05000423/LER-1997-017, Forwards LER 97-017-00 Which Documents Events That Occurred on 970206 & 13.Commitments,encl: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
Line 1: Line 1:
{{Adams
#REDIRECT [[05000423/LER-1997-017, Forwards LER 97-017-01,documenting an Event That Occurred at Millstone Nuclear Power Station,Unit 3 on 970206.Commitments Made within Ltr,Encl]]
| number = ML20136F376
| issue date = 03/07/1997
| title = Forwards LER 97-017-00 Which Documents Events That Occurred on 970206 & 13.Commitments,encl
| author name = Hicks G
| author affiliation = NORTHEAST NUCLEAR ENERGY CO.
| addressee name =
| addressee affiliation = NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
| docket = 05000423
| license number =
| contact person =
| document report number = B16264, NUDOCS 9703140081
| package number = ML20136F381
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE
| page count = 4
}}
{{LER
| Title = Forwards LER 97-017-00 Which Documents Events That Occurred on 970206 & 13.Commitments,encl
| Plant =
| Reporting criterion =
| Power level =
| Mode =
| Docket = 05000423
| LER year = 2097
| LER number = 17
| LER revision =
| Event date =
| Report date =
| ENS =
| abstract =
}}
 
=text=
{{#Wiki_filter:. _ . . . _            .    . . _      _.        _                    ..      . _ _ _ _            . _ _ _ _            ___ ..
  ,            ' D Northeast                                                                Rogw Fmy Rd. (Rane M Warnfwd. CN385
:                      )T Nuclear Energy                                                      .uat. one N,i,ar eown station Northea.: Nuclear Energy Cornpany i'            '
P.O. Box 128 Waterford, CF 06385-0128 (860) 447-1791 Fax (860) 444-4277 The Northeast Utilities Systern i
l 1
March 7,1997                  I l
Docket No. 50-423 B16264              l l
Re:10CFR 50.73(a)(2)(i)(B)
U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 4
Millstone Nuclear Power Station Unit 3                                                  l Licensee Event Report 97-017-00                                                        l Submitted Pursuant to 10CFR 50.73(a)(2)(i)
This letter forwards Licensee Event Report 97-017-00, documenting conditions that were determined at Millstone Unit No. 3 on February 6 and 13,1997. This LER is submitted pursuant to 10CFR 50.73(a)(2)(i)(B). NNECO's commitments in response to this event are contained within Attachment 1 to this letter.
Should you. have any questions regarding this submittal, please contact Mr.
James M. Peschel at (860) 437-5840.
Very truly yours, 7
W NORTHEAST NUCLEAR ENERGY                                      \
COMPANY                                                        1
                                                                                                                                \
                                                                                                                          \
                                                                                                                              \
                                                              \
bW Unit Director, Millstone Unit No. 3 9703140001 970307 PDR        ADOCK 05000423, 8                            PDR    .
osam.s uv. nas                                        .        .          .
 
U.S. Nuclear Regulatory Commission
  ;                                B16264/Page 2 i                                                                                                                                  ,
                        ~
;                                                                                                                                  \
 
==Attachment:==
: 1)        NNECO's commitments in response to LER 97-017-00 1
: 2)        LER 97-017-00 cc:  H. J. Miller, Region i Administrator A. C. Cerne, Senior Resident inspector, Millstone Unit No. 3 J. W. Andersen, NRC Project Manager, Millstone Unit No. 3                                  l W. D. Travers, Dr., Director, Special Projects
)
i 4
i i
1 l
i.
j i
1 i
4
-}
e 9
                                                            ,v-
 
Docket No. 50-423 B16264 l
I Attachment 1 Millt. tone Nuclear Power Station, Unit No. 3 NNECO's Commitments in Response To (LER 97-017-00) 4 e
i 4
March 1997 4
4 4
'l
 
Enclosure List of Regulatory Commitments The following table identifies those actions committed to by NNECO in this document. Any other actions discussed in the submittal represent intended or planned actions by NNECO. They are described to the NRC for the NRC's information and are not regulatory commitments. Please notify the Manager -
Nuclear Licensing at the Millstone Nuclear Power Station Unit No. 3 of any questions regarding this document or any associated regulatory commitments.
Number                          Commitment                          Due B16264-01      The requirements of Generic Letter 96-01 will    Prior to entry into be reviewed in their entirety. Any reportable          Mode 4 conditions discovered during this review will be reported in a supplement to this LER.
B16264-02      The response to Generic Letter 96-01 will be    Prior to entry into updated.                                              Mode 4 B16264-03      The procedures used to test the response of      Prior to entry into valves to a low low steam generator level              Mode 4 signal will be revised.
B16264-04      The response of valves to a low low steam        Prior to entry into generator level signal will be tested.                Mode 4 B16264-05      The procedures used to test under voltage and    Prior to entry into degraded voltage relaying will be revised to          Mode 4 incorporate testing of the under voltage / degraded voltage tripping contacts for the tie breakers and Reserve Station Services Transformer (RSST) feeder breakers.
B16264-06      The under voltage / degraded voltage tripping    Prior to entry into contacts for the tie breakers and RSST feeder          Mode 4 breakers will be tested.
}}
 