ML003725391: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
(One intermediate revision by the same user not shown) | |||
Line 3: | Line 3: | ||
| issue date = 06/16/2000 | | issue date = 06/16/2000 | ||
| title = June 13-14, 2000 Meeting Summary Letter to Mr. Davis with Enclosures 1 and 2, Attachments Scanned | | title = June 13-14, 2000 Meeting Summary Letter to Mr. Davis with Enclosures 1 and 2, Attachments Scanned | ||
| author name = Beckner W | | author name = Beckner W | ||
| author affiliation = NRC/NRR/DRIP/RTSB | | author affiliation = NRC/NRR/DRIP/RTSB | ||
| addressee name = Davis J | | addressee name = Davis J | ||
| addressee affiliation = Nuclear Energy Institute (NEI) | | addressee affiliation = Nuclear Energy Institute (NEI) | ||
| docket = | | docket = | ||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:June 16, 2000 Mr. James Davis, Director Operations Department Nuclear Energy Institute 1776 I Street, N. W. | ||
Suite 400 Washington, DC 20006-3708 | |||
== | ==Dear Mr. Davis:== | ||
Enclosed is a summary of our joint NRC/Technical Specifications Task Force (TSTF) | |||
Owners Group meeting at the Nuclear Regulatory Commission in Rockville, Maryland on June 13 and 14, 2000. Should the TSTF have any comments or questions, please do not hesitate to contact me on 301-415-1161 or by e-mail at wdb@nrc.gov. | |||
Sincerely, | |||
/RA/ | |||
William D. Beckner, Chief Technical Specifications Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 689 | |||
==Enclosures:== | ==Enclosures:== | ||
1. | : 1. Attendee List | ||
: 2. Summary of Meeting cc: Those on enclosed Attendees List | |||
Nuclear Energy Institute Project No. 689 cc: Mr. Ralph Beedle Ms. Lynnette Hendricks, Director Senior Vice President Plant Support and Chief Nuclear Officer Nuclear Energy Institute Nuclear Energy Institute Suite 400 Suite 400 1776 I Street, NW 1776 I Street, NW Washington, DC 20006-3708 Washington, DC 20006-3708 Mr. Alex Marion, Director Mr. Charles B. Brinkman, Director Programs Washington Operations Nuclear Energy Institute ABB-Combustion Engineering, Inc. | |||
Suite 400 12300 Twinbrook Parkway, Suite 330 1776 I Street, NW Rockville, Maryland 20852 Washington, DC 20006-3708 Mr. David Modeen, Director Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Anthony Pietrangelo, Director Licensing Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Hank Sepp, Manager Regulatory and Licensing Engineering Westinghouse Electric Corporation P.O. Box 355 Pittsburgh, Pennsylvania 15230 Mr. Jim Davis, Director Operations Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 | |||
June 16, 2000 Mr. James Davis, Director Operations Department Nuclear Energy Institute 1776 I Street, N. W. | |||
Suite 400 Washington, DC 20006-3708 | |||
== | ==Dear Mr. Davis:== | ||
Enclosed is a summary of our joint NRC/Technical Specifications Task Force (TSTF) | |||
Owners Group meeting at the Nuclear Regulatory Commission in Rockville, Maryland on June 13 and 14, 2000. Should the TSTF have any comments or questions, please do not hesitate to contact me on 301-415-1161 or by e-mail at wdb@nrc.gov. | |||
Sincerely, | |||
/RA/ | |||
William D. Beckner, Chief Technical Specifications Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 689 | |||
==Enclosures:== | ==Enclosures:== | ||
1. | : 1. Attendee List | ||
: 2. Summary of Meeting cc: Those on enclosed Attendees List DISTRIBUTION: | |||
DBMatthews/SNewberry RTSB Members PUBLIC RTSB R/F WDBeckner JLBirmingham RLDennig ADAMS DOCUMENT NAME: G:\RTSB\TSTF INFO\Owners Group Correspondence\MTGSUM6-13-14.wpd OFFICE RTSB/DRIP RTSB/DRIP RGEB/DRIP SC:RTSB/DRIP C:RTSB/DRIP:NRR NAME TRTjaderTRT LAHillLAH JLBirminghamJLB RLDennigRLD WDBecknerWDB DATE 06/16/00 06/16/00 06/16/00 06/16/00 06/16/00 OFFICIAL RECORD COPY | |||
: | |||
TSB- | NRC/TSTF OWNER'S GROUP MEETING June 13 & 14, 2000 ATTENDEES LIST NAME ORGANIZATION B. L. Woods CEOG/San Onofre J. Arbuckle BWROG/WNP2 H. Pontious BWROG/COMED B. Mann EXCEL D. Hoffman EXCEL N. Clarkson BWOG/DUKE S. Wideman WOG/WCNOC W. Beckner NRC/NRR/RTSB R. Dennig NRC/NRR/RTSB J. Birmingham* NRC/NRR T. R. Tjader NRC/NRR/RTSB N. Gilles** NRC/NRR/RTSB C. Schulten NRC/NRR/RTSB Leslie Hill NRC/NRR/RTSB T. Liu* NRC/NRR/RTSB J. Foster* NRC/NRR/RTSB W. Reckley* NRR/PMAS J. Weil* McGraw Hill | ||
*Attended June 13 only | |||
**Attended June 14 only ENCLOSURE 1 | |||
Technical Specification Task Force Meeting Summary June 13 & 14, 2000 Staff met with the Nuclear Energy Institute Technical Specification Task Force (NEI TSTF) on June 13 & 14, 2000. | |||
The TSTF and staff discussed the status of pending high priority TSTFs as described below. was the pre-meeting status provided by the TSTF and Attachment 2 was the pre-meeting status provided by the staff. | |||
016 R.3: The TSB has the necessary information to complete its review; approval is anticipated. | |||
207 R.5: Approved. | |||
