{{#Wiki_filter:January 14, 2014 by Electronic Information Exchange Administrative Judge Alex S. Karlin Administrative Judge Nicholas G. Trikouros Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel  
{{#Wiki_filter:January 14, 2014 by Electronic Information Exchange Administrative Judge Alex S. Karlin Administrative Judge Nicholas G. Trikouros Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Mail Stop: T-3F23 Rockville, MD 20852 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)
 
Docket Nos. 50-275-LR and 50-323-LR RE: Status Report
U.S. Nuclear Regulatory Commission Two White Flint North  
 
11545 Rockville Pike Mail Stop: T-3F23  
 
Rockville, MD 20852 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)
Docket Nos. 50-275-LR and 50-323-LR RE: Status Report  


==Dear Administrative Judges:==
==Dear Administrative Judges:==
As directed by the Licensing Board Order of June 7, 2011, Pacific Gas and Electric Company (PG&E) hereby provides its monthly report specifying its current best estimate of the dates on which it expects to complete milestones related to 3D seismic studies for Diablo Canyon Power
Plant (DCPP) and the coastal zone consistency certification associated with NRC license renewal for DCPP. 
The schedule for the seismic work is unchanged since PG&E's last submittal on December 10, 2013. PG&E will continue to provide specific dates in the monthly reports to the extent practicable, recognizing that these dates may be modified as more accurate information becomes available. PG&E wishes to assure the Licensing Board that it is making every effort to minimize the extent of the delay in the NRC license renewal process.
Executed in accord with 10 CFR 2.304(d),
    /s/ signed electronically by Jennifer K. Post Attorney Pacific Gas and Electric Company
77 Beale St., B30A
San Francisco, CA  94105
(415) 973-9809 jklm@pge.com
    /s/ signed electronically by David A. Repka Winston & Strawn LLP
1700 K Street, NW
Washington, DC  20006
(202) 282-5726
drepka@winston.com


cc:  Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Service List (via Electronic Information Exchange)  
As directed by the Licensing Board Order of June 7, 2011, Pacific Gas and Electric Company (PG&E) hereby provides its monthly report specifying its current best estimate of the dates on which it expects to complete milestones related to 3D seismic studies for Diablo Canyon Power Plant (DCPP) and the coastal zone consistency certification associated with NRC license renewal for DCPP.
The schedule for the seismic work is unchanged since PG&Es last submittal on December 10, 2013. PG&E will continue to provide specific dates in the monthly reports to the extent practicable, recognizing that these dates may be modified as more accurate information becomes available. PG&E wishes to assure the Licensing Board that it is making every effort to minimize the extent of the delay in the NRC license renewal process.
Executed in accord with 10 CFR 2.304(d),
                                                /s/ signed electronically by Jennifer K. Post Attorney Pacific Gas and Electric Company 77 Beale St., B30A San Francisco, CA 94105 (415) 973-9809 jklm@pge.com


Pacific Gas and Electric Company Updated Best Estimate Sc hedule for Seismic Studies Description of Activity Current Estimate Shoreline Fault Submit Final Report to the NRC  January 2011(a) NRC Review Complete  October 12, 2012(a) Ocean Bottom Seismometer Study Permit Application Submitted to California State Lands Commission (CSLC) May 6, 2011 (a) Permits Issued  May 2013 (a) OBS System Installed August 2013(a) OBS Equipment Repair and Adjustment November 2013 (a) 2D/3D Low Energy Marine Studies Permits Issued N/A Surveys Complete October 2012 (a) Data Processing and Interpretation Complete October 2013 (a) 2D Onshore High Energy Studies Permit Pre-Application Meeting  May 4, 2011 (a) Use Permits Issued  Not Required  Surveys Complete  December 2011 (a) and December 2012 (a) Data Processing and Interpretation Complete June 2014 3D High Energy Marine Studies Permit Application Submitted to CSLC  April 29, 2011 (a) CSLC Environmental Impact Report Scoping Meeting July 21, 2011 (a) Permits Denied November 14, 2012 (a) Issue Final Seismic Report to the NRC and ASLB June 2014 CZMA or Coastal Consistency File Coastal Development Permit  TBD  Coastal Consistency Issued TBD  Note: (a) - Actual Date Completed
                                            /s/ signed electronically by David A. Repka Winston & Strawn LLP 1700 K Street, NW Washington, DC 20006 (202) 282-5726 drepka@winston.com cc: Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Service List (via Electronic Information Exchange)


