ML19042A683: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(One intermediate revision by the same user not shown)
Line 9: Line 9:
| docket =  
| docket =  
| license number =  
| license number =  
| contact person = Sebrosky J M, NRR/DLP, 415-1132
| contact person = Sebrosky J, NRR/DLP, 415-1132
| document type = Slides and Viewgraphs
| document type = Slides and Viewgraphs
| page count = 15
| page count = 15
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:Preliminary Process for the Treatment of Reevaluated Seismic and Flooding Hazard Information Public Meeting February 28, 2019
 
Agenda
* Purpose and Background
* Highlights of Preliminary Process
* Elements of Preliminary Process
* Questions and Feedback
* Next Steps
* Wrapup 2
 
Purpose
* Solicit Stakeholder Feedback on Treatment of Reevaluated Seismic and Flooding Hazard Information in 50.54(f)
Determinations
* Draft document1 outlines preliminary process 1 ADAMS Accession No. ML19037A443 3
 
===Background===
* On March 12, 20122, NRC issued a request for information under 10 CFR 50.54(f) - or 50.54(f) letter
    - Enclosures 1 and 2 requested licensees to reevaluate seismic and flood hazards, respectively
    - Licensees used present-day methods and regulatory guidance
    - Letter outlines a 2 phase approach
* Phase 1 - licensee provides reevaluated hazard information
* Phase 2 - NRC considers reevaluated hazard information and makes a decision on whether a license should be modified, suspended, or revoked 2ADAMS Accession No. ML12053A340 4
 
Background (Cont.)
* Licensee responses to the 50.54(f) letter, Enclosure 1 (reevaluated seismic hazard information), included:
  - Seismic hazard screening report - all sites
  - Other evaluations as needed:
* Expedited seismic evaluation program
* Spent-fuel pool (SFP) seismic integrity evaluations
* Seismic high frequency (HF) confirmations
* Seismic Probabilistic Risk Assessment (SPRA) reports
* Licensee responses to the 50.54(f) letter, Enclosure 2 (reevaluated flood hazard information), included:
  - Flooding hazard reevaluation report - all sites
  - Other evaluations as needed: Flooding focused evaluations (FEs) or flooding integrated assessments (IAs) 5
 
Background (Cont.)
* Licensees also provided seismic and flooding mitigation strategies assessments (MSAs) based on reevaluated hazard information
* Majority of seismic and flooding reevaluated hazard information has been reviewed by the staff
* Status of plant-specific Fukushima lessons learned activities (including reevaluated seismic and flood hazards) can be found at:
  - https://www.nrc.gov/reactors/operating/ops-experience/japan-dashboard/japan-plants.html 6
 
Background (Cont.)
* Commission direction was provided in the staff requirements memorandum (SRM) dated January 24, 20193, associated with SECY-16-0142 - Mitigation of Beyond-Design-Basis Events (MBDBE) rule4
    - The draft final MBDBE rule contained provisions requiring mitigation strategies to address the reevaluated seismic and flood hazards on a generic basis
    - Provisions were removed from the approved final MBDBE rule as described in the SRM
    - The SRM directs the staff to use the 50.54(f) process to take the needed actions, if any, to ensure that each plant is able to withstand the effects of the reevaluated flooding and seismic hazards 3 ADAMS Accession No. ML19023A038 4 ADAMS Accession No. ML16291A186                            7
 
Highlights of Preliminary Process
* Seismic Evaluations
  - SPRA report reviews will continue as scheduled
  - Additional regulatory actions for non-SPRA sites do not appear to be needed
* Flooding Evaluations
  - Staff plans to engage licensees for 21 sites to clarify the status of actions described in flooding MSA and FE/IA submittals
  - Staff will continue to review flooding FEs and flooding IAs
* Staff does not plan to issue staff assessments for any remaining seismic and flooding MSAs
  - If information is needed to support a staff decision, it will be identified during the staffs review of SPRA reports or flooding FE/IAs 8
 
Highlights of Preliminary Process (Cont.)
* Letter(s) to industry envisioned documenting staffs Phase 2 determination
* First letter proposes to bin sites:
  - Category 1 - no additional clarity needed from licensees; no additional regulatory actions are needed
  - Category 2 - additional clarity needed from licensees
  - Category 3 - staff review ongoing
  - Category 4 - deferred sites 9
 
Elements of Preliminary Process
* Seismic Evaluations
  - Based on latest information, staffs preliminary process results with sites in either Category 1 (no additional clarifications needed), Category 3 (under review), or Category 4 (deferred)
  - Staff revisited previously reviewed SFP integrity evaluations, HF confirmations, seismic MSAs, and SPRA reports
  - Staff preliminary determination is additional regulatory actions are not needed for sites whose staff assessments have been completed
  - Staff will continue to review SPRA reports
* 4 SPRA report reviews completed - no regulatory actions identified
* 4 SPRA report reviews underway
* 8 additional SPRA reports expected
* SFP integrity already reviewed 10
 