231 R.1: Approved; RPS Instrumentation Bases (B3.3.1.1) correction. | |||
306 R.1: The TSTF will submit Revision 2 to revise the Bases. | |||
330 R.0: The TSTF will submit Revision 1 which will be a solution that is based upon the temperature averaging concept approved for Brunswick. | |||
332 R.0: The TSTF will submit Revision 1 which will implement the topical, Supplement 1 of NEDO-32291 of October 1999, and remove the non-generic cascading issues. | |||
334 R.1: The TSTF will submit Revision 2 to include a reviewers note based upon a related topical, once it is approved . | |||
342 R.1: Approved. | |||
343 R.0: Staff comments have been provided to the TSTF and the TSTF will submit Revision 1 for staff review in the near future (low priority). | |||
355 R.0: The TSTF will submit Revision 1 to make a correction to the RPS Instrumentation Bases (B3.3.3.1). | |||
360 R.0: Staff is reviewing the latest TSTF justifications/submittals. | |||
361 R.0: Approved. | |||
364 R.0: Approved. | |||
365 R.0 (TSB-22): Approved. | |||
Page 1 ENCLOSURE 2 | |||
Other Topics Discussed: | |||
The TSTF OG will propose a program to include in the Technical Specifications to address delayed LCO entry for taking snubbers out of service for routine maintenance. Attachment 3 was provided to the OG to help clarify issues in order to develop the program. [Though not discussed, in parallel to the industry effort TSB will work on a section 3.0 specification to allow for a delay time entry into the Conditions of an LCO.] The intent is to avoid unnecessary entry into TS required actions for supported systems when removing snubbers from service for surveillance testing. | |||
The Staff presented some questions (Attachment 4) regarding BWR plant refueling outage operations, with the intent to resolve concerns about TSTF-225 and BWR STS 3.10.6. The OG will present the questions to industry experts and provide answers to TSB; TSB will review and discuss the answers with SRXB, clarify the concerns, and present the concerns with proposed solutions to the OG; and, if necessary have an NEI-NRR meeting to resolve issues. The Staff will prepare an SE on Perrys proposed adoption of TSTF-225 from the results of this effort. | |||
The production status of Revision 2 to the STS NUREGs was discussed. The plan is to resolve BWR refueling issues and TSTF-360 issues by the end of July 2000, post the final draft STS Rev 2 for industry and public comment by mid August 2000, and receive and incorporate comments by the end of September 2000. Then publish STS Rev 2 in the early Fall of 2000. | |||
TSB-NEI proofing panels will be convened as needed to resolve editorial issues. A discussion on proposed format changes to the STS Rev 2 Table of Contents (TOC) was conducted briefly, with the OG unanimously agreeing that TOC should remain unchanged (Attachment 5, a strawman for the suggested changes was passed out). | |||
The staff and TSTF members discussed the potential of using the consolidated line item improvement process (CLIIP) for the removal of post accident sampling systems (PASS) from the TS of Westinghouse and Combustion Engineering plants. The owners groups for those plants have received safety evaluations for topical reports that justified removing PASS. The owners groups representatives agreed to pursue a TSTF traveler for the removal of PASS. | |||
Following receipt of the proposed TSTF, the staff believes it is in a position (based on the topical reviews) to quickly publish the notice for comment as called for in the CLIIP. The BWR and B&W Owners Groups would likely submit TSTFs and the CLIIP would be used for the remaining plants using a separate activity. Bill Reckley of the staff provided a possible example of an individual licensee's application using the CLIIP for PASS elimination (Attachment 6). | |||
The status of the Risk Informed Technical Specifications (RITS) effort was discussed. The OG has submitted proposal for Initiatives 1 (preferred end states), 2 (revise delay time for entering required actions upon missing a surveillance), and 3 (modify mode restraint logic); Initiative 1 is currently under review by the staff. Revisions to TSTF-358 and TSTF-359 can be expected from the OG in early July. A proposal on Initiative 6 (modify LCO 3.0.3) is expected from the OG by the end of the year. | |||
Participants agreed to conduct a status conference call at 10 AM on June 27, 2000. The next TSTF meeting will be on July 13-14, 2000 at the NRC. | |||
Page 2 ENCLOSURE 2}} |
Latest revision as of 06:41, 24 November 2019
ML003725391 | |
Person / Time | |
---|---|
Issue date: | 06/16/2000 |
From: | Beckner W Technical Specifications Branch |
To: | Jennifer Davis Nuclear Energy Institute |
References | |
Download: ML003725391 (6) | |
Text
June 16, 2000 Mr. James Davis, Director Operations Department Nuclear Energy Institute 1776 I Street, N. W.
