ML20133K752: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
Line 1: Line 1:
{{Adams
#REDIRECT [[IR 05000445/1984034]]
| number = ML20133K752
| issue date = 10/16/1985
| title = Ack Receipt of 850129 Ltr Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-445/84-34 & 50-446/84-13.Addl Info Required for Item B.1 Re Falsification of Records & Corrective Measures Taken
| author name = Denise R
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
| addressee name = Counsil W
| addressee affiliation = TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
| docket = 05000445, 05000446
| license number =
| contact person =
| document report number = NUDOCS 8510220286
| package number = ML20133K755
| document type = CORRESPONDENCE-LETTERS, NRC TO UTILITY, OUTGOING CORRESPONDENCE
| page count = 2
}}
See also: [[see also::IR 05000445/1984034]]
 
=Text=
{{#Wiki_filter:'
.
    In Reply Refer To:
    Dockets: 50-445/84-34
              50-446/84-13                00T 161985
    Texas Utilities Generating Company-
    ATTN: Mr. W. G. Counsil
            Executive Vice President
                                                                                        I
    400 North Olive, L.B. 81
    Dallas, Texas 75201                                                                  !
    Gentlemen:
    We have reviewed your letter of January 29, 1985, in response to our letter and
    Notice of Violation dated December 31, 1984. Your reply adequately addressed        l
    the specific concerns raised regarding-Item A. We have reviewed the procedure
    changes delineated in your response and the requirements for sway strut and
    snubber installation and find them acceptable. The generic aspects of the            '
    findings were not adequately addressed in your response to our Notice of
    Violation Item A, as required by 10 CFR 2.201; however, we understand that the
    generic' aspects of sway strut and snubber installation will be addressed by the
    Comanche Peak Response Team (CPRT) Program Plan.
    With respect to Item B, we find that you have taken adequate corrective action
    to assure reporting items to the NRC as required by 10 CFR 50.55(e). We will
    review the implementation of your corrective actions for Item B during a-
    future inspection to determine that full compliance has been achieved. and will
    be maintained.
    However, with regard to Item B.-1, specifically, additional information is
    required because at the time the Notice of Violation was written, the associated    1
    nonconformance report (NCR) had been closed without reference made to action
    being taken to determine how the apparent falsification of records had occurred      -
    and to determine if this apparent falsification was an isolated occurrence.
    Your additional response should discuss the following matters:
          Basis' for the statement that the apparent falsification was determined to
          be an isolated instance
                                                                                        l
          basis for the statement that the inspection had, in fact, been performed      ;
          by another inspector;                                                          [
                                                                                        i
          basis for the statement that corrective measures were taken to prevent        j
          recurrence; and                                                                j
                                                                                        !
    RPB2/                RPB^          DRS
    DMHu rnc      :gb      DRHu er        RPDe i              VNoonan I
    1/t,/85              4/th85          10Ab /85            NRRg , 3p/a
                                                              0 / 4 /85    fi''/" h . M
                                                                                          l
                                                                                          :
                                                                                        1
                      8510220286 851016
                      PDR  ADOCK 05000445
                      G                PDR                                        8
 
,
    '
  .
      Texas Utilities Generating Station        2
            measures completed or planned to ensure this apparent falsification was
            not an attempt to deliberately mislead.
      Please provide the additional information requested regarding the apparent
      falsification of records within 30 days of the date of this letter.
      Further, with regard to your response to the Notice of Violation, Item B.2,
      the fact the design oversight (revision to instrument ranges and setpoints)
      would likely be detected during subsequent testing or operations, does not
      alter the reporting requirements of 10 CFR 50.55(e).
                                                Sincerely,
                                                      .gs-grd signed Br.
                                                        D. R. KUNIEII'*
                                                R. P. Denise, Director
                                                Division of Reactor Safety
                                                  ar.d Projects
      cc:
      Texas Utilities Electric Company
      ATTN:  J. W. Beck, Manage ,
                Licensing
      Skyway Tower
      400 Nort? Olive Street
      Lock Box 81
      Dallas, Texas      75201
      Texas Radiation Control Program Director
      bcc to DMB (IE01)
      bec distrib. by RIV:
      *RPB                                * MIS System
      *RRI-0PS                            *RSTS Operator
      *RRI-CONST                          *R&SPB
      *T. F. Westerman, CPTG                R. Denise, D/DRSP
      V. Noonan, NRR                        R. Martin, RA
      S. Treby, ELD                        Juanita Ellis, Pres.- CASE
      *RIV File                              Renea Hicks, A/ Atty General, EP Div.-TX
      *D. Weiss, LFMB (AR-2015)
      RSB
}}

Revision as of 22:14, 25 September 2020