{{#Wiki_filter:Datasheet 1 50-183(A)(B)(C)N(D)N( | {{#Wiki_filter:Datasheet 1 Decommissioining Funding Assurance Analysis As of December 31, 2014 For Plant Name: GE Vallecitos EVESR (DR-10) Docket Number: 50-183 DFP - 10 CFR 50.82(a)(8)(v) | ||
(A) Cumulative Amount Spent on Decommissioning: $0 Amount Spent of Decommissioning Over the Previous Calendar Year: $0 Remaining Balance of Any Decommissioning Funds: $0 Amount Provided by Other Financial Assurance Methods: $13,500,000 (B) Estimated Cost of Remaining Decommissioing Activities as Stated in Most Recent SSCE update: $13,500,000 Difference Between Actual and Estimated Costs For Work Performed During Previous Year: $0 Decommissioning Criteria for SSCE Basis Provided? Y (C) Any modifications to licensee's method of providing financial assurance since last report: N (D) Any material changes to trust agreements or financial assurance contracts: N DFP - 10 CFR 50.82(a)(8)(vi) | |||
Amount in Trust Fund: | If the sum of the balance of any remaining decommissioning funds, earnings credit, and amount provided by other financial assurance methods does not cover the estimated cost to complete decommissioning, provide additional financial assurance to cover the estimated cost of completion below: | ||
Additional Financial Assurance - NA DFP - 10 CFR 50.82(a)(8)(vii) | |||
(A) The total amount of dollars accumulated at the end of the appropriate year designated for managing irradiated fuel: (see below) | |||
Licensee: % Owned: Amount in Trust Fund: | |||
Total Trust Fund Balance $0 (B) The projected cost of spent fuel management until transfer of possession to DOE: N/A (C) If the funds accumulated do not cover the projected cost, provide a plan to obtain addional funds to cover the cost below: | |||
Financial Assurance Plan - | Financial Assurance Plan - | ||
Spreadsheet created by: Aaron Szabo, Shawn Harwell Signature: _______________________________________________ Date: ______________________ Formulas verified by: Clayton Pittiglio | |||
Datasheet 1 Spreadsheet created by: Aaron Szabo, Shawn Harwell Signature: _______________________________________________ Date: ______________________ Formulas verified by: Clayton Pittiglio}} | |||
Spreadsheet created by: Aaron Szabo, Shawn Harwell | |||
Latest revision as of 06:07, 31 October 2019
ML15275A256 | |
Person / Time | |
---|---|
Site: | Vallecitos File:GEH Hitachi icon.png |
Issue date: | 12/31/2014 |
From: | Office of Nuclear Material Safety and Safeguards |
To: | |
Jack Parrott | |
Shared Package | |
ML15275A264 | List: |
References | |
Download: ML15275A256 (1) | |
Text
Datasheet 1 Decommissioining Funding Assurance Analysis As of December 31, 2014 For Plant Name: GE Vallecitos EVESR (DR-10) Docket Number: 50-183 DFP - 10 CFR 50.82(a)(8)(v)
(A) Cumulative Amount Spent on Decommissioning: $0 Amount Spent of Decommissioning Over the Previous Calendar Year: $0 Remaining Balance of Any Decommissioning Funds: $0 Amount Provided by Other Financial Assurance Methods: $13,500,000 (B) Estimated Cost of Remaining Decommissioing Activities as Stated in Most Recent SSCE update: $13,500,000 Difference Between Actual and Estimated Costs For Work Performed During Previous Year: $0 Decommissioning Criteria for SSCE Basis Provided? Y (C) Any modifications to licensee's method of providing financial assurance since last report: N (D) Any material changes to trust agreements or financial assurance contracts: N DFP - 10 CFR 50.82(a)(8)(vi)
If the sum of the balance of any remaining decommissioning funds, earnings credit, and amount provided by other financial assurance methods does not cover the estimated cost to complete decommissioning, provide additional financial assurance to cover the estimated cost of completion below:
Additional Financial Assurance - NA DFP - 10 CFR 50.82(a)(8)(vii)
(A) The total amount of dollars accumulated at the end of the appropriate year designated for managing irradiated fuel: (see below)
Licensee: % Owned: Amount in Trust Fund:
Total Trust Fund Balance $0 (B) The projected cost of spent fuel management until transfer of possession to DOE: N/A (C) If the funds accumulated do not cover the projected cost, provide a plan to obtain addional funds to cover the cost below:
Financial Assurance Plan -
Spreadsheet created by: Aaron Szabo, Shawn Harwell Signature: _______________________________________________ Date: ______________________ Formulas verified by: Clayton Pittiglio
Datasheet 1 Spreadsheet created by: Aaron Szabo, Shawn Harwell Signature: _______________________________________________ Date: ______________________ Formulas verified by: Clayton Pittiglio