Elements of Preliminary Process (Cont.)
* Flooding Evaluations
    - Staffs preliminary process review results in:
* 26 sites in Category 1 - no additional clarity needed
* 21 sites in Category 2 - additional clarity needed
* 9 sites in Category 3 - under review
* 5 sites in Category 4 - deferred
    - For Category 3 sites, if staff identifies a need for clarification related to mitigation strategies, staff will pursue questions as part of flooding FE/IA reviews
    - The process for addressing Category 2 sites is outlined in draft document
* Provides 4 options (see next slide) 11
 
Elements of Preliminary Process (Cont.)
Flooding Category 2 (additional clarification needed) Options5:
* Option 1 - Backfit based on flooding MSA and FE/IA Commitments
* Option 2 - Backfit based solely on FE/IA Commitments
* Option 3- Backfit based solely on flooding MSA Commitments
* Option 4 - Backfit not based on either flooding MSA or FE/IA Commitments 5The staff will not rely on commitments where a question of adequate protection of public health and safety exists.                                                  12
 
Elements of Preliminary Process (Cont.)
* Milestones
    - March 22, 2019, email comments due
    - Mid-2019 - staff confirmation of the status of commitments for flooding Category 2 plants
    - Mid-2019 - letter binning sites issued
* Category 2 sites clarification activities may not be completed before issuance of letter
            - In such cases, a licensee will receive a separate letter after clarification issues have been resolved
* Staff will proceed with issuing the letter before completion of reviews of flooding FE/IAs and SPRAs (i.e., Category 3 efforts completed)
              - In such a case the staffs assessment of the flooding FE/IA and SPRA will document the review and the staffs backfit determination 13
 
QUESTION AND ANSWER SESSION
 
Next Steps
* NRC Staff will assess comments received during the meeting
* Additional comments can be provided via email to:
50.54f_Seismic.Resource@nrc.gov
  - Comments received by March 22, 2019, will be considered
* Staff contacts for additional information
  - Joe Sebrosky, joseph.sebrosky@nrc.gov, 301-415-1132
  - Juan Uribe, juan.uribe@nrc.gov, 301-415-3809
  - Milton Valentin-Olmeda, milton.valentin@nrc.gov, 301-415-2864
* Process will be adjusted, as appropriate, based on stakeholder feedback
  - Letter to industry will be issued based on revised process
  - Letter will include binning of sites
  - Target for issuance of letter is mid-2019 15}}

Latest revision as of 02:17, 20 October 2019

Slides for February 28, 2019, Category 3 Public Meeting to Discuss Preliminary Process for Treatment of Reevaluated Seismic and Flooding Hazard Information in Backfit Determinations
ML19042A683
Person / Time
Issue date: 02/15/2019
From: Joseph Sebrosky
Beyond-Design-Basis Management Branch
To:
Sebrosky J, NRR/DLP, 415-1132
References
Download: ML19042A683 (15)


Text

Preliminary Process for the Treatment of Reevaluated Seismic and Flooding Hazard Information Public Meeting February 28, 2019

Agenda

  • Purpose and Background
  • Highlights of Preliminary Process
  • Elements of Preliminary Process
  • Questions and Feedback
  • Next Steps
  • Wrapup 2

Purpose

  • Solicit Stakeholder Feedback on Treatment of Reevaluated Seismic and Flooding Hazard Information in 50.54(f)

Determinations

  • Draft document1 outlines preliminary process 1 ADAMS Accession No. ML19037A443 3

Background

  • On March 12, 20122, NRC issued a request for information under 10 CFR 50.54(f) - or 50.54(f) letter

- Enclosures 1 and 2 requested licensees to reevaluate seismic and flood hazards, respectively

- Licensees used present-day methods and regulatory guidance

- Letter outlines a 2 phase approach

  • Phase 1 - licensee provides reevaluated hazard information
  • Phase 2 - NRC considers reevaluated hazard information and makes a decision on whether a license should be modified, suspended, or revoked 2ADAMS Accession No. ML12053A340 4

Background (Cont.)

  • Licensee responses to the 50.54(f) letter, Enclosure 1 (reevaluated seismic hazard information), included:

- Seismic hazard screening report - all sites

- Other evaluations as needed:

  • Expedited seismic evaluation program
  • Spent-fuel pool (SFP) seismic integrity evaluations
  • Seismic high frequency (HF) confirmations
  • Licensee responses to the 50.54(f) letter, Enclosure 2 (reevaluated flood hazard information), included:

- Flooding hazard reevaluation report - all sites

- Other evaluations as needed: Flooding focused evaluations (FEs) or flooding integrated assessments (IAs) 5

Background (Cont.)