SF:349580.1}}
Pacific Gas and Electric Company Updated Best Estimate Schedule for Seismic Studies Description of Activity                Current Estimate Shoreline Fault Submit Final Report to the NRC                          January 2011(a)
NRC Review Complete                                      October 12, 2012(a)
Ocean Bottom Seismometer Study Permit Application Submitted to California State Lands  May 6, 2011(a)
Commission (CSLC)
Permits Issued                                          May 2013(a)
OBS System Installed                                    August 2013(a)
OBS Equipment Repair and Adjustment                      November 2013(a) 2D/3D Low Energy Marine Studies Permits Issued                                          N/A Surveys Complete                                        October 2012(a)
Data Processing and Interpretation Complete              October 2013(a) 2D Onshore High Energy Studies Permit Pre-Application Meeting                          May 4, 2011(a)
Use Permits Issued                                      Not Required Surveys Complete                                        December 2011(a) and December 2012(a)
Data Processing and Interpretation Complete              June 2014 3D High Energy Marine Studies Permit Application Submitted to CSLC                    April 29, 2011(a)
CSLC Environmental Impact Report Scoping Meeting        July 21, 2011(a)
Permits Denied                                          November 14, 2012(a)
Issue Final Seismic Report to the NRC and ASLB          June 2014 CZMA or Coastal Consistency File Coastal Development Permit                          TBD Coastal Consistency Issued                              TBD (a)
Note:      - Actual Date Completed SF:349580.1}}

Revision as of 09:27, 4 November 2019

Pacific Gas and Electric Company, Updated Best Estimate Schedule for Seismic Studies
ML14014A103
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 01/14/2014
From: Post J, Repka D
Pacific Gas & Electric Co, Winston & Strawn, LLP
To: Abramson P, Karlin A, Nicholas Trikouros
Atomic Safety and Licensing Board Panel
SECY RAS
References
50-275-LR, 50-323-LR, ASLBP 10-900-01-LR-BD01, RAS 25483
Download: ML14014A103 (3)


Text

January 14, 2014 by Electronic Information Exchange Administrative Judge Alex S. Karlin Administrative Judge Nicholas G. Trikouros Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel U.S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Mail Stop: T-3F23 Rockville, MD 20852 In the Matter of PACIFIC GAS AND ELECTRIC COMPANY (Diablo Canyon Power Plant, Units 1 and 2)

Docket Nos. 50-275-LR and 50-323-LR RE: Status Report

Dear Administrative Judges:

As directed by the Licensing Board Order of June 7, 2011, Pacific Gas and Electric Company (PG&E) hereby provides its monthly report specifying its current best estimate of the dates on which it expects to complete milestones related to 3D seismic studies for Diablo Canyon Power Plant (DCPP) and the coastal zone consistency certification associated with NRC license renewal for DCPP.

The schedule for the seismic work is unchanged since PG&Es last submittal on December 10, 2013. PG&E will continue to provide specific dates in the monthly reports to the extent practicable, recognizing that these dates may be modified as more accurate information becomes available. PG&E wishes to assure the Licensing Board that it is making every effort to minimize the extent of the delay in the NRC license renewal process.

Executed in accord with 10 CFR 2.304(d),

/s/ signed electronically by Jennifer K. Post Attorney Pacific Gas and Electric Company 77 Beale St., B30A San Francisco, CA 94105 (415) 973-9809 jklm@pge.com

/s/ signed electronically by David A. Repka Winston & Strawn LLP 1700 K Street, NW Washington, DC 20006 (202) 282-5726 drepka@winston.com cc: Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Service List (via Electronic Information Exchange)

Pacific Gas and Electric Company Updated Best Estimate Schedule for Seismic Studies Description of Activity Current Estimate Shoreline Fault Submit Final Report to the NRC January 2011(a)

NRC Review Complete October 12, 2012(a)

Ocean Bottom Seismometer Study Permit Application Submitted to California State Lands May 6, 2011(a)

Commission (CSLC)

Permits Issued May 2013(a)

OBS System Installed August 2013(a)

OBS Equipment Repair and Adjustment November 2013(a) 2D/3D Low Energy Marine Studies Permits Issued N/A Surveys Complete October 2012(a)

Data Processing and Interpretation Complete October 2013(a) 2D Onshore High Energy Studies Permit Pre-Application Meeting May 4, 2011(a)

Use Permits Issued Not Required Surveys Complete December 2011(a) and December 2012(a)

Data Processing and Interpretation Complete June 2014 3D High Energy Marine Studies Permit Application Submitted to CSLC April 29, 2011(a)

CSLC Environmental Impact Report Scoping Meeting July 21, 2011(a)

Permits Denied November 14, 2012(a)

Issue Final Seismic Report to the NRC and ASLB June 2014 CZMA or Coastal Consistency File Coastal Development Permit TBD Coastal Consistency Issued TBD (a)

Note: - Actual Date Completed SF:349580.1