Suite 400 Washington, DC 20006-3708
Dear Mr. Davis:
Enclosed is a summary of our joint NRC/Technical Specifications Task Force (TSTF)
Owners Group meeting at the Nuclear Regulatory Commission in Rockville, Maryland on June 13 and 14, 2000. Should the TSTF have any comments or questions, please do not hesitate to contact me on 301-415-1161 or by e-mail at wdb@nrc.gov.
Sincerely,
/RA/
William D. Beckner, Chief Technical Specifications Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 689
Enclosures:
- 1. Attendee List
- 2. Summary of Meeting cc: Those on enclosed Attendees List
Nuclear Energy Institute Project No. 689 cc: Mr. Ralph Beedle Ms. Lynnette Hendricks, Director Senior Vice President Plant Support and Chief Nuclear Officer Nuclear Energy Institute Nuclear Energy Institute Suite 400 Suite 400 1776 I Street, NW 1776 I Street, NW Washington, DC 20006-3708 Washington, DC 20006-3708 Mr. Alex Marion, Director Mr. Charles B. Brinkman, Director Programs Washington Operations Nuclear Energy Institute ABB-Combustion Engineering, Inc.
Suite 400 12300 Twinbrook Parkway, Suite 330 1776 I Street, NW Rockville, Maryland 20852 Washington, DC 20006-3708 Mr. David Modeen, Director Engineering Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Anthony Pietrangelo, Director Licensing Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708 Mr. Hank Sepp, Manager Regulatory and Licensing Engineering Westinghouse Electric Corporation P.O. Box 355 Pittsburgh, Pennsylvania 15230 Mr. Jim Davis, Director Operations Nuclear Energy Institute Suite 400 1776 I Street, NW Washington, DC 20006-3708
June 16, 2000 Mr. James Davis, Director Operations Department Nuclear Energy Institute 1776 I Street, N. W.
Suite 400 Washington, DC 20006-3708
Dear Mr. Davis:
Enclosed is a summary of our joint NRC/Technical Specifications Task Force (TSTF)
Owners Group meeting at the Nuclear Regulatory Commission in Rockville, Maryland on June 13 and 14, 2000. Should the TSTF have any comments or questions, please do not hesitate to contact me on 301-415-1161 or by e-mail at wdb@nrc.gov.
Sincerely,
/RA/
William D. Beckner, Chief Technical Specifications Branch Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Project No. 689
Enclosures:
- 1. Attendee List
- 2. Summary of Meeting cc: Those on enclosed Attendees List DISTRIBUTION:
DBMatthews/SNewberry RTSB Members PUBLIC RTSB R/F WDBeckner JLBirmingham RLDennig ADAMS DOCUMENT NAME: G:\RTSB\TSTF INFO\Owners Group Correspondence\MTGSUM6-13-14.wpd OFFICE RTSB/DRIP RTSB/DRIP RGEB/DRIP SC:RTSB/DRIP C:RTSB/DRIP:NRR NAME TRTjaderTRT LAHillLAH JLBirminghamJLB RLDennigRLD WDBecknerWDB DATE 06/16/00 06/16/00 06/16/00 06/16/00 06/16/00 OFFICIAL RECORD COPY
NRC/TSTF OWNER'S GROUP MEETING June 13 & 14, 2000 ATTENDEES LIST NAME ORGANIZATION B. L. Woods CEOG/San Onofre J. Arbuckle BWROG/WNP2 H. Pontious BWROG/COMED B. Mann EXCEL D. Hoffman EXCEL N. Clarkson BWOG/DUKE S. Wideman WOG/WCNOC W. Beckner NRC/NRR/RTSB R. Dennig NRC/NRR/RTSB J. Birmingham* NRC/NRR T. R. Tjader NRC/NRR/RTSB N. Gilles** NRC/NRR/RTSB C. Schulten NRC/NRR/RTSB Leslie Hill NRC/NRR/RTSB T. Liu* NRC/NRR/RTSB J. Foster* NRC/NRR/RTSB W. Reckley* NRR/PMAS J. Weil* McGraw Hill
- Attended June 13 only
- Attended June 14 only ENCLOSURE 1
Technical Specification Task Force Meeting Summary June 13 & 14, 2000 Staff met with the Nuclear Energy Institute Technical Specification Task Force (NEI TSTF) on June 13 & 14, 2000.