  • Licensees also provided seismic and flooding mitigation strategies assessments (MSAs) based on reevaluated hazard information
  • Majority of seismic and flooding reevaluated hazard information has been reviewed by the staff
  • Status of plant-specific Fukushima lessons learned activities (including reevaluated seismic and flood hazards) can be found at:

- https://www.nrc.gov/reactors/operating/ops-experience/japan-dashboard/japan-plants.html 6

Background (Cont.)

  • Commission direction was provided in the staff requirements memorandum (SRM) dated January 24, 20193, associated with SECY-16-0142 - Mitigation of Beyond-Design-Basis Events (MBDBE) rule4

- The draft final MBDBE rule contained provisions requiring mitigation strategies to address the reevaluated seismic and flood hazards on a generic basis

- Provisions were removed from the approved final MBDBE rule as described in the SRM

- The SRM directs the staff to use the 50.54(f) process to take the needed actions, if any, to ensure that each plant is able to withstand the effects of the reevaluated flooding and seismic hazards 3 ADAMS Accession No. ML19023A038 4 ADAMS Accession No. ML16291A186 7

Highlights of Preliminary Process

  • Seismic Evaluations

- SPRA report reviews will continue as scheduled

- Additional regulatory actions for non-SPRA sites do not appear to be needed

  • Flooding Evaluations

- Staff plans to engage licensees for 21 sites to clarify the status of actions described in flooding MSA and FE/IA submittals

- Staff will continue to review flooding FEs and flooding IAs

  • Staff does not plan to issue staff assessments for any remaining seismic and flooding MSAs

- If information is needed to support a staff decision, it will be identified during the staffs review of SPRA reports or flooding FE/IAs 8

Highlights of Preliminary Process (Cont.)

  • Letter(s) to industry envisioned documenting staffs Phase 2 determination
  • First letter proposes to bin sites:

- Category 1 - no additional clarity needed from licensees; no additional regulatory actions are needed

- Category 2 - additional clarity needed from licensees

- Category 3 - staff review ongoing

- Category 4 - deferred sites 9

Elements of Preliminary Process

  • Seismic Evaluations

- Based on latest information, staffs preliminary process results with sites in either Category 1 (no additional clarifications needed), Category 3 (under review), or Category 4 (deferred)

- Staff revisited previously reviewed SFP integrity evaluations, HF confirmations, seismic MSAs, and SPRA reports

- Staff preliminary determination is additional regulatory actions are not needed for sites whose staff assessments have been completed

- Staff will continue to review SPRA reports

  • 4 SPRA report reviews completed - no regulatory actions identified
  • 4 SPRA report reviews underway
  • 8 additional SPRA reports expected
  • SFP integrity already reviewed 10

Elements of Preliminary Process (Cont.)

  • Flooding Evaluations

- Staffs preliminary process review results in:

  • 26 sites in Category 1 - no additional clarity needed
  • 21 sites in Category 2 - additional clarity needed
  • 9 sites in Category 3 - under review
  • 5 sites in Category 4 - deferred

- For Category 3 sites, if staff identifies a need for clarification related to mitigation strategies, staff will pursue questions as part of flooding FE/IA reviews

- The process for addressing Category 2 sites is outlined in draft document

  • Provides 4 options (see next slide) 11

Elements of Preliminary Process (Cont.)

Flooding Category 2 (additional clarification needed) Options5:

  • Option 1 - Backfit based on flooding MSA and FE/IA Commitments
  • Option 2 - Backfit based solely on FE/IA Commitments
  • Option 3- Backfit based solely on flooding MSA Commitments
  • Option 4 - Backfit not based on either flooding MSA or FE/IA Commitments 5The staff will not rely on commitments where a question of adequate protection of public health and safety exists. 12

Elements of Preliminary Process (Cont.)

  • Milestones

- March 22, 2019, email comments due

- Mid-2019 - staff confirmation of the status of commitments for flooding Category 2 plants

- Mid-2019 - letter binning sites issued

  • Category 2 sites clarification activities may not be completed before issuance of letter

- In such cases, a licensee will receive a separate letter after clarification issues have been resolved

  • Staff will proceed with issuing the letter before completion of reviews of flooding FE/IAs and SPRAs (i.e., Category 3 efforts completed)

- In such a case the staffs assessment of the flooding FE/IA and SPRA will document the review and the staffs backfit determination 13

QUESTION AND ANSWER SESSION

Next Steps

  • NRC Staff will assess comments received during the meeting
  • Additional comments can be provided via email to:

50.54f_Seismic.Resource@nrc.gov

- Comments received by March 22, 2019, will be considered

  • Staff contacts for additional information

- Joe Sebrosky, joseph.sebrosky@nrc.gov, 301-415-1132

- Juan Uribe, juan.uribe@nrc.gov, 301-415-3809

- Milton Valentin-Olmeda, milton.valentin@nrc.gov, 301-415-2864

  • Process will be adjusted, as appropriate, based on stakeholder feedback

- Letter to industry will be issued based on revised process

- Letter will include binning of sites

- Target for issuance of letter is mid-2019 15