nuclear Center 6705Vallecitos Rd M210053 Sunol, CA94586 USA April 19,2021 T 9259186018 U.S. Nuclear Matt.feyrer@ge.com Regulatory Commission Attn: Document Control Desk Washington, D.C.20555-001
Subject:
GEHRequest to Extend Request for Additional Information (RAI) Response DueDate to July 28,2021
References:
1)NRCLicenseDPR-1, Docket 50-18 2)Letter GEHVallecitos Nuclear Center (VNC) Request for Alternate Decommissioning Schedules for DPR-1, DR-10, and TR-1Licenses, 7/10/2015 3)Letter, J.D. Parrot (NRC) to M.F. Feyrer, GEHitachi Request for Alternate Decommissioning Schedule for VBWR atVNC Request -
for Additional Information, (EPID L-2017-LLA-0052), 7/15/2020 4)Letter, M.F. Feyrer Requestingto Extend Requestfor Additional information Due Date toApril 28,2021, 8/14/2020 5)MSTEAMS meeting between GEHand NRC presenting supplemental information regarding thestatus ofVBWRsamplingand analysis, 3/18/2021 6)Letter, M.F. Feyrer Supplemental Information for Request for Additional information Response dueApril 28,2021, 3/22/2021 GEHitachi Nuclear Energy, LLC(GEH) isrequesting toextend theresponse duedate for theNRC's request foradditional information (RAI) related tothealternate decommissioning schedule for theVBWR.
Theinitial request for analternate decommissioning schedule wasmade7/10/2015 (Ref 2)andproposed a VBWRdecommissioning date ofApril 2041tofacilitate a single holistic decommissioning oftheentire VNCsite.
inletter (Ref3)dated 7/15/2020, theNRCrequested GEHprovide additional information related tothe structural integrity ofthe VBWRtoenable anindependent assessment todetermine ifthe requested exemption to10CFR50.82(a)(3) would present anundue risk topublic health andsafetyunder @
50.12(a). Upon reviewing the n ine R Alsi n that letter,GEH requested (Ref and
- 4) wasauthorized until 4/28/2021 torespond toallowtime for extensive concrete structure coresampling, analysis, and evaluation. GEHupdated theNRConthe status ofthat effort andprovided a detailed plan on3/18/2021 (Ref 4 & 5).Sampling wascompleted on4/8/2021 A response duedate of7/28/2021 isbeing requested inthis communication toallow time toanalyze andevaluate the sample results andtocompose afinal response tothe RAls.
If youhaveanyquestions regarding thismatter, please contact meat(925) 918-6018.
Sincerely, , /
g p4- -- ~-
/M V
(/
Matt Feyrer,Site Manager Vallecitos Nuclear Center cc:NRCRegion IVAdministrator S.Anderson, NRCRIV J.D. Parrott,NMSS/DUWP/RDB MJF21-006