{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001       OFFICE OF THE INSPECTOR GENERAL November 13, 2018   MEMORANDUM TO: Margaret M. Doane     Executive Director for Operations   FROM:   Dr. Brett M. Baker /RA/     Assistant Inspector General for Audits  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 OFFICE OF THE INSPECTOR GENERAL November 13, 2018 MEMORANDUM TO:               Margaret M. Doane Executive Director for Operations FROM:                       Dr. Brett M. Baker /RA/
Assistant Inspector General for Audits


==SUBJECT:==
==SUBJECT:==
STATUS OF RECOMMENDATIONS REGULATORY ANALYSIS PROCESS (OIG-15-A-15)
STATUS OF RECOMMENDATION: AUDIT OF NRCS REGULATORY ANALYSIS PROCESS (OIG-15-A-15)


==REFERENCE:==
==REFERENCE:==
DIRECTOR, OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS, MEMORANDUM DATED NOVEMBER 2, 2018   (OIG) analysis and status of the recommendation November 2, 2018. Based on this response recommendation 3 remains in resolved status. Recommendations 1, 2, and 4 were closed previously. Please provide an updated status of the resolved recommendation by May 3, 2019. If you have any questions or concerns, please contact me at (301) 415-5915 or Eric Rivera, Team Leader, at (301) 415-7032. Attachments: As stated cc: R. Lewis, OEDO H. Rasouli, OEDO J. Jolicoeur, OEDO J. Bowen, OEDO EDO_ACS Distribution Audit Report     REGULATORY ANALYSIS PROCESS OIG-15-A-15 Status of Recommendations   Recommendation 3: Update and implement the cost benefit guidance documents as planned in SECY-14-0002. Incorporate this guidance into office procedures by reference. Agency Response Dated November 2, 2018: On March 29, 2018, the staff submitted to the Commission by a notation vote paper SECY-18-NUREG/BR-0058, Regulatory Analysis Guidelines of the U.S. Following Commission review and approval of Revision 5, the staff will issue the final NUREG and publish the document on the NRC document collection Web site. We will issue a publication announcement when the document is finalized. On September 28, 2018, the staff issued Revision 3 of the Office of Nuclear Material Safety and Safeguards (NMSS) Policy and Procedures 6-NMSS Procedures for it includes a reference to NUREG/BR-0058. This reference results in the incorporation of the approved cost benefit guidance into the office policies and procedures. Target Completion Dates: April 2018 (completed) issued notation vote paper with Revision 5 to NUREG/BR-0058 September 2018 (completed) issued NMSS Policy and Procedure 6-10, Revision 3     OIG Analysis: recommendation. This recommendation will be closed when OIG receives and reviews the final NUREG that provides cost benefit guidance, along with evidence that it has been implemented. Status: Resolved.}}
DIRECTOR, OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS, MEMORANDUM DATED NOVEMBER 2, 2018 Attached is the Office of the Inspector Generals (OIG) analysis and status of the recommendation as discussed in the agencys response dated November 2, 2018.
Based on this response recommendation 3 remains in resolved status.
Recommendations 1, 2, and 4 were closed previously. Please provide an updated status of the resolved recommendation by May 3, 2019.
If you have any questions or concerns, please contact me at (301) 415-5915 or Eric Rivera, Team Leader, at (301) 415-7032.
Attachments: As stated cc:     R. Lewis, OEDO H. Rasouli, OEDO J. Jolicoeur, OEDO J. Bowen, OEDO EDO_ACS Distribution
 
