ENS 54460: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
(5 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
{{ENS notification | {{ENS notification | ||
| event number = 54460 | | event number = 54460 | ||
| facility = | | facility = Comanche Peak | ||
| Organization = | | Organization = | ||
| license number = | | license number = | ||
| region = | | region = 4 | ||
| state = | | state = Texas | ||
| city = | | city = | ||
| unit = | | unit = 2 | ||
| utype = | | utype = W-4-LP, W-4-LP | ||
| cfr = | | cfr = 10 CFR 50.72(b)(2)(iv)(B) | ||
| emergency class = | | emergency class = Non Emergency | ||
| notification date = | | notification date = 01/01/2020 16:57 | ||
| notification by = | | notification by = Chris Metz | ||
| NRC officer = | | NRC officer = Brian Lin | ||
| event date = | | event date = 01/01/2020 12:53 CST | ||
| last update date = | | last update date = 01/01/2020 | ||
| title = | | title = Manual Reactor Trip and Specified System Actuation | ||
| event text = | | event text = At 1253 [CST] Unit 2 Reactor was manually tripped due to a trip of both Main Feed Pumps. During an evolution to secure Circulating Water Pump 2-01, vacuum was reduced in the auxiliary condensers for both Main Feed Pumps causing both Main Feed Pumps to trip. Both Motor Driven and the Turbine Driven Auxiliary Feedwater Pumps started due to steam generator Lo-Lo levels. | ||
Unit 2 is being maintained in Hot Standby (Mode 3) in accordance with Integrated Plant Operating Procedure IPO-0078. The Emergency Response Guideline Network has been exited. Decay heat is being rejected to the Main Condenser via the Steam Dump Valves. | |||
The licensee notified the NRC Resident Inspector. | |||
| URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2020/20200102en.html#en54460 | | URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2020/20200102en.html#en54460 | ||
}} | }} | ||
{{ENS-Nav}}[[Category:Power Reactor]] | {{ENS-Nav}}[[Category:Power Reactor]] |
Latest revision as of 13:01, 15 January 2021
Where | |
---|---|
Comanche Peak Texas (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation | |
Time - Person (Reporting Time:+-1.93 h-0.0804 days <br />-0.0115 weeks <br />-0.00264 months <br />) | |
Opened: | Chris Metz 16:57 Jan 1, 2020 |
NRC Officer: | Brian Lin |
Last Updated: | Jan 1, 2020 |
54460 - NRC Website
| |