The TSTF and staff discussed the status of pending high priority TSTFs as described below. was the pre-meeting status provided by the TSTF and Attachment 2 was the pre-meeting status provided by the staff.
016 R.3: The TSB has the necessary information to complete its review; approval is anticipated.
207 R.5: Approved.
231 R.1: Approved; RPS Instrumentation Bases (B3.3.1.1) correction.
306 R.1: The TSTF will submit Revision 2 to revise the Bases.
330 R.0: The TSTF will submit Revision 1 which will be a solution that is based upon the temperature averaging concept approved for Brunswick.
332 R.0: The TSTF will submit Revision 1 which will implement the topical, Supplement 1 of NEDO-32291 of October 1999, and remove the non-generic cascading issues.
334 R.1: The TSTF will submit Revision 2 to include a reviewers note based upon a related topical, once it is approved .
342 R.1: Approved.
343 R.0: Staff comments have been provided to the TSTF and the TSTF will submit Revision 1 for staff review in the near future (low priority).
355 R.0: The TSTF will submit Revision 1 to make a correction to the RPS Instrumentation Bases (B3.3.3.1).
360 R.0: Staff is reviewing the latest TSTF justifications/submittals.
361 R.0: Approved.
364 R.0: Approved.
365 R.0 (TSB-22): Approved.
Page 1 ENCLOSURE 2
Other Topics Discussed:
The TSTF OG will propose a program to include in the Technical Specifications to address delayed LCO entry for taking snubbers out of service for routine maintenance. Attachment 3 was provided to the OG to help clarify issues in order to develop the program. [Though not discussed, in parallel to the industry effort TSB will work on a section 3.0 specification to allow for a delay time entry into the Conditions of an LCO.] The intent is to avoid unnecessary entry into TS required actions for supported systems when removing snubbers from service for surveillance testing.
The Staff presented some questions (Attachment 4) regarding BWR plant refueling outage operations, with the intent to resolve concerns about TSTF-225 and BWR STS 3.10.6. The OG will present the questions to industry experts and provide answers to TSB; TSB will review and discuss the answers with SRXB, clarify the concerns, and present the concerns with proposed solutions to the OG; and, if necessary have an NEI-NRR meeting to resolve issues. The Staff will prepare an SE on Perrys proposed adoption of TSTF-225 from the results of this effort.
The production status of Revision 2 to the STS NUREGs was discussed. The plan is to resolve BWR refueling issues and TSTF-360 issues by the end of July 2000, post the final draft STS Rev 2 for industry and public comment by mid August 2000, and receive and incorporate comments by the end of September 2000. Then publish STS Rev 2 in the early Fall of 2000.
TSB-NEI proofing panels will be convened as needed to resolve editorial issues. A discussion on proposed format changes to the STS Rev 2 Table of Contents (TOC) was conducted briefly, with the OG unanimously agreeing that TOC should remain unchanged (Attachment 5, a strawman for the suggested changes was passed out).
The staff and TSTF members discussed the potential of using the consolidated line item improvement process (CLIIP) for the removal of post accident sampling systems (PASS) from the TS of Westinghouse and Combustion Engineering plants. The owners groups for those plants have received safety evaluations for topical reports that justified removing PASS. The owners groups representatives agreed to pursue a TSTF traveler for the removal of PASS.
Following receipt of the proposed TSTF, the staff believes it is in a position (based on the topical reviews) to quickly publish the notice for comment as called for in the CLIIP. The BWR and B&W Owners Groups would likely submit TSTFs and the CLIIP would be used for the remaining plants using a separate activity. Bill Reckley of the staff provided a possible example of an individual licensee's application using the CLIIP for PASS elimination (Attachment 6).
The status of the Risk Informed Technical Specifications (RITS) effort was discussed. The OG has submitted proposal for Initiatives 1 (preferred end states), 2 (revise delay time for entering required actions upon missing a surveillance), and 3 (modify mode restraint logic); Initiative 1 is currently under review by the staff. Revisions to TSTF-358 and TSTF-359 can be expected from the OG in early July. A proposal on Initiative 6 (modify LCO 3.0.3) is expected from the OG by the end of the year.
Participants agreed to conduct a status conference call at 10 AM on June 27, 2000. The next TSTF meeting will be on July 13-14, 2000 at the NRC.
Page 2 ENCLOSURE 2