Audit Report AUDIT OF NRCS REGULATORY ANALYSIS PROCESS OIG-15-A-15 Status of Recommendations Recommendation 3:       Update and implement the cost benefit guidance documents as planned in SECY-14-0002. Incorporate this guidance into office procedures by reference.
Agency Response Dated November 2, 2018:       On March 29, 2018, the staff submitted to the Commission by a notation vote paper SECY-18-0042, Draft Final NUREG/BR-0058, Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission. Following Commission review and approval of Revision 5, the staff will issue the final NUREG and publish the document on the NRC librarys document collection Web site. We will issue a publication announcement when the document is finalized.
On September 28, 2018, the staff issued Revision 3 of the Office of Nuclear Material Safety and Safeguards (NMSS)
Policy and Procedures 6-10, NMSS Procedures for Preparation and Review of Rulemaking Packages, and it includes a reference to NUREG/BR-0058. This reference results in the incorporation of the approved cost benefit guidance into the office policies and procedures.
Target Completion Dates:
April 2018 (completed) - issued notation vote paper with Revision 5 to NUREG/BR-0058 September 2018 (completed) - issued NMSS Policy and Procedure 6-10, Revision 3 OIG Analysis:           The proposed corrective action addresses the intent of OIGs recommendation. This recommendation will be closed when OIG receives and reviews the final NUREG that provides cost benefit guidance, along with evidence that it has been implemented.
Status:                 Resolved.}}

Latest revision as of 11:44, 20 October 2019

OIG-15-A-15-Status of Recommendations: Audit of Nrc'S Regulatory Analysis Process Dated November 13, 2018
ML18317A119
Person / Time
Issue date: 11/13/2018
From: Baker B
NRC/OIG/AIGA
To: Margaret Doane
NRC/EDO
References
OIG-15-A-15
Download: ML18317A119 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 OFFICE OF THE INSPECTOR GENERAL November 13, 2018 MEMORANDUM TO: Margaret M. Doane Executive Director for Operations FROM: Dr. Brett M. Baker /RA/

Assistant Inspector General for Audits

SUBJECT:

STATUS OF RECOMMENDATION: AUDIT OF NRCS REGULATORY ANALYSIS PROCESS (OIG-15-A-15)

REFERENCE:

DIRECTOR, OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS, MEMORANDUM DATED NOVEMBER 2, 2018 Attached is the Office of the Inspector Generals (OIG) analysis and status of the recommendation as discussed in the agencys response dated November 2, 2018.

Based on this response recommendation 3 remains in resolved status.

Recommendations 1, 2, and 4 were closed previously. Please provide an updated status of the resolved recommendation by May 3, 2019.

If you have any questions or concerns, please contact me at (301) 415-5915 or Eric Rivera, Team Leader, at (301) 415-7032.

Attachments: As stated cc: R. Lewis, OEDO H. Rasouli, OEDO J. Jolicoeur, OEDO J. Bowen, OEDO EDO_ACS Distribution

Audit Report AUDIT OF NRCS REGULATORY ANALYSIS PROCESS OIG-15-A-15 Status of Recommendations Recommendation 3: Update and implement the cost benefit guidance documents as planned in SECY-14-0002. Incorporate this guidance into office procedures by reference.

Agency Response Dated November 2, 2018: On March 29, 2018, the staff submitted to the Commission by a notation vote paper SECY-18-0042, Draft Final NUREG/BR-0058, Regulatory Analysis Guidelines of the U.S. Nuclear Regulatory Commission. Following Commission review and approval of Revision 5, the staff will issue the final NUREG and publish the document on the NRC librarys document collection Web site. We will issue a publication announcement when the document is finalized.

On September 28, 2018, the staff issued Revision 3 of the Office of Nuclear Material Safety and Safeguards (NMSS)

Policy and Procedures 6-10, NMSS Procedures for Preparation and Review of Rulemaking Packages, and it includes a reference to NUREG/BR-0058. This reference results in the incorporation of the approved cost benefit guidance into the office policies and procedures.

Target Completion Dates:

April 2018 (completed) - issued notation vote paper with Revision 5 to NUREG/BR-0058 September 2018 (completed) - issued NMSS Policy and Procedure 6-10, Revision 3 OIG Analysis: The proposed corrective action addresses the intent of OIGs recommendation. This recommendation will be closed when OIG receives and reviews the final NUREG that provides cost benefit guidance, along with evidence that it has been implemented.

Status: Resolved.