A05085, Notifies of Change in 850816 Commitment to Provide Improved Plant Operations Review Committee Review of Plant Design Change Records in Response to Insp 50-213/85-15.Commitment Now Considered W/O Merit & Therefore Eliminated: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
Line 1: Line 1:
{{Adams
#REDIRECT [[A05085, Suppls 860106 Response to NRC Re Violations Noted in Insp Rept 50-213/85-15.Corrective Actions:Nonemergency Plant Design Change Requests Will Be Distributed 7 Days Prior to Committee Meetings]]
| number = ML20235J412
| issue date = 09/18/1987
| title = Notifies of Change in 850816 Commitment to Provide Improved Plant Operations Review Committee Review of Plant Design Change Records in Response to Insp 50-213/85-15.Commitment Now Considered W/O Merit & Therefore Eliminated
| author name = Mroczka E, Sears C
| author affiliation = CONNECTICUT YANKEE ATOMIC POWER CO.
| addressee name = Wenzinger E
| addressee affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
| docket = 05000213
| license number =
| contact person =
| document report number = A05085, A5085, NUDOCS 8710010432
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
| page count = 2
}}
 
=Text=
{{#Wiki_filter:, - 3.
W s
CONNECTICUT YANKEE ATO MIC POWER COMPANY B E R L I N, CONNECTICUT P.o. Box 270 e HARTFORD CONNECTICUT 06141-0270 TELEPHONE September 18,1987 Docket No. 50-213 A05085               g ,
b
                                                                                                                                    =c Mr. Edward C. Wenzinger, Chief                                                                      U $
Project Branch No. 5                                                                                        :
Division of Reactor Projects Region 1
                                                                                                                              .p U.S. Nuclear Regulatory Commission                                                                  c-          1 631 Park Avenue                                                                                      W King of Prussia, PA 19406
 
==References:==
(i)                3. F. Opeka letter to E. C. Wenzinger, " Response to I&E Inspection No. 50-213/85-15," dated August 16,1985.
(2)            E. C. Wenzinger      letter    to      3. F. Opeka,          "Special Inspection 50-213/8 5-15 (June 14-26, 1985)," dated July 19, 1985.
Gentlemen:
Haddam Neck Plant Commitment in Response to IE Inspection No. 50-213/85-15 The purpose of this letter is to inform you that the Connecticut Yankee Atomic Power Company (CYAPCO) has decided to change a commitment made in response (Reference (1)) to IE Inspection No. 50-213/85-15 (Reference (2)).
The specified commitment involved convening separate Piant Operation Review Committee (PORC) meetings for Plant Design Change Records (PDCRs).. The intent of the commitment was to provide improved PORC review of PDCRs by eliminating other items from the agenda.
Experience gained over almost two years of fulfilling this commitment has revealed that it is not as effective as other measures which have been taken (such as advanced distribution of material) to improve the quality of PORC review. It has, however, added an unnecessary administrative burden by artificially increasing the number of PORC meetings with the attendant increase in meeting minutes and other paperwork. Based on this experience, CYAPCO has determined that this commitment has lost its merit and has therefore been eliminated.
8710010432 870918 gDR ADOCK 0 % 2 u                                                                                                                            u i
CT      \
 
x
      ...        e l  ! .# '
l l
l
                      . Mr. Edward C. Wenzinger
                      . A05085/Page 2 September 18, 1937 If you have any questions or comments, please let us know.
Very truly yours, CONNECTICUT YANKEE ATOMIC POWER COMPANY t
5 ib ,    Dat    t l
E. 3. Mroczl:a l~                                                        Senior Vice President                                .]i l                                                                                                                !
O
                                                              'd By: C. F. Sears                                        i Vice President l
cc:    Document Control Desk                                                              l W. T. Russell, Region I Administrator                                          .]
j F. M. Akstulewicz, NRC Project Manager, Haddam Neck Plant                          1 l                            3. T. Shadlosky, Resident Inspector, Haddam Neck Plant l